CN114934671A - Fixed wallboard device for house construction pouring and mounting method thereof - Google Patents

Fixed wallboard device for house construction pouring and mounting method thereof Download PDF

Info

Publication number
CN114934671A
CN114934671A CN202210652087.5A CN202210652087A CN114934671A CN 114934671 A CN114934671 A CN 114934671A CN 202210652087 A CN202210652087 A CN 202210652087A CN 114934671 A CN114934671 A CN 114934671A
Authority
CN
China
Prior art keywords
fixed
base
groove
picture peg
fixing
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202210652087.5A
Other languages
Chinese (zh)
Other versions
CN114934671B (en
Inventor
姚磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Kangxin Construction Engineering Co ltd
Original Assignee
Anhui Kangxin Construction Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Kangxin Construction Engineering Co ltd filed Critical Anhui Kangxin Construction Engineering Co ltd
Priority to CN202210652087.5A priority Critical patent/CN114934671B/en
Publication of CN114934671A publication Critical patent/CN114934671A/en
Application granted granted Critical
Publication of CN114934671B publication Critical patent/CN114934671B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G19/00Auxiliary treatment of forms, e.g. dismantling; Cleaning devices
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/14Bracing or strutting arrangements for formwalls; Devices for aligning forms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/16Members, e.g. consoles, for attachment to the wall to support girders, beams, or the like carrying forms or moulds for floors, lintels, or transoms
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01NINVESTIGATING OR ANALYSING MATERIALS BY DETERMINING THEIR CHEMICAL OR PHYSICAL PROPERTIES
    • G01N29/00Investigating or analysing materials by the use of ultrasonic, sonic or infrasonic waves; Visualisation of the interior of objects by transmitting ultrasonic or sonic waves through the object
    • G01N29/04Analysing solids
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02ATECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE
    • Y02A50/00TECHNOLOGIES FOR ADAPTATION TO CLIMATE CHANGE in human health protection, e.g. against extreme weather

Abstract

The invention discloses a fixed wallboard device for building construction pouring and an installation method thereof, relates to the technical field of building construction, and aims to solve the problem that the existing fixed wallboard device for building construction pouring is time-consuming and labor-consuming in disassembly work after pouring is finished due to inconvenience in positioning, installation and disassembly. Including unable adjustment base, unable adjustment base's upper end is provided with the connecting rod, the upper end of connecting rod is provided with the bracing piece, the upper end of bracing piece is provided with the backup pad, the inboard of backup pad is provided with anti-skidding contact pad, picture peg fixing end face, and it sets up unable adjustment base's up end, one side of picture peg fixing end face is provided with the slot, unable adjustment base's inside is provided with the bolt mounting groove, and sealed end, it sets up unable adjustment base's inboard, both sides are provided with splice plate, concatenation picture peg respectively around unable adjustment base, the inside of splice plate is provided with the splice groove.

Description

Fixed wallboard device for house construction pouring and mounting method thereof
Technical Field
The invention relates to the technical field of building construction, in particular to a fixed wallboard device for building construction pouring and an installation method thereof.
Background
In traditional cast wall panel devices, as application number: 202110659073.1, respectively; the name is as follows: a steel template hoisting device for an assembly type building cast-in-place wallboard. The device includes: the device comprises a wire rope, a base, universal wheels, a support rod, a hook plate, an electric drive module A, a movable pulley A, a winding wheel, an electric drive module B and the like, wherein the support rod is hinged to the base provided with four universal wheels, and the hook plate supported by a steel bar frame in a cast-in-place wall body is matched on the support rod in a sliding manner along the length direction of the support rod; in the process of vertically installing the steel template, the steel template is vertically installed by fully utilizing the existing reinforcing steel bar frame as a support, and equipment is not required to be additionally arranged, so that the equipment cost is reduced. Meanwhile, the tower crane can be withdrawn after the steel template is lifted and placed on a construction floor by the tower crane, and the tower crane is not needed to participate in the whole erecting and installing process of the steel template.
However, the fixed wallboard device for building construction pouring is inconvenient to position, install and disassemble, so that the problem that the disassembly work after pouring is time-consuming and labor-consuming is caused; therefore, the existing requirements are not met, and a fixed wallboard device for house construction pouring and an installation method thereof are provided.
Disclosure of Invention
The invention aims to provide a fixed wallboard device for house construction pouring and an installation method thereof, and aims to solve the problem that the disassembly work after pouring is time-consuming and labor-consuming due to inconvenience in positioning, installation and disassembly of the conventional fixed wallboard device for house construction pouring in the background art.
In order to achieve the purpose, the invention provides the following technical scheme: a fixed wallboard device for building construction pouring comprises a fixed base, wherein a connecting rod is arranged at the upper end of the fixed base, a supporting rod is arranged at the upper end of the connecting rod, a supporting plate is arranged at the upper end of the supporting rod, the supporting plate and the supporting rod are integrally formed, an anti-skid contact pad is arranged on the inner side of the supporting plate, and the anti-skid contact pad is fixedly connected with a supporting plate bolt;
further comprising:
the plug board fixing end face is arranged on the upper end face of the fixing base and is integrally formed with the fixing base, one side of the plug board fixing end face is provided with a slot, the slot and the fixing base are integrally formed, a bolt mounting groove is formed in the fixing base, and the bolt mounting groove and the fixing base are integrally formed;
and the sealing end is arranged on the inner side of the fixed base, and the sealing end is connected with the fixed base in an adhesive manner.
Preferably, both sides are provided with splice plate, concatenation picture peg respectively around unable adjustment base, and splice plate, concatenation picture peg and unable adjustment base integrated into one piece set up, the inside of splice plate is provided with the splice groove, and splice groove and splice plate integrated into one piece set up to concatenation picture peg and splice groove draw-in groove fixed connection.
Preferably, the lower extreme of bracing piece is provided with the cross connector, and cross connector and bracing piece integrated into one piece set up to cross connector and connecting rod draw-in groove fixed connection.
Preferably, an ultrasonic flaw detector is arranged inside the supporting plate.
Preferably, the lower extreme of connecting rod is provided with picture peg connection base, and picture peg connection base and connecting rod integrated into one piece set up to the lower terminal surface and the chute draw-in groove fixed connection of picture peg connection base, one side that the base was connected to the picture peg is provided with the picture peg, and picture peg connection base integrated into one piece set up, and picture peg and slot draw-in groove fixed connection.
Preferably, one side of sealed end is provided with the porous rubber membrane, the inside of sealed end is provided with the elasticity breather pipe, one side of elasticity breather pipe is provided with the porous rubber layer, one side of porous rubber layer is provided with the blotter.
Preferably, the upper end face of the inserting plate fixing end face is provided with a chute, and the chute and the fixing base are integrally formed.
Preferably, a fixing bolt is arranged in the bolt mounting groove and fixedly connected with the inner wall of the fixing base in a threaded manner.
Preferably, the use method of the fixed wall panel device for house construction pouring comprises the following steps:
the method comprises the following steps: firstly, determining the installation position of the device, tightly attaching a fixed base to a fixed wallboard to screw a fixing bolt, fixing the fixed base to the outer side of the fixed wallboard, inserting a plug board of a connecting rod into the slot to fix, wherein the slot improves the connection stability before the connecting base is connected with the plug board, and then fixedly connecting a cross connector at the lower end of a supporting rod with a connecting rod clamping slot, so that the whole device can be completely installed;
step two: the two fixed bases are installed side by side, and the splicing spiles are inserted into the splicing grooves in the splicing plates to facilitate the side by side fixed installation, so that the supporting strength of the device on the fixed wallboard is improved, and the problem that the existing fixed wallboard device for building construction and pouring wastes time and labor due to the inconvenience in positioning, installation and disassembly is solved;
step three: when unable adjustment base hugs closely fixed wallboard, porous rubber layer and cushion discharge its inside air from the porous rubber membrane along elasticity breather pipe, have greatly improved the inseparable degree of installation between unable adjustment base and the fixed wallboard.
Compared with the prior art, the invention has the beneficial effects that:
1. according to the invention, through the arrangement of the fixed base, the connecting rod, the supporting plate, the anti-skidding contact pad, the bolt mounting groove, the fixed bolt, the inserting plate fixed end face, the chute, the slot and the cross connector, the installation position of the device is determined firstly, the fixed base is tightly attached to the fixed wall plate to screw the fixed bolt, the fixed base is fixed on the outer side of the fixed wall plate, then the inserting plate of the connecting rod is inserted into the slot to be fixed, the chute improves the connection stability before the connecting base is connected with the inserting plate, then the cross connector at the lower end of the supporting rod is fixedly connected with the connecting rod clamping groove, the whole device can be installed completely, the supporting plate is used for supporting the fixed wall plate, and the ultrasonic flaw detector detects concrete on the inner side of the fixed wall plate in an ultrasonic mode, so that the fastening practicability and the convenient detection performance of the device are greatly improved.
2. Through the setting of splice plate, splice groove, concatenation picture peg, with two unable adjustment base installation side by side, the concatenation picture peg inserts the inside splice groove of splice plate and is convenient for fixed mounting side by side to improved the device and to the support dynamics of fixed wall board, solved current house construction and pour and use fixed wall board device, because its location, installation, disassemble inconvenient, cause the dismantlement work after pouring the completion problem that wastes time and energy.
3. Through the setting of sealed end, when unable adjustment base hugs closely fixed wallboard, porous rubber layer and buffer pad discharge its inside air from the porous rubber membrane along elastic vent pipe, have greatly improved the inseparable degree of installation between unable adjustment base and the fixed wallboard.
Drawings
FIG. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is an enlarged view of the fixing base structure of the present invention;
FIG. 3 is a side view of the support plate of the present invention;
FIG. 4 is a side view of the fixing base of the present invention;
FIG. 5 is an enlarged view of the structure of part A of the present invention;
FIG. 6 is a schematic view of the internal structure of the sealing end of the present invention;
in the figure: 1. a fixed base; 2. a connecting rod; 3. a support bar; 4. a support plate; 5. an anti-slip contact pad; 6. a bolt mounting groove; 7. fixing the bolt; 8. the end surface is fixed by the inserting plate; 9. a chute; 10. inserting slots; 11. sealing the end; 12. splicing plates; 13. splicing grooves; 14. splicing the plugboards; 15. the inserting plate is connected with the base; 16. inserting plates; 17. a cross connector; 18. an ultrasonic flaw detector; 19. a porous rubber film; 20. an elastic vent pipe; 21. a porous rubber layer; 22. a cushion pad.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments.
Further to fig. 1-6, an embodiment of the present invention provides: a fixed wallboard device for building construction pouring comprises a fixed base 1, wherein the upper end of the fixed base 1 is provided with a connecting rod 2, the upper end of the connecting rod 2 is provided with a supporting rod 3, the upper end of the supporting rod 3 is provided with a supporting plate 4, the supporting plate 4 and the supporting rod 3 are integrally formed, the inner side of the supporting plate 4 is provided with an anti-skidding contact pad 5, and the anti-skidding contact pad 5 is fixedly connected with the supporting plate 4 through a bolt;
further comprising:
the plug board fixing end face 8 is arranged on the upper end face of the fixing base 1, the plug board fixing end face 8 and the fixing base 1 are integrally formed, a slot 10 is formed in one side of the plug board fixing end face 8, the slot 10 and the fixing base 1 are integrally formed, a bolt mounting groove 6 is formed in the fixing base 1, and the bolt mounting groove 6 and the fixing base 1 are integrally formed;
and the sealing end 11 is arranged on the inner side of the fixed base 1, and the sealing end 11 is connected with the fixed base 1 in an adhesive manner.
Further, splice plates 12 and splice plates 14 are respectively arranged on the front side and the rear side of the fixed base 1, the splice plates 12 and the splice plates 14 are integrally formed with the fixed base 1, splice grooves 13 are formed in the splice plates 12, the splice grooves 13 and the splice plates 12 are integrally formed, and the splice plates 14 are fixedly connected with the splice grooves 13 in a clamping groove.
Further, the lower extreme of bracing piece 3 is provided with cross connector 17, and cross connector 17 sets up with bracing piece 3 integrated into one piece to cross connector 17 and 2 draw-in grooves fixed connection of connecting rod.
Further, an ultrasonic flaw detector 18 is provided inside the support plate 4.
Further, the lower extreme of connecting rod 2 is provided with picture peg connection base 15, and picture peg connection base 15 sets up with connecting rod 2 integrated into one piece to the lower terminal surface and chute 9 draw-in groove fixed connection of picture peg connection base 15, one side that base 15 was connected to the picture peg is provided with picture peg 16, and picture peg 16 sets up with picture peg connection base 15 integrated into one piece, and picture peg 16 and slot 10 draw-in groove fixed connection.
Further, a porous rubber film 19 is arranged on one side of the sealed end 11, an elastic vent pipe 20 is arranged inside the sealed end 11, a porous rubber layer 21 is arranged on one side of the elastic vent pipe 20, and a cushion pad 22 is arranged on one side of the porous rubber layer 21.
Furthermore, the upper end face of the inserting plate fixing end face 8 is provided with a chute 9, and the chute 9 and the fixing base 1 are integrally formed.
Further, the inside of the bolt mounting groove 6 is provided with a fixing bolt 7, and the fixing bolt 7 is fixedly connected with the inner wall thread of the fixing base 1.
Further, a using method of the fixed wallboard device for house construction pouring comprises the following steps:
the method comprises the following steps: firstly, determining the installation position of the device, tightly attaching the fixed base 1 to the fixed wallboard and screwing the fixed bolt 7, fixing the fixed base 1 on the outer side of the fixed wallboard, then inserting the inserting plate 16 of the connecting rod 2 into the slot 10 for fixing, improving the connection stability before the connecting base is connected with the inserting plate 15 by the chute 9, then fixedly connecting the cross-shaped connector 17 at the lower end of the supporting rod 3 with the clamping slot of the connecting rod 2, finishing the integral installation of the device, wherein the supporting plate 4 is used for supporting the fixed wallboard, and the ultrasonic flaw detector 18 detects the concrete at the inner side of the fixed wallboard in an ultrasonic mode, thereby greatly improving the practicability of the fastening of the device and the convenient detection performance;
step two: the two fixed bases 1 are installed side by side, and the splicing spiles 14 are inserted into the splicing grooves 13 in the splicing plates 12 to facilitate the side by side fixed installation, so that the supporting strength of the device on the fixed wallboard is improved, and the problem that the existing fixed wallboard device for building construction and pouring is time-consuming and labor-consuming in the disassembling work after pouring due to the inconvenience in positioning, installation and disassembling is solved;
step three: when unable adjustment base 1 hugs closely fixed wallboard, porous rubber layer 21 and cushion 22 discharge its inside air from porous rubber membrane 19 along elasticity breather pipe 20, have greatly improved the installation inseparable degree between unable adjustment base 1 and the fixed wallboard.
It will be evident to those skilled in the art that the invention is not limited to the details of the foregoing illustrative embodiments, and that the present invention may be embodied in other specific forms without departing from the spirit or essential attributes thereof. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.

Claims (9)

1. A fixed wallboard device for house construction pouring comprises a fixed base (1), wherein a connecting rod (2) is arranged at the upper end of the fixed base (1), a supporting rod (3) is arranged at the upper end of the connecting rod (2), a supporting plate (4) is arranged at the upper end of the supporting rod (3), the supporting plate (4) and the supporting rod (3) are integrally formed, an anti-skidding contact pad (5) is arranged on the inner side of the supporting plate (4), and the anti-skidding contact pad (5) is fixedly connected with the supporting plate (4) through bolts;
the method is characterized in that: further comprising:
the inserting plate fixing end face (8) is arranged on the upper end face of the fixing base (1), the inserting plate fixing end face (8) and the fixing base (1) are integrally formed, a slot (10) is formed in one side of the inserting plate fixing end face (8), the slot (10) and the fixing base (1) are integrally formed, a bolt installing groove (6) is formed in the fixing base (1), and the bolt installing groove (6) and the fixing base (1) are integrally formed;
and the sealing end (11) is arranged on the inner side of the fixed base (1), and the sealing end (11) is connected with the fixed base (1) in an adhesive manner.
2. The fixed wall panel device for house building pouring according to claim 1, wherein: splice plate (12), concatenation picture peg (14) are provided with respectively to both sides around unable adjustment base (1), and splice plate (12), concatenation picture peg (14) and unable adjustment base (1) integrated into one piece set up, the inside of splice plate (12) is provided with splice groove (13), and splice groove (13) and splice plate (12) integrated into one piece set up to concatenation picture peg (14) and splice groove (13) draw-in groove fixed connection.
3. The fixed wall panel device for house building pouring according to claim 1, wherein: the lower extreme of bracing piece (3) is provided with cross connector (17), and cross connector (17) and bracing piece (3) integrated into one piece set up to cross connector (17) and connecting rod (2) draw-in groove fixed connection.
4. The fixed wall panel device for house building pouring according to claim 1, wherein: an ultrasonic flaw detector (18) is arranged in the supporting plate (4).
5. The fixed wall panel device for house building pouring according to claim 1, wherein: the lower extreme of connecting rod (2) is provided with picture peg connection base (15), and picture peg connection base (15) and connecting rod (2) integrated into one piece setting to the lower terminal surface and chute (9) draw-in groove fixed connection of picture peg connection base (15), one side that base (15) were connected to the picture peg is provided with picture peg (16), and picture peg (16) are connected base (15) integrated into one piece setting with the picture peg to picture peg (16) and slot (10) draw-in groove fixed connection.
6. The fixed wall panel device for house building pouring according to claim 1, wherein: one side of sealed end (11) is provided with porous rubber membrane (19), the inside of sealed end (11) is provided with elasticity breather pipe (20), one side of elasticity breather pipe (20) is provided with porous rubber layer (21), one side of porous rubber layer (21) is provided with blotter (22).
7. The fixed wall panel device for house building pouring according to claim 1, wherein: the upper end face of the inserting plate fixing end face (8) is provided with a chute (9), and the chute (9) and the fixing base (1) are integrally formed.
8. The fixed wall panel device for house building pouring according to claim 1, wherein: and a fixing bolt (7) is arranged in the bolt mounting groove (6), and the fixing bolt (7) is fixedly connected with the inner wall thread of the fixing base (1).
9. A method for using a fixed wall panel device for house construction pouring, which is realized by the fixed wall panel device for house construction pouring according to any one of claims 1 to 8, and is characterized by comprising the following steps:
the method comprises the following steps: firstly, determining the installation position of the device, tightly attaching the fixed base (1) to the fixed wallboard to screw the fixing bolt (7), fixing the fixed base (1) on the outer side of the fixed wallboard, then inserting the inserting plate (16) of the connecting rod (2) into the inserting groove (10) to be fixed, improving the connection stability of the connecting groove (9) before the connecting groove and the inserting plate are connected with the base (15), then fixedly connecting the cross-shaped connector (17) at the lower end of the supporting rod (3) with the inserting groove of the connecting rod (2), finishing the integral installation of the device, supporting the supporting plate (4) to support the fixed wallboard, and detecting the concrete on the inner side of the fixed wallboard by the ultrasonic flaw detector (18) in an ultrasonic mode;
step two: the two fixed bases (1) are arranged side by side, and the splicing insertion plates (14) are inserted into the splicing grooves (13) in the splicing plates (12) to facilitate the parallel fixed installation;
step three: when the fixed base (1) is tightly attached to the fixed wall board, the porous rubber layer (21) and the buffer cushion (22) discharge air in the fixed wall board from the porous rubber film (19) along the elastic vent pipe (20).
CN202210652087.5A 2022-06-09 2022-06-09 Fixing wallboard device for building construction pouring and mounting method thereof Active CN114934671B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210652087.5A CN114934671B (en) 2022-06-09 2022-06-09 Fixing wallboard device for building construction pouring and mounting method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210652087.5A CN114934671B (en) 2022-06-09 2022-06-09 Fixing wallboard device for building construction pouring and mounting method thereof

Publications (2)

Publication Number Publication Date
CN114934671A true CN114934671A (en) 2022-08-23
CN114934671B CN114934671B (en) 2023-09-12

Family

ID=82866152

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210652087.5A Active CN114934671B (en) 2022-06-09 2022-06-09 Fixing wallboard device for building construction pouring and mounting method thereof

Country Status (1)

Country Link
CN (1) CN114934671B (en)

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06200622A (en) * 1993-01-07 1994-07-19 Junichi Sugisaka Concrete form device
WO2016115937A1 (en) * 2015-01-19 2016-07-28 刘思斌 Spliced multifunctional plastic pallet
KR200484857Y1 (en) * 2016-05-10 2017-11-03 강문형 Container house horizontality device
JP2018091018A (en) * 2016-12-01 2018-06-14 清水建設株式会社 Concrete form fixture, concrete form fixing device, concrete form, concrete form fixing method and construction method of joint
CN210976626U (en) * 2019-09-23 2020-07-10 富利建设集团有限公司 Basement outer wall unilateral formwork reinforcing apparatus
CN211899817U (en) * 2020-03-14 2020-11-10 王彦明 Novel building engineering formwork supports device
CN112031418A (en) * 2020-08-17 2020-12-04 浙江舜杰建筑集团股份有限公司 Temporary supporting device of aluminum formwork for building construction
CN212743439U (en) * 2020-06-29 2021-03-19 甘肃万得绿色建筑有限责任公司 Wall body panel fixes auxiliary device for light steel house
CN213173754U (en) * 2020-09-08 2021-05-11 马沛沛 House building's foundation ditch retaining structure
CN113353832A (en) * 2021-06-15 2021-09-07 杭州谦泰五金机械制造有限公司 Steel template hoist device of wallboard is pour to prefabricated construction now
CN214696888U (en) * 2020-12-17 2021-11-12 中煤建工集团有限公司 Wall pouring formwork supporting device

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06200622A (en) * 1993-01-07 1994-07-19 Junichi Sugisaka Concrete form device
WO2016115937A1 (en) * 2015-01-19 2016-07-28 刘思斌 Spliced multifunctional plastic pallet
KR200484857Y1 (en) * 2016-05-10 2017-11-03 강문형 Container house horizontality device
JP2018091018A (en) * 2016-12-01 2018-06-14 清水建設株式会社 Concrete form fixture, concrete form fixing device, concrete form, concrete form fixing method and construction method of joint
CN210976626U (en) * 2019-09-23 2020-07-10 富利建设集团有限公司 Basement outer wall unilateral formwork reinforcing apparatus
CN211899817U (en) * 2020-03-14 2020-11-10 王彦明 Novel building engineering formwork supports device
CN212743439U (en) * 2020-06-29 2021-03-19 甘肃万得绿色建筑有限责任公司 Wall body panel fixes auxiliary device for light steel house
CN112031418A (en) * 2020-08-17 2020-12-04 浙江舜杰建筑集团股份有限公司 Temporary supporting device of aluminum formwork for building construction
CN213173754U (en) * 2020-09-08 2021-05-11 马沛沛 House building's foundation ditch retaining structure
CN214696888U (en) * 2020-12-17 2021-11-12 中煤建工集团有限公司 Wall pouring formwork supporting device
CN113353832A (en) * 2021-06-15 2021-09-07 杭州谦泰五金机械制造有限公司 Steel template hoist device of wallboard is pour to prefabricated construction now

Also Published As

Publication number Publication date
CN114934671B (en) 2023-09-12

Similar Documents

Publication Publication Date Title
CN210767797U (en) Connecting structure of prefabricated outer wall and external scaffold
CN114934671A (en) Fixed wallboard device for house construction pouring and mounting method thereof
CN210316214U (en) Assembled steel construction building dysmorphism post
CN218449310U (en) Cable groove laying structure
CN215168080U (en) Accept template reinforcing apparatus
CN216303057U (en) Hoist device of prefabricated assembled concrete side fascia
CN210105278U (en) Straight insertion type wheel buckle type steel pipe support
CN208220977U (en) A kind of mounting rack of plant area's wind-driven generator
CN209890036U (en) Derrick structure for villa elevator
CN201971520U (en) Connection structure of a small-well elevator car wall
CN218091935U (en) Novel combined type aluminum alloy climbing frame
CN220645355U (en) Civil engineering wall body bearing structure
CN218619761U (en) Wall-attached embedded part of construction elevator
CN111254975A (en) Construction method and fixing device for pre-buried U-shaped groove of comprehensive pipe gallery
CN110729949A (en) Device convenient for mounting solar panel roof and using method thereof
CN214994963U (en) Mounting structure of assembled partition wall
CN210101443U (en) Mounting device of road surface damage collection equipment
CN213449467U (en) Repeatedly usable's building templates
CN217205379U (en) Concrete host computer discharge hopper
CN211447767U (en) Floor post-cast strip supporting back-jacking structure and template structure thereof
CN212534682U (en) Curtain installation is with dismantling connecting piece
CN219842270U (en) Horizontal testing machine for steel wire rope detection
CN220335917U (en) Install elevator foundation ditch reinforcing apparatus additional
CN211589881U (en) Fixing device for automobile bearing seat
CN217602186U (en) Safety protection frame suitable for limit construction is faced to super high-rise building

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant