CN114704288A - A shock attenuation is from restoring to throne tunnel structure for broken area of fault - Google Patents
A shock attenuation is from restoring to throne tunnel structure for broken area of fault Download PDFInfo
- Publication number
- CN114704288A CN114704288A CN202210539652.7A CN202210539652A CN114704288A CN 114704288 A CN114704288 A CN 114704288A CN 202210539652 A CN202210539652 A CN 202210539652A CN 114704288 A CN114704288 A CN 114704288A
- Authority
- CN
- China
- Prior art keywords
- reset
- elastic
- shock
- layer
- fault
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
- 230000035939 shock Effects 0.000 title claims abstract description 20
- 238000013016 damping Methods 0.000 claims abstract description 28
- 238000009412 basement excavation Methods 0.000 claims abstract description 17
- 238000010521 absorption reaction Methods 0.000 claims abstract description 15
- 229910001285 shape-memory alloy Inorganic materials 0.000 claims abstract description 15
- 239000011435 rock Substances 0.000 claims abstract description 7
- 229910000831 Steel Inorganic materials 0.000 claims description 12
- 239000010959 steel Substances 0.000 claims description 12
- 238000005096 rolling process Methods 0.000 claims description 9
- 239000004567 concrete Substances 0.000 claims description 6
- 239000000463 material Substances 0.000 claims description 3
- 230000006870 function Effects 0.000 abstract description 3
- 239000011359 shock absorbing material Substances 0.000 abstract description 3
- 230000008878 coupling Effects 0.000 abstract 1
- 238000010168 coupling process Methods 0.000 abstract 1
- 238000005859 coupling reaction Methods 0.000 abstract 1
- 239000010410 layer Substances 0.000 description 67
- 238000010586 diagram Methods 0.000 description 6
- 230000000694 effects Effects 0.000 description 6
- 230000008439 repair process Effects 0.000 description 6
- 238000010276 construction Methods 0.000 description 5
- 238000006073 displacement reaction Methods 0.000 description 5
- 238000009434 installation Methods 0.000 description 5
- 230000002427 irreversible effect Effects 0.000 description 3
- 238000000034 method Methods 0.000 description 3
- 239000004033 plastic Substances 0.000 description 3
- 230000005540 biological transmission Effects 0.000 description 2
- 239000011241 protective layer Substances 0.000 description 2
- 239000011150 reinforced concrete Substances 0.000 description 2
- 239000002689 soil Substances 0.000 description 2
- 230000004888 barrier function Effects 0.000 description 1
- 230000007812 deficiency Effects 0.000 description 1
- 230000005611 electricity Effects 0.000 description 1
- 239000011210 fiber-reinforced concrete Substances 0.000 description 1
- 230000010354 integration Effects 0.000 description 1
- 238000002955 isolation Methods 0.000 description 1
- 230000021715 photosynthesis, light harvesting Effects 0.000 description 1
- 239000002986 polymer concrete Substances 0.000 description 1
- 239000011148 porous material Substances 0.000 description 1
- 230000008569 process Effects 0.000 description 1
- 239000011378 shotcrete Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/003—Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
-
- E—FIXED CONSTRUCTIONS
- E21—EARTH OR ROCK DRILLING; MINING
- E21D—SHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
- E21D11/00—Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
- E21D11/04—Lining with building materials
- E21D11/10—Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Architecture (AREA)
- Structural Engineering (AREA)
- Civil Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Geochemistry & Mineralogy (AREA)
- Geology (AREA)
- Lining And Supports For Tunnels (AREA)
Abstract
Description
技术领域technical field
本发明属于隧道施工领域,具体涉及一种用于断层破碎带中的且具有减震自复位功能的隧道结构。The invention belongs to the field of tunnel construction, and in particular relates to a tunnel structure which is used in a fault crush zone and has the function of shock absorption and self-reset.
背景技术Background technique
现有的隧道支护结构一般包括初衬和二衬,初衬是在开挖隧道后,通过打锚杆、挂网、喷射混凝土等手段形成的初期支护,此初期支护主要利用围岩强度形成支护;二衬则是用钢筋混凝土在初衬内部形成一个完整的钢筋混凝土结构。The existing tunnel support structure generally includes primary lining and secondary lining. The primary lining is the initial support formed by bolting, hanging nets, shotcrete and other means after the tunnel is excavated. This initial support mainly uses the surrounding rock. The strength forms support; the secondary lining uses reinforced concrete to form a complete reinforced concrete structure inside the primary lining.
当隧道穿越断层或者破碎带时,由于断层或破碎带处的围岩本身很破碎、强度很低,容易发生大变形。隧道穿越活动断层时,若无相应工程措施应对,活动断层的错动,尤其是大位移错动,会造成隧道结构的严重破损,严重威胁行车及生命财产安全,也使得救援及灾后修复工作难以进行。因此,解决大位移活动断层错动对隧道结构的严重威胁,是隧道工程建设的重大技术难题。When a tunnel passes through a fault or broken zone, the surrounding rock at the fault or broken zone is very broken and has low strength, and is prone to large deformation. When the tunnel crosses the active fault, if there is no corresponding engineering measures to deal with it, the dislocation of the active fault, especially the large displacement dislocation, will cause serious damage to the tunnel structure, seriously threaten the safety of traffic and life and property, and also make rescue and post-disaster repair work difficult. conduct. Therefore, solving the serious threat of large displacement active fault dislocation to the tunnel structure is a major technical problem in tunnel engineering construction.
在跨断层隧道的抗震及抗断方面,目前主要采取以下几种措施:(1)改善隧道衬砌材料的力学特性来提升结构的抗震性能,如采用钢纤维混凝土来增加阻尼,采用聚合物混凝土来降低刚度等;(2)设置减震缝,即减小衬砌节段长度,使断层错动时破坏集中于接缝处,而保证衬砌的整体性能;(3)根据断层可能的错动量,扩大隧道断面尺寸,在外衬和内衬之间填充多孔材料,通过外衬和内衬之间的间隙抵消断层错动影响,但超挖尺寸会受限于经济因素。In terms of seismic resistance and fracture resistance of cross-fault tunnels, the following measures are mainly taken at present: (1) Improve the mechanical properties of tunnel lining materials to improve the seismic performance of the structure, such as using steel fiber reinforced concrete to increase damping, using polymer concrete to Reduce the stiffness, etc.; (2) Set up shock absorption joints, that is, reduce the length of the lining segment, so that the damage is concentrated at the joints when the fault is dislocated, so as to ensure the overall performance of the lining; (3) According to the possible dislocation amount of the fault, expand For the tunnel section size, the porous material is filled between the outer lining and the inner lining, and the effect of fault dislocation is offset by the gap between the outer lining and the inner lining, but the over-excavation size will be limited by economic factors.
综上所述,目前虽然也有一部分隧道采用了隔离消能设计、铰接设计、超挖设计等相关措施进行跨越活动断层带的隧道修建,但由于方式较为单一,抵抗断层错动的能力有限,不能保证断层活动情况下隧道的安全运营,断层活动后隧道的整修任务艰巨,往往要耗费大量人力物力和时间成本进行抢修,影响隧道正常通行。To sum up, although some tunnels have adopted measures such as isolation energy dissipation design, articulation design, over-excavation design and other related measures to construct tunnels across active fault zones, due to the relatively simple method, the ability to resist fault dislocation is limited and cannot be To ensure the safe operation of the tunnel under the condition of fault activity, the task of repairing the tunnel after the fault activity is arduous, and it often takes a lot of manpower, material resources and time cost for emergency repair, which affects the normal passage of the tunnel.
发明内容SUMMARY OF THE INVENTION
本发明解决了现有技术中的不足,提供了一种用于断层破碎带的减震自复位隧道结构,该隧道结构不仅具有减震抗震的功能,而且能够在强震发生后,将错位的管节进行复位,大大缩减了抢修的时间,尽快恢复隧道内通行。The invention solves the deficiencies in the prior art, and provides a shock-absorbing and self-resetting tunnel structure for a fault fracture zone. The pipe joints are reset, which greatly reduces the time for emergency repairs and restores traffic in the tunnel as soon as possible.
实现本发明上述目的所采用的技术方案为:The technical scheme adopted to realize the above-mentioned purpose of the present invention is:
一种用于断层破碎带的减震自复位隧道结构,至少包括普通段以及与断层破碎带相对应的扩挖段,所述扩挖段由外至内依次包括与围岩相接触的初衬层、由弹性减震材质填充的弹性减震层以及二衬层,所述二衬层由多个管节依次连接而成,管节与管节之间通过记忆合金弹簧连接固定;A shock-absorbing and self-resetting tunnel structure for a fault fractured zone, comprising at least a common section and an excavation section corresponding to the fault fractured zone, the expansion and excavation sections sequentially include a primary lining in contact with surrounding rock from outside to inside layer, an elastic shock-absorbing layer filled with elastic shock-absorbing material, and a second lining layer, the second lining layer is formed by connecting a plurality of tube sections in sequence, and the tube sections are connected and fixed by a memory alloy spring;
所述二衬层的底部设置有复位架,复位架的顶面与二衬层的外轮廓相贴合,复位架的底部与初衬层相接触,且复位架的底部上设置有滚动单元,复位架与初衬层之间能够相对移动;The bottom of the second lining layer is provided with a reset frame, the top surface of the reset frame is fitted with the outer contour of the second lining layer, the bottom of the reset frame is in contact with the primary lining layer, and the bottom of the reset frame is provided with a rolling unit, Relative movement between the reset frame and the primary lining layer;
所述复位架的两侧面与初衬层的内壁之间横向设置有复位弹性臂,复位弹性臂中设置有用于减震的弹性阻尼杆以及用于复位的电动推杆,复位弹性臂的底端固定于初衬层的内壁上,复位弹性臂的顶端铰接于复位架的侧面。A reset elastic arm is arranged laterally between the two sides of the reset frame and the inner wall of the primary lining layer, and the reset elastic arm is provided with an elastic damping rod for shock absorption and an electric push rod for reset, and the bottom end of the reset elastic arm is provided with It is fixed on the inner wall of the primary lining layer, and the top of the reset elastic arm is hinged to the side of the reset frame.
所述复位弹性臂沿隧道行进方向均匀设置,且每一个管片对应的复位架的左右两侧均对应设置有复位弹性臂。The reset elastic arms are evenly arranged along the traveling direction of the tunnel, and reset elastic arms are correspondingly provided on the left and right sides of the reset frame corresponding to each segment.
所述复位弹性臂包括:The reset elastic arm includes:
相互平行设置的底板、层板以及顶板,层板中的中部设置有通道;The bottom plate, the layer plate and the top plate are arranged parallel to each other, and the middle part of the layer plate is provided with a channel;
安装于顶板上方的用于连接复位架的铰接座;The hinge seat installed above the top plate for connecting the reset frame;
设置于顶板和层板之间的多根阻尼杆,阻尼杆的顶部与顶板固定,阻尼杆的底部与层板固定,顶板和层板之间的间距弹性可变;A plurality of damping rods arranged between the top plate and the layer plate, the top of the damping rod is fixed to the top plate, the bottom of the damping rod is fixed to the layer plate, and the spacing between the top plate and the layer plate is elastically variable;
连接于底板与层板之间将底板与层板相固定的连接杆;The connecting rod is connected between the bottom plate and the layer plate to fix the bottom plate and the layer plate;
固定于底板上的电动推杆,电动推杆的伸缩杆从层板上的通道内伸出,且能够上下伸缩。The electric push rod is fixed on the bottom plate, and the telescopic rod of the electric push rod protrudes from the channel on the floor plate and can be stretched up and down.
所述阻尼杆设置有四根,四根阻尼杆分布在层板及顶板的四个边角处。Four damping rods are provided, and the four damping rods are distributed at the four corners of the layer plate and the top plate.
所述电动推杆为蜗轮蜗杆式电动推杆。The electric push rod is a worm gear type electric push rod.
所述弹性减震层中采用弹性橡胶棒填充或者采用弹性混凝土浇筑。The elastic damping layer is filled with elastic rubber rods or poured with elastic concrete.
所述管节的端面上均匀分布有用于安装固定记忆合金弹簧的安装孔,所述安装孔沿径向朝内延伸至二衬层的内壁处;不同的管节上所设置的安装孔的位置相同。Mounting holes for installing and fixing memory alloy springs are evenly distributed on the end face of the pipe section, and the mounting holes extend radially inward to the inner wall of the second lining layer; the positions of the mounting holes set on different pipe sections are same.
所述复位架为钢桁架结构,复位架底部的滚动单元采用钢滚轴,所述钢滚轴沿隧道行进方向安装。The reset frame is a steel truss structure, and the rolling unit at the bottom of the reset frame adopts a steel roller, and the steel roller is installed along the traveling direction of the tunnel.
与现有技术相比,本发明提供的用于断层破碎带的减震自复位隧道结构具有以下优点:1、本发明首先在断层破碎带区域进行扩挖,在初衬层和二衬层之间设置弹性减震层,弹性减震层能够对二衬层形成防护,对二衬层的周边形成一层弹性防护层,降低隧道所收到的地震作用侵害。2、当发生较大级别地震时,二衬的管节之间会发生不可逆的错位,本申请中通过在管节与管节之间设置记忆合金弹簧,通过记忆合金弹簧的弹性连接,尽可能的减小管节之间错位的程度。3、在地震发生后,管节与管节之间发生不可逆错位后,本申请中所设置的复位架和复位弹性臂能够尽可能的促使管节复位,大大缩减了抢修的时间,尽快恢复隧道内通行。同时,由于复位弹性臂连接在复位架上,并未直接与管节相接触,因此能够避免在地震发生时复位弹性臂将二衬管节顶破。Compared with the prior art, the shock-absorbing and self-resetting tunnel structure for the fault fracture zone provided by the present invention has the following advantages: 1. The present invention firstly carries out expansion and excavation in the fault fracture zone area, and between the primary lining layer and the secondary lining layer; An elastic damping layer is arranged between the two linings, and the elastic damping layer can form protection for the second lining layer, and form an elastic protective layer around the second lining layer, so as to reduce the earthquake damage received by the tunnel. 2. When a large-scale earthquake occurs, irreversible dislocation will occur between the tube sections of the secondary lining. In this application, memory alloy springs are arranged between the tube sections and the tube sections, and the elastic connection of the memory alloy springs is as possible as possible. to reduce the degree of misalignment between pipe sections. 3. After the earthquake occurs, after the irreversible dislocation occurs between the pipe sections, the reset frame and the reset elastic arm set in this application can promote the reset of the pipe sections as much as possible, which greatly reduces the time for emergency repairs and restores the tunnel as soon as possible. Internal access. At the same time, since the reset elastic arm is connected to the reset frame and does not directly contact the pipe section, it can be avoided that the reset elastic arm will burst the secondary lining pipe section when an earthquake occurs.
附图说明Description of drawings
图1为本发明提供的用于断层破碎带的减震自复位隧道结构的整体结构示意图;Fig. 1 is the overall structural schematic diagram of the shock-absorbing self-resetting tunnel structure for fault fracture zone provided by the present invention;
图2为扩挖段的断面结构图;Figure 2 is a cross-sectional structural diagram of the excavation section;
图3为复位架的结构示意图;Fig. 3 is the structural representation of the reset frame;
图4为复位弹性臂的结构示意图;4 is a schematic structural diagram of a reset elastic arm;
图5为复位弹性臂在进行复位时的工作示意图;Fig. 5 is the working schematic diagram of the reset elastic arm when it is reset;
图6为实施例中所提供的减震自复位隧道结构的精细化有限元模型图;6 is a refined finite element model diagram of the shock-absorbing self-resetting tunnel structure provided in the embodiment;
图7为实施例中所提供的减震自复位隧道结构的精细化有限元模型透视图;7 is a perspective view of a refined finite element model of the shock-absorbing self-resetting tunnel structure provided in the embodiment;
图8为实施例中所提供的减震自复位隧道结构的精细化模型图(含初衬层、二衬层和减震层);FIG. 8 is a refined model diagram of the shock-absorbing self-resetting tunnel structure provided in the embodiment (including the primary lining layer, the secondary lining layer and the shock-absorbing layer);
图中:1-普通段,2-扩挖段,3-围岩,4-初衬层,5-弹性减震层,6-二衬层,7-安装孔,8-管节,9-复位架,10-滚动单元,11-复位弹性臂,12-底板,13-层板,14-顶板,15-铰接座,16-阻尼杆,17-连接杆,18-电动推杆,19-伸缩杆。In the picture: 1- Ordinary section, 2- Excavation section, 3- Surrounding rock, 4- Primary lining, 5- Elastic shock absorption layer, 6- Second lining, 7- Mounting hole, 8- Pipe section, 9- Reset frame, 10-rolling unit, 11-reset elastic arm, 12-bottom plate, 13-layer plate, 14-top plate, 15-articulated seat, 16-damping rod, 17-connecting rod, 18-electric push rod, 19- Telescopic rod.
具体实施方式Detailed ways
下面结合附图和具体实施例对本发明做详细具体的说明,但是本发明的保护范围并不局限于以下实施例。The present invention will be described in detail below with reference to the accompanying drawings and specific embodiments, but the protection scope of the present invention is not limited to the following embodiments.
本发明提供了一种用于断层破碎带的减震自复位隧道结构,其整体结构如图1所示,断层破碎带的两侧为正常的山体,此处采用普通的隧道结构施工即可,即为图1中所示的普通段1;在断层破碎带区域要进行扩挖,即为扩挖段2,扩挖段的断面结构如图2所示:所述扩挖段由外至内依次包括与围岩3相接触的初衬层4、由弹性减震材质填充的弹性减震层5以及二衬层6,所述弹性减震层中采用弹性橡胶棒填充或者采用弹性混凝土浇筑。所述二衬层由多个管节8依次连接而成,所述管节的端面上均匀分布有用于安装固定记忆合金弹簧的安装孔7,所述安装孔沿径向朝内延伸至二衬层的内壁处;不同的管节上所设置的安装孔的位置相同,管节与管节之间通过记忆合金弹簧连接固定。The present invention provides a shock-absorbing and self-resetting tunnel structure for a fault fractured zone. The overall structure is shown in Figure 1. The two sides of the fault fractured zone are normal mountains, and ordinary tunnel structures can be used here for construction. That is the common section 1 shown in Figure 1; in the area of the fault broken zone, the expansion and excavation are to be carried out, that is, the expansion and
所述二衬层的底部设置有复位架9,其结构如图3所示(图中复位架是由多节拼装而成),复位架的顶面与二衬层的外轮廓相贴合,复位架的底部与初衬层相接触,且复位架的底部上设置有滚动单元10,复位架与初衬层之间能够相对移动;所述复位架为钢桁架结构,复位架底部的滚动单元采用钢滚轴,所述钢滚轴沿隧道行进方向安装。The bottom of the two lining layers is provided with a
所述复位架的两侧面与初衬层的内壁之间横向设置有复位弹性臂11,其结构如图4所示,复位弹性臂中设置有用于减震的弹性阻尼杆以及用于复位的电动推杆,复位弹性臂的底端固定于初衬层的内壁上,复位弹性臂的顶端铰接于复位架的侧面。所述复位弹性臂沿隧道行进方向均匀设置,且每一个管片对应的复位架的左右两侧均对应设置有复位弹性臂。所述复位弹性臂包括:相互平行设置的底板12、层板13以及顶板14,层板中的中部设置有通道;安装于顶板上方的用于连接复位架的铰接座15;设置于顶板和层板之间的四根阻尼杆16,阻尼杆的顶部与顶板固定,阻尼杆的底部与层板固定,顶板和层板之间的间距弹性可变,四根阻尼杆分布在层板及顶板的四个边角处;连接于底板与层板之间将底板与层板相固定的连接杆17;固定于底板上的电动推杆18,电动推杆的伸缩杆19从层板上的通道内伸出,且能够上下伸缩,所述电动推杆为蜗轮蜗杆式电动推杆,能够获得很大的传动比。A reset
在施工过程中,当隧道掘进至断层破碎带时,首先进行扩挖,扩挖及初衬施工完毕后,并且与扩挖段相连接的普通段的二衬已经施工完毕的前提下,进行管节的安装,管节采用逐节施工的方式。扩挖段的首个管节安装前,先放置复位架,复位架放置在扩挖段的初衬层上,然后调整复位架的位置后,再来安装复位弹性臂。复位弹性臂的一端与复位架的侧壁铰接,复位弹性臂的另一端与初衬层固定,复位弹性臂的电力线路接口从管节之间的间隙内引出。复位弹性臂安装完毕后即安装首个管节,管节通过隧道预制拱墙衬砌分块式运安一体机从隧道外运入,将组成管节的各管片拼装成环并放置在复位架上。接着再来对管节与初衬层之间的弹性减震层进行施工,通过填塞弹性橡胶棒或者浇筑弹性混凝土进行充填(复位架与复位弹性臂的上方设置有阻隔层将两者与弹性减震层隔开)。最后再安装记忆合金弹簧,工作人员进入管节内部将记忆合金弹簧由内壁处的开口塞入至安装孔的底部,然后通过压块和螺栓将记忆合金弹簧的端部固定至安装孔内。至此即完成扩挖段首节管节的安装,然后循环此步骤进行下一管节的安装即可。During the construction process, when the tunnel is excavated to the fault fracture zone, the expansion and excavation shall be carried out first. After the expansion and initial lining construction is completed, and the secondary lining of the ordinary section connected with the expansion and excavation section has been completed, the pipeline shall be excavated. For the installation of sections, the pipe sections shall be constructed section by section. Before the first pipe section of the excavation section is installed, place the reset frame first, and the reset frame is placed on the initial lining layer of the excavation section, and then adjust the position of the reset frame, and then install the reset elastic arm. One end of the reset elastic arm is hinged with the side wall of the reset frame, the other end of the reset elastic arm is fixed with the initial lining layer, and the power line interface of the reset elastic arm is drawn out from the gap between the pipe sections. After the reset elastic arm is installed, the first pipe section is installed. The pipe section is transported from outside the tunnel through the tunnel prefabricated arch wall lining block transport and safety integrated machine, and the segments that make up the pipe section are assembled into rings and placed on the reset frame superior. Next, construct the elastic shock-absorbing layer between the pipe section and the primary lining layer, and fill it by filling elastic rubber rods or pouring elastic concrete (a barrier layer is set above the reset frame and the reset elastic arm to connect the two with the elastic shock-absorbing layer. separate layers). Finally, the memory alloy spring is installed. The staff enters the pipe section and inserts the memory alloy spring from the opening at the inner wall to the bottom of the installation hole, and then fixes the end of the memory alloy spring into the installation hole through the pressing block and bolt. At this point, the installation of the first pipe section of the excavation section is completed, and then repeat this step to install the next pipe section.
本发明提供的用于断层破碎带的减震自复位隧道结构的工作原理如下:当发生轻微地震时,断层破碎带产生轻微位移,此时在初衬层和二衬层之间设置弹性减震层,弹性减震层能够对二衬层形成防护,对二衬层的周边形成一层弹性防护层,降低隧道所受到的地震侵害,使隧道的结构基本上不受到破坏。当发生中大级别的地震时,断层破碎带产生较大位移,这会导致二衬管节之间会发生较大的晃动,本申请中通过在管节与管节之间设置记忆合金弹簧,通过记忆合金弹簧的弹性连接,尽可能的减小管节之间错位的程度。同时,管节的移动错位会导致复位架也随管节一起错位,复位架两侧所设置的复位弹性臂(常态下复位弹性臂的伸缩杆处于收缩状态,如图4所示)中的阻尼杆此时能够发挥阻尼作用,尽量减缓管节所受到的晃动。地震发生后,管节与管节之间发生不可逆错位,此时根据各管节在横向上错位的程度,控制复位弹性臂中的电动推杆启动(若管节向左侧错位说明左侧的复位弹性臂受到了挤压,启动复位架左侧的电动推杆,同理向右错位则启动复位架右侧的电动推杆),电动推杆由于为蜗轮蜗杆式电动推杆,能够获得很大的传动比,再加上复位架底部沿隧道行进方向安装安装的钢滚轴,能够通过电动推杆中伸缩杆的缓慢伸出,逐步的将管节缓慢复位(如图5所示),从而大大缩减了抢修的时间,尽快恢复隧道内基本通行(保证生命救援线路的尽快打通)。若地震将隧道内的电力设施破坏,在隧道抢修时可通过外带发电机进行发电,对具体的复位弹性臂进行供电。The working principle of the shock-absorbing self-resetting tunnel structure for the fault fracture zone provided by the present invention is as follows: when a slight earthquake occurs, the fault fracture zone is slightly displaced, and at this time, elastic shock absorption is arranged between the primary lining layer and the secondary lining layer. The elastic shock absorption layer can form protection for the second lining layer, and form an elastic protective layer around the second lining layer, which reduces the earthquake damage to the tunnel, so that the structure of the tunnel is basically not damaged. When a medium-to-large earthquake occurs, the fault fracture zone will have a large displacement, which will lead to a large sway between the two-liner pipe sections. In this application, memory alloy springs are arranged between the pipe sections. Through the elastic connection of the memory alloy spring, the degree of misalignment between the tube sections is reduced as much as possible. At the same time, the displacement of the pipe section will cause the reset frame to be dislocated together with the pipe section, and the damping in the reset elastic arms set on both sides of the reset frame (the telescopic rod of the reset elastic arm is in a retracted state under normal conditions, as shown in Figure 4) The rod can now act as a damper to minimize the shaking experienced by the tube section. After the earthquake, irreversible dislocation occurs between the pipe sections. At this time, according to the degree of lateral dislocation of each pipe section, the electric push rod in the reset elastic arm is controlled to start (if the pipe section is dislocated to the left, it means that the The reset elastic arm is squeezed, and the electric push rod on the left side of the reset frame is activated. Similarly, if it is displaced to the right, the electric push rod on the right side of the reset frame is activated. The large transmission ratio, coupled with the steel roller installed at the bottom of the reset frame along the traveling direction of the tunnel, can gradually reset the pipe section slowly through the slow extension of the telescopic rod in the electric push rod (as shown in Figure 5). In this way, the time for emergency repairs is greatly reduced, and the basic traffic in the tunnel can be restored as soon as possible (to ensure that the life rescue line is opened as soon as possible). If the earthquake damages the power facilities in the tunnel, the external generator can be used to generate electricity during the emergency repair of the tunnel to supply power to the specific reset elastic arm.
本实施例中提供的用于断层破碎带的减震自复位隧道结构的上述效果,通过以下方式进行验证:The above-mentioned effects of the shock-absorbing self-resetting tunnel structure for the fault fracture zone provided in this embodiment are verified in the following ways:
本申请采用ABAQUS有限元软件进行断层破碎带的减震自复位隧道结构验证(该模型不包含电动推杆的复位作用),如图6、图7、图8所示。具体建模细节如下:模型分为上盘、下盘与隧道结构三个部分,其中土体、衬砌和减震层的网格类型为8节点六面体线性减缩积分单元(C3D8R),钢筋骨架的网格类型为2节点桁架单元(T3D2);土体采用摩尔-库伦弹塑性本构,钢筋与减震层采用经典的塑性本构,初衬及二衬采用混凝土弹塑性损伤本构(Concrete damaged plasticity),管节与管节之间的记忆合金弹簧采用弹性单元模拟。This application uses ABAQUS finite element software to verify the structure of the shock-absorbing self-resetting tunnel of the fault fracture zone (the model does not include the reset function of the electric push rod), as shown in Figure 6, Figure 7, and Figure 8. The specific modeling details are as follows: The model is divided into three parts: the upper wall, the lower wall and the tunnel structure. The mesh type of the soil, lining and shock absorption layer is 8-node hexahedral linear reduced integration element (C3D8R), and the mesh of the steel skeleton The lattice type is a 2-node truss element (T3D2); the soil adopts the Moore-Coulomb elasto-plastic constitutive, the steel bar and the damping layer adopt the classical plastic constitutive, and the primary lining and the secondary lining adopt the concrete elasto-plastic damage constitutive (Concrete damaged plasticity). ), and the memory alloy springs between the tube sections are simulated by elastic elements.
采用小、中、大震分析模型中断层破碎带隧道的管节与管节之间的错动量,并与无减震层、无记忆合计和无阻尼杆模型进行对比。具体结果如下表所示,发现采用减震自复位隧道结构后,在同等条件下管节与管节之间的错动量仅分别为无任何减震措施情况下的24.5%,18.7%和16.5%,随着震级的增大减震效果更加明显(且在无电动推杆复位的情况下的效果)。Small, medium and large earthquake models are used to analyze the dislocation momentum between the tube and tube sections of the tunnel in the fractured zone of the fault layer, and compared with the models without shock absorption layer, memory summation and damping rod. The specific results are shown in the table below. It is found that after adopting the shock-absorbing and self-resetting tunnel structure, the dislocation amount between the tube sections under the same conditions is only 24.5%, 18.7% and 16.5% of those without any shock absorption measures, respectively. , the shock absorption effect is more obvious as the magnitude increases (and the effect without electric push rod reset).
不同工况下隧道管节之间错动量值(单位:mm)Displacement value between tunnel joints under different working conditions (unit: mm)
Claims (8)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210539652.7A CN114704288B (en) | 2022-05-18 | 2022-05-18 | A shock attenuation is from restoring to throne tunnel structure for broken area of fault |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202210539652.7A CN114704288B (en) | 2022-05-18 | 2022-05-18 | A shock attenuation is from restoring to throne tunnel structure for broken area of fault |
Publications (2)
Publication Number | Publication Date |
---|---|
CN114704288A true CN114704288A (en) | 2022-07-05 |
CN114704288B CN114704288B (en) | 2022-11-29 |
Family
ID=82177441
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202210539652.7A Active CN114704288B (en) | 2022-05-18 | 2022-05-18 | A shock attenuation is from restoring to throne tunnel structure for broken area of fault |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN114704288B (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116006213A (en) * | 2023-01-10 | 2023-04-25 | 广州大学 | Seismic isolation structure and construction method of a shield tunnel |
Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000204891A (en) * | 1999-01-19 | 2000-07-25 | Toda Constr Co Ltd | Tunnel structure passing through a fault |
JP2006233626A (en) * | 2005-02-25 | 2006-09-07 | National Institute Of Advanced Industrial & Technology | Tunnel structure |
CN103195447A (en) * | 2013-04-08 | 2013-07-10 | 西南交通大学 | Construction method of quake-proof tunnel structure penetrating through flexible fracture zone |
CN106522977A (en) * | 2016-10-26 | 2017-03-22 | 西南交通大学 | Multistage tunnel shock absorption structure penetrating through active fault |
CN109681231A (en) * | 2019-01-24 | 2019-04-26 | 中铁第四勘察设计院集团有限公司 | A kind of active fault section Tunneling by mining method displacement adaptive structure and installation method |
CN110159314A (en) * | 2019-05-07 | 2019-08-23 | 山东大学 | A kind of tunnel flexibility ring type support system suitable for passing through active breaking belt |
CN112632837A (en) * | 2020-12-31 | 2021-04-09 | 华中科技大学 | Method for determining longitudinal seismic resistance value of underground structure |
CN213175663U (en) * | 2020-10-10 | 2021-05-11 | 中国科学院武汉岩土力学研究所 | Shock-absorbing structure and tunnel lining structure of crossing active fault tunnel |
CN113153356A (en) * | 2021-04-28 | 2021-07-23 | 中铁第四勘察设计院集团有限公司 | Anti-fault-breaking structure of drilling and blasting tunnel for crossing active fault |
CN215860202U (en) * | 2021-07-28 | 2022-02-18 | 中国科学院武汉岩土力学研究所 | An anti-fault structure for tunnels across active faults |
-
2022
- 2022-05-18 CN CN202210539652.7A patent/CN114704288B/en active Active
Patent Citations (10)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2000204891A (en) * | 1999-01-19 | 2000-07-25 | Toda Constr Co Ltd | Tunnel structure passing through a fault |
JP2006233626A (en) * | 2005-02-25 | 2006-09-07 | National Institute Of Advanced Industrial & Technology | Tunnel structure |
CN103195447A (en) * | 2013-04-08 | 2013-07-10 | 西南交通大学 | Construction method of quake-proof tunnel structure penetrating through flexible fracture zone |
CN106522977A (en) * | 2016-10-26 | 2017-03-22 | 西南交通大学 | Multistage tunnel shock absorption structure penetrating through active fault |
CN109681231A (en) * | 2019-01-24 | 2019-04-26 | 中铁第四勘察设计院集团有限公司 | A kind of active fault section Tunneling by mining method displacement adaptive structure and installation method |
CN110159314A (en) * | 2019-05-07 | 2019-08-23 | 山东大学 | A kind of tunnel flexibility ring type support system suitable for passing through active breaking belt |
CN213175663U (en) * | 2020-10-10 | 2021-05-11 | 中国科学院武汉岩土力学研究所 | Shock-absorbing structure and tunnel lining structure of crossing active fault tunnel |
CN112632837A (en) * | 2020-12-31 | 2021-04-09 | 华中科技大学 | Method for determining longitudinal seismic resistance value of underground structure |
CN113153356A (en) * | 2021-04-28 | 2021-07-23 | 中铁第四勘察设计院集团有限公司 | Anti-fault-breaking structure of drilling and blasting tunnel for crossing active fault |
CN215860202U (en) * | 2021-07-28 | 2022-02-18 | 中国科学院武汉岩土力学研究所 | An anti-fault structure for tunnels across active faults |
Non-Patent Citations (1)
Title |
---|
方林等: "穿越断层破碎带隧道减震措施研究", 《公路》 * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN116006213A (en) * | 2023-01-10 | 2023-04-25 | 广州大学 | Seismic isolation structure and construction method of a shield tunnel |
Also Published As
Publication number | Publication date |
---|---|
CN114704288B (en) | 2022-11-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110939457B (en) | A kind of inflatable shock-absorbing tunnel lining structure and construction method | |
CN106522977A (en) | Multistage tunnel shock absorption structure penetrating through active fault | |
CN103195447A (en) | Construction method of quake-proof tunnel structure penetrating through flexible fracture zone | |
CN112324459B (en) | Yielding lining structure suitable for crossing fault and soft rock large-deformation section | |
CN105019918B (en) | A kind of underwater shield tunneling structure anti-shock methods and device | |
CN104153792B (en) | A kind of energy-absorbing being applicable to weak broken wall rock allows presses tunnel support system and method | |
CN110836120B (en) | Tunnel lining structure and construction method suitable for self-monitoring adjustment across active faults | |
CN106089235B (en) | A kind of water-conveyance tunnel error resilience for passing through large-scale activity fracture belt is broken structure | |
CN105735503B (en) | Power consumption steel column system with replaceable mild steel damper | |
CN114704288B (en) | A shock attenuation is from restoring to throne tunnel structure for broken area of fault | |
CN114542122A (en) | Energy-absorbing yielding tunnel primary support structure system and construction method thereof | |
CN110043278A (en) | A kind of anti-type mountain tunnel structure and its construction method of breaking of classification for passing through active breaking belt | |
CN110159315B (en) | Assembled semi-movable connecting tunnel suitable for crossing fault fracture zone and method | |
CN110043296B (en) | Freezing-resistant drainage plate suitable for cold region tunnel and construction method thereof | |
CN118128559A (en) | Adaptive anti-dislocation tunnel type based on variable stiffness induction and construction method | |
CN106194215A (en) | A kind of Tunnel dynamic across the anti-stick slide of active fault and method of construction thereof | |
CN114542105A (en) | Implementation method suitable for lining energy dissipation and shock absorption structure of tunnel in earthquake high-intensity area | |
CN108951703A (en) | Assembled underground pipe gallery and its construction method | |
CN118933935A (en) | Flexible initial support structure and construction method for tunnels in high-energy geological environments | |
CN111779499B (en) | Construction method of tunnel structure | |
CN206706555U (en) | Pier is waved without the double interfaces of bearing Self-resetting bridge | |
CN216588620U (en) | Tunnel lining support and tunnel penetrating through active fault fracture zone | |
CN211598678U (en) | Composite supporting device for tunnel of ground fracture section | |
CN116517022A (en) | A high-resistance comprehensive pipe gallery in a strong earthquake area and its manufacturing method | |
CN210033452U (en) | Hierarchical anti-fracture type mountain tunnel structure passing through movable fracture zone |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |