CN106522977A - Multistage tunnel shock absorption structure penetrating through active fault - Google Patents

Multistage tunnel shock absorption structure penetrating through active fault Download PDF

Info

Publication number
CN106522977A
CN106522977A CN201610949404.4A CN201610949404A CN106522977A CN 106522977 A CN106522977 A CN 106522977A CN 201610949404 A CN201610949404 A CN 201610949404A CN 106522977 A CN106522977 A CN 106522977A
Authority
CN
China
Prior art keywords
tunnel
fault
lining
section
active fault
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201610949404.4A
Other languages
Chinese (zh)
Other versions
CN106522977B (en
Inventor
高波
周裕
王帅帅
吴冬
徐旭炜
王英学
申玉生
周佳媚
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southwest Jiaotong University
Original Assignee
Southwest Jiaotong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southwest Jiaotong University filed Critical Southwest Jiaotong University
Priority to CN201610949404.4A priority Critical patent/CN106522977B/en
Publication of CN106522977A publication Critical patent/CN106522977A/en
Application granted granted Critical
Publication of CN106522977B publication Critical patent/CN106522977B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating

Abstract

The invention discloses a multistage tunnel shock absorption structure penetrating through an active fault. The area of the tunnel cross section of a main deformation area of a fault fracture zone of a tunnel is larger than the area of the tunnel cross section of a stable section. A tunnel lining layer is of a longitudinal variable structure and is laid in a sectioned mode, and shock absorption joints formed between adjacent lining sections are connected through flexible connectors. In the fault fracture zone and the range of influence of the fault fracture zone, a surrounding rock reinforcing circle is arranged in a grouting reinforcing mode. The space between the inner wall of the surrounding rock reinforcing circle and the tunnel lining layer is filled with a deformation adjusting layer composed of light sand. By the adoption of the multistage tunnel shock absorption structure, the safety of a tunnel structure and the stability of surrounding rocks can be improved substantially; the maximum primary stress peak value and the minimum primary stress peak value of all lining parts are decreased remarkably, and the tunnel section which is possibly damaged due to tension or pressing is remarkably reduced. After diastrophism of the lining structure happens at a diastrophism surface, the surrounding rocks can be prevented from losing stability and collapsing within a wide range, and the influences of fault diastrophism on the tunnel are reduced.

Description

Pass through active fault tunnel multi-stage shock-absorbing structure
Technical field
The present invention relates to technical field of tunnel construction, specially passes through active fault tunnel multi-stage shock-absorbing structure.
Background technology
Tunnel as a kind of engineering structure for being built in underground, its stress and deform it is closely related with surrounding formation, it is existing Earthquake is investigated it has been shown that in high intensity Zone, tunnel may suffer serious earthquake.Especially for passing through active fault The tunnel of crushed zone, is acted on by fault disruption zone rock mass pressure and the active fault changing of the relative positions in strong earthquakes, and tunnel occurs in that lining Cracking, dislocation, the even overall Earthquake damages for collapsing are built, the sub- tunnel of disaster-stricken serious dragon's cave-stalactite cave such as in Wenchuan earthquake.In strong earthquakes Dynamic when occurring, the dislocation amount of active fault may increase to several meters of scope by several centimetres, and for using conventional structure form Tunnel structure shearing that the relative changing of the relative positions of tomography upper lower burrs causes is born during fault movement, directly, is extruded or is pullled Effect, so as to be subject to heavy damage.At present, it is for the tunnel of active fault crushed zone is passed through in high intensity Zone, general to adopt Longitudinal varistructure and laterally dig two kinds of measures of structure.
Longitudinal varistructure is mainly disconnected by along the longitudinally disposed a number of flexible joint in tunnel or absorbing joint, reducing Layer causes tunnel Axinlly nonuniform deformation, improves tunnel self adaptation deformability, acts on tunnel axle so as to reduce fault movement To shearing and squeezing action power, but partial cut, extruding are likely to occur at tunnel setting flexible joint and absorbing joint and are stretched Destruction, is on the one hand difficult to ensure that tunnel water proofing function, on the other hand when tomography passes through large-scale fault belt, the variable knot in longitudinal direction Structure is difficult to provide enough tunnel total bearing capacities.
Structure is laterally digged mainly by digging using transverse section in fault movement section tunnel, reserve fault movement amount, inhale Fault movement displacement is received, but section is digged and increases construction economy cost, while country rock is also weakened from bearing capacity, it is disconnected in activity Layer shearing, under squeezing action, crushed zone Instability of Rock Body may be caused, cause tunnel cannot bear crushed zone Instability of Rock Body pressure and Produce the serious earthquake such as total collapse and retention of excessive fluid.
As applied research of the damping Rotating fields in structure shock resisting is more and more, part experts and scholars are for passing through work Tomography tunnel shock-absorbing Rotating fields have carried out research.Under strong earthquake motion effect, damping floor shear stiffness is low, can reduce tunnel lining Build and the shear action between country rock, effectively reduce tunnel internal force, but for active fault tunnel is passed through under strong earthquake motion effect, mainly Acted on by fault movement and crushed zone Instability of Rock Body pressure, buffer layer is set and is difficult to ensure that tunnel bearing capacity, while big face Product implements damping Rotating fields, the problems such as be also faced with big, long in time limit difficulty of construction and high cost.
At present the country also has and few in number passes through active fault Tunnel structure, but the single consideration of these versions Flexible joint or absorbing joint design, while in just lining and secondary lining filled and process concrete buffer layer, and fail to take into full account The crushed zone wall rock destabilization pressure influence that fault movement causes, existing earthquake is it has been shown that wall rock destabilization pressure is likely to result in tunnel There is cracking, fall block even fall damage in road;Simultaneously under fault movement effect, local can occur at flexible joint or absorbing joint Destruction, it is difficult to ensure tunnel water proofing function.
The content of the invention
For the problems referred to above it is an object of the invention to provide one kind can solve the problem that passing through active fault crushed zone tunnel exists The activity of passing through that the problem of tunnel support structure cracking, leak and landslide occurs under fault movement and breaking surrounding rock buckling pressure is disconnected Layer tunnel multi-stage shock-absorbing structure.Technical scheme is as follows:
Active fault tunnel multi-stage shock-absorbing structure is passed through, the tunnel cross section of the main deformed area of fault belt in tunnel is more than stable The tunnel cross sectional of section;Tunnel-liner layer is longitudinal varistructure:Tunnel-liner layer is segmentation lining cutting, and the intersegmental structure of adjacent lining cutting Into absorbing joint by flexible joint connect.
Further, surrounding rock consolidation is set in the fault belt and its coverage by way of grouting and reinforcing Circle.
Further, filled with the change being made up of lightweight sand between the surrounding rock consolidation circle inwall and tunnel-liner layer Shape adjustment layer.
Further, the surrounding rock consolidation circle and deformation adjustment interlayer also are provided with waterproof layer.
Further, the tunnel-liner layer includes the secondary lining of preliminary bracing and its inwall, preliminary bracing and two Waterproof layer is additionally provided between secondary lining cutting.
Further, joint local strengthening is additionally provided with the absorbing joint that flexible joint is set.
The invention has the beneficial effects as follows:The present invention can be such that the safety of tunnel structure and the stability of country rock obtains Greatly improve;The maximum at each position of lining cutting, minimum principal stress peak value are substantially reduced, and make to be likely to occur because tension or in compression and broken Bad tunnel section is substantially reduced;After liner structure occurs the changing of the relative positions at changing of the relative positions face, displacement is undergone mutation at interface, hands over Steel bar stretching surrender in the secondary lining of interface, with respect to the deformation that stratum can be preferably adapted to for structure in the air, prevents Only cave on a large scale by unstability for country rock, reduces impact of the fault movement to tunnel, it is ensured that structure of the tunnel in " waterproof after first structure " Lower realization is open to traffic.
Description of the drawings
Fig. 1 is the structural representation that the present invention passes through active fault tunnel multi-stage shock-absorbing structure.
Fig. 2 is lining cutting Rotating fields schematic diagram of the present invention.
Fig. 3 is across the active fault tunnel structure entirety profile of the present invention.
Fig. 4 digs schematic diagram for tunnel cross-section of the present invention.
Fig. 5 is this practical new deformation adjustment layer mechanism of action schematic diagram
1- lower wall country rocks;2- fault belt country rocks;3- surrounding rock consolidation circles;4- deforms adjustment layer;5- preliminary bracings;Bis- linings of 6- Build;7- flexible joints;8- joint local strengthenings;9- waterproof layers;10- changing of the relative positions faces;11- longitudinal reinforcements;12- fault belts;13- Normal tunnel lining section;14- digs tunnel-liner section;A section tunnel-liner section is digged after the 15- changing of the relative positions;The 16- changing of the relative positions is adjusted It is domatic afterwards;17- deformations adjustment layer particle flow direction, 18- are come to nothing bottom area.
Specific embodiment
The present invention is described in further details with specific embodiment below in conjunction with the accompanying drawings.As shown in figure 1, the activity of passing through is disconnected Layer tunnel multi-stage shock-absorbing structure, the tunnel cross section of the 12 main deformed area of fault belt in tunnel are transversal more than the tunnel of stable section Face;Tunnel-liner layer is longitudinal varistructure:Tunnel-liner layer leads to for segmentation lining cutting, and the absorbing joint of the intersegmental composition of adjacent lining cutting Cross flexible joint 7 to connect.Joint local strengthening 8 is additionally provided with the absorbing joint that flexible joint 7 is set, to strengthen absorbing joint water proofing property Energy.
Tunnel-liner is using the varistructured form in longitudinal direction and carries out local strengthening, and longitudinal varistructure mainly includes segmentation Lining cutting and flexible joint, according to different stratum deformation amounts, are arranged in Light deformation section, three sections of small deformation section and main deformation section The length of different lining cutting sections, the tunnel-liner positioned at main deformation section arrange the length of its lining cutting sections and are narrower than small deformation section Segmental length, arranges flexible joint between segmentation lining cutting, flexible joint can adopt foam concrete or rubber, polystyrene hard Matter plastic foam is filled;Main transformer shape section under the influence of the changing of the relative positions is reserved disconnected using the cross-section for digging method enlarged configuration Fault momentum.
In the fault belt 12 of the present embodiment and its coverage, surrounding rock consolidation circle is set by way of grouting and reinforcing 3.Grouting and reinforcing is adopted to strengthen the bearing capacity of the self-stable ability and ground of country rock in fault belt and its coverage Mode reinforce country rock and ground.Surrounding rock consolidation circle 3 allows for fault belt and the neighbouring self of interface is poor, Thus the active force acted on tunnel structure may be increased, therefore slip casting be adopted in fault belt and its coverage The mode of reinforcing reinforces country rock and ground, to strengthen the bearing capacity of the self-stable ability and ground of country rock, prevents in tunnel structure When there is destruction, unstability is caved on a large scale for peripheral rock appearance, while the active force acted on structure can also be reduced.
Adjust filled with the deformation being made up of lightweight sand between 3 inwall of surrounding rock consolidation circle of the present embodiment and tunnel-liner layer Flood 4.Deformation adjustment layer is the adjustment by itself deforming and the flowing of implant, consumes and absorbs the deformation and energy being transmitted to Amount, so as to reduce impact of the fault movement to tunnel.In the selection of deformation adjustment layer material, morphotropism, flowing are considered Property and economy, choose the mixing light sand that mixed according to certain ratio using EPS granules, coarse sand, middle sand as Deformation adjustment layer.The characteristics of mixing light sand is:Density is little, and inertia force is little;EPS particle deformabilities are strong, and modulus of shearing is low, The active force acted in lining cutting is reduced by self-deformation etc.;Coarse sand and middle sand good fluidity, and produce ball effect and make to mix Close sand there is preferable mobility, when occur occurring coming to nothing below tunnel under the changing of the relative positions area when, mixing sand flowing filling come to nothing Area, therefore the stratum deformation under different fault movement amounts can be better conformed to.
Waterproof layer 9 is provided between the surrounding rock consolidation circle 3 and deformation adjustment layer 4 of the present embodiment, tunnel-liner layer includes the initial stage The secondary lining 6 of shield 5 and its inwall, is additionally provided with waterproof layer, as shown in Figure 2 between preliminary bracing 5 and secondary lining 6.Multiple tracks Waterproof is to pay attention to the waterproof at the self waterproofing and absorbing joint of concrete, between deformation adjustment layer and surrounding rock consolidation circle, just and The waterproof layer of waterproofing and anti-leakage is all set between secondary lining, the purpose of waterproof is preferably reached using the fortification measure of multiple tracks.It is special Other, the waterproof strengthened at absorbing joint can be using following measures such as:GINA waterstop methods, dismountable type pipe sheet assembling double-decker method And BQXF(Ripple reinforcing rubber composite)Anticracking water-stop method etc..
Such as Fig. 4, shown in Fig. 5, there is the changing of the relative positions in tomography at interface, be subjected to displacement mutation, cause crushed zone at interface Wall rock destabilization, the design adopt grouting reinforcement rock, improve country rock from bearing capacity, while compatibility of deformation layer can be effectively adapted to Deformation and energy absorption, so as to realize protecting the purpose of liner structure.Mixing light sand in compatibility of deformation layer is made in the changing of the relative positions With under the influence of, granule flows to the area 18 of coming to nothing of tunnel bottom, so as to adapt to stratum deformation.Liner structure is using segmentation lining cutting Form, improve longitudinal adaptive deformation ability, by country rock and malformation(Or the changing of the relative positions of lining cutting)Reduce fault movement to draw Play the internal force of tunnel-liner, it is to avoid possible at interface and crushed zone stress concentration phenomenon occur.Segmentation lining cutting can also Damage localization of the tunnel under fault movement is made, the total collapse of structure will not be caused.Laterally dig and can protect after the changing of the relative positions The internal headroom of card, adopting the forms such as backfill, pading plate to adjust the gradient can be open to traffic with Quick-return, when there is the accessory structures such as track When, tackle which and be adjusted and repair.

Claims (6)

1. active fault tunnel multi-stage shock-absorbing structure is passed through, it is characterised in that the fault belt in tunnel(12)Main deformed area Tunnel cross sectional of the tunnel cross section more than stable section;Tunnel-liner layer is longitudinal varistructure:Tunnel-liner layer is segmentation lining Build, and the absorbing joint of the intersegmental composition of adjacent lining cutting passes through flexible joint(7)Connection.
2. it is according to claim 1 to pass through active fault tunnel multi-stage shock-absorbing structure, it is characterised in that the fault disruption zone Band(12)And its surrounding rock consolidation circle is set by way of grouting and reinforcing in coverage(3).
3. it is according to claim 2 to pass through active fault tunnel multi-stage shock-absorbing structure, it is characterised in that the surrounding rock consolidation Circle(3)Filled with the deformation adjustment layer being made up of lightweight sand between inwall and tunnel-liner layer(4).
4. it is according to claim 3 to pass through active fault tunnel multi-stage shock-absorbing structure, it is characterised in that the surrounding rock consolidation Circle(3)With deformation adjustment layer(4)Between be provided with waterproof layer(9).
5. active fault tunnel multi-stage shock-absorbing structure is passed through according to any one of claim 1-4, it is characterised in that described Tunnel-liner layer includes preliminary bracing(5)With the secondary lining of its inwall(6), preliminary bracing(5)And secondary lining(6)Between also It is provided with waterproof layer.
6. it is according to claim 1 to pass through active fault tunnel multi-stage shock-absorbing structure, it is characterised in that flexible joint is set (7)Absorbing joint at be additionally provided with joint local strengthening(8).
CN201610949404.4A 2016-10-26 2016-10-26 Pass through active fault tunnel multi-stage shock-absorbing structure Expired - Fee Related CN106522977B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610949404.4A CN106522977B (en) 2016-10-26 2016-10-26 Pass through active fault tunnel multi-stage shock-absorbing structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610949404.4A CN106522977B (en) 2016-10-26 2016-10-26 Pass through active fault tunnel multi-stage shock-absorbing structure

Publications (2)

Publication Number Publication Date
CN106522977A true CN106522977A (en) 2017-03-22
CN106522977B CN106522977B (en) 2019-03-29

Family

ID=58325161

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610949404.4A Expired - Fee Related CN106522977B (en) 2016-10-26 2016-10-26 Pass through active fault tunnel multi-stage shock-absorbing structure

Country Status (1)

Country Link
CN (1) CN106522977B (en)

Cited By (24)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107100631A (en) * 2017-05-12 2017-08-29 西南交通大学 Pass through the construction method of active fault Tunnel Second Lining
CN107120125A (en) * 2017-06-29 2017-09-01 西南交通大学 A kind of tunnel antidetonation support system suitable for the regional Cross-fault leveling of highlight lines
CN107255033A (en) * 2017-06-23 2017-10-17 乌鲁木齐城市轨道集团有限公司 The error resilience for passing through active fault moves the construction method of Tunnel Second Lining
CN108150192A (en) * 2018-01-22 2018-06-12 中铁第四勘察设计院集团有限公司 A kind of bilayer lining cutting shield tunnel deformation joint structure and shield tunnel
CN108547633A (en) * 2018-06-22 2018-09-18 西南交通大学 It is a kind of to cross over active fault anti-seismic structure and its construction method
CN108593892A (en) * 2018-06-22 2018-09-28 西南交通大学 Tunnel-liner model, the experimental rig and experimental method for simulating tunnel longitudinal effect
CN109252552A (en) * 2018-11-07 2019-01-22 中南大学 A kind of progressive rate Aseismatic Design method of underground structure
CN109989768A (en) * 2019-04-26 2019-07-09 山东大学 A kind of liner structure and its construction method suitable for Tunnel Passing active fault
CN110005444A (en) * 2019-05-05 2019-07-12 西南交通大学 Highly seismic region method for tunnel construction and tunnel support structure
CN110159314A (en) * 2019-05-07 2019-08-23 山东大学 A kind of tunnel flexibility ring type support system suitable for passing through active breaking belt
CN110359954A (en) * 2019-08-02 2019-10-22 西南交通大学 One kind passing through creep faults tunnel particle-filled layers error resilience structure and its construction method
CN110836120A (en) * 2019-11-07 2020-02-25 山东大学 Tunnel lining structure suitable for self-monitoring and adjusting of crossing active fault and construction method
CN110924976A (en) * 2019-12-03 2020-03-27 中南大学 Surrounding rock outer ring grouting reinforcement method
CN111706354A (en) * 2020-07-06 2020-09-25 四川农业大学 Frozen soil layer fracture zone tunnel shock-absorbing structure
CN112031808A (en) * 2020-09-11 2020-12-04 广州大学 Connecting device for fixing tunnel and shock insulation tunnel
CN112065432A (en) * 2020-09-14 2020-12-11 浙江华东工程咨询有限公司 Tunnel structure penetrating through movable fault fracture zone and construction method thereof
CN112664208A (en) * 2020-12-31 2021-04-16 中国科学院武汉岩土力学研究所 Cross-active fault tunnel shock absorption seam structure, tunnel structure and construction method
CN113338999A (en) * 2021-07-07 2021-09-03 西南交通大学 Tunnel supporting structure
CN113685199A (en) * 2021-09-01 2021-11-23 中铁二院工程集团有限责任公司 Tunnel crossing active fault and calculation method for length of fortification extension section of tunnel
CN114324142A (en) * 2021-11-26 2022-04-12 北京中煤矿山工程有限公司 Contact surface friction measuring device
CN114352312A (en) * 2021-11-26 2022-04-15 中铁二十五局集团第一工程有限公司 Unequal-length self-adaptive multi-segment lining structure for tunnel crossing movable fracture zone
CN114352311A (en) * 2021-11-26 2022-04-15 中铁二十五局集团第一工程有限公司 Multi-section lining structure for tunnel to penetrate through movable fracture zone and construction method
CN114704288A (en) * 2022-05-18 2022-07-05 华中科技大学 A shock attenuation is from restoring to throne tunnel structure for broken area of fault
CN115142871A (en) * 2022-04-06 2022-10-04 中国科学院武汉岩土力学研究所 Pass through active fault tunnel structure, assembled mistake proofing seam structure and articulated joint structure

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101550831A (en) * 2009-04-09 2009-10-07 西南交通大学 Shock resisting and reducing structure spanning movable fault tunnel
CN104863615A (en) * 2015-06-16 2015-08-26 西南交通大学 Anti-seismic tunnel structure spanning large-scale active fault zone

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101550831A (en) * 2009-04-09 2009-10-07 西南交通大学 Shock resisting and reducing structure spanning movable fault tunnel
CN104863615A (en) * 2015-06-16 2015-08-26 西南交通大学 Anti-seismic tunnel structure spanning large-scale active fault zone

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
胡辉: "穿越活动断层的隧道减震结构研究", 《中国博士学位论文全文数据库工程科技II辑》 *

Cited By (35)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107100631B (en) * 2017-05-12 2019-04-02 西南交通大学 Pass through the construction method of active fault Tunnel Second Lining
CN107100631A (en) * 2017-05-12 2017-08-29 西南交通大学 Pass through the construction method of active fault Tunnel Second Lining
CN107255033A (en) * 2017-06-23 2017-10-17 乌鲁木齐城市轨道集团有限公司 The error resilience for passing through active fault moves the construction method of Tunnel Second Lining
CN107120125A (en) * 2017-06-29 2017-09-01 西南交通大学 A kind of tunnel antidetonation support system suitable for the regional Cross-fault leveling of highlight lines
CN107120125B (en) * 2017-06-29 2018-11-09 西南交通大学 A kind of tunnel antidetonation support system suitable for highlight lines area Cross-fault leveling
CN108150192A (en) * 2018-01-22 2018-06-12 中铁第四勘察设计院集团有限公司 A kind of bilayer lining cutting shield tunnel deformation joint structure and shield tunnel
CN108150192B (en) * 2018-01-22 2023-11-28 中铁第四勘察设计院集团有限公司 Double-layer lining shield tunnel deformation joint structure and shield tunnel
CN108547633A (en) * 2018-06-22 2018-09-18 西南交通大学 It is a kind of to cross over active fault anti-seismic structure and its construction method
CN108593892A (en) * 2018-06-22 2018-09-28 西南交通大学 Tunnel-liner model, the experimental rig and experimental method for simulating tunnel longitudinal effect
CN109252552A (en) * 2018-11-07 2019-01-22 中南大学 A kind of progressive rate Aseismatic Design method of underground structure
CN109989768A (en) * 2019-04-26 2019-07-09 山东大学 A kind of liner structure and its construction method suitable for Tunnel Passing active fault
CN110005444A (en) * 2019-05-05 2019-07-12 西南交通大学 Highly seismic region method for tunnel construction and tunnel support structure
CN110159314A (en) * 2019-05-07 2019-08-23 山东大学 A kind of tunnel flexibility ring type support system suitable for passing through active breaking belt
CN110159314B (en) * 2019-05-07 2020-08-25 山东大学 Tunnel flexible ring type supporting system suitable for penetrating through movable fracture zone
CN110359954A (en) * 2019-08-02 2019-10-22 西南交通大学 One kind passing through creep faults tunnel particle-filled layers error resilience structure and its construction method
CN110836120A (en) * 2019-11-07 2020-02-25 山东大学 Tunnel lining structure suitable for self-monitoring and adjusting of crossing active fault and construction method
CN110924976B (en) * 2019-12-03 2020-09-18 中南大学 Surrounding rock outer ring grouting reinforcement method
CN110924976A (en) * 2019-12-03 2020-03-27 中南大学 Surrounding rock outer ring grouting reinforcement method
CN111706354A (en) * 2020-07-06 2020-09-25 四川农业大学 Frozen soil layer fracture zone tunnel shock-absorbing structure
CN112031808A (en) * 2020-09-11 2020-12-04 广州大学 Connecting device for fixing tunnel and shock insulation tunnel
CN112031808B (en) * 2020-09-11 2022-03-22 广州大学 Connecting device for fixing tunnel and shock insulation tunnel
CN112065432A (en) * 2020-09-14 2020-12-11 浙江华东工程咨询有限公司 Tunnel structure penetrating through movable fault fracture zone and construction method thereof
CN112664208A (en) * 2020-12-31 2021-04-16 中国科学院武汉岩土力学研究所 Cross-active fault tunnel shock absorption seam structure, tunnel structure and construction method
CN112664208B (en) * 2020-12-31 2024-02-23 中国科学院武汉岩土力学研究所 Shock absorption joint structure of cross-movable fault tunnel, tunnel structure and construction method
CN113338999A (en) * 2021-07-07 2021-09-03 西南交通大学 Tunnel supporting structure
CN113338999B (en) * 2021-07-07 2023-09-15 西南交通大学 Tunnel supporting structure
CN113685199B (en) * 2021-09-01 2022-10-18 中铁二院工程集团有限责任公司 Tunnel crossing active fault and calculation method for length of fortification extension section of tunnel
CN113685199A (en) * 2021-09-01 2021-11-23 中铁二院工程集团有限责任公司 Tunnel crossing active fault and calculation method for length of fortification extension section of tunnel
CN114352311A (en) * 2021-11-26 2022-04-15 中铁二十五局集团第一工程有限公司 Multi-section lining structure for tunnel to penetrate through movable fracture zone and construction method
CN114352312A (en) * 2021-11-26 2022-04-15 中铁二十五局集团第一工程有限公司 Unequal-length self-adaptive multi-segment lining structure for tunnel crossing movable fracture zone
CN114324142A (en) * 2021-11-26 2022-04-12 北京中煤矿山工程有限公司 Contact surface friction measuring device
CN114324142B (en) * 2021-11-26 2024-03-26 北京中煤矿山工程有限公司 Contact surface friction force measuring device
CN115142871A (en) * 2022-04-06 2022-10-04 中国科学院武汉岩土力学研究所 Pass through active fault tunnel structure, assembled mistake proofing seam structure and articulated joint structure
CN114704288A (en) * 2022-05-18 2022-07-05 华中科技大学 A shock attenuation is from restoring to throne tunnel structure for broken area of fault
CN114704288B (en) * 2022-05-18 2022-11-29 华中科技大学 A shock attenuation is from restoring to throne tunnel structure for broken area of fault

Also Published As

Publication number Publication date
CN106522977B (en) 2019-03-29

Similar Documents

Publication Publication Date Title
CN106522977A (en) Multistage tunnel shock absorption structure penetrating through active fault
CN104863615B (en) Across large-scale activity fracture belt tunnel Anti-seismic structure
CN106014452B (en) A kind of Confined High Strength Concrete support system suitable for subterranean tunnel
CN108252721B (en) A kind of anti-disconnected hinged tunnel of type and its application for passing through Active Fault Area
CN110159314A (en) A kind of tunnel flexibility ring type support system suitable for passing through active breaking belt
CN102720196B (en) Anticorrosive anchor rod capable of preventing slurry from leaking
CN201746840U (en) Foundation pit support system equipped with a plurality of inclined rear anchors capable of recycling
CN209891214U (en) Assembled damping anchor rod frame beam
CN107988893A (en) The anti-fall girder construction of ball buffering energy-absorbing Antivibration block is leaned in a kind of direction across bridge taper
CN108547633A (en) It is a kind of to cross over active fault anti-seismic structure and its construction method
CN109578018A (en) A kind of tunnel inverted arch structure of anti-pucking
CN114635720A (en) Large-section deep-buried soft rock tunnel combined supporting system and construction method
CN110645018B (en) Mine underground strong dynamic pressure roadway prestress anchor-charging integrated supporting structure and method
CN106382124A (en) Flexible force transferring member as well as tunnel joint structure with force transferring member and construction method thereof
CN207229125U (en) A kind of thrust device for being exclusively used in concrete filled steel tube pier stud
CN113833491A (en) Tunnel lining support and tunnel penetrating through active fault fracture zone
CN109026016A (en) A kind of construction method in the tunnel for passing through strike-slip fault
CN107034905A (en) Control the combination retaining structure and its construction method of biased deformation
CN207672344U (en) Railway bed karez location pin-connected panel foundation stabilization construction
CN208293630U (en) A kind of structural system of the antiseismic liquefaction uplifting in subway station
CN206144582U (en) Tunnel is filled formula complex and is strutted
CN207813075U (en) A kind of bean column node steel hoop ruggedized construction
CN109325320A (en) The energy consumption composite cushion and design method be made of EPE padded coaming and backfill
CN103410155A (en) Recyclable front-assembled supporting envelop enclosure and applying method thereof
CN210013239U (en) Prevent landslide protection retaining wall

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20190329

Termination date: 20201026

CF01 Termination of patent right due to non-payment of annual fee