CN114542105A - Implementation method suitable for lining energy dissipation and shock absorption structure of tunnel in earthquake high-intensity area - Google Patents

Implementation method suitable for lining energy dissipation and shock absorption structure of tunnel in earthquake high-intensity area Download PDF

Info

Publication number
CN114542105A
CN114542105A CN202111652151.1A CN202111652151A CN114542105A CN 114542105 A CN114542105 A CN 114542105A CN 202111652151 A CN202111652151 A CN 202111652151A CN 114542105 A CN114542105 A CN 114542105A
Authority
CN
China
Prior art keywords
lining
anchor rod
tunnel
layer
lining layer
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202111652151.1A
Other languages
Chinese (zh)
Inventor
吴红刚
朱宝龙
李仁强
李永强
马至刚
阎树东
蔡书洪
衣忠强
张俊德
朱兆荣
杨刚涛
孙浩
戴龙
周垣
张博
冯康
孟庆友
李静
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Ninth Bureau Group No1 Construction Co ltd
Southwest University of Science and Technology
China Railway No 9 Group Co Ltd
Northwest Research Institute Co Ltd of CREC
Original Assignee
Southwest University of Science and Technology
Northwest Research Institute Co Ltd of CREC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southwest University of Science and Technology, Northwest Research Institute Co Ltd of CREC filed Critical Southwest University of Science and Technology
Priority to CN202111652151.1A priority Critical patent/CN114542105A/en
Publication of CN114542105A publication Critical patent/CN114542105A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/152Laggings made of grids or nettings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • E21D21/0093Accessories
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/20Hydro energy

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses an implementation method of an energy dissipation and shock absorption structure suitable for a tunnel lining in a seismic high-intensity area, which specifically comprises the following steps of: 1) excavating a tunnel; 2) installing an anchor rod; 3) constructing a primary lining layer; 4) constructing a second lining; 5) installing a damping buffer piece; 6) EPS concrete construction; the damping structure is characterized in that a damping piece is arranged at the tail end of the anchor rod on the basis of a primary lining layer and a secondary lining layer, an EPS concrete filling layer is poured between the primary lining layer and the secondary lining layer, and the primary lining layer and the secondary lining layer are connected with the damping piece; under the earthquake effect, the shock attenuation piece can slow down the vibrations of stock, and shock attenuation bolster and EPS concrete filling layer can slow down the impact of first lining to two linings, effectively reduces and dispersed load, prevents that the load from concentrating to realize the absorbing effect of energy dissipation.

Description

Implementation method suitable for lining energy dissipation and shock absorption structure of tunnel in earthquake high-intensity area
Technical Field
The invention belongs to the technical field of tunnel construction, and particularly relates to an implementation method of a tunnel lining energy dissipation and shock absorption structure suitable for a high-intensity earthquake area.
Background
Because of the wide territory and the complex terrain in China, the tunnel becomes a necessary mode for traversing complex territories such as mountains and the like in the construction process of traffic facilities, and according to incomplete statistics, the mileage of the tunnel which is constructed and built in China currently exceeds 10000 km. Due to the influence of natural disasters such as design, construction, terrain, earthquake and the like, the phenomena of lining structure damage, tunnel water leakage, ballast bed damage and the like easily occur in the tunnel, and the normal use of the tunnel structure is further influenced. Among them, the destruction of the tunnel lining structure is one of the main causes of tunnel damage. Under the action of earthquake, the lining structure of the tunnel and the surrounding rock can interact, and a buffering and damping structure is lacked, so that the structural damage of the tunnel lining occurs.
Disclosure of Invention
The invention provides an implementation method of an energy dissipation and shock absorption structure suitable for a tunnel lining in an earthquake high-intensity area, aiming at improving the shock absorption performance of a tunnel and solving the problem that the tunnel lining structure is easy to damage in the high-intensity area due to natural disasters such as earthquakes.
Therefore, the invention adopts the following technical scheme:
an implementation method suitable for a tunnel lining energy dissipation and shock absorption structure in a seismic high-intensity area specifically comprises the following steps:
1) excavating a tunnel;
2) and (3) anchor rod installation: selecting an anchor rod installation area in an excavated tunnel, drilling holes in the surrounding rock in the same cross section of the tunnel, wherein the drilling direction is located in the cross section, the drilling positions are distributed on the top and the side of the surrounding rock in a radial manner; continuing drilling construction in the anchor rod installation area at intervals according to the method, so that the drilling hole covers the whole anchor rod installation area;
installing and fixing an anchor rod in the drilled hole, wherein the head end of the anchor rod is exposed, a damping piece is installed at the front end of the anchor rod, and the front end of the anchor rod is elastically and movably connected with the damping piece;
3) primary lining layer construction: primary lining spraying protection is carried out on the lower surface of the surrounding rock, and the anchor rod and the damping piece are wrapped in the primary lining layer, so that the anchor rod and the damping piece are prevented from leaking;
4) construction of a second lining: laying two lining reinforcing steel bar meshes in the tunnel, forming a gap between the two lining reinforcing steel bar meshes and the lower surface of the primary lining layer, then injecting secondary lining concrete to form a secondary lining layer, and leaving a gap between the formed secondary lining layer and the primary lining layer;
5) installation of the damping buffer piece: the damping buffer piece is arranged between the primary lining layer and the secondary lining layer and is positioned in the section where each anchor rod is positioned; the damping buffer piece comprises a damper and a steel spring, the steel spring is sleeved on a piston rod of the damper, and the piston rod drives the steel spring to act when being stretched; the head end of the piston rod of the damper is fixedly connected to the primary lining, and the base of the damper is fixedly connected to the upper surfaces of the two linings;
6) EPS concrete construction: installing a template in a gap between the primary lining layer and the secondary lining layer, pouring EPS concrete in the template, solidifying the lower surface of the EPS concrete and the upper surfaces of the secondary lining layers into a whole, forming a gap layer between the upper surface of the EPS concrete and the lower surface of the primary lining layer, and enabling a piston rod of the damper to leak into the gap layer;
further, a rubber pad is fixedly connected to the damper base, a steel base plate is fixedly connected to the bottom of the rubber pad and fixed to the upper surfaces of the two lining layers through screws, and the rubber pad and the steel base plate are fixed in EPS concrete in a pouring mode.
Furthermore, the steel backing plate is an arc-shaped steel plate, the radian of the steel backing plate is opposite to the radian of the upper surfaces of the two lining layers, the length of the steel backing plate is not less than 40cm, and the width of the steel backing plate is not less than 20 cm.
Furthermore, the damping piece comprises a metal sleeve, an opening is formed in the top of the metal sleeve, and the head end of the anchor rod penetrates into the metal sleeve through the opening; a movable rod vertical to the anchor rod penetrates through the metal sleeve, and the middle part of the movable rod is fixedly connected with the anchor rod; two springs are sleeved on the movable rod, one end of each spring abuts against the end part of the metal sleeve, and the other end of each spring abuts against the anchor rod; when the anchor rod swings left and right, the movable rod moves left and right along with the anchor rod; the metal sleeve is sleeved with a rubber sleeve for sealing.
Further, a screw hole is formed in the tail end of the anchor rod, an external thread is arranged in the middle of the movable rod, and the middle of the movable rod is in threaded connection with the anchor rod.
Further, the templates in the step 6) are arc-shaped, gaps are reserved on the templates, the gaps on the adjacent templates are spliced to form circular gaps, and the circular gaps are used for placing dampers.
Further, the single construction length of the two lining layers and the EPS concrete is 2-4 m.
The damping structure is characterized in that a damping piece is arranged at the tail end of the anchor rod on the basis of a primary lining layer and a secondary lining layer, an EPS concrete filling layer is poured between the primary lining layer and the secondary lining layer, and the primary lining layer and the secondary lining layer are connected with the damping piece; under the earthquake effect, the shock attenuation piece can slow down the vibrations of stock, and shock attenuation bolster and EPS concrete filling layer can slow down the impact of first lining to two linings, effectively reduces and dispersed load, prevents that the load from concentrating to realize the absorbing effect of energy dissipation.
Drawings
FIG. 1 is a schematic cross-sectional view of a tunnel of the present invention;
FIG. 2 is an enlarged view of a portion A of FIG. 1;
FIG. 3 is a partial enlarged view of portion B of FIG. 1;
FIG. 4 is a schematic view of the construction of the template of the present invention;
FIG. 5 is a schematic view of the use of the template of the present invention;
in the figure: 1-primary lining layer, 2-secondary lining layer, 3-EPS concrete, 4-gap layer, 5-anchor rod, 6-shock-absorbing piece, 61-metal sleeve, 62-movable rod, 63-spring, 64-rubber sleeve, 7-shock-absorbing buffer piece, 71-damper, 72-steel spring, 73-rubber pad, 74-steel backing plate, 75-support backing plate, 8-template and 81-circular notch.
Detailed Description
The invention will be further described with reference to the following drawings and specific embodiments:
as shown in fig. 1, an implementation method of an energy dissipation and shock absorption structure suitable for a tunnel lining in a seismic high-intensity area specifically includes the following steps:
1) excavating a tunnel: according to the line planning and the actual situation of the site, tunnel excavation operation is carried out, excavation operation can be carried out in various modes such as a heading machine or a drilling and blasting method, supporting is carried out while tunnel excavation is carried out, and according to geological reports, the damping supporting structure is adopted in high-intensity areas.
2) And (3) anchor rod installation: and (3) defining a high-intensity region as an anchor rod 5 installation region, drilling holes on the surrounding rock in the same cross section of the tunnel by using drilling equipment, ensuring that the drilling direction is positioned in the cross section, and the drilling positions are distributed on the top and the side of the surrounding rock in a radial manner. The drilling construction is continued in the installation area of the anchor rod 5 at intervals according to the above method, so that the drill hole covers the whole installation area of the anchor rod 5.
The distance between adjacent drill holes in the same cross section is 20-50cm, and the distance between the construction cross sections of the adjacent drill holes is 50-200 cm. Specific distance can be according to multiple factor integrated analysis such as tunnel size, geological activity degree, basement rock firmness, in the higher area of safe risk level, should reduce 5 intervals of stock to improve and strut intensity. Because the stress concentration of the transition part of the top surface and the side surface of the surrounding rock is easy to crack, the anchor rods 5 at the position are high in distribution density and used for improving the tunnel strength.
Installing an anchor rod 5 in the drilled hole, and pouring concrete to fix the anchor rod 5; the 5 head ends of stock expose, and the exposure distance of 5 head ends of each stock is roughly equal, makes things convenient for follow-up construction operation. BFRP combined material stock 5 is selected for use to stock 5, and intensity is high, and corrosion resistance is good, helps improving 5 life-spans of stock, then connects damping piece 6 at 5 front ends of stock, and 6 structures of damping piece are as follows:
as shown in fig. 3, the shock absorbing member 6 comprises a square metal sleeve 61, an opening is formed at the top of the metal sleeve 61, and the tail end of the anchor rod 5 penetrates into the metal sleeve 61 through the opening. Both ends are equipped with the opening about metal sleeve 61, wear to establish perpendicular stock 5's movable rod 62 in metal sleeve 61 through the opening, and the screw has been seted up to stock 5 tail end, and the movable rod 62 middle part is equipped with the external screw thread, and movable rod 62 middle part and stock 5 threaded connection. The left end and the right end of the movable rod 62 are respectively sleeved with a spring 63, one end of the spring 63 abuts against the side wall of the inner cavity of the metal sleeve 61, and the other end of the spring 63 abuts against the anchor rod 5. When the anchor rod 5 swings left and right, the movable rod 62 moves left and right, and the movable rod 62 is driven to extrude the spring 63. The metal sleeve 61 is externally sleeved with a rubber sleeve 64 for sealing, and the rubber sleeve 64 blocks each hole on the metal sleeve 61 to prevent concrete from entering the metal sleeve 61.
3) Primary lining layer construction: the primary lining is sprayed and protected on the lower surface of the surrounding rock according to the prior art and equipment, the primary lining concrete uniformly covers the bedrock, and the primary lining layer 1 wraps the head end of the anchor rod 5 and the damping piece 6 therein, so that the anchor rod 5 and the damping piece 6 are prevented from leaking.
4) Construction of a second lining: two lining reinforcing steel bar meshes are laid in the tunnel, a gap is reserved between the two lining reinforcing steel bar meshes and the lower surface of the primary lining layer 1, then secondary lining concrete is sprayed and protected to form a secondary lining layer 2, and a gap is reserved between the formed secondary lining layer 2 and the primary lining layer 1, so that subsequent construction is facilitated.
5) Installing a damping buffer piece: shock attenuation bolster 7 is installed and is being in lining 1 and two lining 2 between, and shock attenuation bolster 7 is located each stock 5 place cross sections, for convenient construction, should mark stock 5 place cross sections of being under construction during the construction of stock 5, makes the mountable of shock attenuation bolster 7 to stock 5 planes in, convenient construction. The shock absorption buffer 7 comprises a damper 71 and a steel spring 72, the steel spring 72 is sleeved on a piston rod of the damper 71, and the piston rod drives the steel spring 72 to act when being stretched; the head end of the piston rod of the damper 71 is fixedly connected to the surrounding rock through a support cushion plate 75 with a hole and a screw, and the base of the damper 71 is fixedly connected to the upper surfaces of the two lining layers 2.
When the shock absorption buffering member 7 is installed, a mounting position is reserved by removing partial concrete from the notch on the lower surface of the primary lining layer 1, the mounting position is used for placing a supporting base plate 75, the notch position and the mounting position of the anchor rod 5 are arranged in a staggered mode, and the upper end of the damper 71 is fixed through the supporting base plate 75.
As shown in fig. 2, to prevent load concentration from damaging the two liner 2 structure. A rubber pad 73 is fixedly connected to the base of the damper 71, a steel pad plate 74 is fixedly connected to the bottom of the rubber pad 73, and the steel pad plate 74 is fixed to the upper surfaces of the two lining layers 2 through screws. The steel backing plate 74 is an arc-shaped steel plate, the radian of the steel backing plate corresponds to that of the upper surface of the two lining layers 2, so that the steel backing plate 74 is in close contact with the two lining layers 2, the length of the steel backing plate 74 is not less than 40cm, and the width of the steel backing plate 74 is not less than 20 cm. The steel backing plate 74 increases the stress area and reduces the pressure, thereby reducing the risk of load concentration.
6) EPS concrete 3 construction: install template 8 in the space between first lining 1 and two linings 2, pour EPS concrete 3 in template 8, EPS concrete 3 bottom and two lining 2 upper surfaces solidify and be an organic whole, form clearance layer 4 between EPS concrete 3 upper surface and the first lining 1 lower surface, and the piston rod of attenuator 71 leaks outward to clearance layer 4 in, guarantees that attenuator 71 can normally stretch out and draw back.
As shown in fig. 4 and 5, the formwork 8 has an arcuate plate shape and can be customized according to the tunnel structure and size. The templates 8 are supported at the left side and the right side of the tunnel, and the templates 8 do not need to be supported near the top of the tunnel. The gaps are reserved on the formworks 8, the gaps on the adjacent formworks 8 are spliced into a circular gap 81, the diameter of the circular gap 81 is equal to the outer diameter of the damper 71, the circular gap 81 is used for placing the damper 71, and the formworks 8 are detached after the EPS concrete 3 is cured and molded.
The function of the damper 6: when natural disasters such as earthquakes occur, surrounding rock vibration drives the anchor rod 5 to vibrate, and as the tail end of the anchor rod 5 is connected with the damping piece 6, the movable rod 62 is driven to swing left and right in the metal sleeve 61 to release partial energy when the tail end of the anchor rod 5 swings; prevent that load from concentrating to stock 5 tail end, lead to stock 5 and the primary lining 1 junction destructive fracture, cause the tunnel structure damage.
The function of the shock absorbing bumper 7: the load that the earthquake produced acts on attenuator 71 through first lining 1, thereby attenuator 71 is compressed and absorbs partial energy, and the load passes through attenuator 71 and conducts to rubber pad 73 and steel backing plate 74 on, because steel backing plate 74 is arc and area great, helps dispersing load to two lining 2 fast on, avoids taking place to appear stress concentration phenomenon on two lining 2, and then improves the shock resistance of tunnel when the earthquake.
EPS concrete filling layer 3: a10-30 cm gap layer is formed between the EPS concrete filling layer 3 and the primary lining layer 1, and the load generated by earthquake acts on the buffer layer, so that a large amount of earthquake wave energy can be consumed, and the impact of the earthquake on the secondary lining layer 2 is reduced.

Claims (7)

1. The utility model provides an implementation method suitable for earthquake high intensity district tunnel lining energy dissipation shock-absorbing structure which characterized in that specifically includes the following steps and goes on:
1) excavating a tunnel;
2) and (3) installing an anchor rod (5): selecting an anchor rod (5) installation area in an excavated tunnel, drilling holes in the surrounding rock in the same cross section of the tunnel, wherein the drilling direction is located in the cross section, the drilling positions are distributed on the top and the side of the surrounding rock, and the drilling holes are distributed radially; continuing drilling construction in the installation area of the anchor rod (5) at intervals according to the method, so that the drilling hole covers the whole installation area of the anchor rod (5);
an anchor rod (5) is installed and fixed in a drilled hole, the head end of the anchor rod (5) is exposed, a damping piece (6) is installed at the front end of the anchor rod (5), and the front end of the anchor rod (5) is elastically and movably connected with the damping piece (6);
3) primary lining layer construction: primary lining spraying protection is carried out on the lower surface of the surrounding rock, the head end of the anchor rod (5) and the damping piece (6) are wrapped in the primary lining layer (1), and the anchor rod (5) and the damping piece (6) are prevented from leaking;
4) construction of a second lining: laying two lining steel bar meshes in the tunnel, forming a gap between the two lining steel bar meshes and the lower surface of the primary lining layer (1), then injecting secondary lining concrete to form a secondary lining layer (2), and leaving a gap between the secondary lining layer (2) and the primary lining layer (1) after the secondary lining layer (2) is formed;
5) installation of the damping buffer piece: the shock absorption buffer parts (7) are arranged between the primary lining layer (1) and the secondary lining layer (2), the shock absorption buffer parts (7) are positioned in the section where each anchor rod (5) is positioned, and the shock absorption buffer parts (7) and the anchor rods (5) are arranged in a staggered mode; the shock absorption buffer piece (7) comprises a damper (71) and a steel spring (72), the steel spring (72) is sleeved on a piston rod of the damper (71), and the steel spring (72) is driven to act when the piston rod stretches; the head end of a piston rod of the damper (71) is fixedly connected to the primary lining layer (1), and the base of the damper (71) is fixedly connected to the secondary lining layer (2);
6) EPS concrete (3) construction: installing a template (8) in a gap between the primary lining (1) and the secondary lining (2), pouring EPS concrete (3) in the template (8), solidifying the bottom layer of the EPS concrete (3) and the upper surface of the secondary lining (2) into a whole, forming a clearance layer (4) between the upper surface of the EPS concrete (3) and the lower surface of the primary lining (1), and enabling a piston rod of a damper (71) to leak into the clearance layer (4).
2. The implementation method of the energy-dissipation and shock-absorption structure suitable for the tunnel lining in the earthquake high-intensity area as claimed in claim 1, wherein a rubber pad (73) is fixedly connected to the base of the damper (71), a steel pad plate (74) is further fixedly connected to the bottom of the rubber pad (73), the steel pad plate (74) is fixed to the upper surfaces of the two lining layers (2) through screws, and the rubber pad (73) and the steel pad plate (74) are fixed in the EPS concrete (3) in a pouring mode.
3. The implementation method of the energy dissipation and shock absorption structure for the tunnel lining in the earthquake high-intensity area as claimed in claim 2, wherein the steel backing plate (74) is an arc-shaped steel plate, the radian is opposite to the radian of the upper surface of the two lining layers (2), and the length of the steel backing plate (74) is not less than 40cm, and the width of the steel backing plate is not less than 20 cm.
4. The implementation method of the energy dissipation and shock absorption structure for the tunnel lining in the high-intensity earthquake region is characterized in that the shock absorption piece (6) comprises a metal sleeve (61), an opening is formed in the top of the metal sleeve (61), and the head end of the anchor rod (5) penetrates into the metal sleeve (61) through the opening; a movable rod (62) vertical to the anchor rod (5) penetrates through the metal sleeve (61), and the middle part of the movable rod (62) is fixedly connected with the anchor rod (5); two springs (63) are sleeved on the movable rod (62), one end of each spring (63) abuts against the end part of the metal sleeve (61), and the other end of each spring (63) abuts against the anchor rod (5); when the anchor rod (5) swings left and right, the movable rod (62) moves left and right along with the swing; the metal sleeve (61) is externally sleeved with a rubber sleeve (64) for sealing.
5. The implementation method of the energy dissipation and shock absorption structure for the tunnel lining in the earthquake high-intensity area as claimed in claim 4, wherein the tail end of the anchor rod (5) is provided with a screw hole, the middle part of the movable rod (62) is provided with an external thread, and the middle part of the movable rod (62) is in threaded connection with the anchor rod (5).
6. The implementation method of the energy-dissipation and shock-absorption structure suitable for the tunnel lining in the high-intensity earthquake region as claimed in claim 4, wherein the form boards (8) in the step 6) are arc-shaped, gaps are reserved on the form boards (8), the gaps on the adjacent form boards (8) are spliced to form circular gaps (81), and the circular gaps (81) are used for placing the dampers (71).
7. The implementation method of the energy-dissipation and shock-absorption structure suitable for the tunnel lining of the earthquake high-intensity area as claimed in claim 1, wherein the length of each construction of the two lining layers (2) and the EPS concrete (3) is 2-4 meters.
CN202111652151.1A 2021-12-31 2021-12-31 Implementation method suitable for lining energy dissipation and shock absorption structure of tunnel in earthquake high-intensity area Pending CN114542105A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111652151.1A CN114542105A (en) 2021-12-31 2021-12-31 Implementation method suitable for lining energy dissipation and shock absorption structure of tunnel in earthquake high-intensity area

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111652151.1A CN114542105A (en) 2021-12-31 2021-12-31 Implementation method suitable for lining energy dissipation and shock absorption structure of tunnel in earthquake high-intensity area

Publications (1)

Publication Number Publication Date
CN114542105A true CN114542105A (en) 2022-05-27

Family

ID=81670093

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111652151.1A Pending CN114542105A (en) 2021-12-31 2021-12-31 Implementation method suitable for lining energy dissipation and shock absorption structure of tunnel in earthquake high-intensity area

Country Status (1)

Country Link
CN (1) CN114542105A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115263353A (en) * 2022-08-10 2022-11-01 大连理工大学 Large-deformation self-adaptive supporting structure for soft rock tunnel

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106593464A (en) * 2016-11-24 2017-04-26 山东科技大学 Tunnel axial damping and energy absorbing device and tunnel lining structure with same
CN111501789A (en) * 2020-04-21 2020-08-07 中铁西北科学研究院有限公司 Multi-directional composite lining anti-seismic structure for landslide and fault zone and construction method thereof
CN111577326A (en) * 2020-04-21 2020-08-25 中铁西北科学研究院有限公司 Anti-seismic structure suitable for tunnel lining of high-intensity seismic area and construction method thereof
CN217270211U (en) * 2021-12-31 2022-08-23 西南科技大学 Energy dissipation and shock absorption structure suitable for tunnel lining in earthquake high-intensity area

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106593464A (en) * 2016-11-24 2017-04-26 山东科技大学 Tunnel axial damping and energy absorbing device and tunnel lining structure with same
CN111501789A (en) * 2020-04-21 2020-08-07 中铁西北科学研究院有限公司 Multi-directional composite lining anti-seismic structure for landslide and fault zone and construction method thereof
CN111577326A (en) * 2020-04-21 2020-08-25 中铁西北科学研究院有限公司 Anti-seismic structure suitable for tunnel lining of high-intensity seismic area and construction method thereof
CN217270211U (en) * 2021-12-31 2022-08-23 西南科技大学 Energy dissipation and shock absorption structure suitable for tunnel lining in earthquake high-intensity area

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
黄胜;陈卫忠;杨建平;郭小红;乔春江;: "地下工程地震动力响应及抗震研究", 岩石力学与工程学报, no. 03, 15 March 2009 (2009-03-15) *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115263353A (en) * 2022-08-10 2022-11-01 大连理工大学 Large-deformation self-adaptive supporting structure for soft rock tunnel

Similar Documents

Publication Publication Date Title
CN109989768B (en) Lining structure suitable for tunnel crossing active fault and construction method thereof
Di et al. In situ grouting tests for differential settlement treatment of a cut-and-cover metro tunnel in soft soils
CN105672517A (en) Swing self-reset and self-standing type high-rise structure
CN111577326B (en) Anti-seismic structure suitable for tunnel lining of high-intensity seismic area and construction method thereof
CN114635720A (en) Large-section deep-buried soft rock tunnel combined supporting system and construction method
CN113123325B (en) Underground continuous wall and construction method thereof
CN217270211U (en) Energy dissipation and shock absorption structure suitable for tunnel lining in earthquake high-intensity area
CN111501789B (en) Multi-directional composite lining anti-seismic structure for landslide and fault zone and construction method thereof
CN213175663U (en) Shock-absorbing structure and tunnel lining structure of crossing active fault tunnel
CN112096418A (en) Shock-absorbing structure and tunnel lining structure of crossing active fault tunnel
CN114542105A (en) Implementation method suitable for lining energy dissipation and shock absorption structure of tunnel in earthquake high-intensity area
CN110985079A (en) Energy-absorbing impact-resistant roadway support method
CN214035683U (en) Adopt buffer's slip fault tunnel energy-absorbing shock-absorbing structure strides
CN110836120A (en) Tunnel lining structure suitable for self-monitoring and adjusting of crossing active fault and construction method
CN213175682U (en) Supporting structure and tunnel lining structure of crossing active fault tunnel
CN110805164B (en) Assembled shear force wall that bottom has shock attenuation power consumption connecting piece
CN213953615U (en) Rubber lining shock-absorbing layer
CN210460499U (en) Miniature stake grouser drilling location guider
CN109139022B (en) Construction method of fabricated lining tunnel capable of resisting active fault dislocation
CN116517022A (en) High-toughness comprehensive pipe rack in strong earthquake area and manufacturing method
Han et al. A treatment technology for optimizing the stress state of railway tunnel bottom structure
CN112302681A (en) Rubber lining shock-absorbing layer and construction method thereof
CN113073681B (en) Long and narrow underground structure adaptive to strong earthquake action and construction method thereof
CN212376670U (en) Broken roof supporting device of underground mine
CN114704288A (en) A shock attenuation is from restoring to throne tunnel structure for broken area of fault

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right

Effective date of registration: 20241008

Address after: 730000 No. 365, East Democratic Road, Chengguan District, Gansu, Lanzhou

Applicant after: NORTHWEST RESEARCH INSTITUTE Co.,Ltd. OF C R E C

Country or region after: China

Applicant after: Southwest University of Science and Technology

Applicant after: CHINA RAILWAY NO.9 GROUP Co.,Ltd.

Applicant after: China Railway ninth Bureau Group No.1 Construction Co.,Ltd.

Address before: 730000 No. 365, East Democratic Road, Chengguan District, Gansu, Lanzhou

Applicant before: NORTHWEST RESEARCH INSTITUTE Co.,Ltd. OF C R E C

Country or region before: China

Applicant before: Southwest University of Science and Technology