CN114439247B - Large-span large-breadth suspended ceiling mobile construction method - Google Patents

Large-span large-breadth suspended ceiling mobile construction method Download PDF

Info

Publication number
CN114439247B
CN114439247B CN202210233227.5A CN202210233227A CN114439247B CN 114439247 B CN114439247 B CN 114439247B CN 202210233227 A CN202210233227 A CN 202210233227A CN 114439247 B CN114439247 B CN 114439247B
Authority
CN
China
Prior art keywords
suspended ceiling
breadth
span
steel structure
span large
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202210233227.5A
Other languages
Chinese (zh)
Other versions
CN114439247A (en
Inventor
曹雁冰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Anhui Weihong Steel Structure Group Co ltd
Original Assignee
Anhui Weihong Steel Structure Group Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Anhui Weihong Steel Structure Group Co ltd filed Critical Anhui Weihong Steel Structure Group Co ltd
Priority to CN202210233227.5A priority Critical patent/CN114439247B/en
Publication of CN114439247A publication Critical patent/CN114439247A/en
Application granted granted Critical
Publication of CN114439247B publication Critical patent/CN114439247B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/342Structures covering a large free area, whether open-sided or not, e.g. hangars, halls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/162Handles to carry construction blocks
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/18Adjusting tools; Templates
    • E04G21/1841Means for positioning building parts or elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to the technical field of engineering construction, and discloses a mobile construction method of a large-span large-breadth suspended ceiling, which comprises the following steps: s1, firstly fixing struts of a large-span large-breadth suspended ceiling according to a drawing, then assembling a plurality of limiting devices, and then assembling the large-span large-breadth suspended ceiling with a steel structure on the ground; s2, next, installing each limiting device on a strut of the large-span large-breadth suspended ceiling, and simultaneously assembling the large-span large-breadth suspended ceiling with the steel structure on a plurality of limiting devices. The mobile construction method for the large-span large-breadth suspended ceiling can effectively shorten the time and workload of the large-span large-breadth suspended ceiling of the expanded installation of the steel structure building, can ensure the normal use of the existing steel structure building, can improve the convenience and efficiency of the large-span large-breadth suspended ceiling of the expanded installation of the steel structure building, and also reduces the cost of the large-span large-breadth suspended ceiling installation and the labor intensity of workers.

Description

Large-span large-breadth suspended ceiling mobile construction method
Technical Field
The invention relates to the technical field of engineering construction, in particular to a movable construction method for a large-span large-breadth suspended ceiling.
Background
In recent years, with the rapid development of domestic economy, population flow is rapidly increased, facilities such as rainsheds or suspended ceilings of railway stations, airports and squares in various places are continuously developed to be functional and large-scale, building forms are also changed day by day, building is often required to be expanded on the basis of the original rainsheds or suspended ceilings, and normal operation of ground work cannot be affected during construction.
At present, when a large-span large-format suspended ceiling is installed in a steel structure building in an expanding manner, a scaffold is required to be built in the existing steel structure building, the steel structure is required to be lifted to the top of the building, then workers gradually install the large-span large-format suspended ceiling through the scaffold, finally the scaffold is required to be detached, but the construction progress of the large-span large-format suspended ceiling installation mode is slower, the workload is large, convenience and efficiency of the large-span large-format suspended ceiling installation of the steel structure building are affected, the cost of the large-span large-format suspended ceiling installation is increased, the labor intensity of the workers is increased, and normal use of the existing steel structure building is affected.
Disclosure of Invention
(one) solving the technical problems
Aiming at the defects of the prior art, the invention provides a movable construction method for a large-span large-format suspended ceiling, which can effectively shorten the time and the workload of expanding and installing the large-span large-format suspended ceiling of a steel structure building, can ensure the normal use of the existing steel structure building, can improve the convenience and the efficiency of expanding and installing the large-span large-format suspended ceiling of the steel structure building, can reduce the installation cost of the large-span large-format suspended ceiling, can reduce the labor intensity of workers, and can solve the problems that the construction progress is slower when the large-span large-format suspended ceiling of the existing steel structure building is expanded and installed, the convenience and the efficiency of expanding and installing the large-span large-format suspended ceiling of the steel structure building are influenced, the installation cost of the large-span large-format suspended ceiling is increased, and the labor intensity of the workers and the normal use of the existing steel structure building are increased.
(II) technical scheme
In order to achieve the purposes that the time and the workload of expanding and installing the large-span large-format suspended ceiling of the steel structure building can be effectively shortened, the normal use of the existing steel structure building can be guaranteed, the convenience and the efficiency of expanding and installing the large-span large-format suspended ceiling of the steel structure building can be improved, the cost of installing the large-span large-format suspended ceiling is reduced, and the labor intensity of workers is reduced, the invention provides the following technical scheme: a mobile construction method for a large-span large-breadth suspended ceiling comprises the following steps:
s1, firstly fixing struts of a large-span large-breadth suspended ceiling according to a drawing, then assembling a plurality of limiting devices, and then assembling the large-span large-breadth suspended ceiling with a steel structure on the ground;
s2, next, installing each limiting device on a strut of the large-span large-breadth suspended ceiling, and simultaneously assembling the large-span large-breadth suspended ceiling with the steel structure on a plurality of limiting devices;
s3, fixing the welded and assembled steel structure large-span large-breadth suspended ceiling on a limiting device, and guaranteeing that the steel structure large-span large-breadth suspended ceiling cannot shake when being lifted upwards;
s4, hanging the steel structure large-span large-breadth suspended ceiling on a plurality of cranes simultaneously through hanging ropes, then hanging the steel structure large-span large-breadth suspended ceiling on the plurality of cranes simultaneously, moving a limiting device upwards along a support column of the large-span large-breadth suspended ceiling in the hanging process of the steel structure large-span large-breadth suspended ceiling, stopping hanging when the limiting device moves to the top of the support column of the large-span large-breadth suspended ceiling, and starting a fixing device of an internal braking mechanism of the limiting device;
s5, then, a worker moves the hydraulic lifter to the side of the large-span large-breadth suspended ceiling pillar, meanwhile, the worker takes the hydraulic lifter to rise to the top of the large-span large-breadth suspended ceiling pillar, and pushes the large-span large-breadth suspended ceiling of the steel structure to the top of the pillar through a limiting device top roller mechanism, and the process does not need to repeatedly adjust a crane to align the large-span large-breadth suspended ceiling of the steel structure, so that time and labor are saved;
s6, finally, fixing the large-span large-breadth suspended ceiling of the steel structure with the top of the support column by a worker through the connecting piece and the tool, and then removing the crane to enable the large-span large-breadth suspended ceiling of the steel structure to be movably installed without disassembling the scaffold, thereby saving time and labor.
Preferably, the stop device includes the U-shaped board, the fluting has all been seted up to the both sides outer wall of U-shaped board, grooved cell wall swing joint has the screw rod, the pole wall activity of screw rod has cup jointed the sleeve, the fixed ring that has cup jointed of pole wall of screw rod, the pole wall screw thread of screw rod has cup jointed fixation nut, two round holes have been seted up to the outer wall of U-shaped board, and the pore wall fixedly connected with first electric putter of round hole, the output fixedly connected with tight piece of stopping of first electric putter, the outer wall fixedly connected with complementary unit of U-shaped board.
Preferably, the auxiliary mechanism comprises a fixed frame fixedly connected with the outer wall of the U-shaped plate, a rectangular through hole is formed in the upper surface of the fixed frame, a plurality of rollers are connected to the hole wall of the rectangular through hole through rolling bearings, a second electric push rod is fixedly connected to the outer wall of the fixed frame, and a clamping block is connected to the top end of the second electric push rod through the rolling bearings.
Preferably, the outer wall of the fixing nut is fixedly connected with two symmetrically distributed U-shaped handles.
Preferably, the bottom connection part of the large-span large-breadth suspended ceiling of the steel structure and the top end of the large-span large-breadth suspended ceiling pillar are fixedly welded with connecting flanges.
Preferably, a steel wire rope is arranged on the top guardrail of the hydraulic lifter, and the top end of the steel wire rope is fixedly connected with an anti-toppling hook.
Preferably, one side of the tightening block away from the first electric push rod is fixedly connected with an anti-skid rubber pad.
(III) beneficial effects
Compared with the prior art, the invention provides a large-span large-breadth suspended ceiling mobile construction method, which has the following beneficial effects:
the method for mobile construction of the large-span large-format suspended ceiling comprises the steps of firstly fixing the support posts of the large-span large-format suspended ceiling according to a drawing, then assembling a plurality of limiting devices, then assembling the large-span large-format suspended ceiling with a steel structure on the ground, next installing each limiting device on the support posts of the large-span large-format suspended ceiling, simultaneously assembling the large-span large-format suspended ceiling with the steel structure on the plurality of limiting devices, then fixing the welded and assembled large-span large-format suspended ceiling with the steel structure on the limiting devices, ensuring that the large-span large-format suspended ceiling with the steel structure cannot shake when being lifted upwards, next simultaneously hanging the large-span large-format suspended ceiling with the steel structure on a plurality of cranes through hanging ropes, then simultaneously lifting the large-span large-format suspended ceiling with the steel structure by the plurality of cranes, upwards moving the limiting devices along the support posts of the large-span large-format suspended ceiling with the steel structure in the large-span large-format suspended ceiling lifting process, finally, starting a fixing device of an internal braking mechanism of a limiting device, then lifting a hydraulic lifter of a worker to the top of a large-span large-format suspended ceiling pillar, pushing the large-span large-format suspended ceiling of the steel structure to the top of the pillar through a roller mechanism at the top of the limiting device, wherein the process does not need to repeatedly adjust a crane to align the large-span large-format suspended ceiling of the steel structure, saves time and labor, and finally, the worker fixes the large-span large-format suspended ceiling of the steel structure with the top of the pillar through a connecting piece and a tool, and meanwhile, the normal use of the existing steel structure building is not influenced, the method can effectively shorten the time and the workload of expanding and installing the large-span large-format suspended ceiling of the steel structure building, can ensure the normal use of the existing steel structure building, and can not only improve the convenience and the efficiency of expanding and installing the large-span large-format suspended ceiling of the steel structure building, and the cost of installing the large-span large-breadth suspended ceiling is reduced, and the labor intensity of workers is reduced.
Drawings
FIG. 1 is a schematic structural view of a limiting device in a method for moving and constructing a large-span and large-breadth suspended ceiling according to the present invention;
fig. 2 is a schematic diagram of a partial top view structure of a limiting device in a mobile construction method of a large-span and large-breadth suspended ceiling.
In the figure: a 1U plate, a 2 groove, a 3 screw rod, a 4 sleeve, a 5 baffle ring, a 6 fixing nut, a 7 first electric push rod, an 8 braking block, a 9 auxiliary mechanism, a 91 fixing frame, a 92 roller, a 93 second electric push rod, a 94 clamping block and a 10U handle.
Description of the embodiments
The following description of the technical solutions in the embodiments of the present invention will be clear and complete, and it is obvious that the described embodiments are only some embodiments of the present invention, but not all embodiments. All other embodiments, which can be made by those skilled in the art based on the embodiments of the invention without making any inventive effort, are intended to be within the scope of the invention.
Referring to fig. 1-2, a method for mobile construction of a large-span and large-format suspended ceiling includes the following steps:
s1, firstly fixing struts of a large-span large-breadth suspended ceiling according to a drawing, then assembling a plurality of limiting devices, and then assembling the large-span large-breadth suspended ceiling with a steel structure on the ground;
s2, next, installing each limiting device on a strut of the large-span large-breadth suspended ceiling, and simultaneously assembling the large-span large-breadth suspended ceiling with the steel structure on a plurality of limiting devices;
s3, fixing the welded and assembled steel structure large-span large-breadth suspended ceiling on a limiting device, and guaranteeing that the steel structure large-span large-breadth suspended ceiling cannot shake when being lifted upwards;
s4, hanging the steel structure large-span large-breadth suspended ceiling on a plurality of cranes simultaneously through hanging ropes, then hanging the steel structure large-span large-breadth suspended ceiling on the plurality of cranes simultaneously, moving a limiting device upwards along a support column of the large-span large-breadth suspended ceiling in the hanging process of the steel structure large-span large-breadth suspended ceiling, stopping hanging when the limiting device moves to the top of the support column of the large-span large-breadth suspended ceiling, and starting a fixing device of an internal braking mechanism of the limiting device;
s5, then, a worker moves the hydraulic lifter to the side of the large-span large-breadth suspended ceiling pillar, meanwhile, the worker takes the hydraulic lifter to rise to the top of the large-span large-breadth suspended ceiling pillar, and pushes the large-span large-breadth suspended ceiling of the steel structure to the top of the pillar through a limiting device top roller mechanism, and the process does not need to repeatedly adjust a crane to align the large-span large-breadth suspended ceiling of the steel structure, so that time and labor are saved;
s6, finally, fixing the large-span large-breadth suspended ceiling of the steel structure with the top of the support column by a worker through the connecting piece and the tool, and then removing the crane to enable the large-span large-breadth suspended ceiling of the steel structure to be movably installed without disassembling the scaffold, thereby saving time and labor.
The limiting device comprises a U-shaped plate 1, a slot 2 is formed in the outer walls of two sides of the U-shaped plate 1, a screw rod 3 is movably connected to the slot wall of the slot 2, a sleeve 4 is movably sleeved on the rod wall of the screw rod 3, a baffle ring 5 is fixedly sleeved on the rod wall of the screw rod 3, a fixing nut 6 is sleeved on the rod wall screw thread of the screw rod 3, two round holes are formed in the outer wall of the U-shaped plate 1, a first electric push rod 7 is fixedly connected to the hole wall of the round hole, an auxiliary mechanism 9 is fixedly connected to the outer wall of a tightening block 8,U plate 1, the auxiliary mechanism 9 comprises a fixing frame 91 fixedly connected with the outer wall of the U-shaped plate 1, a rectangular through hole is formed in the upper surface of the fixing frame 91, a plurality of rollers 92 are connected to the hole wall of the rectangular through rolling bearings, a clamping block 94 is connected to the top end of the second electric push rod 93 through the rolling bearings, the limiting device can ensure that a large-span suspended ceiling of the steel structure cannot shake when being lifted upwards, and the convenience of the large-span suspended ceiling installation is improved, and the auxiliary mechanism 9 is convenient for aligning and installing the large-span suspended ceiling between the large-span suspended ceiling and the large-span suspended ceiling of the steel structure.
The outer wall fixedly connected with two symmetrically distributed U-shaped handles 10 of fixation nut 6, U-shaped handles 10 can the direction rotatory fixation nut 6, and fixation nut 6 cooperation keep off ring 5 can fixing screw rod 3, and one side fixedly connected with antiskid rubber pad that the tight piece of stopping 8 kept away from first electric putter 7, antiskid rubber pad can increase the frictional force of the tight piece 8 junction surface of stopping, and then improves stop device spacing stability.
The bottom junction of the large-span large-format suspended ceiling of steel construction and the equal fixed welding in top of the large-span large-format suspended ceiling pillar have flange, and flange can make things convenient for the installation of the large-span large-format suspended ceiling of steel construction and large-span large-format suspended ceiling pillar fixed, installs wire rope on hydraulic lift's the top guardrail, and wire rope's top fixedly connected with prevents empting the couple, prevents empting the couple on suspended ceiling steel structure to cooperate wire rope can prevent that hydraulic lift from empting, improves the security of staff's operation.
In summary, according to the method for moving and constructing the large-span large-format suspended ceiling, the struts of the large-span large-format suspended ceiling are fixed according to the drawing, then a plurality of limiting devices are assembled, then the large-span large-format suspended ceiling of a steel structure is assembled on the ground, the U-shaped plate 1 of each limiting device is inserted into the suspended ceiling struts, the screw 3 is plugged into the slot, meanwhile, the fixing nuts 6 are rotated to fix the U-shaped plate 1, the suspended ceiling struts are prevented from being separated, meanwhile, the large-span large-format suspended ceiling of the steel structure is assembled on the fixing frames 91 of the plurality of limiting devices, then the clamping blocks 94 are rotated to be close to the suspended ceiling, the second electric push rods 93 are started, the clamping blocks 94 are pulled to fix the large-span large-format suspended ceiling on the top of the limiting devices in a downward moving manner, and the limiting devices can ensure that the large-span large-format suspended ceiling of the steel structure cannot shake when being lifted upwards, so that the convenience of installing the large-span large-format suspended ceiling is improved;
the method comprises the steps that a large-span large-format suspended ceiling with a steel structure is hung on a plurality of cranes at the same time through hanging ropes, then the cranes hoist the large-span large-format suspended ceiling with the steel structure at the same time, in the process of hanging the large-span large-format suspended ceiling with the steel structure, a U-shaped plate 1 and a sleeve 4 of a limiting device move upwards along a support column of the large-span large-format suspended ceiling, hanging is stopped when the limiting device moves to the top of the support column of the large-span large-format suspended ceiling, a first electric push rod 7 of the limiting device is started, a brake block 8 is pushed by the first electric push rod 7 to be close to the support column of the suspended ceiling, and the limiting device is fixed through friction between the brake block 8 and the support column of the suspended ceiling;
then the staff removes the hydraulic lift to the side of the large-span large format furred ceiling pillar, simultaneously the staff takes the hydraulic lift to rise to the large-span large format furred ceiling pillar top, then start the second hydraulic stem, the second hydraulic stem makes fixture block 94 rotatory break away from the furred ceiling, then promote the large-span large format furred ceiling of steel construction to the pillar top through stop device top cylinder 92, this process need not to adjust the crane repeatedly and counterpoint the large-span large format furred ceiling of steel construction, labour saving and time saving, finally the staff fixes the large-span large format furred ceiling of steel construction and pillar top through connecting piece and instrument, remove the crane, make the large-span large format furred ceiling of steel construction remove the installation need not to dismantle the scaffold, labour saving and time saving, do not influence current steel construction building normal use simultaneously, this mechanism can effectively shorten the time and the work load of the large-span large format furred ceiling of steel construction building extension installation, simultaneously can improve the convenience and efficiency of the large-span large format furred ceiling of steel construction extension installation, and the cost of large-span furred ceiling installation has been reduced, and the intensity of staff has been reduced.
It should be noted that the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation, an element defined by the phrase "comprising one … …" does not exclude the presence of other like elements in a process, method, article, or apparatus that comprises the element.
Although embodiments of the present invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made therein without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (3)

1. The mobile construction method of the large-span large-breadth suspended ceiling is characterized by comprising the following steps of: s1, firstly fixing struts of a large-span large-breadth suspended ceiling according to a drawing, then assembling a plurality of limiting devices, and then assembling the large-span large-breadth suspended ceiling with a steel structure on the ground;
s2, next, installing each limiting device on a strut of the large-span large-breadth suspended ceiling, and simultaneously assembling the large-span large-breadth suspended ceiling with the steel structure on a plurality of limiting devices;
s3, fixing the welded and assembled steel structure large-span large-breadth suspended ceiling on a limiting device, and guaranteeing that the steel structure large-span large-breadth suspended ceiling cannot shake when being lifted upwards;
s4, hanging the steel structure large-span large-breadth suspended ceiling on a plurality of cranes simultaneously through hanging ropes, then hanging the steel structure large-span large-breadth suspended ceiling on the plurality of cranes simultaneously, moving a limiting device upwards along a support column of the large-span large-breadth suspended ceiling in the hanging process of the steel structure large-span large-breadth suspended ceiling, stopping hanging when the limiting device moves to the top of the support column of the large-span large-breadth suspended ceiling, and starting a fixing device of an internal braking mechanism of the limiting device;
s5, then, a worker moves the hydraulic lifter to the side of the large-span large-breadth suspended ceiling pillar, meanwhile, the worker takes the hydraulic lifter to rise to the top of the large-span large-breadth suspended ceiling pillar, and pushes the large-span large-breadth suspended ceiling of the steel structure to the top of the pillar through a limiting device top roller mechanism, and the process does not need to repeatedly adjust a crane to align the large-span large-breadth suspended ceiling of the steel structure, so that time and labor are saved;
s6, finally, fixing the large-span large-breadth suspended ceiling of the steel structure with the top of the support column by a worker through a connecting piece and a tool, and then removing the crane to enable the large-span large-breadth suspended ceiling of the steel structure to be movably installed without dismounting the scaffold, so that time and labor are saved;
the limiting device comprises a U-shaped plate (1), grooves (2) are formed in the outer walls of two sides of the U-shaped plate (1), a screw rod (3) is movably connected to the groove walls of the grooves (2), a sleeve (4) is movably sleeved on the rod wall of the screw rod (3), a baffle ring (5) is fixedly sleeved on the rod wall of the screw rod (3), a fixing nut (6) is sleeved on the rod wall of the screw rod (3) through threads, two round holes are formed in the outer wall of the U-shaped plate (1), a first electric push rod (7) is fixedly connected to the hole wall of each round hole, a brake block (8) is fixedly connected to the output end of each first electric push rod (7), and an auxiliary mechanism (9) is fixedly connected to the outer wall of the U-shaped plate (1);
the auxiliary mechanism (9) comprises a fixed frame (91) fixedly connected with the outer wall of the U-shaped plate (1), a rectangular through hole is formed in the upper surface of the fixed frame (91), a plurality of rollers (92) are connected to the hole wall of the rectangular through hole through rolling bearings, a second electric push rod (93) is fixedly connected to the outer wall of the fixed frame (91), and a clamping block (94) is connected to the top end of the second electric push rod (93) through the rolling bearings;
a steel wire rope is arranged on the top guardrail of the hydraulic lifter, and the top end of the steel wire rope is fixedly connected with an anti-toppling hook;
one side of the braking block (8) far away from the first electric push rod (7) is fixedly connected with an anti-skid rubber pad.
2. The large-span large-format suspended ceiling mobile construction method according to claim 1, characterized in that the outer wall of the fixing nut (6) is fixedly connected with two symmetrically distributed U-shaped handles (10).
3. The mobile construction method for the large-span large-format suspended ceiling according to claim 1, wherein connecting flanges are fixedly welded at the bottom connecting part of the large-span large-format suspended ceiling of the steel structure and at the top ends of the large-span large-format suspended ceiling struts.
CN202210233227.5A 2022-03-10 2022-03-10 Large-span large-breadth suspended ceiling mobile construction method Active CN114439247B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202210233227.5A CN114439247B (en) 2022-03-10 2022-03-10 Large-span large-breadth suspended ceiling mobile construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202210233227.5A CN114439247B (en) 2022-03-10 2022-03-10 Large-span large-breadth suspended ceiling mobile construction method

Publications (2)

Publication Number Publication Date
CN114439247A CN114439247A (en) 2022-05-06
CN114439247B true CN114439247B (en) 2023-11-17

Family

ID=81359774

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202210233227.5A Active CN114439247B (en) 2022-03-10 2022-03-10 Large-span large-breadth suspended ceiling mobile construction method

Country Status (1)

Country Link
CN (1) CN114439247B (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0048468A1 (en) * 1980-09-22 1982-03-31 Kurt Pätz Holding device for frontal adjusting boards for the casting of concrete for ceilings of buildings
CN101338582A (en) * 2008-07-25 2009-01-07 中铁四局集团有限公司 Movable hanging basket type construction method for large-span large-breadth suspended ceiling
CN101769032A (en) * 2009-12-28 2010-07-07 中国水电顾问集团华东勘测设计研究院 Long-span suspended ceiling structure of underground plant and construction technology thereof
CN204152181U (en) * 2014-10-24 2015-02-11 中铁航空港建设集团北京有限公司 A kind of high-altitude hanging horizontal shifting platform
CN206299107U (en) * 2016-12-26 2017-07-04 天津博斯特膜装饰工程有限公司 Without scaffold hanging basket
CN112942852A (en) * 2021-01-27 2021-06-11 关国荣 Hoisting method for large-span steel structure
CN113323405A (en) * 2021-06-10 2021-08-31 中国建筑第八工程局有限公司 Sliding construction method applied to large-span steel structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP0048468A1 (en) * 1980-09-22 1982-03-31 Kurt Pätz Holding device for frontal adjusting boards for the casting of concrete for ceilings of buildings
CN101338582A (en) * 2008-07-25 2009-01-07 中铁四局集团有限公司 Movable hanging basket type construction method for large-span large-breadth suspended ceiling
CN101769032A (en) * 2009-12-28 2010-07-07 中国水电顾问集团华东勘测设计研究院 Long-span suspended ceiling structure of underground plant and construction technology thereof
CN204152181U (en) * 2014-10-24 2015-02-11 中铁航空港建设集团北京有限公司 A kind of high-altitude hanging horizontal shifting platform
CN206299107U (en) * 2016-12-26 2017-07-04 天津博斯特膜装饰工程有限公司 Without scaffold hanging basket
CN112942852A (en) * 2021-01-27 2021-06-11 关国荣 Hoisting method for large-span steel structure
CN113323405A (en) * 2021-06-10 2021-08-31 中国建筑第八工程局有限公司 Sliding construction method applied to large-span steel structure

Also Published As

Publication number Publication date
CN114439247A (en) 2022-05-06

Similar Documents

Publication Publication Date Title
CN108979131B (en) Integral lifting platform device for high-rise building construction steel formwork and operation frame
CN111677299A (en) Lifting device and method for steel bar truss floor support plate
CN104746883A (en) Construction method for three-crane lifting installation used for bow-shaped space truss
CN111456425A (en) Temporary supporting device, temporary supporting structure and temporary supporting method for floor bearing plate
CN114439247B (en) Large-span large-breadth suspended ceiling mobile construction method
CN210316214U (en) Assembled steel construction building dysmorphism post
JP2011162298A (en) Installing construction method and device for overhead crane
CN208534069U (en) The assembled support device of steel bar truss floor support plate composite floor system
CN217400394U (en) High-altitude manual hoisting profiled steel sheet construction device
CN216515141U (en) Novel cantilever construction creeping formwork device
JP2001115422A (en) Dismantling method of supporting for form fixed to concrete slab
CN111704058B (en) Hoisting and lifting device
CN212773550U (en) Lifting and pulling device for steel bar truss floor support plate
CN208648517U (en) Cladding glass installation self-control electric hoist hanger system
CN111042538A (en) Hoisting and mounting method of buckling restrained brace
CN112761079A (en) Quick installation device of wet joint suspended formwork bottom plate
CN218950808U (en) Be used for prefabricated T roof beam template to install and remove hoist
CN219217235U (en) Detachable prefabricated plate lifting device
CN205476466U (en) Formwork system is hoisted in segmentation of large -span shaped steel concrete conversion truss
CN219819620U (en) Auxiliary tool for threading steel wire rope during traveling crane
CN216551591U (en) Detachable device of cast-in-place box girder steel pipe
CN210396225U (en) Exempt from to set up and tear concrete floor equipment open
CN218088703U (en) Steel bar truss building carrier plate installation device
CN215107150U (en) Stiff beam pouring support structure
CN218715112U (en) Fast-assembling quick detach device for sideboard of building floor template

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant