CN114059568A - River bank slope multiple ecological anchor pad protection construction method - Google Patents
River bank slope multiple ecological anchor pad protection construction method Download PDFInfo
- Publication number
- CN114059568A CN114059568A CN202111566409.6A CN202111566409A CN114059568A CN 114059568 A CN114059568 A CN 114059568A CN 202111566409 A CN202111566409 A CN 202111566409A CN 114059568 A CN114059568 A CN 114059568A
- Authority
- CN
- China
- Prior art keywords
- anchor
- slope
- pad
- plant
- protection
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 238000010276 construction Methods 0.000 title claims abstract description 51
- 239000002689 soil Substances 0.000 claims abstract description 31
- 239000000463 material Substances 0.000 claims abstract description 22
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 16
- 238000000034 method Methods 0.000 claims abstract description 11
- 238000004873 anchoring Methods 0.000 claims description 24
- 239000010410 layer Substances 0.000 claims description 18
- 239000000835 fiber Substances 0.000 claims description 15
- 239000002131 composite material Substances 0.000 claims description 12
- 239000011241 protective layer Substances 0.000 claims description 12
- 238000007711 solidification Methods 0.000 claims description 9
- 230000008023 solidification Effects 0.000 claims description 9
- 238000009434 installation Methods 0.000 claims description 5
- 239000000758 substrate Substances 0.000 claims description 4
- 238000009412 basement excavation Methods 0.000 claims description 3
- 239000004746 geotextile Substances 0.000 claims description 3
- 238000007689 inspection Methods 0.000 claims description 3
- 238000012423 maintenance Methods 0.000 claims description 3
- 230000000050 nutritive effect Effects 0.000 claims description 3
- 239000008262 pumice Substances 0.000 claims description 3
- 230000008439 repair process Effects 0.000 claims description 3
- 239000011435 rock Substances 0.000 claims description 3
- 239000004576 sand Substances 0.000 claims description 3
- 238000009958 sewing Methods 0.000 claims description 3
- 239000000725 suspension Substances 0.000 claims description 3
- 230000007306 turnover Effects 0.000 claims description 3
- 230000015572 biosynthetic process Effects 0.000 claims 1
- 230000000694 effects Effects 0.000 abstract description 4
- 230000008569 process Effects 0.000 abstract description 4
- 230000006641 stabilisation Effects 0.000 abstract description 3
- 238000011105 stabilization Methods 0.000 abstract description 3
- 239000011159 matrix material Substances 0.000 abstract description 2
- 230000003014 reinforcing effect Effects 0.000 abstract description 2
- 238000010899 nucleation Methods 0.000 abstract 1
- 238000004162 soil erosion Methods 0.000 abstract 1
- 241000196324 Embryophyta Species 0.000 description 42
- 238000009991 scouring Methods 0.000 description 5
- 239000004567 concrete Substances 0.000 description 4
- 230000006378 damage Effects 0.000 description 4
- 238000010586 diagram Methods 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 2
- 238000005187 foaming Methods 0.000 description 2
- 239000002344 surface layer Substances 0.000 description 2
- 230000004083 survival effect Effects 0.000 description 2
- 238000009941 weaving Methods 0.000 description 2
- 230000009471 action Effects 0.000 description 1
- 230000009286 beneficial effect Effects 0.000 description 1
- 239000004568 cement Substances 0.000 description 1
- 239000004035 construction material Substances 0.000 description 1
- 238000007599 discharging Methods 0.000 description 1
- 230000003628 erosive effect Effects 0.000 description 1
- 239000011174 green composite Substances 0.000 description 1
- 230000002262 irrigation Effects 0.000 description 1
- 238000003973 irrigation Methods 0.000 description 1
- 239000004570 mortar (masonry) Substances 0.000 description 1
- 230000002093 peripheral effect Effects 0.000 description 1
- 229920000642 polymer Polymers 0.000 description 1
- 239000002002 slurry Substances 0.000 description 1
- 238000009331 sowing Methods 0.000 description 1
- 239000004575 stone Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
-
- A—HUMAN NECESSITIES
- A01—AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
- A01C—PLANTING; SOWING; FERTILISING
- A01C1/00—Apparatus, or methods of use thereof, for testing or treating seed, roots, or the like, prior to sowing or planting
- A01C1/04—Arranging seed on carriers, e.g. on tapes, on cords ; Carrier compositions
- A01C1/044—Sheets, multiple sheets or mats
-
- A—HUMAN NECESSITIES
- A01—AGRICULTURE; FORESTRY; ANIMAL HUSBANDRY; HUNTING; TRAPPING; FISHING
- A01G—HORTICULTURE; CULTIVATION OF VEGETABLES, FLOWERS, RICE, FRUIT, VINES, HOPS OR SEAWEED; FORESTRY; WATERING
- A01G24/00—Growth substrates; Culture media; Apparatus or methods therefor
- A01G24/40—Growth substrates; Culture media; Apparatus or methods therefor characterised by their structure
- A01G24/48—Growth substrates; Culture media; Apparatus or methods therefor characterised by their structure containing foam or presenting a foam structure
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/20—Securing of slopes or inclines
- E02D17/202—Securing of slopes or inclines with flexible securing means
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/005—Soil-conditioning by mixing with fibrous materials, filaments, open mesh or the like
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/74—Means for anchoring structural elements or bulkheads
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2600/00—Miscellaneous
- E02D2600/30—Miscellaneous comprising anchoring details
Landscapes
- Engineering & Computer Science (AREA)
- Life Sciences & Earth Sciences (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- General Engineering & Computer Science (AREA)
- Civil Engineering (AREA)
- Paleontology (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Soil Sciences (AREA)
- Environmental Sciences (AREA)
- Agronomy & Crop Science (AREA)
- Environmental & Geological Engineering (AREA)
- Revetment (AREA)
Abstract
The invention discloses a construction method for protecting a river bank slope multiple ecological anchor pad, which comprises a soil curing pad, a side slope, plant sponges, a plant protection pad, a fixing plate and an anchor rod of an expansion type anchor head; adopt the plant sponge, plant protection pad material builds the growth matrix of side slope seeding plant, form biological protection blanket, when increasing the ecological afforestation of river course, increase the scour protection ability of side slope, reduce bank protection soil erosion and water loss, the anchor pad construction adopts the artifical stock fastening of laying the cooperation area fixed plate, compare traditional ecological bank protection, rigidity bank protection efficiency of construction is high, the cost of labor greatly reduced, adopt the stock and the fixed plate of taking expansion anchor head to closely laminate multiple anchor pad and side slope, utilize anchor head expansion reinforcing anchor stabilization effect, still increase the domatic shallow layer stability in stock region, compare traditional rigidity bank protection, the construction process is succinct, when improving the efficiency of construction, add the ecological greening function of river course bank slope, in project practical application, gain good economic benefits.
Description
Technical Field
The invention relates to the technical field of reservoirs, riverways and irrigation areas, in particular to a construction method for protecting multiple ecological anchor pads on a bank slope of a riverway.
Background
The bank slope of the river channel rises and falls along with the water level of river water to form a dry-wet alternate section, and water and soil loss is easily caused under the action of long-time submergence and water flow scouring. The soil of the slope protection can not be ensured only by the soil stabilization of the plant root system, so the engineering measures in the forms of dry masonry slope protection, slurry masonry slope protection, concrete panels and the like are combined by common concrete, mortar and stone materials. However, the construction cost of the rigid revetment is high, and the cement and the concrete damage and pollute the environment and weaken the natural ecological environment of the river bank slope. Although the ecological concrete slope protection keeps the landscape function of the slope protection, the construction is more complex, and the plant survival rate is not easy to control.
Therefore, the technical personnel in the field provide a construction method for protecting multiple ecological anchor pads on the bank slope of the river channel so as to solve the problems in the background technology.
Disclosure of Invention
The invention aims to provide a construction method for protecting multiple ecological anchor pads on a river bank slope, and aims to solve the problems in the background technology.
In order to achieve the purpose, the invention provides the following technical scheme:
the river bank slope multiple ecological anchor pad protection construction method comprises a soil solidification pad 1; a side slope 2; a plant sponge 3; a plant protection pad 4; the fixed plate 5 and the anchor rod 6 of the expanding anchor head are characterized in that the construction method for protecting the river bank slope multiple ecological anchor pads comprises the following specific steps:
s1; leveling the side slope; the method is characterized in that the steps of layering and segmenting are sequentially carried out from top to bottom, the excavation method of inverted suspension is strictly forbidden from bottom to top or adopted, a certain slope potential is formed at any time in slope construction, drainage is facilitated, one-step forming is achieved, the site is cleaned after the construction is finished, pumice, loose rocks, sundries and the like are removed, the surface of the slope is made to be flat as far as possible, effective combination of slope protection components and the slope is facilitated, an anchoring ditch is excavated under the condition that the slope is steep, the width and the depth of the anchoring ditch can be determined according to the slope of the slope, and the anchoring ditch is set to be rectangular.
S2; paving a soil curing mat; the soil solidification pad is a composite geomembrane, including the protective layer below and the filter layer of laying above the protective layer, the geotextile thickness of the composite geomembrane both sides is 1.5 ~ 3.0mm has along the ability of plane direction drainage, make the fibre of protective layer thicker than the fibre of filter layer, and the fibre of protective layer is greater than the fibre space of filter layer, soil solidification pad is laid, it lays to cross the protection slope central line direction with the slice, at first transport composite geomembrane to the top of slope, turn over from the top of slope anchor ditch again, lay downwards, along with laying and pushing down with at the top of slope with sand bag or boulder and prevent sliding, 30cm of overlap joint is made up with electric sewing machine, after laying, apparent inspection, repair the damaged department of composite geomembrane.
S3; paving plant sponge; plant sponge divide into about two-layer, it constitutes plant seed layer with nutritive substrate to set up in the middle of, the thickness of upper sponge is less than the thickness setting of lower floor's sponge, can make things convenient for the root system of plant to grow towards lower floor's sponge more, the stem of plant is towards upper sponge growth and impales the outside growth of upper sponge, furthermore, the upper surface of lower floor's sponge becomes the curved surface that the fluctuation set up, the continuous direction and the bank length direction of curved surface hunch-up position are unanimous, plant seed chooses for use the plant seed that suits local growth, evenly spill on plant sponge, plant sponge material prepares to accomplish the back, it lays to prolong domatic from the top down, lay adjacent material and closely arrange, prevent the landing.
S5; laying a plant protection pad; the plant protection pad adopts fibers with unique section shapes, a three-dimensional structure is formed by vertically weaving warps and wefts, and meshes of a single structure consist of a series of open matrixes and are in an inverted quadrangular pyramid shape. When the protection pad is laid, the protection pad is laid from top to bottom, adjacent structural units are mutually connected through corresponding bottom edges, and pyramid fixed points of all unit structures are used as supporting parts for the surfaces of the protection slopes to be attached to each other.
S6; driving an anchor rod; domatic anchor pad anchor adopts the anchor rod of taking the expansion head, and the anchor head adopts the arrow point form, and stock length is 1.5m, arranges to adopt plum blossom type stock to beat the point, and interval 5m relies on stock application of force end application of force, pulls the anchor rod after the anchor head squeezes into the soil body for the position between anchor member and the anchor rod is crowded to the soil body, forces the anchor member to rotate for the outside open mode of rear end, and it is spacing to receive limit structure until the outside angle of opening of anchor member.
S7; installing a fastening plate; after the anchor rod is driven in, the thread section of the end part of the anchor rod is utilized to be leaked, and a fixing plate is arranged. The middle part of the fixing plate is provided with a threaded hole and is screwed on the threaded section, so that the fastening plate is ensured to rotate to the position during installation until the anchor pads around the fastening plate deform slightly.
S8; watering and maintaining; after the anchor pad is paved and reinforced, clear water is sprayed on the surface of the anchor pad to completely wet the anchor pad, the anchor pad is sprayed once in the morning and at night, the sprayed water is sufficient to keep humidity, personnel are strictly prohibited to walk on the anchor pad during maintenance so as to avoid treading on the germinated seedlings, and when the seeds planted in the anchor pad grow into green skin, the biological protection blanket is formed.
As a further scheme of the invention: when the materials are laid, the materials are lapped, so that the materials are tightly attached to each other, and dislocation caused by influence of water flow scouring after installation is avoided.
As a still further scheme of the invention: the length of the anchor rod is judged according to the loose degree of the soil property of the side slope on site, and the length meeting the anchoring requirement on site is determined through a drawing test.
As a still further scheme of the invention: when the anchoring rod piece is constructed, the anchoring rod is driven into the gap of the plant protection pad on the surface, so that the damage to the material of the surface layer is reduced, and the anchoring depth and the construction arrangement interval meet the requirements of a construction scheme.
As a still further scheme of the invention: selecting a month with the average temperature of 10-15 ℃ continuously for working in the construction time; after the construction is finished, the seedlings which just sprout are prevented from being treaded by the anchor pads without walking on the anchor pads.
Compared with the prior art, the invention has the beneficial effects that:
the plant sponge and the plant protection pad material are adopted to build the growth matrix of the slope sowing plant, so that the biological protection blanket is formed, the ecological greening of the river channel is increased, the anti-scouring capability of the slope is increased, and the water and soil loss of the slope protection is reduced.
Anchor pad construction adopts the artifical stock fastening of laying the cooperation area fixed plate, and slope protection construction easy operation compares traditional ecological bank protection, rigidity bank protection efficiency of construction height, cost of labor greatly reduced.
Adopt the stock and the fixed plate of taking expanding anchor head to closely laminate multiple anchor pad and side slope, utilize anchor head expansion reinforcing anchor stabilization effect, still increase the regional domatic shallow layer stability of stock.
Compared with the traditional rigid revetment, the construction process is simple, the construction efficiency is improved, meanwhile, the ecological greening function of the river bank slope is added, and good economic benefits are obtained in the project practical application; combine each layer geotechnological material's organic combination, realize the green protection of side slope, improved the plant survival rate, construction material quality is light simultaneously, and the appearance is pleasing to the eye and plasticity is strong, and construction process is simple, and is easy and simple to handle, is applicable to multiple side slope, and the turf root system after growing combines together with earth to form the firm green composite protection layer of one deck, strengthens anti impact effect and view effect, avoids the destruction of traditional construction process to the environment, and application prospect is extensive in the peripheral bank protection construction of water.
Drawings
Fig. 1 is a schematic structural diagram of a construction method for protecting multiple ecological anchor pads on a river bank slope.
Fig. 2 is a schematic diagram of an anchor pad protection construction structure of the river bank slope multiple ecological anchor pad protection construction method.
Fig. 3 is a schematic diagram of an anchoring rod structure of a construction method for protecting multiple ecological anchor pads on a river bank slope.
Fig. 4 is a left view of an anchoring rod of the construction method for protecting multiple ecological anchor pads on a river bank slope.
In the figure: 1-soil curing mat; 2-side slope; 3-a plant sponge; 4-plant protection pad; 5, fixing a plate; 6-anchor rod of expanding anchor head.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1 to 4, in the embodiment of the present invention, a construction method for protecting multiple ecological anchor pads on a river bank slope includes a soil solidification pad 1; a side slope 2; a plant sponge 3; a plant protection pad 4; the fixed plate 5 and the anchor rod 6 of the expanding anchor head are characterized in that the construction method for protecting the river bank slope multiple ecological anchor pads comprises the following specific steps:
s1; leveling the side slope; the method is characterized in that the steps of layering and segmenting are sequentially carried out from top to bottom, the excavation method of inverted suspension is strictly forbidden from bottom to top or adopted, a certain slope potential is formed at any time in slope construction, drainage is facilitated, one-step forming is achieved, the site is cleaned after the construction is finished, pumice, loose rocks, sundries and the like are removed, the surface of the slope is made to be flat as far as possible, effective combination of slope protection components and the slope is facilitated, an anchoring ditch is excavated under the condition that the slope is steep, the width and the depth of the anchoring ditch can be determined according to the slope of the slope, and the anchoring ditch is set to be rectangular.
S2; paving a soil curing mat; the soil solidification pad is a composite geomembrane, including the protective layer below and the filter layer of laying above the protective layer, the geotextile thickness of the composite geomembrane both sides is 1.5 ~ 3.0mm has along the ability of plane direction drainage, make the fibre of protective layer thicker than the fibre of filter layer, and the fibre of protective layer is greater than the fibre space of filter layer, soil solidification pad is laid, it lays to cross the protection slope central line direction with the slice, at first transport composite geomembrane to the top of slope, turn over from the top of slope anchor ditch again, lay downwards, along with laying and pushing down with at the top of slope with sand bag or boulder and prevent sliding, 30cm of overlap joint is made up with electric sewing machine, after laying, apparent inspection, repair the damaged department of composite geomembrane.
S3; paving plant sponge; plant sponge divide into about two-layer, it constitutes plant seed layer with nutritive substrate to set up in the middle of, the thickness of upper sponge is less than the thickness setting of lower floor's sponge, can make things convenient for the root system of plant to grow towards lower floor's sponge more, the stem of plant is towards upper sponge growth and impales the outside growth of upper sponge, furthermore, the upper surface of lower floor's sponge becomes the curved surface that the fluctuation set up, the continuous direction and the bank length direction of curved surface hunch-up position are unanimous, plant seed chooses for use the plant seed that suits local growth, evenly spill on plant sponge, plant sponge material prepares to accomplish the back, it lays to prolong domatic from the top down, lay adjacent material and closely arrange, prevent the landing.
S5; laying a plant protection pad; the plant protection pad adopts fibers with unique section shapes, a three-dimensional structure is formed by vertically weaving warps and wefts, and meshes of a single structure consist of a series of open matrixes and are in an inverted quadrangular pyramid shape. When the protection pad is laid, the protection pad is laid from top to bottom, adjacent structural units are mutually connected through corresponding bottom edges, and pyramid fixed points of all unit structures are used as supporting parts for the surfaces of the protection slopes to be attached to each other.
S6; driving an anchor rod; domatic anchor pad anchor adopts the anchor rod of taking the expansion head, and the anchor head adopts the arrow point form, and stock length is 1.5m, arranges to adopt plum blossom type stock to beat the point, and interval 5m relies on stock application of force end application of force, pulls the anchor rod after the anchor head squeezes into the soil body for the position between anchor member and the anchor rod is crowded to the soil body, forces the anchor member to rotate for the outside open mode of rear end, and it is spacing to receive limit structure until the outside angle of opening of anchor member.
S7; installing a fastening plate; after the anchor rod is driven in, the thread section of the end part of the anchor rod is utilized to be leaked, and a fixing plate is arranged. The middle part of the fixing plate is provided with a threaded hole and is screwed on the threaded section, so that the fastening plate is ensured to rotate to the position during installation until the anchor pads around the fastening plate deform slightly.
S8; watering and maintaining; after the anchor pad is paved and reinforced, clear water is sprayed on the surface of the anchor pad to completely wet the anchor pad, the anchor pad is sprayed once in the morning and at night, the sprayed water is sufficient to keep humidity, personnel are strictly prohibited to walk on the anchor pad during maintenance so as to avoid treading on the germinated seedlings, and when the seeds planted in the anchor pad grow into green skin, the biological protection blanket is formed.
As a further scheme of the invention: when the materials are laid, the materials are lapped, so that the materials are tightly attached to each other, and dislocation caused by influence of water flow scouring after installation is avoided.
As a still further scheme of the invention: the length of the anchor rod is judged according to the loose degree of the soil property of the side slope on site, and the length meeting the anchoring requirement on site is determined through a drawing test.
As a still further scheme of the invention: when the anchoring rod piece is constructed, the anchoring rod is driven into the gap of the plant protection pad on the surface, so that the damage to the material of the surface layer is reduced, and the anchoring depth and the construction arrangement interval meet the requirements of a construction scheme.
As a still further scheme of the invention: selecting a month with the average temperature of 10-15 ℃ continuously for working in the construction time; after the construction is finished, the seedlings which just sprout are prevented from being treaded by the anchor pads without walking on the anchor pads.
The working principle of the invention is as follows: after the slope foundation is leveled and cleaned, anchoring ditches are excavated at the top and the bottom of the slope, soil curing pads are paved from the top anchoring ditches to the bottom anchoring ditches for discharging seepage water from the slope to ensure stable silt, plant seeds suitable for local growth are uniformly scattered on plant sponges formed by mixing and foaming polymer foaming materials and organic matters or inorganic matters in a certain proportion to provide growth substrates for vegetation, plant roots penetrate through the plant sponges to be connected with the soil curing pads and the soil to form an anti-scouring biological protection blanket, then the plant sponges are paved along the slope from top to bottom, then plant protection pads are paved to reduce erosion of plant roots in normal growth, finally an anchor rod with an expanding anchor head is used for driving into the soil body for anchoring and locking, and the slope is integrally anchored by matching with screw threads at the end of the anchor rod and screw fastening of a fixing plate.
It will be evident to those skilled in the art that the invention is not limited to the details of the foregoing illustrative embodiments, and that the present invention may be embodied in other specific forms without departing from the spirit or essential attributes thereof. The present embodiments are therefore to be considered in all respects as illustrative and not restrictive, the scope of the invention being indicated by the appended claims rather than by the foregoing description, and all changes which come within the meaning and range of equivalency of the claims are therefore intended to be embraced therein. Any reference sign in a claim should not be construed as limiting the claim concerned.
Furthermore, it should be understood that although the present description refers to embodiments, not every embodiment may contain only a single embodiment, and such description is for clarity only, and those skilled in the art should integrate the description, and the embodiments may be combined as appropriate to form other embodiments understood by those skilled in the art.
Claims (5)
1. The river bank slope multiple ecological anchor pad protection construction method comprises a soil solidification pad 1, a side slope 2, plant sponge 3, a plant protection pad 4, a fixing plate 5 and an anchor rod 6 of an expansion type anchor head; the construction method is characterized by comprising the following steps:
s1; leveling the side slope; the method is characterized in that the steps of layering and segmenting are sequentially carried out from top to bottom, the excavation method of inverted suspension is strictly forbidden from bottom to top or adopted, a certain slope potential is formed at any time in slope construction, drainage is facilitated, one-step forming is achieved, the site is cleaned after the construction is finished, pumice, loose rocks, sundries and the like are removed, the surface of the slope is made to be flat as far as possible, effective combination of slope protection components and the slope is facilitated, an anchoring ditch is excavated under the condition that the slope is steep, the width and the depth of the anchoring ditch can be determined according to the slope of the slope, and the anchoring ditch is set to be rectangular.
S2; paving a soil curing mat; the soil solidification pad is a composite geomembrane, including the protective layer below and the filter layer of laying above the protective layer, the geotextile thickness of the composite geomembrane both sides is 1.5 ~ 3.0mm has along the ability of plane direction drainage, make the fibre of protective layer thicker than the fibre of filter layer, and the fibre of protective layer is greater than the fibre space of filter layer, soil solidification pad is laid, it lays to cross the protection slope central line direction with the slice, at first transport composite geomembrane to the top of slope, turn over from the top of slope anchor ditch again, lay downwards, along with laying and pushing down with at the top of slope with sand bag or boulder and prevent sliding, 30cm of overlap joint is made up with electric sewing machine, after laying, apparent inspection, repair the damaged department of composite geomembrane.
S3; paving plant sponge; plant sponge divide into about two-layer, it constitutes plant seed layer with nutritive substrate to set up in the middle of, the thickness of upper sponge is less than the thickness setting of lower floor's sponge, can make things convenient for the root system of plant to grow towards lower floor's sponge more, the stem of plant is towards upper sponge growth and impales the outside growth of upper sponge, furthermore, the upper surface of lower floor's sponge becomes the curved surface that the fluctuation set up, the continuous direction and the bank length direction of curved surface hunch-up position are unanimous, plant seed chooses for use the plant seed that suits local growth, evenly spill on plant sponge, plant sponge material prepares to accomplish the back, it lays to prolong domatic from the top down, it closely arranges to lay adjacent material.
S5; laying a plant protection pad; plant protection pad adopts the fibre that has unique cross sectional shape, through warp and weft's perpendicular three-dimensional structure who weaves formation, and the single mesh of structure comprises a series of open matrixes, is the four pyramid of falling, when laying the protection pad, lays from the top down equally, links up each other through the base that corresponds through adjacent constitutional unit, utilizes the pyramid fixed point of each unit construction to be the supporting part that the bank protection surface leaned on mutually.
S6; driving an anchor rod; domatic anchor pad anchor adopts the anchor rod of taking the expansion head, and the anchor head adopts the arrow point form, and stock length is 1.5m, arranges to adopt plum blossom type stock to beat the point, and interval 5m relies on stock application of force end application of force, pulls the anchor rod after the anchor head squeezes into the soil body for the position between anchor member and the anchor rod is crowded to the soil body, forces the anchor member to rotate for the outside open mode of rear end, and it is spacing to receive limit structure until the outside angle of opening of anchor member.
S7; installing a fastening plate; after the anchor rod is driven in, the thread section of the end part of the anchor rod is utilized to be leaked, and a fixing plate is arranged. The middle part of the fixing plate is provided with a threaded hole and is screwed on the threaded section, so that the fastening plate is ensured to rotate to the position during installation until the anchor pads around the fastening plate deform slightly.
S8; watering and maintaining; after the anchor pad is paved and reinforced, clear water is sprayed on the surface of the anchor pad to completely wet the anchor pad, the anchor pad is sprayed once in the morning and at night, the sprayed water is sufficient to keep humidity, personnel are strictly prohibited to walk on the anchor pad during maintenance, and seeds are planted in the anchor pad to grow into green skin to form the biological protection blanket.
2. The river bank slope multiple ecological anchor mat protection construction method as claimed in claim 1, wherein when the materials are laid, overlapping of the materials is paid attention to, and the materials are guaranteed to be tightly attached to each other.
3. The river bank slope multiple ecological anchor pad protection construction method according to claim 1, wherein the length of the anchor rod is judged according to the loose degree of the soil property of the on-site slope, and the length meeting the on-site anchoring requirement is determined through a drawing test.
4. The method for constructing a river bank slope multiple ecological anchor pad protection as claimed in claim 1, wherein during the construction of the anchor rod member, the anchor rod is driven into the gap of the surface plant protection pad.
5. The river bank slope multiple ecological anchor pad protection construction method as claimed in claim 1, wherein the construction time is selected to be suitable for working in months with the average monthly temperature of 10-15 ℃.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111566409.6A CN114059568A (en) | 2021-12-18 | 2021-12-18 | River bank slope multiple ecological anchor pad protection construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111566409.6A CN114059568A (en) | 2021-12-18 | 2021-12-18 | River bank slope multiple ecological anchor pad protection construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN114059568A true CN114059568A (en) | 2022-02-18 |
Family
ID=80230029
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202111566409.6A Pending CN114059568A (en) | 2021-12-18 | 2021-12-18 | River bank slope multiple ecological anchor pad protection construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN114059568A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117868043A (en) * | 2023-12-15 | 2024-04-12 | 重庆地质矿产研究院 | Protection system for river water resources in southwest karst mountain area |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US7384217B1 (en) * | 2007-03-29 | 2008-06-10 | Barrett Robert K | System and method for soil stabilization of sloping surface |
CN202509450U (en) * | 2012-03-21 | 2012-10-31 | 刘威 | Ecological slope protection device |
CN110042798A (en) * | 2019-04-25 | 2019-07-23 | 重庆交通大学 | A kind of falling zone ecology maintenance system and its falling zone bank slope afforest guard method |
-
2021
- 2021-12-18 CN CN202111566409.6A patent/CN114059568A/en active Pending
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US7384217B1 (en) * | 2007-03-29 | 2008-06-10 | Barrett Robert K | System and method for soil stabilization of sloping surface |
CN202509450U (en) * | 2012-03-21 | 2012-10-31 | 刘威 | Ecological slope protection device |
CN110042798A (en) * | 2019-04-25 | 2019-07-23 | 重庆交通大学 | A kind of falling zone ecology maintenance system and its falling zone bank slope afforest guard method |
Non-Patent Citations (2)
Title |
---|
吴明先: "《多年冻土区公路建设环境保护关键技术》", 31 March 2019, 上海科学技术出版社 * |
顾晓鲁: "《地基与基础》", 31 May 2003, 中国建筑工业出版社 * |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN117868043A (en) * | 2023-12-15 | 2024-04-12 | 重庆地质矿产研究院 | Protection system for river water resources in southwest karst mountain area |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101818499B (en) | Revegetation system on steep rocky slopes and implementing method thereof | |
CN102444134B (en) | Slope protecting method based on slope with soil layer as upper part and rock layer as lower part | |
CN108221861A (en) | A kind of ecological slope protection structure to prevent erosion and its construction method | |
CN209482250U (en) | A kind of ecological revetment of erosion control brush-type | |
CN102359113A (en) | Integrally-cast cement pervious concrete ecological protection slope and construction method thereof | |
CN109356177A (en) | One kind is for the steady layer slope protection system of side slope water and soil conservation soil and laying method | |
CN114753385A (en) | Expansive soil slope flexible ecological supporting structure and construction method | |
CN206693140U (en) | A kind of protection slope | |
CN114059568A (en) | River bank slope multiple ecological anchor pad protection construction method | |
CN110233432A (en) | A kind of ecological revetment of erosion control brush-type | |
KR100860748B1 (en) | Honey cell greening works | |
CN113914261A (en) | Reservoir engineering concrete precast block ecological slope protection construction method | |
CN217710769U (en) | Anchor pile type geocell structure for excavation slope ecological protection | |
CN110552322A (en) | Flat-laying type slope protection structure utilizing river channel silt cleaning materials and construction method thereof | |
CN207047873U (en) | A kind of road soil-slope quick bio protector of high and cold arid area | |
CN215105078U (en) | Ecological restoration revetment | |
CN114182686B (en) | Log frame and recycled concrete combined structure ecological slope protection and construction method thereof | |
CN212896409U (en) | Three-dimensional geotechnique's net pad grass planting slope protection structure | |
CN212405193U (en) | Ecological protection structure suitable for high and steep side slope in cold area | |
CN114086507A (en) | Ecological revetment process with high water and soil retention | |
CN114164844A (en) | Construction method of square grid type organic material slope protection structure | |
CN202214733U (en) | Integrally-cast cement water-permeable concrete ecological slope protection | |
CN208379542U (en) | A kind of low water level building blocks for bank protection construction structure | |
CN110169308A (en) | A kind of high mountain hills area wind power plant sandy soil greening recovery construction method | |
CN209741870U (en) | Concrete grass planting side slope |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20220218 |