CN114016649A - Connection structure of assembled composite floor slab and cast-in-place beam - Google Patents
Connection structure of assembled composite floor slab and cast-in-place beam Download PDFInfo
- Publication number
- CN114016649A CN114016649A CN202111414888.XA CN202111414888A CN114016649A CN 114016649 A CN114016649 A CN 114016649A CN 202111414888 A CN202111414888 A CN 202111414888A CN 114016649 A CN114016649 A CN 114016649A
- Authority
- CN
- China
- Prior art keywords
- cast
- floor slab
- composite floor
- place beam
- place
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 239000002131 composite material Substances 0.000 title claims abstract description 52
- 230000003014 reinforcing effect Effects 0.000 claims description 19
- 239000004567 concrete Substances 0.000 claims description 9
- 239000011150 reinforced concrete Substances 0.000 claims description 9
- 238000009415 formwork Methods 0.000 claims description 2
- 229910000831 Steel Inorganic materials 0.000 abstract description 13
- 239000010959 steel Substances 0.000 abstract description 13
- 238000010276 construction Methods 0.000 abstract description 8
- 238000000034 method Methods 0.000 abstract description 5
- 238000004519 manufacturing process Methods 0.000 abstract description 3
- 238000004873 anchoring Methods 0.000 description 4
- 238000009434 installation Methods 0.000 description 4
- 229910001294 Reinforcing steel Inorganic materials 0.000 description 3
- 238000005728 strengthening Methods 0.000 description 3
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 238000005266 casting Methods 0.000 description 1
- 238000011065 in-situ storage Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000006467 substitution reaction Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B5/00—Floors; Floor construction with regard to insulation; Connections specially adapted therefor
- E04B5/16—Load-carrying floor structures wholly or partly cast or similarly formed in situ
- E04B5/17—Floor structures partly formed in situ
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/38—Connections for building structures in general
- E04B1/41—Connecting devices specially adapted for embedding in concrete or masonry
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C3/00—Structural elongated elements designed for load-supporting
- E04C3/02—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces
- E04C3/20—Joists; Girders, trusses, or trusslike structures, e.g. prefabricated; Lintels; Transoms; Braces of concrete or other stone-like material, e.g. with reinforcements or tensioning members
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Joining Of Building Structures In Genera (AREA)
Abstract
The invention discloses a connecting structure of an assembled composite floor slab and a cast-in-place beam, which comprises the cast-in-place beam arranged in a cast-in-place beam template and the composite floor slab connected with the cast-in-place beam in a pouring way. And two sides of the cast-in-place beam extend outwards to form a cantilever lug, and an annular stirrup used for being matched with the composite floor slab is arranged on the cantilever lug. The connection structure of the technical scheme can realize that the composite floor slab is quickly hoisted in place at a construction site, avoids collision between reserved anchor steel bars of the composite floor slab and longitudinal steel bars and stirrup of a cast-in-place beam, solves the problem that the composite floor slab is difficult to install, and does not need to carry out corner cutting at the beam-column joint when the composite floor slab is divided because of the arrangement of the longitudinal steel bars and the annular stirrup at the ear positions, the composite floor slab split by adopting the method is a regular rectangle, improves the production and construction efficiency of the composite floor slab, and ensures that the stress performance of the connection node of the composite floor slab and the cast-in-place beam is reliable.
Description
Technical Field
The invention relates to the field of building construction, in particular to a connecting structure of an assembled composite floor slab and a cast-in-place beam.
Background
When the composite floor slab and the cast-in-place beam are installed, the traditional method for designing the ribbed composite floor slab in the cast-in-place beam system firstly aligns the composite floor slab and the cast-in-place beam, however, reserved anchoring steel bars are generally arranged in the composite floor slab, and the reserved anchoring steel bars are often aligned and not easy to align when the composite floor slab is installed in an aligned mode, so that a large amount of time is wasted in aligning and binding the reserved anchoring steel bars.
Therefore, in order to solve the above problems, a connection structure of an assembled composite floor slab and a cast-in-place beam is required to solve the above problems.
Disclosure of Invention
In view of this, the connection structure of the technical scheme can realize that the composite floor slab is quickly hoisted in place at a construction site, avoids collision between reserved anchor steel bars of the composite floor slab and a cast-in-place beam, and solves the problem that the reserved anchor steel bars of the composite floor slab are difficult to install.
A connection structure of an assembled composite floor slab and a cast-in-place beam comprises the cast-in-place beam arranged in a cast-in-place beam template and the composite floor slab connected with the cast-in-place beam in a pouring mode; the cast-in-place roof beam both sides extend outward and are formed with and choose the ear, it is used for with coincide floor cooperation use annular stirrup to choose to install on the ear.
Furthermore, be provided with the vertical strengthening rib of perpendicular to annular stirrup place plane in the annular stirrup, vertical strengthening rib arranges between choosing ear and annular stirrup.
Further, be provided with in the coincide floor and reserve the anchor reinforcing bar, it is provided with the horizontal locating hole that uses with reserving the anchor reinforcing bar cooperation in the ear to choose.
Furthermore, the composite floor slab is arranged on the cast-in-place beam template, and the reinforced concrete composite layer is poured on the composite floor slab.
And further, a floor concrete layer is arranged on the reinforced concrete superposed layer and the annular stirrups, and reinforcing transverse ribs are arranged in the floor concrete layer.
Further, still include the support frame, cast-in-place roof beam template is installed on the support frame.
The invention has the beneficial effects that: the connection structure of the technical scheme can realize that the composite floor slab is quickly hoisted in place at a construction site, avoids collision between reserved anchor steel bars of the composite floor slab and a cast-in-place beam, solves the problem that the reserved anchor steel bars of the composite floor slab are difficult to install, and because of the arrangement of the longitudinal reinforcing ribs and the annular stirrups at the ear parts, the corner cut at the beam column joint is not needed when the composite floor slab is divided, the composite floor slab split by adopting the method is a regular rectangle, the production and construction efficiency of the composite floor slab is improved, and the stress performance of the connection node of the composite floor slab and the cast-in-place beam is ensured to be reliable.
Drawings
The invention is further described below with reference to the following figures and examples:
fig. 1 is a schematic view of the overall structure of the present invention.
Detailed Description
FIG. 1 is a schematic view of the overall structure of the present invention; as shown in the figure, the connection structure of the assembled composite floor slab and the cast-in-place beam comprises a cast-in-place beam 1 installed in a cast-in-place beam template 2 and a composite floor slab 5 connected with the cast-in-place beam 1 in a pouring mode; the cast-in-place roof beam 1 both sides are outwards extended and are formed with and choose ear 3, choose to install on the ear 3 and be used for the annular stirrup 6 that uses with 5 cooperations of coincide floor, this technical scheme's joint construction can realize that the coincide floor hoists fast in the job site and takes one's place, avoid the coincide floor to reserve anchor reinforcing bar and cast-in-place roof beam collision, the difficult problem of the difficult installation of coincide floor reservation anchor reinforcing bar has been solved, owing to choose the setting of ear department vertical strengthening rib and annular stirrup, the coincide floor need not to carry out the corner cut in beam column junction when dividing, the coincide floor that adopts this method split is the rectangle of rule, improve coincide floor production and efficiency of construction, guaranteed coincide floor and cast-in-place roof beam connected node atress performance reliable.
In this embodiment, a longitudinal reinforcing rib 4 perpendicular to a plane where the annular stirrup 6 is located (i.e., a rectangular cross section of the annular stirrup 6 in fig. 1) is disposed in the annular stirrup 6, and the longitudinal reinforcing rib 4 is disposed between the overhanging lug 3 and the annular stirrup 6. The arrangement of the annular stirrups 6 ensures the installation strength of the ear and the composite floor slab, ensures the stress stability, the arrangement of the longitudinal reinforcing ribs 4 ensures that the whole structure is structurally reinforced in the transverse direction and the longitudinal direction, the whole performance is improved, and after the composite floor slab 5 is installed in place, the longitudinal reinforcing ribs 4 are fixedly bound in place.
In this embodiment, be provided with in the coincide floor 5 and reserve anchor reinforcing bar 53, it is provided with the transverse orientation hole that uses with reserving anchor reinforcing bar 53 cooperation in the ear to choose. Choose ear tip to be provided with transverse orientation hole, carrying out the alignment installation of coincide floor, only need will reserve anchor reinforcing bar 53 and insert transverse orientation downthehole, can realize quick location installation.
In this embodiment, the composite floor slab 5 is installed on a cast-in-place beam formwork, and a reinforced concrete composite layer 51 is poured on the composite floor slab 5. After the reserved anchoring reinforcing steel bars 53 are inserted into the positioning holes, the reinforcing steel bars are bound and fixed, the reinforced concrete superposed layer 51 is formed after concrete is poured, and the stability of the whole structure is ensured by the reinforced concrete superposed layer 51.
In this embodiment, the reinforced concrete laminated layer 51 and the annular stirrups 6 are provided with a floor concrete layer, and the floor concrete layer is provided with reinforcing transverse ribs 52. And after the reinforced concrete laminated layer 51 is poured, continuously pouring the floor concrete layer to finish the construction.
In this embodiment, still include support frame 8, cast-in-place roof beam template is installed on support frame 8.
When the laminated floor slab is installed, the method comprises the following steps: (1) designing a cast-in-place beam template, a lug-picking template and a support frame according to the beam section and elevation specified by design requirements; (2) binding cast-in-place beam steel bars and annular stirrups and longitudinal bars of the cantilever lugs; (3) hoisting the laminated floor slab; (4) positioning and binding the longitudinal steel bars at the upper parts of the picking lugs, and binding and fixing the steel bars at the joint; (5) laying a composite floor equipment pipeline; (6) binding reinforcing steel bars on the upper part of the floor slab; (7) and (5) casting floor concrete in situ.
Finally, the above embodiments are only for illustrating the technical solutions of the present invention and not for limiting, although the present invention has been described in detail with reference to the preferred embodiments, it should be understood by those skilled in the art that modifications or equivalent substitutions may be made to the technical solutions of the present invention without departing from the spirit and scope of the technical solutions of the present invention, and all of them should be covered in the claims of the present invention.
Claims (6)
1. The utility model provides a connection structure of assembled coincide floor and cast-in-place roof beam which characterized in that: the composite floor slab comprises a cast-in-place beam arranged in a cast-in-place beam template and a composite floor slab connected with the cast-in-place beam in a pouring way; the cast-in-place roof beam both sides extend outward and are formed with and choose the ear, it is used for with coincide floor cooperation use annular stirrup to choose to install on the ear.
2. The structure of connecting an assembled composite floor slab and a cast-in-place beam according to claim 1, characterized in that: the annular stirrup is internally provided with a longitudinal reinforcing rib perpendicular to the plane where the annular stirrup is located, and the longitudinal reinforcing rib is arranged between the cantilever lug and the annular stirrup.
3. The structure of connecting an assembled composite floor slab and a cast-in-place beam according to claim 2, wherein: be provided with the reservation anchor reinforcing bar in the coincide floor, it is provided with the horizontal locating hole that uses with the cooperation of reservation anchor reinforcing bar in the ear to choose.
4. A connection structure of an assembled composite floor slab and a cast-in-place beam according to claim 3, wherein: the composite floor slab is arranged on the cast-in-place beam template, and the reinforced concrete composite layer is poured on the composite floor slab.
5. A connection structure of an assembled composite floor slab and a cast-in-place beam according to claim 4, characterized in that: and a floor concrete layer is arranged on the reinforced concrete superposed layer and the annular stirrups, and reinforcing transverse ribs are arranged in the floor concrete layer.
6. The structure of connecting an assembled composite floor slab and a cast-in-place beam as claimed in claim 5, wherein: the cast-in-place beam formwork is arranged on the support frame.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111414888.XA CN114016649A (en) | 2021-11-25 | 2021-11-25 | Connection structure of assembled composite floor slab and cast-in-place beam |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202111414888.XA CN114016649A (en) | 2021-11-25 | 2021-11-25 | Connection structure of assembled composite floor slab and cast-in-place beam |
Publications (1)
Publication Number | Publication Date |
---|---|
CN114016649A true CN114016649A (en) | 2022-02-08 |
Family
ID=80066679
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202111414888.XA Pending CN114016649A (en) | 2021-11-25 | 2021-11-25 | Connection structure of assembled composite floor slab and cast-in-place beam |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN114016649A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114000632A (en) * | 2021-11-29 | 2022-02-01 | 山东高速德建集团有限公司 | Laminated slab construction structure free of ash adhesion and construction process thereof |
Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN202831219U (en) * | 2012-08-16 | 2013-03-27 | 杨众 | Large-span precast monolithic concrete structure |
CN106065663A (en) * | 2016-07-27 | 2016-11-02 | 广东省建科建筑设计院有限公司 | Assembled steel reinforced concrete beam and plate system with in-situ layer in building structure |
CN207436340U (en) * | 2017-03-01 | 2018-06-01 | 浙江华恒建筑设计有限公司 | A kind of Large-span Precast floor construction |
CN210713517U (en) * | 2019-07-12 | 2020-06-09 | 中铁第四勘察设计院集团有限公司 | Assembled superposed beam structure |
CN211499218U (en) * | 2019-11-15 | 2020-09-15 | 中核华辰建筑工程有限公司 | Anchor bar positioning tool for manufacturing embedded part |
CN113027024A (en) * | 2019-12-23 | 2021-06-25 | 浙江省建筑设计研究院 | Floor system structure of prefabricated concrete structure and construction method |
CN214696113U (en) * | 2021-02-05 | 2021-11-12 | 海南威特建设科技有限公司 | Connection structure of assembled prefabricated floor and composite beam |
-
2021
- 2021-11-25 CN CN202111414888.XA patent/CN114016649A/en active Pending
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN202831219U (en) * | 2012-08-16 | 2013-03-27 | 杨众 | Large-span precast monolithic concrete structure |
CN106065663A (en) * | 2016-07-27 | 2016-11-02 | 广东省建科建筑设计院有限公司 | Assembled steel reinforced concrete beam and plate system with in-situ layer in building structure |
CN207436340U (en) * | 2017-03-01 | 2018-06-01 | 浙江华恒建筑设计有限公司 | A kind of Large-span Precast floor construction |
CN210713517U (en) * | 2019-07-12 | 2020-06-09 | 中铁第四勘察设计院集团有限公司 | Assembled superposed beam structure |
CN211499218U (en) * | 2019-11-15 | 2020-09-15 | 中核华辰建筑工程有限公司 | Anchor bar positioning tool for manufacturing embedded part |
CN113027024A (en) * | 2019-12-23 | 2021-06-25 | 浙江省建筑设计研究院 | Floor system structure of prefabricated concrete structure and construction method |
CN214696113U (en) * | 2021-02-05 | 2021-11-12 | 海南威特建设科技有限公司 | Connection structure of assembled prefabricated floor and composite beam |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN114000632A (en) * | 2021-11-29 | 2022-02-01 | 山东高速德建集团有限公司 | Laminated slab construction structure free of ash adhesion and construction process thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN108049498B (en) | The prefabricated post and Prefabricated beam connection structure and method of assembled architecture frame structure | |
CN202831203U (en) | Assembly type concrete frame-shear wall split assembling structure and fabricative structure | |
CN102808465A (en) | Assembly connecting structure and assembly connecting method of assembled concrete frame and shear wall combination | |
CN212866536U (en) | Concrete wall department steel bar truss floor carrier plate side supporting device | |
CN110924537A (en) | Construction process of H-shaped steel concrete transfer beam-reinforced concrete column joint | |
CN114508175A (en) | Connecting joint and connecting method for assembled reinforced concrete prefabricated column and beam | |
CN110359671B (en) | Construction method of assembled rail top air duct | |
CN114016649A (en) | Connection structure of assembled composite floor slab and cast-in-place beam | |
CN114319977A (en) | Steel pipe concrete row column type connection prefabricated shear wall structure and construction method | |
CN106592821B (en) | Side-standing type integral forming structure and method of shear steel plate and one side reinforcing mesh | |
CN219671054U (en) | Steel-concrete combined small box girder prefabricated by integral hoisting | |
CN113026993A (en) | Assembly type combined connecting beam window opening component, structure and manufacturing and construction method | |
CN114197289A (en) | Assembling method of superposed beam type steel-concrete combined section | |
CN106592820A (en) | Horizontal integral forming structure and method of shear steel-plates and one side reinforcement fabric | |
CN215670408U (en) | Node connection structure of rib-outlet composite floor slab and cast-in-situ beam | |
CN217204673U (en) | Connection node of prefabricated reinforced concrete column and beam | |
CN213898249U (en) | Reinforced structure of newly-added concrete beam | |
CN115305833A (en) | Capping beam construction system and method | |
CN214061940U (en) | Precast concrete assembled structure with rib mold structure | |
CN212642113U (en) | Formwork support system and construction structure | |
CN211143121U (en) | Prefabricated rail top air duct structural unit | |
CN211447283U (en) | Connecting beam of main building and skirt house | |
CN114277993A (en) | Connecting joint of steel bar truss floor bearing plate and steel reinforced concrete beam and construction method thereof | |
CN113668706A (en) | Installation and construction method for connecting node area of steel reinforced concrete column and steel beam | |
CN111677106A (en) | Conversion connection structure of variable cross-section joint reinforcing steel bars of assembled structural column and implementation method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |