CN211447283U - Connecting beam of main building and skirt house - Google Patents

Connecting beam of main building and skirt house Download PDF

Info

Publication number
CN211447283U
CN211447283U CN201922016999.XU CN201922016999U CN211447283U CN 211447283 U CN211447283 U CN 211447283U CN 201922016999 U CN201922016999 U CN 201922016999U CN 211447283 U CN211447283 U CN 211447283U
Authority
CN
China
Prior art keywords
main building
skirt
steel
column
bracket
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201922016999.XU
Other languages
Chinese (zh)
Inventor
肖遥
左廷忠
刘火明
张辑
胥路
张悦
陈波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Eighth Engineering Division Co Ltd
Original Assignee
China Construction Eighth Engineering Division Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Eighth Engineering Division Co Ltd filed Critical China Construction Eighth Engineering Division Co Ltd
Priority to CN201922016999.XU priority Critical patent/CN211447283U/en
Application granted granted Critical
Publication of CN211447283U publication Critical patent/CN211447283U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Joining Of Building Structures In Genera (AREA)

Abstract

The utility model relates to a tie-beam of main building and skirt room, include: horizontal connection is in main building strength nature post and skirt house strength nature post, and the tie-beam includes: a first bracket horizontally fixed on the stiff column of the main building; a second bracket horizontally fixed on the rigid column of the skirt house; the profile steel is horizontally arranged between the main building stiffness column and the skirt house stiffness column, and two opposite ends of the profile steel are correspondingly fixed on the first bracket and the second bracket; the two opposite ends of the steel reinforcement framework are convexly extended and fixed on the corresponding first bracket and the second bracket along the steel reinforcement framework arranged on the section steel; and the concrete structure is poured on the section steel and the steel reinforcement framework and fixedly connected with the main building stiff column and the skirt house stiff column. The utility model provides a tie-beam of main building and skirt room, in order to guarantee sufficient bearing capacity when solving among the prior art when the distance between main building and the skirt room is too big, the great occupation space of cross-sectional dimension of concrete structure roof beam is too big, influences the problem of the construction of other structures.

Description

Connecting beam of main building and skirt house
Technical Field
The utility model relates to a construction field indicates a tie-beam of main building and skirt room especially.
Background
In some buildings, the foundation structures between the main building and the skirt building are different in form, the construction periods are not synchronous, and the outer frame of the main building also occupies the construction space. The main building is generally connected with the skirt house through a concrete structure beam. When the distance between the main building and the skirt house is too large, the cross section of the concrete structure beam is large in size and occupies too large space in order to ensure enough bearing capacity, and construction of other structures is affected.
SUMMERY OF THE UTILITY MODEL
An object of the utility model is to overcome prior art's defect, provide a tie-beam of main building and skirt room, in order to guarantee sufficient bearing capacity when solving the distance between main building and the skirt room among the prior art when too big, the great occupation space of cross sectional dimension of concrete structure roof beam is too big, influences the problem of the construction of other structures.
The technical scheme for realizing the purpose is as follows:
the utility model provides a tie-beam of main building and skirt room, include:
horizontal connection is in main building strength nature post and skirt house strength nature post, and its characterized in that, the tie-beam includes:
a first bracket horizontally fixed on the stiff column of the main building;
a second bracket horizontally fixed on the rigid column of the skirt house;
the profile steel is horizontally arranged between the main building stiff column and the skirt house stiff column, and two opposite ends of the profile steel are correspondingly fixed on the first bracket and the second bracket;
the two opposite ends of the steel bar framework are convexly extended and fixed on the corresponding first bracket and the second bracket; and
and the concrete structure is poured on the section steel and the steel reinforcement framework and fixedly connected with the main building stiff column and the skirt house stiff column.
The utility model discloses the beneficial effect of the tie-beam of main building and skirt room:
the utility model discloses a set up first bracket and second bracket and connect shaped steel and concreting, form to connect the tie beam who is fixed in main building strength nature post and skirt building strength nature post, included the advantage of concrete and shaped steel simultaneously, solved among the prior art distance between main building and the skirt room in order to guarantee sufficient bearing capacity when too big, the great occupation space of cross sectional dimension of concrete structure roof beam is too big, influences the problem of the construction of other structures.
The utility model has the further improvement of the connecting beam of the main building and the skirt house,
and a vertical construction joint is formed on the concrete structure at the position, close to the end part, of the first bracket.
The utility model discloses the further improvement of tie-beam of main building and skirt room lies in, main building strength nature post includes:
a main building steel column vertically arranged on the ground;
main building concrete poured on the main building steel column;
and the plurality of sleeves are fixed on the main building steel column and are matched with the steel reinforcement frameworks, and the corresponding end parts of the steel reinforcement frameworks are inserted and fixed in the sleeves.
The utility model discloses the further improvement of the tie-beam of main building and skirt room lies in, first bracket with main building steel column welded fastening.
The utility model discloses the further improvement of tie-beam of main building and skirt room lies in, skirt room strength nature post includes:
skirt house steel columns vertically arranged on the ground;
skirt house concrete poured on the skirt house steel column;
and the steel reinforcement framework is fixed on the lap rib plate, and the corresponding end part of the steel reinforcement framework is fixed on the lap rib plate.
The utility model discloses the further improvement of the tie-beam of main building and skirt room lies in, the second bracket with skirt room steel column welded fastening.
Drawings
Fig. 1 is the schematic view of the utility model of the connection beam of main building and skirt house before installation.
Fig. 2 is the schematic view of the utility model of the tie-beam after installation of main building and skirt house.
Fig. 3 is a schematic plan view of the connecting beam of the main building and the skirt house of the present invention.
Fig. 4 is the utility model discloses main building and the schematic diagram of the steel reinforcement framework of the tie-beam of skirt room.
Detailed Description
The invention will be further explained with reference to the drawings and the specific embodiments.
Referring to fig. 1, a schematic view of the connecting beam of the main building and the skirt house of the present invention before installation is shown. Fig. 2 is the schematic view of the utility model of the tie-beam after installation of main building and skirt house. With reference to fig. 1 and 2, the utility model discloses tie-beam of main building and skirt room, horizontal connection are in main building strength nature post 10 and skirt room strength nature post 20, and the tie-beam includes:
a first corbel 30 horizontally fixed to the stiff column 10 of the main building;
a second bracket 40 horizontally fixed to the skirt house stiff column 20;
the section steel 50 is horizontally arranged between the main building stiff column 10 and the skirt house stiff column 20, and two opposite ends of the section steel 50 are correspondingly fixed on the first bracket 30 and the second bracket 40;
the reinforcing steel bar framework 60 is arranged along the section steel 50, and the opposite ends of the reinforcing steel bar framework 60 are convexly extended and fixed on the corresponding first bracket 30 and the second bracket 40; and
and the concrete structure is poured on the section steel 50 and the steel reinforcement framework 60 and fixedly connected with the main building stiff column 10 and the skirt house stiff column 20.
As a preferred embodiment of the connection beam of the main building and the skirt house of the present invention, the concrete structure is formed with a vertical construction joint 70 at a position of the first bracket 30 near the end portion. The construction joint refers to a joint formed between the concrete poured before and after the concrete is poured in sections due to design requirements or construction needs in the concrete pouring process. The concrete face out of the construction joint 70 is roughened to facilitate the reinforcement and the fixing of the concrete to be poured later. Meanwhile, the problem that if the conventional setting principle that the construction joints are arranged at the 1/3 positions is adopted, the stiff columns of the main building are inconvenient to hoist is solved.
As a preferred embodiment of the connection beam for main building and skirt house of the present invention, fig. 3 is a schematic plan view of the connection beam for main building and skirt house of the present invention. Fig. 4 is the utility model discloses main building and the schematic diagram of the steel reinforcement framework of the tie-beam of skirt room. As shown in fig. 3 and 4, the main building stiff column 10 includes: a main building steel column 11 vertically arranged on the ground; main building concrete 12 poured on the main building steel column 11; be fixed in main building steel column 11 and a plurality of sleeves 13 of adaptation in framework of steel reinforcement 60, the corresponding tip of framework of steel reinforcement 60 is inserted and is established and be fixed in sleeve 13.
In this embodiment, the first bracket 30 and the main building steel column 11 are welded and fixed.
As the utility model discloses a preferred embodiment of the tie-beam of main building and skirt room, skirt room strength nature post 20 includes: skirt house steel columns 21 erected on the ground; skirt house concrete 22 poured on the skirt house steel column 21; be fixed in skirt house steel column 21 and adaptation in the gusset 23 of shaped steel 50, the corresponding tip of framework of steel reinforcement 60 is fixed in on the gusset 23.
In this embodiment, the second bracket 40 and the skirt house steel column 21 are welded and fixed.
The utility model discloses the tie-beam of main building and skirt room is strength nature concrete structure, is a integrated configuration that forms by steel skeleton outsourcing reinforced concrete. The steel skeleton and the high-strength concrete are configured to be mutually constrained, so that the stiff concrete structure can more effectively exert the respective advantages of the section steel and the concrete, the defect that the steel structure is easy to partially buckle is overcome, the ductility of the structure and the member is increased, and the brittle characteristic which is not beneficial to earthquake resistance and is caused by the poor ductility of the high-strength concrete is improved; in addition, compared with a reinforced concrete structure, the reinforced concrete structure effectively reduces the section size of the member, increases the use space, reduces the beam column section, adjusts the axial compression ratio and improves the bearing capacity of the structure; compared with a steel structure, the steel structure has the advantages that the steel consumption is saved, the manufacturing cost is reduced, and the fireproof and anti-corrosion performances are improved.
The following is the construction steps of the utility model discloses the tie-beam of main building and skirt room do the concrete description:
and hoisting and installing the steel column of the rigid column of the main building and the steel column of the rigid column of the skirt house, and erecting an outer frame.
The span of the connecting beam between the main building and the skirt house is large (the span of partial beam exceeds 14m), and the hoisting of the stiff column of the main building is inconvenient according to the setting principle of the conventional construction joint at the position of 1/3, so that only a bracket with the length of 1.2m is arranged on the stiff column of the main building.
And a plurality of sleeves are welded on the flanges of the stiff steel columns of the main building and are used for connecting longitudinal main reinforcements of the steel reinforcement framework. And main ribs of the steel reinforcement framework are connected on flanges of the stiffness steel column of the skirt house by adopting rib plates, wherein the width of the rib plates is the same as that of the section steel, and the length of the rib plates is 10d for single-side welding or 5d for double-side welding.
When the construction joint is kept somewhere in the main building construction stage, the reserved longitudinal bottom rib below the orthographic projection section of the steel beam is 100mm shorter than the bracket, and the main ribs in other positions are adjacently staggered for one lap joint length for reservation and are shortest to be not less than 1200mm, so that the operation is facilitated. And protecting all the reserved main reinforcement mantle fibers by using a protective cap. And after the main building stiff column is poured and demoulded, chiseling and cleaning the construction joint.
When the skirt building is constructed, in order to avoid the influence of the main building outer frame, the section steel is firstly hoisted to the plate surface, then the section steel is hoisted and positioned from the plate surface to the lower part and the upper part, and the section steel is welded and fixed after being in place.
For facilitating the operation of workers, the skirt house beam slab formwork support frame is erected by adopting a quick-dismantling frame, a step frame body is reserved at the beam bottom, the beam bottom die is not installed temporarily, and a springboard is laid simultaneously to serve as an operation platform for binding beam bottom ribs by workers. And meanwhile, when a bottom die of the floor slab is laid, the width of 1m is reserved on one side of the stiff beam to be used as a beam bottom rib mounting opening, so that beam bottom ribs can be bound conveniently.
Installing the stiff beam gluten and sleeving all stirrups, temporarily not positioning and binding the stirrups, and welding the main tendon at one side of the skirt house on the reinforcing plate. And erecting the main reinforcement and the stirrup at the bottom of the gluten every 1m by adopting a steel pipe so as to facilitate the penetration of the bottom reinforcement.
And (3) mounting the beam waist ribs and the beam bottom ribs, penetrating all the waist ribs and the longitudinal bottom ribs, positioning all the stirrups according to the designed intervals, and binding. Wherein, vertical end muscle divide into two sections, and the first section is installed one side of leaning on the main building straight threaded connection earlier, and the second section is connected to the reuse positive and negative silk sleeve. The tail end of the second section is connected to the rib plate of the rigid column of the skirt house. And bending the end parts of all the waist ribs, and welding the bent sections on the steel beams. And after all the waist ribs and the bottom ribs are installed, the distance between the stirrups is adjusted, and finally the stirrups are bound.
And after the steel bars are bound, dismantling the springboard of the beam bottom operation platform, supplementing the rest one-step supporting frame, inserting the adjustable U support, installing the beam bottom die and the back ridge in place, and integrally adjusting the adjustable U support to the designed elevation.
And (4) installing the side die of the connecting beam and the reserved floor slab bottom template, and pouring concrete in the space enclosed by the templates after binding the slab ribs to finish construction.
The utility model discloses the beneficial effect of the tie-beam of main building and skirt room does:
the utility model discloses a set up first bracket and second bracket and connect shaped steel and concreting, form to connect the tie beam who is fixed in main building strength nature post and skirt building strength nature post, included the advantage of concrete and shaped steel simultaneously, solved among the prior art distance between main building and the skirt room in order to guarantee sufficient bearing capacity when too big, the great occupation space of cross sectional dimension of concrete structure roof beam is too big, influences the problem of the construction of other structures.
The present invention has been described in detail with reference to the embodiments shown in the drawings, and those skilled in the art can make various modifications to the present invention based on the above description. Therefore, certain details of the embodiments should not be construed as limitations of the invention, which are intended to be covered by the following claims.

Claims (6)

1. The utility model provides a tie-beam of main building and skirt room, horizontal connection are in main building strength nature post and skirt room strength nature post, its characterized in that, the tie-beam includes:
a first bracket horizontally fixed on the stiff column of the main building;
a second bracket horizontally fixed on the rigid column of the skirt house;
the profile steel is horizontally arranged between the main building stiff column and the skirt house stiff column, and two opposite ends of the profile steel are correspondingly fixed on the first bracket and the second bracket;
the two opposite ends of the steel bar framework are convexly extended and fixed on the corresponding first bracket and the second bracket; and
and the concrete structure is poured on the section steel and the steel reinforcement framework and fixedly connected with the main building stiff column and the skirt house stiff column.
2. A coupling beam for main buildings and skirts as claimed in claim 1,
and a vertical construction joint is formed on the concrete structure at the position, close to the end part, of the first bracket.
3. A main building and skirt connection beam as in claim 1 wherein said main building rigid columns comprise:
a main building steel column vertically arranged on the ground;
main building concrete poured on the main building steel column;
and the plurality of sleeves are fixed on the main building steel column and are matched with the steel reinforcement frameworks, and the corresponding end parts of the steel reinforcement frameworks are inserted and fixed in the sleeves.
4. The connecting beam for main building and skirt house according to claim 3, wherein said first bracket and said main building steel column are welded and fixed.
5. A connector beam for main building and skirt house according to claim 1, wherein said skirt house stiffness column comprises:
skirt house steel columns vertically arranged on the ground;
skirt house concrete poured on the skirt house steel column;
and the steel reinforcement framework is fixed on the lap rib plate, and the corresponding end part of the steel reinforcement framework is fixed on the lap rib plate.
6. The connecting beam for main building and skirt house according to claim 5, wherein the second bracket and the skirt house steel column are welded and fixed.
CN201922016999.XU 2019-11-21 2019-11-21 Connecting beam of main building and skirt house Active CN211447283U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201922016999.XU CN211447283U (en) 2019-11-21 2019-11-21 Connecting beam of main building and skirt house

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201922016999.XU CN211447283U (en) 2019-11-21 2019-11-21 Connecting beam of main building and skirt house

Publications (1)

Publication Number Publication Date
CN211447283U true CN211447283U (en) 2020-09-08

Family

ID=72296113

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201922016999.XU Active CN211447283U (en) 2019-11-21 2019-11-21 Connecting beam of main building and skirt house

Country Status (1)

Country Link
CN (1) CN211447283U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114673366A (en) * 2022-05-10 2022-06-28 陕西建工机械施工集团有限公司 Sectional steel beam high-altitude bracket-free sectional butt joint installation method

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114673366A (en) * 2022-05-10 2022-06-28 陕西建工机械施工集团有限公司 Sectional steel beam high-altitude bracket-free sectional butt joint installation method

Similar Documents

Publication Publication Date Title
CN107476476B (en) Combined construction method of long-span steel bar truss floor bearing plate and reinforced concrete beam
CN104018581A (en) Prestress concrete F slab and framework structure system
CN107254933A (en) The high-rise single through hole precast shear wall of assembled and its assembling structure and construction method
CN107227812A (en) A kind of inverted cone-shaped is encorbelmented brick arcading Curtain Wall and its construction method
CN212405468U (en) Stiff concrete structure beam column core area structure
CN106032706A (en) Integrated casting molding construction method of reinforced concrete shear wall
CN100460613C (en) Suspension holder construction method
CN109208785B (en) Assembled superposed structure system
CN211447283U (en) Connecting beam of main building and skirt house
CN114033111A (en) Assembled cornice inclined roof and installation and construction method thereof
CN108316150B (en) Construction system and construction method for main tower and steel anchor beam of cable-stayed bridge
CN211421637U (en) Connecting structure of prefabricated gutter
CN202520017U (en) Construction structure of variable cross-section prestress overhanging type folding beam for stand
CN216664766U (en) Assembled parapet that cornices
CN218345930U (en) Bridge structure
CN111576620A (en) Construction method for beam-column core area of stiffened concrete structure
CN207003803U (en) The single through hole precast shear wall of high-rise assembled and its assembling structure
CN215670408U (en) Node connection structure of rib-outlet composite floor slab and cast-in-situ beam
CN215330707U (en) Prefabricated assembled shear force wall
CN212078226U (en) Novel prefabricated air conditioner board subassembly of encorbelmenting
CN114059715A (en) Formwork-supporting-free cast-in-situ inverted-trapezoid combined beam and construction method thereof
CN114033171A (en) Clamp type triangular support system of overhanging roof panel and construction method thereof
CN208152409U (en) A kind of parapet of roofing
CN111395514A (en) Novel prefabricated overhanging air conditioner plate assembly and construction method thereof
CN213014998U (en) Reinforced concrete decorative constructional column

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant