CN113882565B CN202111312005.4A CN202111312005A CN113882565B CN 113882565 B CN113882565 B CN 113882565B CN 202111312005 A CN202111312005 A CN 202111312005A CN 113882565 B CN113882565 B CN 113882565B
Authority
CN
China
Prior art keywords
stainless steel
ceramic
hole
replacement
ceramic brick
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202111312005.4A
Other languages
Chinese (zh)
Other versions
CN113882565A (en
Inventor
卜继斌
方宏强
陈舟
刘刚明
江幸莲
陈康荣
赵任
王小雨
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou Pearl River Decoration Engineering Co ltd
Original Assignee
Guangzhou Pearl River Decoration Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou Pearl River Decoration Engineering Co ltd filed Critical Guangzhou Pearl River Decoration Engineering Co ltd
Priority to CN202111312005.4A priority Critical patent/CN113882565B/en
Publication of CN113882565A publication Critical patent/CN113882565A/en
Application granted granted Critical
Publication of CN113882565B publication Critical patent/CN113882565B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/88Curtain walls
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/88Curtain walls
    • E04B2/96Curtain walls comprising panels attached to the structure through mullions or transoms

Abstract

The invention discloses an assembly type unit ceramic brick dry hanging curtain wall system and a construction method thereof, and relates to the technical field of building curtain walls. The invention has the advantages of dry construction in the whole process, no field wet operation, simple structure, convenient operation and capability of rapidly mounting and dismounting the curtain wall.

Description

Assembly type unit ceramic brick dry-hanging curtain wall system and construction method thereof
Technical Field
The invention relates to the technical field of building curtain walls, in particular to an assembly type unit ceramic brick dry hanging curtain wall system and a construction method thereof.
Background
The curtain wall is an outer wall enclosure of a building, is a light wall with decorative effect commonly used by modern large and high-rise buildings, and can be composed of various materials such as glass, metal, ceramic brick and the like and a supporting structure behind the glass, metal, ceramic brick and the like according to the requirement of decorative design. But current curtain is when assembling, and the construction complicacy and the structure between the curtain all are fixed, difficult dismantlement, and the decorative effect of current curtain often lacks the visual effect of former design after the installation is accomplished.
Disclosure of Invention
In order to overcome the defects of the prior art, the invention aims to provide an assembly type unit ceramic brick dry hanging curtain wall system and a construction method thereof, so as to solve the problems in the prior art.
In order to achieve the purpose, the technical scheme adopted by the invention is as follows: the curtain wall system comprises a fixed mounting structure, a curtain wall structure and a mounting and connecting structure, wherein the curtain wall structure is sleeved on the mounting and connecting structure, the curtain wall structure is in sliding fit with the mounting and connecting structure, the mounting and connecting structure is positioned on the fixed mounting structure, and the mounting and connecting structure is detachably connected with the fixed mounting structure.
Preferably, the fixed mounting structure includes two vertical joists and three crossbeams, two vertical joists are the symmetry and set up, and three crossbeams equidistant setting are on two vertical joists, the crossbeam is the level setting, the both ends of crossbeam are passed through the bolt and are connected with two vertical joists, the crossbeam is T type structure.
Preferably, the installation and connection structure comprises a plurality of stainless steel support rods, stainless steel sleeves in threaded connection with the stainless steel support rods are arranged at the tops and the bottoms of the stainless steel support rods, a plurality of mounting holes in sliding fit with the stainless steel support rods are formed in the cross beams, the stainless steel support rods are clamped in the mounting holes in the cross beams through the stainless steel sleeves, thread sections are arranged at the bottoms and the tops of the stainless steel support rods, and the tops and the bottoms of the stainless steel support rods are fixed among the three cross beams through the stainless steel sleeves.
Preferably, the curtain wall construction includes ceramic brick, first cushion ceramic brick and second cushion ceramic brick, be equipped with two joint holes on the ceramic brick, every the top in the joint hole of ceramic brick all is equipped with the nylon cushion, nylon cushion and ceramic brick sliding fit realize being connected through the joint mouth, and are a plurality of the ceramic brick is installed on a plurality of stainless steel support rods through equidistant crisscross of a plurality of nylon cushion.
An assembly type unit ceramic brick dry-hanging curtain wall system and a construction method thereof are disclosed, wherein the construction method comprises the following steps:
the first step is as follows: fixing two vertical keels with the existing embedded parts through bolts to fix the positions of the two vertical keels, and horizontally connecting the cross beam positioned at the lower layer to the two vertical keels through the bolts;
the second step is that: after the crossbeam positioned at the lower layer is fixed, sleeving a stainless steel sleeve in a mounting hole on the crossbeam, mounting the stainless steel sleeve at the bottom of a stainless steel support rod and at the bottom of the crossbeam positioned at the lower layer, fixing the stainless steel support rod and the crossbeam positioned at the lower layer, and then sequentially mounting a plurality of stainless steel sleeves on the crossbeam positioned at the lower layer so that the stainless steel support rods and the crossbeam positioned at the lower layer are fixed together;
the third step: placing two nylon cushion blocks at the tops of two clamping holes of a ceramic brick, sequentially mounting the ceramic brick, a first cushion block ceramic brick and a second cushion block ceramic brick on a plurality of stainless steel support rods at equal intervals through the two nylon cushion blocks, connecting a cross beam at the middle position with two vertical keels through bolts after the ceramic brick, the first cushion block ceramic brick and the second cushion block ceramic brick are mounted to the middle position, fixing the cross beam at the middle position on the two vertical keels, and sequentially mounting the two ceramic bricks on the plurality of stainless steel support rods at equal intervals through the two nylon cushion blocks;
the fourth step: after the ceramic bricks are installed, the cross beam positioned on the upper layer is fixed on the two vertical keels through the bolts, and after the cross beam is installed, the stainless steel support rods are fixed on the cross beam positioned on the upper layer through the stainless steel sleeves, so that the assembly type unit ceramic brick dry-hanging curtain wall system is installed.
Compared with the prior art, the invention has the beneficial effects that:
when using, need not carry out the concrete, moreover, the steam generator is simple in structure, and convenient operation, can be quick install and dismantle the curtain, equidistant crisscross installation between a plurality of ceramic bricks for the front of curtain produces three-dimensional visual effect, the decorative effect of curtain has been increased, under the cooperation of follow-up light at night, realize the visual effect of curtain, can be according to the not co-altitude needs of curtain installation, install the stainless steel bracing piece of suitable height can, in order to realize the installation to the not co-altitude curtain, satisfy different user demands.
Drawings
FIG. 1 is a schematic perspective view of an assembled unit ceramic brick dry-hanging curtain wall system;
FIG. 2 is a schematic perspective view of a prefabricated unit ceramic tile dry-hanging curtain wall system;
FIG. 3 is a front view of an assembled unit ceramic tile dry-hang curtain wall system;
FIG. 4 is a top view of an assembled unit ceramic tile dry-hang curtain wall system;
FIG. 5 is a first perspective view of a curtain wall structure;
FIG. 6 is a schematic perspective view of a curtain wall structure;
FIG. 7 is a third schematic perspective view of a curtain wall structure;
FIG. 8 is a fourth schematic perspective view of a curtain wall structure;
FIG. 9 is a first perspective view of a ceramic tile;
FIG. 10 is a schematic perspective view of a second embodiment of the ceramic tile;
FIG. 11 is a perspective view of the mounting connection structure;
FIG. 12 is a schematic perspective view of a stainless steel sleeve;
FIG. 13 is a perspective view of a mounting structure
Fig. 14 is a schematic view of the alternative ceramic tile before and after installation.
In the figure: fixed mounting structure 1, vertical fossil fragments 11, crossbeam 12, curtain wall construction 2, ceramic brick 21, first cushion ceramic brick 22, second cushion ceramic brick 23, joint hole 24, installation connection structure 3, stainless steel bracing piece 31, stainless steel sleeve 32, installation section 33 on the stainless steel, lower installation section 34, mounting nut 35, nylon cushion 4, replacement ceramic brick 5, first replacement hole 51, second replacement hole 52.
Detailed Description
The invention will be further described with reference to the accompanying drawings, figures 1 to 14, and the detailed description of the invention: the utility model provides an assembled unit ceramic brick hangs curtain system futilely, includes fixed mounting structure 1, curtain structure 2 and erection joint structure 3, curtain structure 2 cover is on erection joint structure 3, curtain structure 2 and erection joint structure 3 sliding fit, erection joint structure 3 is located fixed mounting structure 1, erection joint structure 3 is connected with fixed mounting structure 1 detachable.
Specifically, fixed mounting structure 1 includes two vertical keel 11 and three crossbeams 12, two vertical keel 11 is the symmetry setting, and three crossbeams 12 equidistant setting is on two vertical keel 11, crossbeam 12 is the level setting, the both ends of crossbeam 12 are passed through the bolt and are connected with two vertical keel 11, crossbeam 12 is T type structure. Two vertical keels 11 may be fixed and installed with an embedded part in an existing building device, and three beams 12 are used to support and arrange a plurality of tiles 21, a first cushion tile 22, and a second cushion tile 23.
Specifically, the stainless steel support rod structure further comprises a plurality of stainless steel support rods 31, the stainless steel support rods 31 are arranged on the three cross beams 12 at equal intervals, stainless steel sleeves 32 in threaded connection with the stainless steel support rods 31 are arranged at the top, the bottom and the middle of each stainless steel support rod 31, threaded sections are arranged at the top, the bottom and the middle of each stainless steel support rod 31, and the stainless steel support rods 31 are fixed on the cross beams 12 through the stainless steel sleeves 32. The stainless steel support rods 31 are used to support the ceramic bricks 21, the first mat ceramic brick 22 and the second mat ceramic brick 23 by being installed through the nylon mat 4.
Specifically, an external thread section and an external thread section are respectively arranged on the outer side wall and the inner side wall of the stainless steel sleeve 32; the stainless steel sleeve 32 is in threaded connection with the mounting hole on the cross beam 12; the thread section on the stainless steel support rod 31 is in threaded connection with the inner thread section on the stainless steel sleeve 32; the stainless steel sleeve 32 is divided into an upper mounting section 33, a lower mounting section 34 and a mounting nut 35, and the length of the stainless steel upper mounting section 33 is larger than that of the lower mounting section 34. Use at stainless steel support rod 31, 34 threaded connection on crossbeam 12 of lower installation section through stainless steel sleeve 32, can drive stainless steel sleeve 32's rotation through rotatory installation nut 35, fix stainless steel support rod 31 on crossbeam 12, when assembling the curtain to co-altitude, only need to rotate stainless steel support rod 31's bottom to stainless steel sleeve 32 on the internal thread in installation section 33, make stainless steel support rod 31 vertically install on stainless steel sleeve 32, can be according to the not co-altitude needs of curtain installation, install suitable high stainless steel support rod 31 can, in order to realize the installation to co-altitude curtain, satisfy different user demands.
Specifically, curtain wall construction 2 includes ceramic tile 21, first cushion ceramic tile 22 and second cushion ceramic tile 23, ceramic tile 21, first cushion ceramic tile 22 and second cushion ceramic tile 23 all are equipped with a plurality ofly, and are a plurality of first cushion ceramic tile 22 equidistant setting is in the left side of a plurality of stainless steel support rods 31, and is a plurality of second cushion ceramic tile 23 equidistant setting is on the right side of a plurality of stainless steel support rods 31, and is a plurality of ceramic tile 21 equidistant setting is established crisscross on a plurality of stainless steel support rods 31, every ceramic tile 21, first cushion ceramic tile 22 and second cushion ceramic tile 23 all are equipped with nylon cushion block 4. Nylon cushion block 4 is used for the protection to ceramic tile 21, first cushion ceramic tile 22 and second cushion ceramic tile 23, place in ceramic tile 21, when the installation of first cushion ceramic tile 22 and second cushion ceramic tile 23, because ceramic tile 21, first cushion ceramic tile 22 and second cushion ceramic tile 23 rock on stainless steel bracing piece 31 can cause ceramic tile 21, the damage of joint hole 24 on first cushion ceramic tile 22 and second cushion ceramic tile 23, at ceramic tile 21, first cushion ceramic tile 22 and second cushion ceramic tile 23 when the installation, nylon cushion block 4 can lead to the fact ceramic tile 21, joint hole 24 on first cushion ceramic tile 22 and second cushion ceramic tile 23 protects, also can lead to ceramic tile 21, also can carry out spacing to the position of first ceramic tile 22 and second cushion ceramic tile 23, prevent ceramic tile 21, first cushion ceramic tile 22 and second cushion ceramic tile 23 from causing the damage after the installation, first ceramic tile 22 and second cushion ceramic tile 23 are for the staggered left-side ceramic tile 21 that sets up when a plurality of ceramic tiles 21, first cushion ceramic tile 22 and second cushion ceramic tile 23 are used for the left-side ceramic tile 21 and the second cushion ceramic tile 23 to fill up the space, the left-side ceramic tile gap and the second cushion ceramic tile 23 and realize the intermittent filling of the intermittent type installation.
Specifically, the ceramic tile 21 is in a right trapezoid shape, the first cushion block ceramic tile 22 is in a rectangular shape, and the second cushion block ceramic tile 23 is in a square shape; the ceramic brick 21 is provided with two symmetrically arranged clamping holes 24, and the first cushion block ceramic brick 22 and the second cushion block ceramic brick are also provided with the clamping holes 24; the nylon cushion block 4 is sleeved above the clamping holes 24 on the ceramic brick 21, the first cushion block ceramic brick 22 and the second cushion block ceramic brick 23; the nylon cushion block 4 is cylindrical, the outer diameter of the nylon cushion block 4 is larger than the diameter of the clamping hole 24, and the inner diameter of the nylon cushion block 4 is larger than the diameter of the stainless steel support rod 31; the two adjacent ceramic bricks 21 are arranged in a staggered manner, and the clamping hole 24 on the right side of the upper ceramic brick 21 and the nylon cushion block 4 on the clamping hole 24 on the left side of the lower ceramic brick 21 are connected to the same vertically-arranged stainless steel support rod 31; the first cushion block ceramic brick 22 is positioned between the two staggered ceramic bricks 21 on the left upper layer and the left lower layer, and the second cushion block ceramic brick 23 is positioned between the two staggered ceramic bricks 21 on the right upper layer; when installing ceramic brick 21, install the right-angle side of right trapezoid's ceramic brick 21 at the back that is located whole curtain, install the hypotenuse of right trapezoid's ceramic brick 21 in the front that is located whole curtain, make the front of curtain produce three-dimensional visual effect after the installation is accomplished, increased the decorative effect of curtain, under the cooperation of follow-up night light, realize the visual effect of curtain.
The stainless steel support rod is characterized by further comprising a replacing ceramic brick 5, wherein the replacing ceramic brick 5 is in a right trapezoid shape, the replacing ceramic brick 5 is provided with a first replacing hole 51 and a second replacing hole 52, the first replacing hole 51 is located on the high length side of the right trapezoid, the second replacing hole 52 is located on the lower bottom side of the right trapezoid, and the distance between the first replacing hole 51 and the second replacing hole 52 is equal to the distance between two adjacent stainless steel support rods 31; the first replacing hole 51 is of a mirror-image L-shaped structure, the long side of the first replacing hole 51 is an open side, and the short side of the first replacing hole 51 is in a circular shape; the right-angle edge of the L-shaped structure is chamfered with a round angle; the round corners are beneficial to the subsequent installation of the replacement ceramic bricks 5 during replacement, and the second replacement holes 52 are in U-shaped open shapes; the first replacement hole 51 and the second replacement hole 52 have a diameter larger than the outer diameter of the nylon insert 4. If the overall ceramic brick 21 of the curtain wall is damaged and needs to be replaced, the straight edge of the right trapezoid-shaped replacement ceramic brick 5 is installed on the back face of the curtain wall, the bevel edge of the right trapezoid-shaped replacement ceramic brick 5 is installed on the front face of the curtain wall, the opening ends of the first replacement hole 51 and the second replacement hole 52 face the two nylon cushion blocks 4 on the two stainless steel support rods 31, the two nylon cushion blocks 4 are wrapped in the first replacement hole 51 and the second replacement hole 52, the replacement ceramic brick 5 is moved rightwards after placement is completed, the two nylon cushion blocks 4 are completely wrapped in the first replacement hole 51 and the second replacement hole 52, after the placement is correct, the gaps of the first replacement hole 51 and the second replacement hole 52 are plugged through the gluing material, the replacement ceramic brick 5 is completely fixed with the two nylon cushion blocks 4, and replacement of the damaged ceramic brick 21 is completed.
An assembly type unit ceramic brick dry-hanging curtain wall system and a construction method thereof are disclosed, wherein the construction method comprises the following steps:
the first step is as follows: fixing the two vertical keels 11 with the existing embedded parts through bolts so as to fix the positions of the two vertical keels 11, and horizontally connecting the cross beam 12 positioned at the lower layer to the two vertical keels 11 through bolts;
the second step is that: after the beam 12 at the lower layer is fixed, sleeving a stainless steel sleeve in a mounting hole on the beam 12, mounting a stainless steel sleeve 32 at the bottom of a stainless steel support rod 31 and at the bottom of the beam 12 at the lower layer, fixing the stainless steel support rod 31 and the beam 12 at the lower layer, and then sequentially mounting a plurality of stainless steel sleeves 32 on the beam 12 at the lower layer, so that the stainless steel support rods 31 and the beam 12 at the lower layer are fixed together;
the third step: after two nylon cushion blocks 4 are placed at the tops of two clamping holes 24 of a ceramic brick 21, the ceramic brick 21, a first cushion block ceramic brick 22 and a second cushion block ceramic brick 23 are sequentially installed on a plurality of stainless steel support rods 31 at equal intervals through the two nylon cushion blocks 4, after the ceramic brick 21, the first cushion block ceramic brick 22 and the second cushion block ceramic brick 23 are installed at the middle position, a cross beam 12 at the middle position is connected with two vertical keels 11 through bolts, the cross beam 12 at the middle position is fixed on the two vertical keels 11, and then the two ceramic bricks 21 are sequentially installed on the plurality of stainless steel support rods 31 at equal intervals through the two nylon cushion blocks 4;
the fourth step: after the installation of the ceramic tiles 21 is completed, the cross beam 12 positioned on the upper layer is fixed on the two vertical keels 11 through bolts, and after the installation of the cross beam 12 is completed, the stainless steel support rods 31 are fixed on the cross beam 12 positioned on the upper layer through the stainless steel sleeves 32, so that the installation of the assembled unit ceramic tile dry-hanging curtain wall system is completed.
When using, need not carry out the concrete, moreover, the steam generator is simple in structure, high durability and convenient operation, can be quick install and dismantle the curtain, equidistant crisscross installation between a plurality of ceramic bricks 21 for the front of curtain produces three-dimensional visual effect, the decorative effect of curtain has been increased, under the cooperation of follow-up light at night, realize the visual effect of curtain, can be according to the not co-altitude needs of curtain installation, install the stainless steel bracing piece 31 of suitable height can, in order to realize the installation to the not co-altitude curtain, realize different user demands.
Various other modifications and changes may be made by those skilled in the art based on the above-described technical solutions and concepts, and all such modifications and changes should fall within the scope of the claims of the present invention.

Claims (2)

1. The utility model provides a curtain system is hung futilely to assembled unit ceramic brick which characterized in that: the curtain wall structure comprises a fixed mounting structure (1), a curtain wall structure (2) and a mounting and connecting structure (3), wherein the curtain wall structure (2) is sleeved on the mounting and connecting structure (3), the curtain wall structure (2) is in sliding fit with the mounting and connecting structure (3), the mounting and connecting structure (3) is positioned on the fixed mounting structure (1), and the mounting and connecting structure (3) is detachably connected with the fixed mounting structure (1); the fixed mounting structure (1) comprises two vertical keels (11) and three beams (12), the two vertical keels (11) are symmetrically arranged, the three beams (12) are arranged on the two vertical keels (11) at equal intervals, the beams (12) are horizontally arranged, two ends of each beam (12) are connected with the two vertical keels (11) through bolts, and the beams (12) are of a T-shaped structure;
the mounting and connecting structure (3) comprises a plurality of stainless steel supporting rods (31), stainless steel sleeves (32) in threaded connection with the stainless steel supporting rods (31) are arranged at the top and the bottom of each stainless steel supporting rod (31), a plurality of mounting holes in sliding fit with the stainless steel supporting rods (31) are formed in the cross beams (12), the stainless steel supporting rods (31) are clamped in the mounting holes in the cross beams (12) through the stainless steel sleeves (32), thread sections are arranged at the bottom and the top of each stainless steel supporting rod (31), and the top and the bottom of each stainless steel supporting rod (31) are fixed among the three cross beams (12) through the stainless steel sleeves (32);
the curtain wall structure (2) comprises ceramic bricks (21), first cushion block ceramic bricks (22) and second cushion block ceramic bricks (23), two symmetrically arranged clamping holes (24) are formed in the ceramic bricks (21), nylon cushion blocks (4) are arranged at the tops of the clamping holes (24) of the ceramic bricks (21), the nylon cushion blocks (4) are in sliding fit with the ceramic bricks (21), and the ceramic bricks (21) are installed on the stainless steel support rods (31) in an equidistant staggered mode through the nylon cushion blocks (4);
the ceramic brick (21) is in a right-angled trapezoid shape; two adjacent ceramic bricks (21) are arranged in a staggered manner, and the clamping hole (24) on the right side of the upper ceramic brick (21) and the nylon cushion block (4) on the clamping hole (24) on the left side of the lower ceramic brick (21) are connected to the same vertically arranged stainless steel support rod (31); the first cushion block ceramic tile (22) is positioned between two staggered ceramic tiles (21) on the upper layer and the lower layer on the left side, and the second cushion block ceramic tile (23) is positioned between two staggered ceramic tiles (21) on the upper layer on the right side; the first cushion block ceramic brick 22 and the second cushion block ceramic brick 23 are used for generating intermittent gaps at the left end and the right end of the curtain wall when the ceramic bricks 21 are arranged in an equidistant and staggered manner, and the first cushion block ceramic brick 22 and the second cushion block ceramic brick 23 can be used for filling the intermittent gaps to realize the auxiliary installation of the ceramic bricks 21; when the ceramic bricks (21) are installed, the right-angle sides of the right-angle trapezoidal ceramic bricks (21) are installed on the back side of the integral curtain wall, the oblique sides of the right-angle trapezoidal ceramic bricks (21) are installed on the front side of the integral curtain wall, and the front side of the curtain wall generates a three-dimensional visual effect after the installation is finished;
the stainless steel support rod replacing device is characterized by further comprising a replacing ceramic brick (5), wherein the replacing ceramic brick (5) is in a right trapezoid shape, the replacing ceramic brick (5) is provided with a first replacing hole (51) and a second replacing hole (52), the first replacing hole (51) is located on the high length side of the right trapezoid, the second replacing hole (52) is located on the lower bottom side of the right trapezoid, and the distance between the first replacing hole (51) and the second replacing hole (52) is equal to the distance between two adjacent stainless steel support rods (31); the first replacing hole (51) is of a mirror-image L-shaped structure, the long side of the first replacing hole (51) is an open side, and the short side of the first replacing hole (51) is in a circular shape; the right-angle edge of the L-shaped structure is chamfered with a round angle; the second replacement hole (52) is in a U-shaped open shape; the diameters of the first replacement hole (51) and the second replacement hole (52) are larger than the outer diameter of the nylon cushion block (4);
when the ceramic brick (21) is damaged and needs to be replaced, the straight edge of the right-trapezoid-shaped replacement ceramic brick (5) is installed on the back face of the curtain wall, the bevel edge of the right-trapezoid-shaped replacement ceramic brick (5) is installed on the front face of the curtain wall, the opening ends of the first replacement hole (51) and the second replacement hole (52) face the two nylon cushion blocks (4) on the two stainless steel support rods (31), the two nylon cushion blocks (4) are wrapped in the first replacement hole (51) and the second replacement hole (52), the replacement ceramic brick (5) is moved rightwards after placement is completed, the two nylon cushion blocks (4) are completely wrapped in the first replacement hole (51) and the second replacement hole (52), after the placement is correct, gaps of the first replacement hole (51) and the second replacement hole (52) are plugged through a gluing material, the replacement ceramic brick (5) is completely fixed with the two nylon cushion blocks (4), and replacement of the damaged ceramic brick (21) is completed.
2. The construction method of the prefabricated unit ceramic tile dry-hanging curtain wall system according to claim 1, characterized in that: the construction method comprises the following steps:
the first step is as follows: the two vertical keels (11) are fixed with the existing embedded part through bolts, so that the positions of the two vertical keels (11) are fixed, and the cross beam (12) positioned on the lower layer is horizontally connected to the two vertical keels (11) through the bolts;
the second step is that: after the crossbeam (12) positioned at the lower layer is fixed, sleeving a stainless steel cylinder in a mounting hole on the crossbeam (12), mounting a stainless steel cylinder (32) at the bottom of a stainless steel support rod (31) and at the bottom of the crossbeam (12) positioned at the lower layer, fixing the stainless steel support rod (31) and the crossbeam (12) positioned at the lower layer, and then sequentially mounting a plurality of stainless steel cylinders (32) on the crossbeam (12) positioned at the lower layer to fix the stainless steel support rods (31) and the crossbeam (12) positioned at the lower layer together;
the third step: placing two nylon cushion blocks (4) at the tops of two clamping holes (24) of a ceramic brick (21), sequentially installing the ceramic brick (21), a first cushion block ceramic brick (22) and a second cushion block ceramic brick (23) on a plurality of stainless steel support rods (31) at equal intervals through the two nylon cushion blocks (4), after the ceramic brick is installed to a middle position, connecting a cross beam (12) at the middle position with two vertical keels (11) through bolts, fixing the cross beam (12) at the middle position on the two vertical keels (11), and sequentially installing the two ceramic bricks (21) on the plurality of stainless steel support rods (31) at equal intervals through the two nylon cushion blocks (4);
the fourth step: after the ceramic bricks (21) are installed, the cross beam (12) on the upper layer is fixed on the two vertical keels (11) through bolts, after the cross beam (12) is installed, the stainless steel support rods (31) are fixed on the cross beam (12) on the upper layer through the stainless steel sleeves (32), and the assembly type unit ceramic brick dry-hanging curtain wall system is installed;
when the ceramic brick (21) is damaged and needs to be replaced, the straight edge of the right-trapezoid-shaped replacement ceramic brick (5) is installed on the back face of the curtain wall, the bevel edge of the right-trapezoid-shaped replacement ceramic brick (5) is installed on the front face of the curtain wall, the opening ends of the first replacement hole (51) and the second replacement hole (52) face the two nylon cushion blocks (4) on the two stainless steel support rods (31), the two nylon cushion blocks (4) are wrapped in the first replacement hole (51) and the second replacement hole (52), the replacement ceramic brick (5) is moved rightwards after placement is completed, the two nylon cushion blocks (4) are completely wrapped in the first replacement hole (51) and the second replacement hole (52), after the placement is correct, gaps of the first replacement hole (51) and the second replacement hole (52) are plugged through a gluing material, the replacement ceramic brick (5) is completely fixed with the two nylon cushion blocks (4), and replacement of the damaged ceramic brick (21) is completed.
CN202111312005.4A 2021-11-08 2021-11-08 Assembly type unit ceramic brick dry-hanging curtain wall system and construction method thereof Active CN113882565B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202111312005.4A CN113882565B (en) 2021-11-08 2021-11-08 Assembly type unit ceramic brick dry-hanging curtain wall system and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202111312005.4A CN113882565B (en) 2021-11-08 2021-11-08 Assembly type unit ceramic brick dry-hanging curtain wall system and construction method thereof

Publications (2)

Publication Number Publication Date
CN113882565A CN113882565A (en) 2022-01-04
CN113882565B true CN113882565B (en) 2023-03-17

Family

ID=79016810

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202111312005.4A Active CN113882565B (en) 2021-11-08 2021-11-08 Assembly type unit ceramic brick dry-hanging curtain wall system and construction method thereof

Country Status (1)

Country Link
CN (1) CN113882565B (en)

Families Citing this family (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115370052B (en) * 2022-09-07 2023-09-22 北京凌云宏达幕墙工程有限公司 Aluminum pipe small ceramic brick curtain wall system and construction method thereof

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006022509A (en) * 2004-07-06 2006-01-26 Ykk Ap Inc Curtain wall and its mounting method
CN210105073U (en) * 2019-05-19 2020-02-21 湖南建工集团装饰工程有限公司 Hang argil brick curtain wall construction futilely
CN110130550A (en) * 2019-05-31 2019-08-16 中建东方装饰有限公司 The dried hanging hang structure and its construction method of assembled hollow out earthenware brick curtain wall
CN210459693U (en) * 2019-07-09 2020-05-05 青岛北洋建筑设计有限公司 Dry-hanging ceramic brick curtain wall system
CN210439520U (en) * 2019-07-30 2020-05-01 江苏金科天宸房地产有限公司 Hollow curtain wall structure
CN210887886U (en) * 2019-09-12 2020-06-30 西安翔远装饰工程有限责任公司 Dry construction hollow ceramic brick wall
CN111287467B (en) * 2020-02-17 2021-08-03 上海市建筑装饰工程集团有限公司 Integral dry hanging process for ceramic brick curtain wall

Also Published As

Publication number Publication date
CN113882565A (en) 2022-01-04

Similar Documents

Publication Publication Date Title
CN110409811B (en) Non-dismantling forming column template containing reinforcement cage, template structure and building process
CN111206698A (en) Construction method of assembled wallboard
CN110409813B (en) Non-dismantling forming beam template containing reinforcement cage, template structure and building process
CN209924196U (en) Assembled infilled wall connected in rail clamping groove type and frame system thereof
CN113882565B (en) Assembly type unit ceramic brick dry-hanging curtain wall system and construction method thereof
CN210032203U (en) Prefabricated wallboard of casting type
CN216475772U (en) Curtain is decorated to building outer wall
CN109797969B (en) Construction method of post-cast strip tool type advanced formwork lifting system
CN211498507U (en) Whole reassembling type protection rack
CN102587665B (en) Pouring method of coupled shear wall structure
CN216475797U (en) Connecting device for dry-hanging curtain wall
CN216475773U (en) Opening ceramic brick curtain wall structure suitable for dry construction
CN215594693U (en) Steel pipe pull rod hollow ceramic archaized brick combined wall
CN209924197U (en) Piston-type connected assembly type infilled wall and frame system thereof
CN212129234U (en) Utility tunnel
CN211286650U (en) Foot-supported split heads for suspending high and large wall formworks
CN211621021U (en) Inclined shaft assembled support high track
CN109235709B (en) Full cast-in-place outer wall structure of building
CN107965145B (en) Horizontal convex concrete construction joint hanging die supporting device
CN111561150A (en) Post-cast strip supporting system
CN210659251U (en) Non-dismantling formed beam template containing reinforcement cage and template structure
CN210659245U (en) Non-dismantling forming column template containing reinforcement cage and template structure
CN217782857U (en) Combined template device for one-step forming of bay window and window board
CN219158051U (en) Waterproof outer wall of building
CN218375533U (en) Prefabricated floor bearing structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant