CN113502921B - Construction method of concrete filled steel tube arch rib - Google Patents
Construction method of concrete filled steel tube arch rib Download PDFInfo
- Publication number
- CN113502921B CN113502921B CN202110813735.6A CN202110813735A CN113502921B CN 113502921 B CN113502921 B CN 113502921B CN 202110813735 A CN202110813735 A CN 202110813735A CN 113502921 B CN113502921 B CN 113502921B
- Authority
- CN
- China
- Prior art keywords
- concrete
- arch rib
- steel pipe
- gap
- steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
- 229910000831 Steel Inorganic materials 0.000 title claims abstract description 127
- 239000010959 steel Substances 0.000 title claims abstract description 127
- 239000004567 concrete Substances 0.000 title claims abstract description 86
- 238000010276 construction Methods 0.000 title claims abstract description 21
- 238000000034 method Methods 0.000 claims abstract description 10
- 238000002347 injection Methods 0.000 claims description 28
- 239000007924 injection Substances 0.000 claims description 28
- 238000007789 sealing Methods 0.000 claims description 10
- 238000003466 welding Methods 0.000 claims description 5
- 239000011440 grout Substances 0.000 claims description 4
- 239000011376 self-consolidating concrete Substances 0.000 claims description 4
- 238000004519 manufacturing process Methods 0.000 claims description 3
- 239000000203 mixture Substances 0.000 claims description 3
- 239000002002 slurry Substances 0.000 claims description 2
- 239000000463 material Substances 0.000 abstract description 3
- 239000011800 void material Substances 0.000 abstract description 3
- 238000010586 diagram Methods 0.000 description 10
- 239000003921 oil Substances 0.000 description 3
- 238000005086 pumping Methods 0.000 description 3
- 230000005540 biological transmission Effects 0.000 description 2
- 230000000694 effects Effects 0.000 description 2
- 239000000243 solution Substances 0.000 description 2
- 230000009286 beneficial effect Effects 0.000 description 1
- 238000009435 building construction Methods 0.000 description 1
- 230000000295 complement effect Effects 0.000 description 1
- 238000007796 conventional method Methods 0.000 description 1
- 230000007423 decrease Effects 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 230000005484 gravity Effects 0.000 description 1
- 239000010720 hydraulic oil Substances 0.000 description 1
- 230000003993 interaction Effects 0.000 description 1
- 239000007788 liquid Substances 0.000 description 1
- 238000000465 moulding Methods 0.000 description 1
- 238000000926 separation method Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/18—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
- E04B1/30—Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts being composed of two or more materials; Composite steel and concrete constructions
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D4/00—Arch-type bridges
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/32—Arched structures; Vaulted structures; Folded structures
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
Description
技术领域technical field
本发明涉及建筑施工技术领域,尤其涉及一种钢管混凝土拱肋的施工方法。The invention relates to the technical field of building construction, in particular to a construction method of a steel pipe concrete arch rib.
背景技术Background technique
近些年,钢管混凝土在超高层建筑和大跨桥梁中得到广泛应用,其截面以圆形为主。钢管和混凝土相辅相成,一方面钢管类似箍筋,使得混凝土三向受压,抗压能力增强,另一方面,内填混凝土又解决了钢管潜在的失稳问题。In recent years, CFST has been widely used in super high-rise buildings and long-span bridges, and its cross-section is mainly circular. Steel pipes and concrete complement each other. On the one hand, the steel pipes are similar to stirrups, which make the concrete three-dimensionally compressed and the compressive capacity is enhanced. On the other hand, the inner filling of concrete solves the potential instability of the steel pipes.
随着实际工程中钢管混凝土应用的增多,发现很多内部混凝土和钢管内壁存在空隙,空隙厚度大的称为脱空,间隙厚度很小的一般称为脱粘。钢管混凝土拱桥的拱肋暴露在野外,且采用泵送混凝土灌注,一般认为,按照相关的工艺标准进行施工,混凝土的内部即可达到密实。但按常规方法施工的钢管混凝土拱桥,混凝土和钢管间的脱空不可避免。脱空的主要原因是混凝土在形成强度过程中的干缩,使用过程中温度作用下混凝土径向收缩,或钢管径向膨胀造成的二者脱离等。在建筑结构中,主要是这种界面脱离造成径向的脱粘。对于钢管混凝土拱桥,脱空和脱粘主要发生在拱顶段,因为拱顶段相对较平坦,且是整个拱肋的最高部位。脱空直接影响钢管和混凝土的共同作用,且多数设计规范目前尚未考虑脱空的影响。With the increase in the application of concrete filled steel pipes in actual engineering, it is found that there are gaps in many internal concrete and the inner wall of steel pipes. The gaps with large thickness are called voids, and those with small gap thicknesses are generally called debonding. The arch ribs of concrete-filled steel tube arch bridges are exposed in the field, and are poured with pumped concrete. It is generally believed that the interior of the concrete can be compacted if the construction is carried out in accordance with relevant process standards. However, for the concrete-filled steel tube arch bridge constructed by conventional methods, the space between the concrete and the steel tube is unavoidable. The main reason for voiding is the shrinkage of concrete during the process of forming strength, the radial shrinkage of concrete under the action of temperature during use, or the separation of the two caused by the radial expansion of steel pipes. In building structures, it is mainly this interfacial detachment that causes radial debonding. For CFST arch bridges, voiding and debonding mainly occur in the vault section, because the vault section is relatively flat and is the highest part of the entire arch rib. The void directly affects the interaction between the steel pipe and the concrete, and most design codes have not yet considered the effect of the void.
如何避免钢管混凝土构件的脱空引起了关注。现行的方法主要是采用微膨胀混凝土、缓膨胀混凝土、以及在钢管内壁焊接防脱粘的连接件等。因较多的防脱粘连接件,会增加混凝土泵送的阻力,不能过多设置。目前主要靠混凝土的膨胀增强钢管对混凝土的紧箍力,从而防范脱粘。然而混凝土的体积膨胀量有限,高温使钢管的膨胀作用更大,因此,混凝土和钢管的脱粘不可避免。How to avoid voiding of CFST members has attracted attention. The current method mainly uses micro-expansion concrete, slow-expansion concrete, and welding anti-debonding connectors on the inner wall of the steel pipe. Because more anti-debonding connectors will increase the resistance of concrete pumping, it cannot be set too much. At present, the expansion of concrete is mainly used to enhance the tightness of the steel pipe to the concrete, so as to prevent debonding. However, the volume expansion of concrete is limited, and the high temperature makes the expansion of the steel pipe greater. Therefore, the debonding of the concrete and the steel pipe is inevitable.
发明内容Contents of the invention
本发明的目的是为了解决现有技术中存在的缺点,而提出的一种钢管混凝土拱肋的施工方法。The object of the present invention is to propose a construction method of a steel tube concrete arch rib in order to solve the shortcomings in the prior art.
发明采用的技术方案:使拱肋内的混凝土在受到外加压力的状态下终凝成型,避免在随后的使用过程中脱粘,具体的施工方法包括以下步骤:The technical solution adopted by the invention: make the concrete in the arch rib finally set under the state of external pressure to avoid debonding in the subsequent use process. The specific construction method includes the following steps:
S1:钢管段的制作 制作各钢管段;在拱肋顶部钢管段的端部焊接横隔板,横隔板中部连接圆筒状的缸体,缸体的外端临时固定有活塞体,活塞体的加载面朝外;S1: Manufacture of steel pipe sections. Each steel pipe section is manufactured; a diaphragm is welded at the end of the steel pipe section at the top of the arch rib, and the middle part of the diaphragm is connected to a cylindrical cylinder. The outer end of the cylinder is temporarily fixed with a piston body. The loading side faces outward;
S2:安装钢管段 吊装拱肋的各个钢管段,在拱顶留一间隙,间隙两侧为上一步骤中制作的顶部钢管段,横隔板靠近间隙;调整各钢管段标高,符合设计要求后,焊接相邻钢管段;拱顶间隙两侧的顶部钢管段,焊接连接钢构件;S2: Install steel pipe sections to hoist each steel pipe section of the arch rib, leave a gap on the vault, the two sides of the gap are the top steel pipe sections made in the previous step, and the diaphragm is close to the gap; adjust the elevation of each steel pipe section to meet the design requirements , to weld the adjacent steel pipe sections; the top steel pipe sections on both sides of the vault gap are welded to connect the steel members;
S3:压注混凝土 向拱顶两侧的拱肋段内压注混凝土,确保压注饱满,混凝土上表面和钢管间没有滞留空气;S3: Injection of concrete: Inject concrete into the arch ribs on both sides of the vault to ensure that the injection is full and there is no trapped air between the upper surface of the concrete and the steel pipe;
S4:施加压力 向间隙内吊放并安装加力设备,撤除缸体和活塞体间的临时固定措施,加力设备对两端的活塞体施加顶推力;靠近拱顶的钢管外表面安装有应变计,监测钢管的环向应力,以设定的环向应力限值,控制顶推;在混凝土达到设定强度前,维持此顶推力;S4: Apply pressure to hang in the gap and install the booster device, remove the temporary fixing measures between the cylinder body and the piston body, and the booster device applies thrust to the piston body at both ends; strain gauges are installed on the outer surface of the steel pipe near the vault , monitor the hoop stress of the steel pipe, and control the jacking force with the set hoop stress limit; maintain the jacking force before the concrete reaches the set strength;
S5:完成间隙段的混凝土灌注 移除加力设备,用钢管片连接间隙两侧的拱肋段,各钢管片连接在一起,组成连接两侧拱肋段的间隙钢管段;向间隙钢管段内压注混凝土;新压注的混凝土终凝并达到设定的强度后,拆除原先跨越间隙的连接钢构件。S5: Complete the concrete pouring of the gap section and remove the booster equipment, connect the arch rib sections on both sides of the gap with steel pipe pieces, and connect the steel pipe pieces together to form the gap steel pipe section connecting the arch rib sections on both sides; Concrete injection: After the newly injected concrete has finally set and reached the set strength, the connecting steel members that originally spanned the gap are removed.
优选地,所述混凝土为微膨胀的自密实混凝土,强度等级至少为C60。Preferably, the concrete is micro-expansion self-compacting concrete with a strength grade of at least C60.
优选地,所述活塞体的组成包括端板、侧板、端板的加劲矩形板;侧板为圆筒状,外表面光洁。Preferably, the composition of the piston body includes an end plate, a side plate, and a stiffened rectangular plate of the end plate; the side plate is cylindrical and has a smooth outer surface.
优选地,所述缸体为圆筒状,内表面光洁。Preferably, the cylinder body is cylindrical with a smooth inner surface.
优选地,所述活塞体的侧板的远离端板的端部,外侧面上沿圆周有密封槽,密封槽内放置有密封圈。Preferably, at the end of the side plate of the piston body away from the end plate, there is a sealing groove along the circumference on the outer surface, and a sealing ring is placed in the sealing groove.
优选地,所述间隙的宽度、两个临时固定的活塞体的端板间的距离,均大于加力设备的初始长度。Preferably, the width of the gap and the distance between the end plates of the two temporarily fixed piston bodies are both greater than the initial length of the force-applying device.
优选地,所述加力设备为液压千斤顶。Preferably, the force adding device is a hydraulic jack.
优选地,所述拱肋段的中部有密封的横隔板,将拱肋段分为多个压注仓;在步骤S3中,从低到高依次压注两侧对应的压注仓;Preferably, there is a sealed diaphragm in the middle of the arch rib section, which divides the arch rib section into a plurality of injection chambers; in step S3, the corresponding injection chambers on both sides are injected sequentially from low to high;
优选地,在压注靠近桥面的压注仓时,压注口设在该压注仓的上端,混凝土从压注仓的高端进入压注仓。Preferably, when the injection chamber is close to the bridge deck, the injection port is set at the upper end of the injection chamber, and the concrete enters the injection chamber from the high end of the injection chamber.
优选地,所述钢管片的横向中部靠近连接钢构件,从而避免连接钢构件影响相邻钢管片的焊接作业。Preferably, the transverse middle part of the steel pipe sheet is close to the connecting steel member, so as to prevent the connecting steel member from affecting the welding operation of adjacent steel pipe sheets.
本发明的有益效果为:通过对钢管内刚压注的混凝土施加外部压力,使混凝土更密实;外部压力及混凝土的微膨胀,均使钢管的直径发生膨胀,在混凝土终凝后,钢管紧密地箍在内部的混凝土柱上,增强了两者间的粘结力,可避免脱粘;该发明中的外部作用力施加在拱顶位置,考虑到新浇筑的混凝土不同于水和液压油等常规的液体,压力的传递受到混凝土与钢管壁间粘滞阻力等因素的影响,压力的作用向拱肋底部逐渐递减,有效的范围主要在拱顶段,而这正是容易发生脱空和脱粘的部位,因此,本发明中将加力装置设置在顶部,方法效率高;该方案中采用的材料为型钢,采用的设备均为工地常用设备,增加的操作仅为焊接和液压千斤顶的操作,因此,用材料少,操作简单,只增加极少的造价。The beneficial effects of the present invention are: by applying external pressure to the concrete that has just been poured in the steel pipe, the concrete is made denser; both the external pressure and the micro-expansion of the concrete cause the diameter of the steel pipe to expand, and after the final setting of the concrete, the steel pipe tightly The hoop is on the inner concrete column, which enhances the bonding force between the two and can avoid debonding; the external force in this invention is applied at the position of the vault, considering that the newly poured concrete is different from the conventional ones such as water and hydraulic oil. The transmission of pressure is affected by factors such as the viscous resistance between the concrete and the steel pipe wall, and the effect of the pressure gradually decreases toward the bottom of the arch rib, and the effective range is mainly at the top of the arch, which is where voiding and debonding are prone to occur. Therefore, in the present invention, the boosting device is arranged on the top, and the method is efficient; the material adopted in this scheme is section steel, and the equipment adopted are all commonly used equipment on the construction site, and the increased operations are only the operation of welding and hydraulic jacks. Therefore, less material is used, the operation is simple, and only a small increase in cost is required.
附图说明Description of drawings
图1为实施例1中对拱肋混凝土施加顶推力期间拱顶拱肋纵剖示意图;Fig. 1 is the arch rib longitudinal sectional schematic view during the arch rib concrete is applied to the arch rib concrete in
图2图1中A-A的剖视示意图;The sectional schematic diagram of A-A in Fig. 2 Fig. 1;
图3连接前的拱肋侧视示意图;Figure 3 is a schematic side view of the arch rib before connection;
图4图3中过B-B的剖视示意图;Fig. 4 Fig. 3 crosses the schematic sectional view of B-B;
图5制作中的缺陷体的轴向剖视示意图;Figure 5 is a schematic diagram of an axial cross-section of a defect body being produced;
图6拱肋段间的连接钢梁侧视示意图;Figure 6 is a schematic side view of the connecting steel beams between the arch rib sections;
图7连接后的拱肋纵剖示意图;Fig. 7 is a schematic diagram of longitudinal section of arch rib after connection;
图8压注混凝土后的两拱肋段纵剖示意图;Figure 8 is a schematic diagram of the longitudinal section of the two arch ribs after injection of concrete;
图9缸体和活塞体间的初始连接示意图;Figure 9 is a schematic diagram of the initial connection between the cylinder body and the piston body;
图10两拱肋段间焊接钢管段后的纵剖示意图;Fig. 10 is a schematic diagram of the longitudinal section after the steel pipe section is welded between the two arch rib sections;
图11拱肋成型后的纵剖示意图;Figure 11 is a schematic diagram of the longitudinal section after the arch rib is formed;
图12间隙钢管段钢片拼装示意图。Fig. 12 Schematic diagram of assembling the steel sheets of the gap steel pipe section.
图中:1-钢管,2-混凝土,3-第一阶段排气管,4-T型钢梁,5-千斤顶,6-加劲三角板,7-横隔板,8-缸体,9-活塞体,10-缺口,11-立柱,12-横梁,13-加劲矩形板,14-端板,15-侧板,16-螺杆,17-密封圈,18-第二阶段排气管,19-第二阶段进料管,20-上钢管片,21-下钢管片,22-补浆孔。In the figure: 1-steel pipe, 2-concrete, 3-first-stage exhaust pipe, 4-T-shaped steel beam, 5-jack, 6-stiffened triangular plate, 7-diaphragm, 8-cylinder, 9-piston body, 10-notch, 11-column, 12-beam, 13-stiffened rectangular plate, 14-end plate, 15-side plate, 16-screw, 17-sealing ring, 18-second stage exhaust pipe, 19- The second stage feed pipe, 20-upper steel pipe piece, 21-lower steel pipe piece, 22-replenishing grout hole.
具体实施方式Detailed ways
实施例1Example 1
本实施例以某钢管混凝土拱桥中的一根拱肋的成型为例。该拱肋的钢管外径为1200mm,壁厚20mm。为提高成型后钢管与内部混凝土间的抗脱粘能力,采用本发明中的施工方案。该钢管混凝土拱肋的施工方法包括以下步骤:This embodiment takes the forming of an arch rib in a concrete-filled steel tube arch bridge as an example. The outer diameter of the steel pipe of the arch rib is 1200mm, and the wall thickness is 20mm. In order to improve the anti-bonding ability between the formed steel pipe and the internal concrete, the construction scheme in the present invention is adopted. The construction method of the steel pipe concrete arch rib comprises the following steps:
S1:钢管段的制作 以拱顶为界,两侧各为一个拱肋段,两个拱肋段相对于跨中位置对称。每个拱肋段由数个钢管段组成。制作各钢管段。在拱肋顶部钢管段的端部焊接横隔板7,横隔板7中部连接圆筒状的缸体8,缸体8的外端临时固定有活塞体9,参见图1、图5和图9。横隔板7和钢管1的连接处,增加有加劲三角板6,见图4。临时固定措施包括沿圆周均匀分布的16个直径为20mm的螺杆16,螺杆16穿过缸体8上的通孔后,进入侧板15上的非贯通螺孔。活塞体9的组成包括端板14、侧板15、加劲矩形板13;侧板15为圆筒状,外表面光洁。缸体8为圆筒状,内径600mm,内表面光洁。活塞体9的侧板15的远离端板14的端部,外侧面上沿圆周有密封槽,密封槽内放置有密封圈17。横隔板7上有补浆孔22,内安有单向阀,只能流入不能流出。S1: Manufacture of steel pipe section With the vault as the boundary, there is an arch rib section on both sides, and the two arch rib sections are symmetrical relative to the mid-span position. Each arch rib segment is composed of several steel pipe segments. Make each steel pipe segment. The
S2:安装钢管段 吊装拱肋的各个钢管段,参见图3。在拱顶留一间隙,间隙两侧为上一步骤中制作的顶部钢管段,横隔板7靠近间隙;间隙的宽度为800mm,端板14的外表面距离间隙100mm。调整各钢管段标高,符合设计要求后,焊接相邻钢管段;拱顶间隙两侧的顶部钢管段,焊接T型钢梁4作为连接钢构件。沿间隙的一周均匀设置有5根T型钢梁4,见图2。T型钢梁4采用常规的T型钢,T型钢高294mm宽300mm腹板厚12mm,翼板厚20mm;在T型钢翼缘上加焊一与翼缘同宽度,厚度为18mm的钢板,确保所有T型钢梁4的截面面积之和大于钢管1的截面面积。拱肋段间的T型钢梁4的侧视示意图如图6所示,为方便后续施工,T型钢梁4中部有一长度为1000mm的缺口10,缺口10的深度为40mm。在此阶段,安装由立柱11和横梁12组成的吊架,见图7。S2: Install steel pipe sections Lift and install the steel pipe sections of the arch rib, see Figure 3. Leave a gap in the vault, the top steel pipe sections made in the previous step are on both sides of the gap, and the
S3:压注混凝土 所述混凝土2为微膨胀的自密实混凝土,强度等级为C60。每侧的拱肋段为一个压注仓,有多个第一阶段排气管3。有多个进料口,最低处的进料口位于拱肋高度的中部。两侧同步地从低到高向两拱肋段内压注混凝土2;在最低处的进料口压注时,开始阶段,混凝土2依靠自身重力,从高端流入低端;后续压注时,比直接从桥面端压注所需的压力小。压注过程中,从低到高,及时关闭出浆的第一阶段排气管3.完成两个拱肋段的混凝土2的泵送施工,压注混凝土后的两拱肋段纵剖示意图见图8。拱肋段内已压注饱满,混凝土2上表面和钢管1间没有滞留空气。S3: injection concrete The
S4:施加压力 混凝土2的泵送施工完成后,立即向拱顶的间隙内吊放并安装千斤顶5,采用手动葫芦调整千斤顶5的位置。顶伸杆完全回缩后,千斤顶5的初始长度为700mm,外径为600mm,内径为400mm。卸除临时固定缸体8和活塞体9间的螺杆16。千斤顶5对两端的活塞体9施加顶推力;拱肋段拱顶端钢管1外表面安装应变计,监测钢管1的环向应力。设定的环向应力限值150MPa,以此控制顶推;在混凝土2达到设计强度80%前,维持顶推力。S4: Apply pressure After the pumping construction of
靠近拱顶处的混凝土2,可以近似按常规液体中的方法分析压强的传递,以此估算所需的千斤顶顶推力。根据缸体8内径与千斤顶5内径的尺寸,在混凝土2内产生1MPa的压强增量,至少对应千斤顶5内油压2.25MPa的油压增量;再考虑到钢管1的尺寸,混凝土内1MPa的压强增量,对应钢管1环向29MPa的应力增量。因此,若设定使拱肋段拱顶端钢管1内产生150MPa的应力增量,对应地混凝土内的压强增量大于5MPa,千斤顶5内的油压增量约为11.3MPa,对应千斤顶5的顶推力为165tonf。因此,在选择千斤顶5时,可选择额定顶推力为250tonf或300tonf的。在施加力过程中,观测钢管1上的应变计,监控拱顶附近钢管1的环向应力。若在环向应力达到限值前,千斤顶5的行程将达到最大值,可通过补浆孔22向拱肋段内压注不含粗集料的混凝土2的浆液,同时,千斤顶5回程;千斤顶5回程结束后,停止通过补浆孔22的压注,继续开始操作千斤顶5,使其伸长。如此循环,直到环向应力达到限值。For the
S5:完成间隙段的混凝土灌注 移除千斤顶5,用上钢管片20和下钢管片21连接间隙两侧的拱肋段,两个钢管片间也焊接,组成连接两侧拱肋段的间隙钢管段,见图10和图12;间隙钢管段的底部和顶部分别设置有第二阶段进料管19和第二阶段排气管18。间隙钢管段上包裹电热毯,对该段钢管加热,促使钢管膨胀。向间隙钢管段内压注混凝土2;新压注的混凝土2终凝并达到设定的强度后,拆除电热毯;拆除原先跨越间隙的T型钢梁4,以及吊架等,修正拱肋表面,拱肋成型后的纵剖示意图见图11。S5: Complete the concrete pouring of the gap section and remove the
至此,按本发明的方案,完成了该拱肋的成型施工。So far, according to the solution of the present invention, the molding construction of the arch rib has been completed.
Claims (7)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110813735.6A CN113502921B (en) | 2021-07-19 | 2021-07-19 | Construction method of concrete filled steel tube arch rib |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202110813735.6A CN113502921B (en) | 2021-07-19 | 2021-07-19 | Construction method of concrete filled steel tube arch rib |
Publications (2)
Publication Number | Publication Date |
---|---|
CN113502921A CN113502921A (en) | 2021-10-15 |
CN113502921B true CN113502921B (en) | 2022-11-08 |
Family
ID=78013799
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202110813735.6A Active CN113502921B (en) | 2021-07-19 | 2021-07-19 | Construction method of concrete filled steel tube arch rib |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN113502921B (en) |
Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001098514A (en) * | 1999-10-01 | 2001-04-10 | Ps Corp | Method for constructing arch rib of concrete arch bridge |
CN207988359U (en) * | 2018-02-05 | 2018-10-19 | 中建三局集团有限公司 | Concrete filled steel tube high pressure forming device and concrete filled steel tube |
Family Cites Families (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH05149096A (en) * | 1991-01-16 | 1993-06-15 | Taisei Corp | Lining shield method |
JP2011179239A (en) * | 2010-03-02 | 2011-09-15 | Nishimatsu Constr Co Ltd | Construction method of cast-in-place concrete pile |
CN104153295A (en) * | 2014-07-21 | 2014-11-19 | 广东省基础工程公司 | Self-compacting concrete jack-up pouring construction method for steel tube arch bridges |
-
2021
- 2021-07-19 CN CN202110813735.6A patent/CN113502921B/en active Active
Patent Citations (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2001098514A (en) * | 1999-10-01 | 2001-04-10 | Ps Corp | Method for constructing arch rib of concrete arch bridge |
CN207988359U (en) * | 2018-02-05 | 2018-10-19 | 中建三局集团有限公司 | Concrete filled steel tube high pressure forming device and concrete filled steel tube |
Also Published As
Publication number | Publication date |
---|---|
CN113502921A (en) | 2021-10-15 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110259184B (en) | Column pulling construction method based on joist and column pulling combined supporting and jacking system | |
CN105201514B (en) | A kind of water-bearing stratum shaft wall structure and construction method | |
CN110306726B (en) | Composite structure and manufacturing method thereof | |
CN109183607A (en) | Precast spliced UHPC pipe-concrete super-high pier and construction method | |
CN111749714B (en) | Window-by-window layered pouring system for circular water delivery tunnel wall and construction method | |
CN109403366B (en) | Assembled steel pipe concrete pile foundation and construction method thereof | |
CN108678287A (en) | A kind of bar connecting full grout sleeve of slurry pin bank conjunction | |
CN102352668B (en) | Prefabricated reinforced concrete assembled column and its manufacturing method | |
CN111828053A (en) | Tunnel support system and construction method of concrete-filled steel tube and shotcrete stiffness composite structure | |
CN110700439A (en) | Prefabricated assembly type shear wall rapid formwork erecting connection construction method | |
CN113502921B (en) | Construction method of concrete filled steel tube arch rib | |
CN104060590B (en) | The reinforcement leakage preventing structure of a kind of pressure diversion tunnel and construction method thereof | |
CN109112967B (en) | Tower beam thrust connection device and quick construction method for self-anchored suspension bridge | |
CN112041516A (en) | Prefabricated floor element, structure comprising prefabricated floor element and device for obtaining prefabricated floor element | |
CN105926634B (en) | The pressurization external member of shaped steel combination support | |
CN113502922B (en) | A method for anti-debonding forming of concrete-filled steel tube arch ribs | |
CN110185486B (en) | Permanent outburst prevention air door wall body with steel pipe concrete structure and construction method thereof | |
CN109610338B (en) | Construction method for preventing slurry leakage at bottom opening of tower column of suspension bridge | |
CN112895105A (en) | Demoulding system and demoulding method of UHPC (ultra high performance polycarbonate) low rib plate | |
CN110388215B (en) | Construction method for vertical jacking pipe of urban underground comprehensive pipe gallery tunnel | |
CN207244618U (en) | A kind of soil nailing applies prestressed device | |
CN103243910B (en) | Hydraulic pressure controlled reinforced concrete structure bed die vertical supporting system and construction method thereof | |
CN212641534U (en) | A load box using a self-service in-cylinder grouting jack | |
CN212716667U (en) | Steel pipe concrete and sprayed concrete rigid combined structure tunnel supporting system | |
CN111364529B (en) | A load box using a self-service in-cylinder grouting jack |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |