CN113373922A - Geothermal energy pile construction equipment and construction method thereof - Google Patents

Geothermal energy pile construction equipment and construction method thereof Download PDF

Info

Publication number
CN113373922A
CN113373922A CN202110747835.3A CN202110747835A CN113373922A CN 113373922 A CN113373922 A CN 113373922A CN 202110747835 A CN202110747835 A CN 202110747835A CN 113373922 A CN113373922 A CN 113373922A
Authority
CN
China
Prior art keywords
pile
heat transfer
transfer pipe
section
planting
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202110747835.3A
Other languages
Chinese (zh)
Inventor
陈洪雨
张日红
舒佳明
明维
邱风雷
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Ningbo Zcone High Tech Co ltd
Original Assignee
Ningbo Zcone High Tech Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Ningbo Zcone High Tech Co ltd filed Critical Ningbo Zcone High Tech Co ltd
Priority to CN202110747835.3A priority Critical patent/CN113373922A/en
Publication of CN113373922A publication Critical patent/CN113373922A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D7/00Methods or apparatus for placing sheet pile bulkheads, piles, mouldpipes, or other moulds
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/02Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes with non-adjustable and non-inclinable jibs mounted solely for slewing movements
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/04Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes with jibs the effective length of which is variable in operation, e.g. longitudinally displaceable, extensible
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66CCRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
    • B66C23/00Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes
    • B66C23/16Cranes comprising essentially a beam, boom, or triangular structure acting as a cantilever and mounted for translatory of swinging movements in vertical or horizontal planes or a combination of such movements, e.g. jib-cranes, derricks, tower cranes with jibs supported by columns, e.g. towers having their lower end mounted for slewing movements
    • B66C23/166Simple cranes with jibs which may be fixed or can slew or luff
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D13/00Accessories for placing or removing piles or bulkheads, e.g. noise attenuating chambers
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F24HEATING; RANGES; VENTILATING
    • F24TGEOTHERMAL COLLECTORS; GEOTHERMAL SYSTEMS
    • F24T10/00Geothermal collectors
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F25REFRIGERATION OR COOLING; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS; MANUFACTURE OR STORAGE OF ICE; LIQUEFACTION SOLIDIFICATION OF GASES
    • F25BREFRIGERATION MACHINES, PLANTS OR SYSTEMS; COMBINED HEATING AND REFRIGERATION SYSTEMS; HEAT PUMP SYSTEMS
    • F25B30/00Heat pumps
    • F25B30/06Heat pumps characterised by the source of low potential heat
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/10Geothermal energy

Abstract

The invention discloses geothermal energy pile construction equipment and a construction method thereof, wherein the equipment comprises an equipment main platform provided with a walking mechanism, the center of the equipment main platform is provided with a pile planting system and a hoisting system, a heat transfer pipe arrangement device used for winding and releasing a heat transfer pipe is also arranged right behind the pile planting system, the equipment main platform is provided with a heat transfer pipe passage at the rear end adjacent to the pile planting system, and the heat transfer pipe passage is a rectangular hole which can enable the heat transfer pipe wound on the heat transfer pipe arrangement device to pass through the equipment main platform and be discharged downwards; the center of the pile planting system is provided with a pile planting opening which can enable the precast pile to penetrate through the main platform of the equipment to be planted into the pile hole. The construction method is safe, reliable, simple and high-efficiency, can avoid the heat transfer pipe from being damaged by pulling during the arrangement, and prevents the heat transfer pipe from being damaged in the later earth excavation process.

Description

Geothermal energy pile construction equipment and construction method thereof
Technical Field
The invention relates to the technical field of geothermal energy pile construction, in particular to geothermal energy pile construction equipment and a construction method thereof.
Background
At present, a precast pile implantation method is a development trend of a pile foundation, and arrangement of a ground source heat pump heat transfer pipe by utilizing the precast pile implantation method is a very effective means. In the prior art, the invention patent with the patent number of CN 108570982 a discloses a static drill rooted pile energy pile and a construction method thereof, wherein a heat transfer pipe is embedded by using the static drill rooted pile, and the heat transfer pipe is arranged in a precast pile, so that the defects of high construction difficulty, easy damage of a joint and poor heat transfer effect exist. The invention patent with the patent number of CN 108709328A also discloses a geothermal energy pile of static drilling root planting method and a heat transfer pipe burying method thereof, which also uses the static drilling root planting pile to bury the heat transfer pipe. No protective measures are taken for the heat transfer pipe at the position of the welding joint of the precast pile and the pile top, and the heat transfer pipe is easily damaged in the precast pile welding and later-stage earthwork excavation engineering. In the pile sinking process of the precast pile, the heat transfer pipe can be easily damaged by strong resistance of peripheral cement soil.
The invention provides equipment and a method for laying a ground source heat pump heat transfer pipe by a precast pile embedding method, provides effective protection measures for a precast pile welded joint, the heat transfer pipe at the top of the precast pile and a construction process, and solves the problem of arranging the heat transfer pipe by the existing precast pile embedding method.
Disclosure of Invention
The invention aims to solve the technical problem of the prior art and provides geothermal energy pile construction equipment and a construction method thereof, wherein the construction method is simple, the efficiency is high, the quality is reliable, and the safety of the arrangement of a heat transfer pipe can be ensured.
The technical scheme adopted by the invention for solving the technical problems is as follows:
a geothermal energy pile construction device comprises a device main platform provided with a walking mechanism, wherein a pile planting system used for planting piles is arranged in the center of the device main platform, a hoisting system used for hoisting precast piles is arranged on the device main platform and is close to the front end of the device main platform, a heat transfer pipe arrangement device used for winding and retracting heat transfer pipes is arranged right behind the pile planting system on the device main platform, a heat transfer pipe passage is arranged at the rear end close to the pile planting system on the device main platform, and the heat transfer pipe passage is a rectangular hole which enables the heat transfer pipes wound on the heat transfer pipe arrangement device to penetrate through the device main platform and to be discharged downwards; the center of the pile planting system is provided with a pile planting opening which can enable the precast pile to penetrate through the main platform of the equipment to be planted into the pile hole.
In order to optimize the technical scheme, the specific measures adopted further comprise:
the main platform of the equipment is of a rectangular structure; the center of the pile planting system, the center of the heat transfer pipe passage and the center of the heat transfer pipe arrangement device are all positioned on the same center dividing line of the equipment main platform, and the center dividing line is parallel to the long edge of the equipment main platform; the hoisting system is arranged to deviate from the center parting line.
The hoisting system is arranged on the main platform of the equipment at a position relatively close to the left front corner; the lifting system comprises a rotary operating platform which is arranged on a main platform of the equipment and can rotate by 360 degrees, and a lifting arm which is hinged on the rotary operating platform and can be extended and retracted; the suspension arm is provided with a lifting hook through a steel wire rope.
The heat transfer pipe arrangement device comprises a roller bracket fixed on a main platform of the equipment and a cylindrical roller rotatably erected on the roller bracket; the heat transfer pipes are sequentially wound on the cylindrical drum.
The invention also provides a construction method of the geothermal energy pile construction equipment, which comprises the following steps:
1) firstly, fixing the upper end of a heat transfer pipe of a ground source heat pump on a cylindrical roller of a heat transfer pipe arrangement device, and then rotating the cylindrical roller clockwise to enable the heat transfer pipe to be wound on the cylindrical roller in a stacked and orderly manner;
2) the equipment main platform is moved to the pile hole needing pile planting by the aid of the moving mechanism, and the center of a pile planting opening of the pile planting system is made to coincide with the center of the pile hole needing pile planting; then, hoisting the first section of precast pile by using a hoisting system, and enabling the pile bottom of the section of precast pile to downwards penetrate through the equipment main platform from a pile planting opening of a pile planting system;
3) rotating the cylindrical roller of the heat transfer pipe arrangement device anticlockwise to enable the lower end of the heat transfer pipe to be placed down from the cylindrical roller and downwards penetrate through the main equipment platform through the heat transfer pipe passage, and then fixing the lower end of the heat transfer pipe and the lower end of the first section of precast pile together through a binding belt or a hoop;
4) implanting a first section of precast pile into a pile hole by utilizing the matching of a hoisting system and a pile planting system, enabling a heat transfer pipe to be continuously placed from a cylindrical roller under the driving of the first section of precast pile by rotating the cylindrical roller anticlockwise in the pile planting process, and fixing the heat transfer pipe and the first section of precast pile by using a binding belt or a hoop after the first section of precast pile is planted for a certain distance; when the distance between the pile top of the first section of precast pile and the platform surface of the equipment main platform is 0.5 m, stopping pile planting;
5) temporarily fixing the first section of precast pile by using a pile planting system, hoisting the second section of precast pile by using a hoisting system to enable the pile bottom of the second section of precast pile to be aligned and attached to the pile top of the first section of precast pile, and then welding the second section of precast pile and the first section of precast pile together by adopting a welding method;
6) after the welding is finished, loosening the first section of precast pile by the pile planting system, then continuing to plant the pile, and in the same process of planting the pile, rotating the cylindrical roller anticlockwise to enable the heat transfer pipe to be continuously placed from the cylindrical roller under the driving of the first section of precast pile, and fixing the heat transfer pipe and the second section of precast pile by using a binding belt or a hoop after the pile is planted for a certain distance; when the distance between the pile top of the second section of precast pile and the platform surface of the main platform of the equipment is 0.5 m, stopping pile planting;
7) and repeating the step 5) and the step 6) so as to implant a third section of precast pile and a fourth section of precast pile, when the last section of precast pile is implanted, stopping pile implantation after the pile top of the last section of precast pile passes through the pile implanting opening, fixedly mounting a protective sleeve for protecting the heat transfer pipe at the position of the section of precast pile close to the pile top, and then continuously implanting the pile to the designed elevation after the upper end of the heat transfer pipe is accommodated and protected in the protective sleeve.
The corrugated joint with certain elastic contraction function is added in the pipe section of the heat transfer pipe.
The heat transfer pipe is provided with a thin steel wire rope for bearing the tensile force during pile planting, and the thin steel wire rope is fixed with the heat transfer pipe through a binding belt or a hoop.
The heat transfer pipe is adhered with a heat insulation material with a heat insulation function at the welding position of the two sections of precast piles.
The protective sleeve consists of a non-closed circular sleeve with a strip-shaped opening in the axial direction and an upper end cover which is covered on the upper port of the non-closed circular sleeve; the two wings of the strip-shaped opening on the non-closed circular sleeve are formed with flanges which are convenient to be fixedly connected with the precast pile.
The protective sleeve is fixedly arranged on the precast pile by adopting a welding or bolt connection method.
Compared with the comparison document, the heat transfer pipe arranging device for winding and releasing the heat transfer pipes is arranged on the movable equipment main platform, so that the heat transfer pipes can be orderly released on the heat transfer pipe arranging device during construction. In order to ensure the smoothness of the heat transfer pipe application, the heat transfer pipe passage capable of providing a guiding function for the heat transfer pipe application is arranged on the main platform of the equipment, and the heat transfer pipe can downwards penetrate through the main platform of the equipment through the heat transfer pipe passage. The construction method of the geothermal energy pile construction equipment is simple and high in efficiency, the heat transfer pipe can be prevented from being damaged by pulling during arrangement through the arranged steel wire rope and the corrugated joint, and the heat transfer pipe can be prevented from being damaged in the later earth excavation process through the arranged protective sleeve.
Drawings
FIG. 1 is a schematic view showing the construction equipment of the present invention;
FIG. 2 is a top view of FIG. 1;
FIG. 3 is one of the construction state diagrams of the present invention;
FIG. 4 is a second construction state diagram of the present invention;
FIG. 5 is a schematic view of the pile connection of the present invention;
FIG. 6 is an enlarged partial schematic view at A of FIG. 5;
FIG. 7 is an enlarged partial schematic view at B of FIG. 5;
FIG. 8 is a schematic view of the application of the insulating material;
FIG. 9 is a perspective view of a protective cover according to the present invention;
fig. 10 is a schematic perspective view of the second embodiment of the protective cover of the present invention.
Detailed Description
Embodiments of the present invention are described in further detail below with reference to the accompanying drawings.
Fig. 1 to 10 are schematic views of the structure of the present invention and its construction state.
Wherein the reference numerals are: the heat insulation material R, the precast pile Z, the equipment main platform 1, the heat transfer pipe passage 1a, the traveling mechanism 2, the pile planting system 3, the pile planting opening 3a, the hoisting system 4, the rotary operating platform 41, the suspension arm 42, the lifting hook 43, the heat transfer pipe arrangement device 5, the roller bracket 51, the cylindrical roller 52, the heat transfer pipe 6, the corrugated joint 61, the binding belt 7, the protective sleeve 8, the non-closed circular sleeve 81, the strip-shaped opening 81a, the flange 811, the upper end cover 82 and the thin steel wire rope 9.
As shown in fig. 1 and 2, the invention discloses a geothermal energy pile construction device, which comprises a device main platform 1 provided with a traveling mechanism 2, wherein the device main platform 1 is in a rectangular structure, and the traveling mechanism 2 can carry the device main platform 1 and all components arranged on the device main platform 1 to move front and back, left and right. The center of equipment primary platform 1 is equipped with the stake system of planting 3 that is used for planting the stake, contains among the system of planting 3 to have hydraulic actuator, can grasp the precast pile through hydraulic actuator to the connection of two sections of stake convenience is planted in the pause. The center of the pile planting system 3 is provided with a pile planting opening 3a penetrating through the equipment main platform 1, the pile planting opening 3a is a cylindrical hole, and the diameter of the hole is larger than that of the precast pile Z, so that the precast pile can penetrate through the equipment main platform 1 through the pile planting opening 3a and is planted into the pile hole. The equipment main platform 1 is provided with a hoisting system 4 near the front end, and the hoisting system 4 comprises a rotating operation platform 41 fixedly arranged on the equipment main platform 1 and a suspension arm 42 hinged on the rotating operation platform 41 and capable of extending and contracting. A hook 43 is mounted on the boom 42 through a wire rope. The rotating operation platform 41 is provided with a rotating disc, so that the boom 42 can be driven to rotate for 360 degrees, the rotating operation platform 41 is also provided with a winch, and the lifting hook 43 can be controlled by the winding and unwinding of the winch on the steel wire rope. The hoisting system 4 has the main functions of hoisting and positioning the precast pile and carrying out other hoisting operations. The biggest contribution of the invention is as follows: the main platform 1 of the equipment is provided with a heat transfer pipe arranging device 5, and the heat transfer pipe arranging device 5 can enable the heat transfer pipes 6 to be wound on the heat transfer pipe arranging device 5 in a stacking and orderly mode so that the heat transfer pipes 6 can be arranged and released in the subsequent construction. The heat transfer pipe arranging device 5 is arranged right behind the pile planting system 3, so that the heat transfer pipe 6 can be more smoothly discharged. The rear end of the equipment main platform 1, which is tightly attached to the pile planting system 3, is provided with a heat transfer pipe passage 1a, the heat transfer pipe passage 1a is a rectangular hole which penetrates through the equipment main platform 1 downwards, and therefore the heat transfer pipe 6 wound on the heat transfer pipe arrangement device 5 can penetrate through the equipment main platform 1 through the heat transfer pipe passage 1a to be discharged downwards.
In order to ensure that the heat transfer tubes 6 are not scratched by the heat transfer tube path 1a when they are discharged, guide wheels for guiding the heat transfer tubes 6 are further provided in the heat transfer tube path 1a, and the heat transfer tubes 6 pass through the heat transfer tube path 1a in rolling frictional contact with the guide wheels.
In the embodiment, as can be seen from fig. 2, the center of the pile planting system 3, the center of the heat transfer pipe passage 1a, and the center of the heat transfer pipe arranging device 5 of the present invention are all located on the same bisector of the main equipment platform 1, and the bisector is parallel to the long sides of the main equipment platform 1. The hoisting system 4 is installed on the main platform 1 of the equipment at a position relatively close to the front left corner, so that the hoisting system 4 is arranged in a manner of deviating from the center parting line of the main platform 1 of the equipment.
In the embodiment, the heat transfer pipe arranging apparatus 5 of the present invention is composed of a drum holder 51 fixed to the main platform 1 of the apparatus and a cylindrical drum 52 rotatably mounted on the drum holder 51. The heat transfer pipes 6 are sequentially wound on the cylindrical drum 52. In winding, the upper end of the heat transfer pipe 6 may be fixed on the cylindrical drum 52, and then the cylindrical drum 52 is rotated to wind the heat transfer pipe 6 on the cylindrical drum 52 layer by layer from inside to outside until the lower end of the heat transfer pipe 6 is also wound on the cylindrical drum 52.
The invention also provides a construction method of the geothermal energy pile construction equipment, which comprises the following steps:
1) the upper end of the heat transfer pipe 6 of the ground source heat pump is firstly fixed on the cylindrical drum 52 of the heat transfer pipe arranging device 5, and then the cylindrical drum 52 is rotated clockwise, so that the heat transfer pipe 6 can be completely wound on the cylindrical drum 52 in a stacked manner. In consideration of the fact that the heat transfer pipe 8 is subjected to a large tensile force during the piling process and the heat transfer pipe 8 is easily broken or damaged by careless handling, the heat transfer pipe 6 of the present invention is provided with a full length of thin wire ropes 9, and the thin wire ropes 9 are fixed to the heat transfer pipe 6 by tie bands 7 or clips. That is, the upper end of the ground source heat pump heat transfer pipe 6 bound with the thin wire rope 9 is first fixed to the cylindrical drum 52 of the heat transfer pipe arranging device 5. The thin steel wire rope 9 is used for bearing the pulling force during pile planting, so that the pulling force of the pile planting is mainly borne by the thin steel wire rope 9, and a corrugated joint 61 with a certain elastic contraction function is additionally arranged in the pipe section of the heat transfer pipe 6 (as shown in fig. 6). The corrugated joint 61 can ensure that the internal structure of the heat transfer pipe 6 is not affected by a certain elastic deformation under the action of an external force.
2) The equipment main platform 1 is moved to a pile hole needing pile planting by the travelling mechanism 2, and the center of a pile planting opening 3a of the pile planting system 3 is coincided with the center of the pile hole needing pile planting; then, hoisting the first section of precast pile Z by using a hoisting system 4, and enabling the pile bottom of the section of precast pile Z to downwards penetrate through the equipment main platform 1 from a pile planting port 3a of a pile planting system 3;
3) rotating the cylindrical drum 52 of the heat transfer pipe arranging device 5 counterclockwise so that the lower end of the heat transfer pipe 6 is lowered from the cylindrical drum 52 and passes downward through the apparatus main platform 1 via the heat transfer pipe passage 1a, and then fixing the lower end of the heat transfer pipe 6 and the lower end of the first precast pile section Z together with a tie 7 or a band (see fig. 3); the first section of precast pile Z is a bamboo joint pile, and the rest precast piles Z can be bamboo joint piles or other types of precast piles, such as tubular piles.
4) Implanting a first section of precast pile Z into a pile hole by utilizing the matching of the hoisting system 4 and the pile planting system 3, enabling the heat transfer pipe 6 to be continuously placed from the cylindrical roller 52 under the driving of the first section of precast pile Z by rotating the cylindrical roller 52 anticlockwise in the pile planting process, and fixing the heat transfer pipe 6 and the first section of precast pile Z by using a binding belt 7 or a hoop after the first section of precast pile Z is planted for a certain distance; when the distance between the pile top of the first section of precast pile Z and the platform surface of the equipment main platform 1 is 0.5 m, stopping pile planting;
5) temporarily fixing the first section of precast pile Z by using a pile planting system 3, hoisting the second section of precast pile Z by using a hoisting system 4 to enable the pile bottom of the second section of precast pile Z to be aligned and attached to the pile top of the first section of precast pile Z, and welding the second section of precast pile Z and the first section of precast pile Z together by adopting a welding method (see figure 4);
6) after the welding is finished, loosening the first section of precast pile Z by the pile planting system 3, then continuing to plant the pile, and in the same pile planting process, rotating the cylindrical roller 52 anticlockwise to enable the heat transfer pipe 6 to be continuously placed from the cylindrical roller 52 under the driving of the first section of precast pile Z, and fixing the heat transfer pipe 6 and the second section of precast pile Z by using a binding belt 7 or a hoop after the pile is planted for a certain distance; when the distance between the pile top of the second section of precast pile Z and the platform surface of the equipment main platform 1 is 0.5 m, stopping pile planting;
7) and repeating the step 5) and the step 6) to implant a third section of precast pile and a fourth section of precast pile, when the last section of precast pile is implanted, stopping pile implantation after the pile top of the last section of precast pile passes through the pile implanting opening 3a, fixedly mounting a protecting sleeve 8 for protecting the heat transfer pipe 6 at the position of the section of precast pile Z close to the pile top, and then continuously implanting the pile to the designed elevation after the upper end of the heat transfer pipe 6 is accommodated and protected in the protecting sleeve 8. The lag 8 is used for protecting heat-transfer pipe 6, can prevent that the earth excavation in later stage from causing the harm to heat-transfer pipe 6.
As shown in fig. 9 and 10, the protective cover 8 of the present invention is composed of a non-closed circular sleeve 81 having a strip-shaped opening 81a in the axial direction and an upper end cap 82 covering the upper end opening of the non-closed circular sleeve 81; flanges 811 for facilitating the fixed connection with the precast pile Z are formed on both wings of the strip-shaped opening 81a of the non-closed circular sleeve 81.
The protective sleeve 8 is fixedly arranged on the precast pile Z by welding or bolt connection.
Because a large amount of heat is generated during welding of the two sections of precast piles, the heat cannot be dissipated in time during pile planting, and the heat is possibly damaged by contact with the heat transfer pipe 6, in order to prevent the risk, the heat transfer pipe 6 is protected by adopting the heat insulation material R at the welding interface of the two sections of piles, and the heat insulation material R has a quick adhesion function, as shown in fig. 7 and 8, the heat insulation material R is adhered and coated on the heat transfer pipe 6 at the welding position of the two sections of precast piles.
The main advantages of the invention are:
1. the construction equipment for constructing the heat transfer pipe is provided, the current situation that the heat transfer pipe is manually placed is changed, the labor is greatly saved, and the construction efficiency is improved;
2. provided is a corrugated joint for a heat transfer pipe, which prevents the heat transfer pipe from being damaged by external force during construction. The corrugated pipe pile joint is combined, and the steel wire rope is used as a main stress member, so that the stress of the heat transfer pipe is reduced, and the heat transfer pipe is effectively protected from being damaged;
3. a protective measure for the welded joint is provided to prevent the heat of the welded joint from damaging the heat transfer pipe. The construction is quick and effective;
4. a novel protective sleeve is provided, and the heat transfer pipe is effectively protected from being damaged during later excavation.
While the preferred embodiments of the present invention have been illustrated, various changes and modifications may be made by one skilled in the art without departing from the scope of the invention.

Claims (10)

1. The utility model provides a geothermal energy stake construction equipment, is including installing equipment primary platform (1) of running gear (2), the center of equipment primary platform (1) be equipped with and be used for planting stake plant a system (3), this equipment primary platform (1) is gone up and is being close to front end department and install lifting system (4) that are used for lifting by crane precast pile (Z), characterized by: a heat transfer pipe arrangement device (5) for winding and unwinding a heat transfer pipe (6) is arranged right behind the pile planting system (3) on the equipment main platform (1), a heat transfer pipe passage (1a) is formed in the equipment main platform (1) and is close to the rear end of the pile planting system (3), and the heat transfer pipe passage (1a) is a rectangular hole which enables the heat transfer pipe (6) wound on the heat transfer pipe arrangement device (5) to penetrate through the equipment main platform (1) to be discharged downwards; the center of the pile planting system (3) is provided with a pile planting opening (3a) which can enable the precast pile (Z) to penetrate through the main platform (1) of the equipment to be planted in the pile hole.
2. The geothermal energy pile construction equipment according to claim 1, wherein: the equipment main platform (1) is of a rectangular structure; the center of the pile planting system (3), the center of the heat transfer pipe passage (1a) and the center of the heat transfer pipe arrangement device (5) are all positioned on the same center parting line of the main equipment platform (1), and the center parting line is parallel to the long side of the main equipment platform (1); the hoisting system (4) is arranged to deviate from the center parting line.
3. The geothermal energy pile construction equipment according to claim 2, wherein: the hoisting system (4) is arranged on the main platform (1) of the equipment at a position relatively close to the left front corner; the hoisting system (4) comprises a rotating operation platform (41) which is arranged on the main platform (1) of the equipment and can rotate in 360 degrees, and a suspension arm (42) which is hinged on the rotating operation platform (41) and can stretch out and draw back; and a lifting hook (43) is arranged on the suspension arm (42) through a steel wire rope.
4. The geothermal energy pile construction equipment according to claim 3, wherein: the heat transfer pipe arrangement device (5) comprises a roller bracket (51) fixed on the main platform (1) of the equipment and a cylindrical roller (52) rotatably erected on the roller bracket (51); the heat transfer pipe (6) is orderly wound on the cylindrical roller (52).
5. The construction method of the geothermal energy pile construction equipment according to claim 4, wherein the construction method comprises the following steps: the method comprises the following steps:
1) firstly, fixing the upper end of a heat transfer pipe (6) of a ground source heat pump on a cylindrical roller (52) of a heat transfer pipe arrangement device (5), and then rotating the cylindrical roller (52) clockwise to enable the heat transfer pipe (6) to be completely wound on the cylindrical roller (52) in a stacking and orderly manner;
2) the equipment main platform (1) is moved to a pile hole needing pile planting by using the moving mechanism (2), and the center of a pile planting opening (3a) of the pile planting system (3) is coincided with the center of the pile hole needing pile planting; then, hoisting the first section of precast pile (Z) by using a hoisting system (4), and enabling the pile bottom of the section of precast pile (Z) to downwards penetrate through the equipment main platform (1) from a pile planting opening (3a) of a pile planting system (3);
3) rotating a cylindrical roller (52) of the heat transfer pipe arrangement device (5) anticlockwise, so that the lower end of the heat transfer pipe (6) is placed from the cylindrical roller (52) and downwards passes through the equipment main platform (1) through a heat transfer pipe passage (1a), and then fixing the lower end of the heat transfer pipe (6) and the lower end of the first section of precast pile (Z) together by using a binding belt (7) or a hoop;
4) implanting a first section of precast pile (Z) into a pile hole by utilizing the matching of a hoisting system (4) and a pile planting system (3), wherein in the pile planting process, a heat transfer pipe (6) can be continuously placed from a cylindrical roller (52) under the driving of the first section of precast pile (Z) by rotating the cylindrical roller (52) anticlockwise, and the heat transfer pipe (6) and the first section of precast pile (Z) are fixed by using a binding belt (7) or a hoop after each pile planting is carried out for a certain distance; when the distance between the pile top of the first section of precast pile (Z) and the platform surface of the main platform (1) of the equipment is 0.5 m, stopping pile planting;
5) temporarily fixing the first section of precast pile (Z) by using a pile planting system (3), hoisting the second section of precast pile (Z) by using a hoisting system (4) to enable the pile bottom of the second section of precast pile (Z) to be aligned and attached to the pile top of the first section of precast pile (Z), and then welding and connecting the second section of precast pile (Z) and the first section of precast pile (Z) together by adopting a welding method;
6) after the welding is finished, loosening the first section of precast pile (Z) by the pile planting system (3), then continuously planting the pile, and in the same pile planting process, rotating the cylindrical roller (52) anticlockwise to enable the heat transfer pipe (6) to be continuously placed from the cylindrical roller (52) under the driving of the first section of precast pile (Z), and fixing the heat transfer pipe (6) and the second section of precast pile (Z) by using a binding belt (7) or a hoop after the pile is planted for a certain distance; when the distance between the pile top of the second section of precast pile (Z) and the platform surface of the main platform (1) of the equipment is 0.5 m, stopping pile planting;
7) so repeat step 5) and step 6) and plant third section precast pile, fourth section precast pile, when planting last section precast pile, stop planting the pile after the pile bolck of last section precast pile passes planting stake mouth (3a) to in this section precast pile (Z) be close to the position department fixed mounting one be used for protecting lag (8) of heat-transfer pipe (6), then hold the upper end of heat-transfer pipe (6) and protect in this lag (8) after, continue to plant the stake to design elevation.
6. The construction method of the geothermal energy pile construction equipment according to claim 5, wherein the construction method comprises the following steps: the corrugated joint (61) with certain elastic contraction function is added in the pipe section of the heat transfer pipe (6).
7. The construction method of the geothermal energy pile construction equipment according to claim 6, wherein: the heat transfer pipe (6) lead to long dispose one be used for bearing tensile thin wire rope (9) when the stake is planted, thin wire rope (9) pass through ligature area (7) or clamp and heat transfer pipe (6) are fixed together.
8. The construction method of the geothermal energy pile construction equipment according to claim 7, wherein: and a heat insulation material (R) with a heat insulation function is adhered to the welding position of the two sections of precast piles on the heat transfer pipe (6).
9. The construction method of a geothermal energy pile construction equipment according to claim 8, wherein: the protective sleeve (8) consists of a non-closed circular sleeve (81) with a strip-shaped opening (81a) in the axial direction and an upper end cover (82) which is covered on the upper port of the non-closed circular sleeve (81); flanges (811) for conveniently and fixedly connecting the precast pile (Z) are formed on two wings of the strip-shaped opening (81a) of the non-closed circular cylinder sleeve (81).
10. The construction method of a geothermal energy pile construction equipment according to claim 9, characterized in that: the protective sleeve (8) is fixedly arranged on the precast pile (Z) by adopting a welding or bolt connection method.
CN202110747835.3A 2021-07-02 2021-07-02 Geothermal energy pile construction equipment and construction method thereof Pending CN113373922A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202110747835.3A CN113373922A (en) 2021-07-02 2021-07-02 Geothermal energy pile construction equipment and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202110747835.3A CN113373922A (en) 2021-07-02 2021-07-02 Geothermal energy pile construction equipment and construction method thereof

Publications (1)

Publication Number Publication Date
CN113373922A true CN113373922A (en) 2021-09-10

Family

ID=77580615

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202110747835.3A Pending CN113373922A (en) 2021-07-02 2021-07-02 Geothermal energy pile construction equipment and construction method thereof

Country Status (1)

Country Link
CN (1) CN113373922A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116289905A (en) * 2023-04-17 2023-06-23 浙江华宇基础工程有限公司 Hoisting threading device for static drilling root planting pile and construction method thereof

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN116289905A (en) * 2023-04-17 2023-06-23 浙江华宇基础工程有限公司 Hoisting threading device for static drilling root planting pile and construction method thereof
CN116289905B (en) * 2023-04-17 2023-08-11 浙江华宇基础工程有限公司 Hoisting threading device for static drilling root planting pile and construction method thereof

Similar Documents

Publication Publication Date Title
CN109630015A (en) A kind of friction pile mechanical hole building method
CN108930324B (en) Municipal road sewer pipeline construction equipment and method
CN102587380A (en) Construction method for wholly removing drilling pile head
CN113373922A (en) Geothermal energy pile construction equipment and construction method thereof
CN110260043B (en) Pipe jacking and sewage pipeline construction process using same
CN113795989A (en) Method for offshore installation of a power cable or a pipe of a power cable for a wind turbine installation and a subsea vehicle
KR20140029276A (en) Guide frame for guiding a cutting apparatus
US5967698A (en) Permitting two adjacent pipe lengths to be joined together
EP2458698A1 (en) Method and device for introducing an electrical cable at a depth in a seabed.
CN215441885U (en) Geothermal energy pile construction equipment
CN205224036U (en) Device is abolished to bridge pile foundation pile head
US8096733B2 (en) Apparatus for inserting sheet pile having an independently adjustable insertion axis and method for using the same
CN112252589A (en) Steel reinforcement cage structure and installation method thereof
CN214176690U (en) Bury cable and spread husky auxiliary device
US7033114B2 (en) Method for installing reinforcements around a cylindrical underground pipeline
JP6761556B1 (en) Mountain retaining wall formation method
US8342778B2 (en) Method and apparatus for facilitating the subterranean support of underground conduits having a fixed insertion axis
KR101103554B1 (en) Apparutus and method for installing underground pipe line
JP7357517B2 (en) Pipe construction method using propulsion method
CN112736773B (en) Method for assisting sand paving by using buried cable sand paving auxiliary device
CN217412895U (en) Traction device for raise boring pipeline construction
CN109371961B (en) Steel pipe column for subway station and construction process thereof
KR101120958B1 (en) Self propelled apparatus for installing underground pipe line and method for installing underground pipe line using the same
CN218373801U (en) Pile head connector for rapid construction of precast tubular pile
CN218093026U (en) Shaft boring equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination