CN109630015A - A kind of friction pile mechanical hole building method - Google Patents

A kind of friction pile mechanical hole building method Download PDF

Info

Publication number
CN109630015A
CN109630015A CN201811415914.9A CN201811415914A CN109630015A CN 109630015 A CN109630015 A CN 109630015A CN 201811415914 A CN201811415914 A CN 201811415914A CN 109630015 A CN109630015 A CN 109630015A
Authority
CN
China
Prior art keywords
hole
concrete
conduit
reinforcement cage
friction pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811415914.9A
Other languages
Chinese (zh)
Inventor
何武
刘勇
赵明雄
周强
郭瑞
冯振宁
王平玉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Sichuan Renmu Expressway Co Ltd
China Railway 20th Bureau Group Corp
Original Assignee
Sichuan Renmu Expressway Co Ltd
China Railway 20th Bureau Group Corp
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Sichuan Renmu Expressway Co Ltd, China Railway 20th Bureau Group Corp filed Critical Sichuan Renmu Expressway Co Ltd
Priority to CN201811415914.9A priority Critical patent/CN109630015A/en
Publication of CN109630015A publication Critical patent/CN109630015A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/06Placing concrete under water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/06Foundation trenches ditches or narrow shafts
    • E02D17/08Bordering or stiffening the sides of ditches trenches or narrow shafts for foundations
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/36Concrete or concrete-like piles cast in position ; Apparatus for making same making without use of mouldpipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B21/00Methods or apparatus for flushing boreholes, e.g. by use of exhaust air from motor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B3/00Rotary drilling
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B47/00Survey of boreholes or wells
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B47/00Survey of boreholes or wells
    • E21B47/04Measuring depth or liquid level
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21BEARTH OR ROCK DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/04Directional drilling
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Geology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Physics & Mathematics (AREA)
  • Structural Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Fluid Mechanics (AREA)
  • General Engineering & Computer Science (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Geophysics (AREA)
  • Mechanical Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a kind of friction pile mechanical hole building methods, include the following steps: step 1, construction site cleaning, leveling;Step 2, surveying setting-out;Step 3, fore shaft is constructed;Step 4, rotary drilling rig beats pilot hole;Step 5, chute forming machine modifies hole wall;Step 6, churning driven borehole cleaning;Step 7, steel reinforcement cage installation, decentralization are installed steel reinforcement cage using crawler crane in aperture, are transferred after molding to design position;Step 8, conduit and perfusion Underwater Concrete are installed.The present invention has the advantages that the construction time is short, construction efficiency is high, reduces the security risk of manually digging hole.

Description

A kind of friction pile mechanical hole building method
Technical field
The present invention relates to friction pile hole creating technology field, in particular to a kind of friction pile mechanical hole building method.
Background technique
It causes damages to prevent from coming down to life, the property of the mankind, needs that reasonable control measures is taken to prevent its sliding. Currently, common Anti-sliding stopping structure object has antiskid retaining wall, prestress anchorage cable pier (beam), prestressing force in landslide control engineering Anchored frame, common friction pile and pre-stress anti-slide pile etc..Wherein friction pile is a kind of work that landslide control is maximally efficient The thrust of slip mass is transmitted to sliding surface good ground below by the collective effect of stake and surrounding Rock And Soil by journey measure. Since its regulation effect is obvious, flexible arrangement is convenient, adaptable, biggish Thrust of Landslide can be resisted, in Harnessing of Landslide work It is widely used and develops in journey.But there is also some disadvantages for currently used manually digging hole friction pile:
(1) stake well manually excavates entirely, one section of excavation, and one section of supporting, and stake must be jumped and constructed in batches, the duration is tediously long, imitates Rate is low, is not suitable for emergency repair engineering;
(2) during artificial digging pile lifting dregs, security risk is big, Frequent Accidents, especially cost of labor in recent years Increase, excavated by manual work stake cost also gradually increases;
(3) dregs dug out from stake need to be placed with setting, if stacking is improper, less serious case can destroy blue mountains and green waters environment, severe one The Secondary Geological Hazards such as mud-rock flow, landslide will be induced.
Summary of the invention
The present invention in view of the drawbacks of the prior art, provides a kind of friction pile mechanical hole building method, can effectively solve State problem of the existing technology.
In order to realize the above goal of the invention, the technical solution adopted by the present invention is as follows:
A kind of friction pile mechanical hole building method, includes the following steps:
Step 1, construction site cleaning, leveling;
Step 2, surveying setting-out;
Step 3, fore shaft is constructed;
Step 4, rotary drilling rig beats pilot hole, and according to geological exploration data, tissue is entered the court the rotary drilling rig drilling of respective model It constructs, 5 pilot holes of rotary digging within the scope of pile body section;
Step 5, chute forming machine modifies hole wall, and chute forming machine in place modifies hole wall from top to bottom, last scarfing cinder to design Stake bottom elevation;
Step 6, churning driven borehole cleaning;
Step 7, steel reinforcement cage installation, decentralization install steel reinforcement cage using crawler crane in aperture, are transferred after molding to design position It sets;
Step 8, conduit and perfusion Underwater Concrete are installed.
Further, the fore shaft construction of the step 3, the specific steps are as follows:
(1) surveying and locating: excavation point is marked according to the friction pile axis of setting-out, fore shaft must be located in relatively closely knit soil On body or basement rock;
(2) it excavates: after surveying and locating, fore shaft being excavated using the method that mechanical excavation and manual amendment combine, forbids to surpass It digs;
(3) it formwork erection and pours concrete: making fore shaft position, then assembling reinforcement on bed die.With native Dai Mo outside fore shaft.
Further, the rotary drilling rig of the step 4 beats pilot hole, the specific steps are as follows:
Data according to friction pile is surveyed, 360 type rotary drilling rig match-drills of marching into the arena, and meanwhile it is thick according to chute forming machine bucket body Degree, which determines, is equipped with appropriate boring head;
(1) four angle pilot holes of friction pile are crept into first, and pilot hole disposably gets to design stake bottom elevation;
(2) bottom 5m range basement rock is harder, terminates in four angle pilot hole drillings, then perform middle part pilot hole.
(3) four angle pilot holes require the verticality of control pilot hole, and rotary drilling rig is in place to carry out seat in the plane with excavator before Smooth, after rotary digging contraposition, operator will carry out borer drill rod Uprightness adjusting, and be close to drill bit under the both sides at fore shaft angle, start to revolve Requiring when digging must be slow, could accelerate after drill bit fully enters ground.
Further, the chute forming machine of the step 5 rebuilds hole wall, specific as follows:
(1) after rotary drilling rig drills out pilot hole, dynamic compaction machinery cooperates chute forming machine in place, is adjacent to four angles and draws trimming hole wall, In renovation process, the amplitude that each chute forming machine is promoted is determined according to the soft or hard degree of basement rock, the amplitude that promoted cannot be excessive or too small, General hoisting depth is 0.5m~1m;
(2) bottom hole scarfing cinder
After the completion of hole wall trimming, is cleared up, transported outward, cleaning to bottom hole using brill digging brill Special slagging cylinder device to hole bedstone slag No empty slag is extremely;
(3) pore-forming inspection
After bottom hole rock ballast cleans out, for technical staff to stake holes inspection, the pile foundation end hole scope of examination includes stake holes center line Situations such as offset deviation, sectional dimension deviation, hole termination depth, bottom hole sediment, every deviation should be in design and specification allowed bands It is interior.
Further, the fabrication of reinforcing cage of the step 7 with hang;
Steel reinforcement cage main reinforcement and stirrup are in reinforcement yard's concentrated processing, and clamshell car is transported to scene classification and stacks, steel reinforcement cage Binding and installation aperture complete, the installation and lifting of steel reinforcement cage need pedrail crane cooperation complete;
(1) main reinforcement connects
HRB400 Φ 32mm main reinforcement spreading is using mechanical connection;HRB400 Φ 22mm main reinforcement uses two-sided overlap welding, reinforcing bar During spreading, the connector that is staggered being paid attention to, meeting jointing code requirement, connector percentage is not more than 50%;
(2) reinforcing bar framed bent welds
Divide four section welded reinforcement framed bents, lays main reinforcement according to design spacing, lift decentralization extremely respectively after the completion of welding Bottom hole;
(3) stirrup welds
Four section framed bents are transferred to bottom hole, and 2m welding stirrup every first makes steel reinforcement cage become an entirety, are conveniently hung Dress;Then according to steel reinforcement cage from stake top to stake bottom ordered encryption stirrup, stirrup is lifted during encrypting using crawler crane cooperation, Construction personnel operates in aperture always;Steel reinforcement cage is transferred after the completion of encryption to bottom hole design position.
Further, it should measure section by section conduit physical length when the conduit installation of the step 8 and sequentially number, do easy to remember Record controls pipe laying depth so as to concrete pouring in the process.And it should be noted that whether elastic tape disposes and check that each conduit both ends screw thread has Phenomena such as without silk is broken, in order to avoid occur phenomena such as water injection through pipe in filling process.
It needs that water proof then is installed in filling conduit to concrete pipeline and container watering wetting before concrete perfusion Facility starts pouring underwater concrete after storage hopper stores up full concrete.The quantity of first batch of concrete perfusion will be able to satisfy conduit Buried depth cannot be less than 1m and fill the needs of conduit bottom level for the first time, and depth when back cover in conduit Transducers Embedded in Concrete is not It obtains and is less than 1m, first batch of cubic amount of concrete is depending on side's amount of stake diameter and depth of tremie and conduit inner concrete, and mixing is good Concrete is transported at pile foundation mouth with concrete transport vehicle, and in the hopper that injection drilling machine is promoted, about 8m3 measures in interior concrete side, unified by special messenger Water proof bolt and valve are opened simultaneously carry out back cover after being ready to by commander, both sides, and isolation bolt uses steel plate, steel plate finer wire Wire saws are lifted by crane by drilling machine.
Compared with prior art the present invention has the advantages that the construction time is short, construction efficiency is high, reduces the peace of manually digging hole Full blast danger.
Specific embodiment
To make the objectives, technical solutions, and advantages of the present invention more comprehensible, it is exemplified below embodiment, the present invention is done It is further described.
Friction pile mechanical execution is summarized:
Friction pile mechanical excavation, performs fore shaft first, and assembling reinforcement, formwork erection reinforce after-pouring C30 concrete;
According to geological exploration data, tissue is entered the court the rotary drilling rig drilling construction of respective model, pile body section range inward turning Dig 5 pilot holes;
After drilling to design stake bottom elevation, chute forming machine in place modifies hole wall from top to bottom, last scarfing cinder to design Stake bottom elevation;
Steel reinforcement cage is installed using crawler crane in aperture, is transferred after molding to design position;
Conduit and perfusion Underwater Concrete are installed.
Construction technology process:
Pilot hole-chute forming machine finishing hole is beaten in construction site cleaning, leveling-surveying setting-out-fore shaft construction-rotary drilling rig Wall-churning driven borehole cleaning-steel reinforcement cage installation, decentralization-downcomer pour Underwater Concrete.
Fore shaft construction
(1) surveying and locating: excavation point is marked according to the friction pile axis of setting-out, fore shaft must be located in relatively closely knit soil On body or basement rock.
(2) it excavates: after surveying and locating, fore shaft being excavated using the method that mechanical excavation and manual amendment combine, forbids to surpass It digs.
(3) it formwork erection and pours concrete: making fore shaft position, then assembling reinforcement on bed die.Outside fore shaft with native Dai Mo (according to Field geology situation determines that internal model uses bulk steel form).
Rotary drilling rig beats pilot hole
Data according to friction pile is surveyed, 360 type rotary drilling rig match-drills of marching into the arena, and meanwhile it is thick according to chute forming machine bucket body Degree, which determines, is equipped with appropriate boring head.
(1) four angle pilot holes of friction pile are crept into first, and pilot hole disposably gets to design stake bottom elevation.
(2) bottom 5m range basement rock is harder, terminates in four angle pilot hole drillings, then perform middle part pilot hole.
(3) four angle pilot holes require the verticality of control pilot hole, and rotary drilling rig is in place to carry out seat in the plane with excavator before Smooth, after rotary digging contraposition, operator will carry out borer drill rod Uprightness adjusting, and be close to drill bit under the both sides at fore shaft angle, start to revolve Requiring when digging must be slow, could accelerate after drill bit fully enters ground.
Chute forming machine rebuilds hole wall
After rotary drilling rig drills out pilot hole, dynamic compaction machinery cooperates chute forming machine in place, is adjacent to four angles and draws trimming hole wall, rebuilds In the process, the amplitude of each chute forming machine promotion is determined according to the soft or hard degree of basement rock, the amplitude that promoted cannot be excessive or too small, generally Hoisting depth is 0.5m~1m.
Bottom hole scarfing cinder
After the completion of hole wall trimming, is cleared up, transported outward, cleaning to bottom hole using brill digging brill Special slagging cylinder device to hole bedstone slag No empty slag is extremely.
Pore-forming inspection
After bottom hole rock ballast cleans out, for technical staff to stake holes inspection, the pile foundation end hole scope of examination includes stake holes center line Situations such as offset deviation, sectional dimension deviation, hole termination depth, bottom hole sediment, every deviation should be in design and specification allowed bands It is interior.
Fabrication of reinforcing cage with hang
Steel reinforcement cage main reinforcement and stirrup are in reinforcement yard's concentrated processing, and clamshell car is transported to scene classification and stacks, steel reinforcement cage Binding and installation aperture complete, the installation and lifting of steel reinforcement cage need pedrail crane cooperation complete.
(1) main reinforcement connects
HRB400 Φ 32mm main reinforcement spreading is using mechanical connection;HRB400 Φ 22mm main reinforcement uses two-sided overlap welding, reinforcing bar During spreading, pay attention to the connector that is staggered, meet jointing code requirement (connector percentage is not more than 50%).
(2) reinforcing bar framed bent welds
Divide four section welded reinforcement framed bents, lays main reinforcement according to design spacing, lift decentralization extremely respectively after the completion of welding Bottom hole.
(3) stirrup welds
Four section framed bents are transferred to bottom hole, and 2m welding stirrup every first makes steel reinforcement cage become an entirety, are conveniently hung Dress;Then according to steel reinforcement cage from stake top to stake bottom ordered encryption stirrup, stirrup is lifted during encrypting using crawler crane cooperation, Construction personnel operates in aperture always;Steel reinforcement cage is transferred after the completion of encryption to bottom hole design position.
Conduit installation
Conduit should measure section by section conduit physical length and sequentially number when installing, and make a record to control during concrete pouring Pipe laying depth processed.And should be noted that phenomena such as whether disposing and check each conduit both ends screw thread by elastic tape whether there is or not broken silks, in order to avoid fill Occurs phenomena such as water injection through pipe during note.
Pile body concrete pouring
It needs that water proof then is installed in filling conduit to concrete pipeline and container watering wetting before concrete perfusion Facility starts pouring underwater concrete after storage hopper stores up full concrete.The quantity of first batch of concrete perfusion will be able to satisfy conduit Buried depth cannot be less than 1m and fill the needs of conduit bottom level for the first time, and depth when back cover in conduit Transducers Embedded in Concrete is not It obtains and is less than 1m, first batch of cubic amount of concrete is depending on side's amount of stake diameter and depth of tremie and conduit inner concrete, and mixing is good Concrete is transported at pile foundation mouth with concrete transport vehicle, and in the hopper that injection drilling machine is promoted, about 8m3 measures in interior concrete side, unified by special messenger Water proof bolt and valve are opened simultaneously carry out back cover after being ready to by commander, both sides, and isolation bolt uses steel plate, steel plate finer wire Wire saws are lifted by crane by drilling machine.
Following table is the comparison of the method for the present invention Yu traditional artificial borehole
Those of ordinary skill in the art will understand that the embodiments described herein, which is to help reader, understands this hair Bright implementation method, it should be understood that protection scope of the present invention is not limited to such specific embodiments and embodiments.Ability The those of ordinary skill in domain disclosed the technical disclosures can make its various for not departing from essence of the invention according to the present invention Its various specific variations and combinations, these variations and combinations are still within the scope of the present invention.

Claims (6)

1. a kind of friction pile mechanical hole building method, which comprises the steps of:
Step 1, construction site cleaning, leveling;
Step 2, surveying setting-out;
Step 3, fore shaft is constructed;
Step 4, rotary drilling rig beats pilot hole, and according to geological exploration data, tissue is entered the court the rotary drilling rig drilling construction of respective model, 5 pilot holes of rotary digging within the scope of pile body section;
Step 5, chute forming machine modifies hole wall, and chute forming machine in place modifies hole wall from top to bottom, last scarfing cinder to design stake bottom Elevation;
Step 6, churning driven borehole cleaning;
Step 7, steel reinforcement cage installation, decentralization are installed steel reinforcement cage using crawler crane in aperture, are transferred after molding to design position;
Step 8, conduit and perfusion Underwater Concrete are installed.
2. a kind of friction pile mechanical hole building method according to claim 1, it is characterised in that: the fore shaft of the step 3 is applied Work, the specific steps are as follows:
(1) surveying and locating: marking excavation point according to the friction pile axis of setting-out, fore shaft must be located in opposite compact earth or On basement rock;
(2) it excavates: after surveying and locating, fore shaft being excavated using the method that mechanical excavation and manual amendment combine, forbids to backbreak;
(3) it formwork erection and pours concrete: making fore shaft position, then assembling reinforcement on bed die;With native Dai Mo outside fore shaft.
3. a kind of friction pile mechanical hole building method according to claim 1, it is characterised in that: the churning driven of the step 4 Machine beats pilot hole, the specific steps are as follows:
Data according to friction pile is surveyed, 360 type rotary drilling rig match-drills of marching into the arena, and meanwhile it is true according to chute forming machine bucket body thickness Surely it is equipped with appropriate boring head;
(1) four angle pilot holes of friction pile are crept into first, and pilot hole disposably gets to design stake bottom elevation;
(2) bottom 5m range basement rock is harder, terminates in four angle pilot hole drillings, then perform middle part pilot hole;
It is smooth that (3) four angle pilot holes with excavator carry out seat in the plane before requiring the verticality of control pilot hole, rotary drilling rig in place, After rotary digging contraposition, operator will carry out borer drill rod Uprightness adjusting, and be close to drill bit under the both sides at fore shaft angle, start to want when rotary digging Asking must be slow, could accelerate after drill bit fully enters ground.
4. a kind of friction pile mechanical hole building method according to claim 1, it is characterised in that: the chute forming machine of the step 5 Hole wall is rebuild, specific as follows:
(1) after rotary drilling rig drills out pilot hole, dynamic compaction machinery cooperates chute forming machine in place, is adjacent to four angles and draws trimming hole wall, rebuilds In the process, the amplitude of each chute forming machine promotion is determined according to the soft or hard degree of basement rock, the amplitude that promoted cannot be excessive or too small, generally Hoisting depth is 0.5m~1m;
(2) bottom hole scarfing cinder
After the completion of hole wall trimming, is cleared up, transported outward using brill digging brill Special slagging cylinder device to hole bedstone slag, cleaning is to bottom hole without void Slag is extremely;
(3) pore-forming inspection
After bottom hole rock ballast cleans out, technical staff includes stake holes center displacement of the lines to stake holes inspection, the pile foundation end hole scope of examination Situations such as deviation, sectional dimension deviation, hole termination depth, bottom hole sediment, every deviation should be in designs and specification allowed band.
5. a kind of friction pile mechanical hole building method according to claim 1, it is characterised in that: the steel reinforcement cage of the step 7 It makes and hangs;
Steel reinforcement cage main reinforcement and stirrup are in reinforcement yard's concentrated processing, and clamshell car is transported to scene classification and stacks, and steel reinforcement cage is tied up It pricks and installation is completed in aperture, the installation and lifting of steel reinforcement cage need pedrail crane cooperation to complete;
(1) main reinforcement connects
HRB400 Φ 32mm main reinforcement spreading is using mechanical connection;HRB400 Φ 22mm main reinforcement uses two-sided overlap welding, reinforcing bar spreading In the process, pay attention to the connector that is staggered, meet jointing code requirement, connector percentage is not more than 50%;
(2) reinforcing bar framed bent welds
Divide four section welded reinforcement framed bents, lay main reinforcement according to design spacing, lifts decentralization after the completion of welding respectively to bottom hole;
(3) stirrup welds
Four section framed bents are transferred to bottom hole, and 2m welding stirrup every first makes steel reinforcement cage become an entirety, facilitate lifting;So Afterwards according to steel reinforcement cage from stake top to stake bottom ordered encryption stirrup, stirrup utilizes crawler crane cooperation lifting, construction during encrypting Personnel operate in aperture always;Steel reinforcement cage is transferred after the completion of encryption to bottom hole design position.
6. a kind of friction pile mechanical hole building method according to claim 1, it is characterised in that: the conduit of the step 8 is pacified Conduit physical length should be measured section by section when dress and is sequentially numbered, and made a record to control pipe laying depth during concrete pouring;And Phenomena such as whether there is or not broken silks it should be noted that whether elastic tape disposes and check each conduit both ends screw thread, in order to avoid led in filling process Phenomena such as water inlet tube;
It is needed before concrete perfusion to concrete pipeline and container watering wetting, then installation water proof is set in filling conduit It applies, after storage hopper stores up full concrete, starts pouring underwater concrete;The quantity of first batch of concrete perfusion will be able to satisfy conduit head Secondary buried depth cannot be less than 1m and fill the needs of conduit bottom level, and depth when back cover in conduit Transducers Embedded in Concrete must not Less than 1m, first batch of cubic amount of concrete is that mixing is good to mix depending on side's amount of stake diameter and depth of tremie and conduit inner concrete Solidifying soil is transported at pile foundation mouth with concrete transport vehicle, and in the hopper that injection drilling machine is promoted, about 8m3 measures in interior concrete side, is uniformly referred to by special messenger It waves, water proof bolt and valve are opened simultaneously carry out back cover after being ready to by both sides, and isolation bolt uses steel plate, steel plate seizing wire Traction, is lifted by crane by drilling machine.
CN201811415914.9A 2018-11-26 2018-11-26 A kind of friction pile mechanical hole building method Pending CN109630015A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811415914.9A CN109630015A (en) 2018-11-26 2018-11-26 A kind of friction pile mechanical hole building method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811415914.9A CN109630015A (en) 2018-11-26 2018-11-26 A kind of friction pile mechanical hole building method

Publications (1)

Publication Number Publication Date
CN109630015A true CN109630015A (en) 2019-04-16

Family

ID=66069155

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811415914.9A Pending CN109630015A (en) 2018-11-26 2018-11-26 A kind of friction pile mechanical hole building method

Country Status (1)

Country Link
CN (1) CN109630015A (en)

Cited By (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110374091A (en) * 2019-07-09 2019-10-25 云南建投基础工程有限责任公司 A kind of rectangle friction pile mechanical hole building construction method
CN110593753A (en) * 2019-08-30 2019-12-20 中铁七局集团第二工程有限公司 Mechanical rapid hole forming construction method for rectangular slide-resistant pile
CN110820733A (en) * 2019-11-07 2020-02-21 云南建投基础工程有限责任公司 Improved mechanical rapid hole forming construction method for simple rectangular slide-resistant pile
CN110820729A (en) * 2019-11-07 2020-02-21 云南建投基础工程有限责任公司 Efficient and safe integrated rapid hole forming method for anti-slide pile rotary excavating machinery
CN111021954A (en) * 2019-11-18 2020-04-17 四川农业大学 Novel anti-slide pile hole forming device and method thereof
CN111577118A (en) * 2020-05-13 2020-08-25 吉林大学 Mechanical rapid hole forming construction method for slide-resistant pile
CN111676960A (en) * 2020-05-29 2020-09-18 重庆建工第四建设有限责任公司 Construction method for pre-splicing stirrups of large rectangular piles in complex site
CN111691408A (en) * 2020-06-22 2020-09-22 福建省华策建设集团有限公司 Soft rock stratum rectangular slide-resistant pile construction method
CN113529759A (en) * 2021-08-31 2021-10-22 中铁三局集团有限公司 Construction method for mechanically excavating pile plate wall
CN113832958A (en) * 2021-09-08 2021-12-24 中交二公局第三工程有限公司 Anti-slide pile construction method with mechanical cooperation with manual excavation

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110374091B (en) * 2019-07-09 2021-02-19 云南建投基础工程有限责任公司 Mechanical pore-forming construction method for rectangular slide-resistant pile
CN110374091A (en) * 2019-07-09 2019-10-25 云南建投基础工程有限责任公司 A kind of rectangle friction pile mechanical hole building construction method
CN110593753A (en) * 2019-08-30 2019-12-20 中铁七局集团第二工程有限公司 Mechanical rapid hole forming construction method for rectangular slide-resistant pile
CN110820729B (en) * 2019-11-07 2021-04-16 云南建投基础工程有限责任公司 Efficient and safe integrated rapid hole forming method for anti-slide pile rotary excavating machinery
CN110820729A (en) * 2019-11-07 2020-02-21 云南建投基础工程有限责任公司 Efficient and safe integrated rapid hole forming method for anti-slide pile rotary excavating machinery
CN110820733A (en) * 2019-11-07 2020-02-21 云南建投基础工程有限责任公司 Improved mechanical rapid hole forming construction method for simple rectangular slide-resistant pile
CN111021954A (en) * 2019-11-18 2020-04-17 四川农业大学 Novel anti-slide pile hole forming device and method thereof
CN111577118A (en) * 2020-05-13 2020-08-25 吉林大学 Mechanical rapid hole forming construction method for slide-resistant pile
CN111577118B (en) * 2020-05-13 2021-07-23 吉林大学 Mechanical rapid hole forming construction method for slide-resistant pile
CN111676960A (en) * 2020-05-29 2020-09-18 重庆建工第四建设有限责任公司 Construction method for pre-splicing stirrups of large rectangular piles in complex site
CN111691408A (en) * 2020-06-22 2020-09-22 福建省华策建设集团有限公司 Soft rock stratum rectangular slide-resistant pile construction method
CN111691408B (en) * 2020-06-22 2021-08-03 福建省华策建设集团有限公司 Soft rock stratum rectangular slide-resistant pile construction method
CN113529759A (en) * 2021-08-31 2021-10-22 中铁三局集团有限公司 Construction method for mechanically excavating pile plate wall
CN113832958A (en) * 2021-09-08 2021-12-24 中交二公局第三工程有限公司 Anti-slide pile construction method with mechanical cooperation with manual excavation

Similar Documents

Publication Publication Date Title
CN109630015A (en) A kind of friction pile mechanical hole building method
CN110424381A (en) A kind of process for rotary digging drilling hole stake
CN104631470B (en) The large particle diameter sand gravel of high water level geology deep basal pit combination supporting construction method
CN101761083B (en) Underground continuous wall obstacle clearing construction method for traversing ultra-thick obstacle
CN107938656A (en) Complexity rebuilds base pit engineering pile base construction method
CN104499479B (en) It is a kind of to pass through the dug pile construction method that sand gravel backfills layer
CN106284313A (en) Long spire based on circulating mud retaining wall is squeezed into rock filling pile construction method
CN108914931A (en) A kind of ring-like foundation pile of the vertical shield of assembled and construction method
CN102720186B (en) Underwater once pouring method for variable cross-section bored cast-in-place pile
CN107724383B (en) Rotary digging cast-in-place pile construction method
CN107859145A (en) A kind of drainpipe is plugged into construction method under water
CN108457282A (en) Deep water hard rock is without back cover steel sheet pile cofferdam construction method
CN109778869A (en) Foundation ditch construction method
CN105442532A (en) Construction method for pile-head-expanded bored pile
CN104480929B (en) A kind of pile wall interaction construction method that interlocking pile is applied to permanent outer wall of basement
CN110629747A (en) Full-casing full-rotation construction process for pile foundation under complex geological conditions
CN104631438A (en) Method for constructing long auger bored cast-with-pressure concrete uplift pile
CN104153371A (en) Grouting-to-stop-water construction method of underwater rubble bed
CN110528578A (en) Under wear existing railway double track tunnel cover and cut construction method
CN112144514A (en) Simple method for forming hole and pile in sand and pebble stratum easy to collapse during rotary drilling machine
CN206721870U (en) A kind of long auger guncreting pile steel reinforcement cage
CN206408630U (en) Anchor head is placed in the Pile-Anchor Supporting for Deep Excavation system of pile body
CN104711975A (en) Construction technology for long spiral cast-in-situ bored pile
CN201943077U (en) Waterproof curtain of CT-type fore shaft steel pipe pile
CN109610473A (en) A kind of construction method of the large-scale pool structure foundation pit supporting system of municipal administration

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Liu Yong

Inventor after: Zhao Mingxiong

Inventor after: Wang Jingmei

Inventor after: Zhou Qiang

Inventor after: Guo Rui

Inventor after: He Wu

Inventor after: Wang Pingyu

Inventor before: He Wu

Inventor before: Liu Yong

Inventor before: Zhao Mingxiong

Inventor before: Zhou Qiang

Inventor before: Guo Rui

Inventor before: Feng Zhenning

Inventor before: Wang Pingyu

RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190416