CN112761677A - Underground coal mine water prevention and control method for grouting water-resisting layer by adopting mechanical digging groove construction - Google Patents

Underground coal mine water prevention and control method for grouting water-resisting layer by adopting mechanical digging groove construction Download PDF

Info

Publication number
CN112761677A
CN112761677A CN202011430253.4A CN202011430253A CN112761677A CN 112761677 A CN112761677 A CN 112761677A CN 202011430253 A CN202011430253 A CN 202011430253A CN 112761677 A CN112761677 A CN 112761677A
Authority
CN
China
Prior art keywords
water
grouting
rope
resisting layer
coal mine
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202011430253.4A
Other languages
Chinese (zh)
Inventor
任彦龙
张后全
赵华昀
刘延欣
武宇亮
张岭
李海鹏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CN202011430253.4A priority Critical patent/CN112761677A/en
Publication of CN112761677A publication Critical patent/CN112761677A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21BEARTH DRILLING, e.g. DEEP DRILLING; OBTAINING OIL, GAS, WATER, SOLUBLE OR MELTABLE MATERIALS OR A SLURRY OF MINERALS FROM WELLS
    • E21B7/00Special methods or apparatus for drilling
    • E21B7/04Directional drilling
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/10Making by using boring or cutting machines
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings

Abstract

The invention discloses a method for preventing and controlling water in an underground coal mine by adopting a mechanical digging groove construction grouting water-resisting layer, and belongs to the technical field of mine engineering construction. The invention drills a U-shaped communicating drill hole for multiple times through the directional drilling machine and cuts a rock stratum by adopting a rope saw cutting machine, and simultaneously carries out replacement grouting to form a mechanical digging groove grouting water-stop layer which can completely meet the design requirement, can effectively span the whole range of a water-stop layer, and cuts off a seepage channel between the water-stop layer and a coal seam to be exploited.

Description

Underground coal mine water prevention and control method for grouting water-resisting layer by adopting mechanical digging groove construction
Technical Field
The invention relates to the technical field of mine engineering construction, in particular to a method for preventing and controlling water in an underground coal mine by adopting a mechanical digging groove to construct and grout a water-resisting layer.
Background
At present, with gradual depletion of shallow resources, mining of various mineral resources to deep parts is imperative. In deep mining, the face is the complicated environment that ground pressure is big, and the pressure-bearing water pressure is high. Under the disturbance of coal seam mining, the deep original rock environment is damaged, and various coal mining water inrush accidents frequently occur.
At present, a drilling advanced grouting method is mainly adopted for underground coal mine water control, and the concrete method is that before coal seam mining, advanced drilling is carried out on a coal seam top plate (or a bottom plate), slurry is injected into holes, so that the slurry permeates in the middle of rock body pores, seepage channels are blocked, and a tree-shaped fan-shaped grouting water-proof curtain is formed. Due to the characteristics of pore development of the underground rock stratum, engineering practice proves that even if chemical grout with high permeability is adopted for grouting, an effective waterproof curtain which meets design requirements and can tightly seal and block all pore seepage channels is difficult to form, and an ideal water prevention and control effect cannot be achieved.
Disclosure of Invention
In order to overcome the defects of the prior art, the invention provides the underground coal mine water prevention and control method for grouting the water-resisting layer by adopting mechanical groove digging construction, which can effectively cut off a seepage passage between the water-bearing layer and a coal seam to be exploited, greatly improve the reliability of water prevention and control of the underground roof (or the bottom plate) of the coal mine, prevent the water inrush accident of the roof (or the bottom plate) and effectively ensure the production safety of the coal mine under the threat of water damage of the roof (or the bottom plate).
The invention is realized by the following technical scheme: a method for preventing and controlling water in an underground coal mine by adopting a mechanical digging groove construction grouting water-resisting layer is characterized by comprising the following steps:
step 1: constructing an auxiliary roadway before the coal seam to be mined is mined, so that the auxiliary roadway is close to a water-bearing stratum and a safe water-resisting distance is kept;
step 2: constructing a drilling site in the auxiliary roadway at a horizontal position which is 10 meters away from the horizontal line of the coal seam roof and/or the bottom plate aquifer, and arranging a directional drilling machine in the drilling site;
and step 3: two approximately horizontal drill holes are constructed in a coal seam roof (or floor) rock stratum along the horizontal direction of a drill site by adopting a directional drilling machine, the depression angle of the drill holes is within a range of 5 degrees, and the depth of the drill holes is based on the range exceeding a water-bearing stratum;
and 4, step 4: by utilizing the directional drilling function of a directional drilling machine, horizontally turning and drilling from the bottom of a certain drill hole to the bottom of another drill hole in the same horizontal plane, so that the two drill holes are communicated with each other to form a U-shaped communicated drill hole;
and 5: penetrating a diamond rope along the U-shaped communication drill hole, and leading out the diamond rope from two ends of the U-shaped communication through hole; a rope saw cutting machine is adopted in a drilling field to drive a diamond rope to rotate to cut a top plate rock stratum and/or a bottom plate rock stratum, a nearly horizontal blind groove with a certain thickness is formed by cutting through a rope saw, and a mud protective wall is adopted in the blind groove;
step 6: arranging a grouting pipe along the bottom of the blind groove, injecting cement slurry, and replacing the retaining wall slurry until the top plate and/or the bottom plate blind groove is completely filled with the cement slurry; after the cement grout is solidified, forming a grouting water-resisting layer of a cement filling entity with certain strength and certain thickness on the top plate and/or the bottom plate of the coal seam to be mined;
and 7: and if the range of the aquifer is large, repeating the steps 3-6, drilling the U-shaped communicated drill holes and cutting the rock stratum by a rope saw cutting machine for multiple times by adopting a directional drilling machine at every 20 m section on the horizontal plane, and simultaneously performing replacement grouting to enable the grouting water-resisting layer to span the whole range of the aquifer.
Further, in the step 5, after the diamond rope is led out from the two ends of the U-shaped connecting through hole, the diamond rope is wound on a driving wheel and an auxiliary wheel of the rope saw cutting machine, a rope saw electric motor is started, the driving wheel is adjusted through a control panel, the tensile tension of the rope is improved, the diamond rope is ensured to be properly tightened, and circulating cooling water is supplied; and starting the other electric motor to drive the driving wheel to drive the diamond rope to rotate and cut the deep rock stratum.
Further, in the step 5, the wall protecting medium formed by cutting with the rope saw is replaced by the water medium.
Further, in the step 6, the injected cement slurry is replaced by concrete slurry mixed with water glass quick setting medium.
The invention has the beneficial effects that: the invention drills a U-shaped communicating drill hole for multiple times through the directional drilling machine and cuts a rock stratum by adopting a rope saw cutting machine, and simultaneously carries out replacement grouting to form a mechanical digging groove grouting water-stop layer which can completely meet the design requirement, can effectively span the whole range of a water-stop layer, and cuts off a seepage channel between the water-stop layer and a coal seam to be exploited.
Drawings
The invention is further illustrated below with reference to the figures and examples.
FIG. 1 is a schematic view of a construction structure of the present invention;
figure 2 is a cross-sectional view of the inventive drill site.
In the figure, 1, an auxiliary roadway, 2, a drill site, 3, a coal seam to be mined, 4, a water-bearing stratum, 5, a drill hole, 6, a blind slot, 5 and 6 are grouted and a grouting water-resisting stratum is formed.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the specification, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. The following description of at least one exemplary embodiment is merely illustrative in nature and is in no way intended to limit the invention, its application, or uses. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without any inventive step, are within the scope of the present invention.
Techniques, methods, and apparatus known to those skilled in the art may not be discussed in detail but are intended to be part of the specification as appropriate.
The method for preventing and controlling water in the underground coal mine by adopting the mechanical digging groove construction grouting water-resisting layer is characterized by comprising the following steps of:
step 1: constructing an auxiliary roadway before the coal seam to be mined is mined, so that the auxiliary roadway is close to a water-bearing stratum and a safe water-resisting distance is kept; the distance determination refers to coal mine water control rules.
Step 2: constructing a drilling site in the auxiliary roadway at a horizontal position which is 10 meters away from the horizontal line of the coal seam roof and/or the bottom plate aquifer, and arranging a directional drilling machine in the drilling site;
and step 3: two approximately horizontal drill holes are constructed in a coal seam roof (or floor) rock stratum along the horizontal direction of a drill site by adopting a directional drilling machine, the depression angle of the drill holes is within a range of 5 degrees, and the depth of the drill holes is based on the range exceeding a water-bearing stratum;
and 4, step 4: by utilizing the directional drilling function of a directional drilling machine, horizontally turning and drilling from the bottom of a certain drill hole to the bottom of another drill hole in the same horizontal plane, so that the two drill holes are communicated with each other to form a U-shaped communicated drill hole;
and 5: penetrating a diamond rope along the U-shaped communication drill hole, and leading out the diamond rope from two ends of the U-shaped communication through hole; a rope saw cutting machine is adopted in a drilling field to drive a diamond rope to rotate to cut a top plate rock stratum and/or a bottom plate rock stratum, a nearly horizontal blind groove with a certain thickness is formed by cutting through a rope saw, and a mud protective wall is adopted in the blind groove;
step 6: arranging a grouting pipe along the bottom of the blind groove, injecting cement slurry, and replacing the retaining wall slurry until the top plate and/or the bottom plate blind groove is completely filled with the cement slurry; after the cement grout is solidified, forming a grouting water-resisting layer of a cement filling entity with certain strength and certain thickness on the top plate and/or the bottom plate of the coal seam to be mined;
and 7: and if the range of the aquifer is large, repeating the steps 3-6, drilling the U-shaped communicated drill holes and cutting the rock stratum by a rope saw cutting machine for multiple times by adopting a directional drilling machine at every 20 m section on the horizontal plane, and simultaneously performing replacement grouting to enable the grouting water-resisting layer to span the whole range of the aquifer.
Further, in the step 5, after the diamond rope is led out from the two ends of the U-shaped connecting through hole, the diamond rope is wound on a driving wheel and an auxiliary wheel of the rope saw cutting machine, a rope saw electric motor is started, the driving wheel is adjusted through a control panel, the tensile tension of the rope is improved, the diamond rope is ensured to be properly tightened, and circulating cooling water is supplied; and starting the other electric motor to drive the driving wheel to drive the diamond rope to rotate and cut the deep rock stratum.
Further, in the step 5, the wall protecting medium formed by cutting with the rope saw is replaced by the water medium.
Further, in the step 6, the injected cement slurry is replaced by concrete slurry mixed with water glass quick setting medium.
The invention drills a U-shaped communicating drill hole for multiple times through the directional drilling machine and cuts a rock stratum by adopting a rope saw cutting machine, and simultaneously carries out replacement grouting to form a mechanical digging groove grouting water-stop layer which can completely meet the design requirement, can effectively span the whole range of a water-stop layer, and cuts off a seepage channel between the water-stop layer and a coal seam to be exploited.
The above description is only exemplary of the present invention and should not be taken as limiting the invention, as any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (4)

1. A method for preventing and controlling water in an underground coal mine by adopting a mechanical digging groove construction grouting water-resisting layer is characterized by comprising the following steps:
step 1: constructing an auxiliary roadway before the coal seam to be mined is mined, so that the auxiliary roadway is close to a water-bearing stratum and a safe water-resisting distance is kept;
step 2: constructing a drilling site in the auxiliary roadway at a horizontal position which is 10 meters away from the horizontal line of the coal seam roof and/or the bottom plate aquifer, and arranging a directional drilling machine in the drilling site;
and step 3: adopting a directional drilling machine, and constructing two approximately horizontal drill holes in a top plate (or a bottom plate) rock stratum of a coal seam along the horizontal direction of a drilling field, wherein the depression angle of the drill holes is within a range of 5 degrees, and the depth of the drill holes is based on the range exceeding a water-bearing stratum;
and 4, step 4: by utilizing the directional drilling function of a directional drilling machine, horizontally turning and drilling from the bottom of a certain drill hole to the bottom of another drill hole in the same horizontal plane, so that the two drill holes are communicated with each other to form a U-shaped communicated drill hole;
and 5: penetrating a diamond rope along the U-shaped communication drill hole, and leading out the diamond rope from two ends of the U-shaped communication through hole; a rope saw cutting machine is adopted in a drilling field to drive a diamond rope to rotate to cut a top plate rock stratum and/or a bottom plate rock stratum, a nearly horizontal blind groove with a certain thickness is formed by cutting through a rope saw, and a mud protective wall is adopted in the blind groove;
step 6: arranging a grouting pipe along the bottom of the blind groove, injecting cement slurry, and replacing the retaining wall slurry until the top plate and/or the bottom plate blind groove is completely filled with the cement slurry; after the cement grout is solidified, forming a grouting water-resisting layer of a cement filling entity with certain strength and certain thickness on the top plate and/or the bottom plate of the coal seam to be mined;
and 7: and if the range of the aquifer is large, repeating the steps 3-6, drilling the U-shaped communicated drill holes and cutting the rock stratum by a rope saw cutting machine for multiple times by adopting a directional drilling machine at every 20 m section on the horizontal plane, and simultaneously performing replacement grouting to enable the grouting water-resisting layer to span the whole range of the aquifer.
2. The method for preventing and treating water in a coal mine underground by grouting a water-resisting layer through mechanical groove digging construction according to claim 1, wherein in the step 5, after the diamond rope is led out from two ends of the U-shaped connecting through hole, the diamond rope is wound on a driving wheel and an auxiliary wheel of a rope saw cutting machine, a rope saw electric motor is started, the driving wheel is adjusted through a control panel, the tensile tension of the rope is improved, the diamond rope is ensured to be properly tightened, and circulating cooling water is supplied; and starting the other electric motor to drive the driving wheel to drive the diamond rope to rotate and cut the deep rock stratum.
3. The method for preventing and treating water in a coal mine underground by grouting a water-resisting layer through mechanical groove digging construction according to claim 1, wherein in the step 5, the wall protecting medium formed by cutting through a rope saw is replaced by the water medium.
4. The method for preventing and treating water in an underground coal mine by grouting a water-resisting layer through mechanical groove digging construction according to claim 1, wherein in the step 6, the injected cement grout is replaced by concrete grout mixed with a water glass quick setting medium.
CN202011430253.4A 2020-12-09 2020-12-09 Underground coal mine water prevention and control method for grouting water-resisting layer by adopting mechanical digging groove construction Pending CN112761677A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202011430253.4A CN112761677A (en) 2020-12-09 2020-12-09 Underground coal mine water prevention and control method for grouting water-resisting layer by adopting mechanical digging groove construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202011430253.4A CN112761677A (en) 2020-12-09 2020-12-09 Underground coal mine water prevention and control method for grouting water-resisting layer by adopting mechanical digging groove construction

Publications (1)

Publication Number Publication Date
CN112761677A true CN112761677A (en) 2021-05-07

Family

ID=75693528

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202011430253.4A Pending CN112761677A (en) 2020-12-09 2020-12-09 Underground coal mine water prevention and control method for grouting water-resisting layer by adopting mechanical digging groove construction

Country Status (1)

Country Link
CN (1) CN112761677A (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101050709A (en) * 2006-04-03 2007-10-10 郭国政 High water pressure releasing and blocking mining method for mining area
CN101608552A (en) * 2008-06-18 2009-12-23 郭国政 The seat earth aquifer reinforces and protects the method for water barrier in reinforcing process
CN102134967A (en) * 2011-01-25 2011-07-27 煤炭科学研究总院西安研究院 Construction method of consolidating horizontal directional drilling hole by grouting coal seam baseboard
CN103032083A (en) * 2012-12-21 2013-04-10 中南大学 Reconstruction method for water-proof shell
CN107044289A (en) * 2017-06-22 2017-08-15 中国矿业大学 A kind of water damage prevention and controls of bored grouting closure overlying strata water producing fractures main channel
CN108374662A (en) * 2018-01-31 2018-08-07 鄂尔多斯市国源矿业开发有限责任公司 The conduction method of artesian water tomography is crossed in a kind of tunnel
CN108757043A (en) * 2018-08-02 2018-11-06 安徽理工大学 One kind is for the anti-method of harnessing the river of getting working face
CN108894727A (en) * 2018-07-05 2018-11-27 中国矿业大学 The water-retaining method of ground level directional drilling slip casting closure overlying strata water producing fractures main channel
CN109029832A (en) * 2018-06-29 2018-12-18 中国矿业大学 A method of aquifer water pressure is adopted based on the monitoring of incorporated light fiber sensor
CN111927480A (en) * 2020-08-11 2020-11-13 中国矿业大学 Construction method of underground continuous blind slot grouting curtain for water-based rock rich in pores

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101050709A (en) * 2006-04-03 2007-10-10 郭国政 High water pressure releasing and blocking mining method for mining area
CN101608552A (en) * 2008-06-18 2009-12-23 郭国政 The seat earth aquifer reinforces and protects the method for water barrier in reinforcing process
CN102134967A (en) * 2011-01-25 2011-07-27 煤炭科学研究总院西安研究院 Construction method of consolidating horizontal directional drilling hole by grouting coal seam baseboard
CN103032083A (en) * 2012-12-21 2013-04-10 中南大学 Reconstruction method for water-proof shell
CN107044289A (en) * 2017-06-22 2017-08-15 中国矿业大学 A kind of water damage prevention and controls of bored grouting closure overlying strata water producing fractures main channel
CN108374662A (en) * 2018-01-31 2018-08-07 鄂尔多斯市国源矿业开发有限责任公司 The conduction method of artesian water tomography is crossed in a kind of tunnel
CN109029832A (en) * 2018-06-29 2018-12-18 中国矿业大学 A method of aquifer water pressure is adopted based on the monitoring of incorporated light fiber sensor
CN108894727A (en) * 2018-07-05 2018-11-27 中国矿业大学 The water-retaining method of ground level directional drilling slip casting closure overlying strata water producing fractures main channel
CN108757043A (en) * 2018-08-02 2018-11-06 安徽理工大学 One kind is for the anti-method of harnessing the river of getting working face
CN111927480A (en) * 2020-08-11 2020-11-13 中国矿业大学 Construction method of underground continuous blind slot grouting curtain for water-based rock rich in pores

Similar Documents

Publication Publication Date Title
CN110761814B (en) Roof water control method based on presplitting and grouting modification
CN102493822B (en) Method for performing curtain grouting construction on tunnel by water rich fault influence zone
CN105041325B (en) Construction method of high-tension water-rich extra-large-section weak breccia tunnel
CN102787846B (en) Upper-blocking and lower-draining construction method for undersea tunnel fault fracture zone
CN110242301A (en) A kind of modified water-protection coal-mining method of two step slip casting of top plate water-bearing layer
CN106223998B (en) Rock protective layer face gas administering method under a kind of closely tight roof
CN204253054U (en) Mountain tunnel stake arch cap excavation method comprehensive support structure
CN101781993A (en) Shield driving construction method for bearing water-rich soil layer
CN108343418B (en) Method for controlling mining influence range from surface directional hydraulic fracturing pre-cracked bedrock
CN106050185B (en) A kind of coal mining bottom plate meets the control method that tomography produces water inrush channel
CN112502663B (en) Curtain grouting method based on directional hydraulic mechanical splitting technology
CN111927480B (en) Construction method of underground continuous blind slot grouting curtain for water-based rock rich in pores
CN103498644A (en) Outburst prevention method in rock cross-cut coal uncovering and gas outburst coal seam double-curtain grouting
CN107152309A (en) A kind of coal seam is the high water level and high-speed drainage water damage prevention and controls of Main aquifer
CN107313743B (en) Method for repairing weak zone of coal seam floor water-resisting layer by utilizing coal seam gas well
CN112761677A (en) Underground coal mine water prevention and control method for grouting water-resisting layer by adopting mechanical digging groove construction
CN114352317B (en) Subway tunnel non-precipitation construction method based on sand layer or sand pebble layer
CN106948860B (en) The method for cooperateing with progressive draining coal seam gas with directional drilling based on U-shaped well
CN202131603U (en) Seepage interception structure applied to weak interbed or fracture zone in batholite
CN115419384A (en) Aquifer dynamic grouting, interception and water plugging method for mining overburden rock complete breakage
SU1352067A1 (en) Method of isolating vertical mine workings from subsoil water inflow
CN114278372A (en) Guiding arrangement method for underground directional drilling area of ultra-thick water-rich layer
Wang et al. Study on Technology of Surface Pre-grouting for Vertical Shaft in Broken and Water-rich Granite Strata of Gaoligong Mountain Tunnel of Dali-Ruili Railway
CN108798589B (en) Modification method of aquifer
CN110952951A (en) High-air-tightness hole sealing method for short-distance pressure-relief coal seam crossing gas extraction drill hole

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20210507