CN112600373B - 一种转子吊装监测方法 - Google Patents
一种转子吊装监测方法 Download PDFInfo
- Publication number
- CN112600373B CN112600373B CN202011459140.7A CN202011459140A CN112600373B CN 112600373 B CN112600373 B CN 112600373B CN 202011459140 A CN202011459140 A CN 202011459140A CN 112600373 B CN112600373 B CN 112600373B
- Authority
- CN
- China
- Prior art keywords
- rotor
- point
- stator
- distance
- hoisting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02K—DYNAMO-ELECTRIC MACHINES
- H02K15/00—Methods or apparatus specially adapted for manufacturing, assembling, maintaining or repairing of dynamo-electric machines
- H02K15/16—Centering rotors within the stator; Balancing rotors
Abstract
Description
技术领域
本发明属于监控设备技术领域,尤其是涉及一种转子吊装监测方法。
背景技术
在安装水轮发电机转子的过程中,如何精确的将其安装于定子中央是一个关键性问题,由于转子的体积比较大,且重量过重,所以安装过程存在一定难度。在安装过程中,起重员通过插板人员的实时反馈进行吊装和调整。现有的方法在吊装过程中容易产生侧向压力,使定子受力。在转子进入定子后,若一侧发生卡条,此时需要调整转子位置,在很小的空间移动桥机,将不可避免移位过多后导致转子挤压木板,从而对定子产生侧向推力,可能引起定子移位或变形。同时,因安装过程中需要经常调整转子中心,吊装时间较长,起重设备长时间满负荷运行,容易造成安全隐患,缩短起重设备的使用寿命。
发明内容
本发明的目的是提供一种转子吊装监测方法,采用不同方向的传感器对转子吊装进行定位矫正,可以精确判断转子的吊装位置,减小转子安装过程难度,提高转子吊装质量。
本发明采用如下技术方案:
一种转子吊装监测方法,所述方法为在转子下方选6个互相构成60度的六个探测点,在所述6个点上方垂直向上相等距离处再安装6个探测点,转子下方的6个探测点上各安装3个测量不同方向的红外线距离探测器,分别测量转子与定子距离x,转子与油管距离y,转子与地面距离h;转子上方探测点安装6个红外线距离探测器,测量转子与定子距离x*;
设上方6个红外线探测器测量转子与定子距离为x* 1,x* 2,x* 3,x* 4,x* 5,x* 6,下方6个红外线探测器测量转子与定子距离为x1,x2,x3,x4,x5,x6;下方6个红外线探测器测量向内方向与油管距离为y1,y2,y3,y4,y5,y6,下方6个红外线探测器测量转子与地面距离为h1,h2,h3,h4,h5,h6;
步骤一:吊装前,测量定子半径和转子半径,定子半径设为F,转子半径设为A,转子上方探测点进入定子的时刻记为t0=0,在转子下方6个互相构成60度的探测点中任选一点为起始点,记为点1,按逆时针方向依次将与起始点相隔60度的点记为点2,与起始点相隔120度的点记为点3;
当Δx1=Δx2=Δx3=0后,调整吊绳下降速度恒为v;
步骤二:在吊装的t1时刻,设Δh=ht0-ht1,当时,若Δh1-v(t1-t0)>0,Δh2-v(t1-t0)>0,Δh3-v(t1-t0)>0,则步骤一中点1、点2、点3向上调整距离分别为Δh1-v(t1-t0),Δh2-v(t1-t0),Δh3-v(t1-t0),若Δh1-v(t1-t0)<0,Δh2-v(t1-t0)<0,Δh3-v(t1-t0)<0,则点1、点2、点3向下调整距离分别为|Δh1-v(t1-t0)|,|Δh2-v(t1-t0)|,|Δh3-v(t1-t0)|;
步骤三:当转子在定子内部为水平状态时,以转子中心为原点,建立直角坐标系;根据测距结果,利用矢量相加法,外圈为定子,内圈为转子,测量点1、点2、点3、点4、点5、点6到转子中心的方向及距离,记为dx1、dx2、dx3、dx4、dx5、dx6;
计算dx=dx1+dx2+dx3+dx4+dx5+dx6,dx为操作人员应该移动转子的方向及移动距离;
步骤四:当吊装完成吊装后进行检验;
若y1=y2=y3=y4=y5=y6=A,x1=x2=x3=x4=x5=x6=F-A,Δh1=Δh2=Δh3=Δh4=Δh5=Δh6,则吊装成功;
进一步地,所述在转子下方选6个探测点,在所述6个探测点上方垂直向上相等10cm处再选取6个探测点;
本发明的优点与效果为:
通过本发明的转子吊装监测方法,进行转子的安装和矫正,可确保转子的准确安装。
附图说明
图1为转子下方互相构成60度的6个探测点分布图;
图2为红外线探测器的分布图。
具体实施方式
下面结合附图及实施例对本发明做进一步解释。
在转子下方选6个互相构成60度的六个探测点,在所述6个点上方垂直向上相等距离处再安装6个探测点,转子下方的6个探测点上各安装3个测量不同方向的红外线距离探测器,分别测量转子与定子距离x,转子与油管距离y,转子与地面距离h;转子上方探测点安装6个红外线距离探测器,测量转子与定子距离x*;通过本发明方法,进行转子的安装和矫正,以确保转子的准确安装;
设上方6个红外线探测器测量转子与定子距离为x* 1,x* 2,x* 3,x* 4,x* 5,x* 6,下方6个红外线探测器测量转子与定子距离为x1,x2,x3,x4,x5,x6;下方6个红外线探测器测量向内方向与油管距离为y1,y2,y3,y4,y5,y6,下方6个红外线探测器测量转子与地面距离为h1,h2,h3,h4,h5,h6;
步骤一:吊装前,测量定子半径和转子半径,定子半径设为F,转子半径设为A,转子上方探测点进入定子的时刻记为t0=0,观察x* 1,x* 2,x* 3,x* 4,x* 5,x* 6与x1,x2,x3,x4,x5,x6数据变化;
在转子下方6个互相构成60度的探测点中任选一点记为点1,按逆时针方向依次将其余测量点标记为点2、点3、点4、点5、点6;
当Δx1=Δx2=Δx3=0后,调整吊绳下降速度恒为v;
步骤二:在吊装的t1时刻,设Δh=ht0-ht1,当时,若Δh1-v(t1-t0)>0,Δh2-v(t1-t0)>0,Δh3-v(t1-t0)>0,则步骤一中点1、点2、点3向上调整距离分别为Δh1-v(t1-t0),Δh2-v(t1-t0),Δh3-v(t1-t0),若Δh1-v(t1-t0)<0,Δh2-v(t1-t0)<0,Δh3-v(t1-t0)<0,则点1、点2、点3向下调整距离分别为|Δh1-v(t1-t0)|,|Δh2-v(t1-t0)|,|Δh3-v(t1-t0)|;
式中,v为吊绳下降速度,t1为当前吊装时刻,t0为吊装起始时刻,Δh1、Δh2、Δh3分别为t1时刻点1、点2、点3下降的实际距离;
步骤三:当转子在定子内部为水平状态时,以转子中心为原点,建立直角坐标系;根据测距结果,利用矢量相加法,外圈为定子,内圈为转子,测量点1、点2、点3、点4、点5、点6到转子中心的方向及距离,记为dx1、dx2、dx3、dx4、dx5、dx6;
计算dx=dx1+dx2+dx3+dx4+dx5+dx6,dx为操作人员应该移动转子的方向及移动距离;
步骤四:当吊装完成吊装后进行检验;
若y1=y2=y3=y4=y5=y6=A,x1=x2=x3=x4=x5=x6=F-A,Δh1=Δh2=Δh3=Δh4=Δh5=Δh6,则吊装成功。
Claims (2)
1.一种转子吊装监测方法,其特征在于:所述方法为在转子下方选6个互相构成60度的六个探测点,在6个点上方垂直向上相等距离处再安装6个探测点,转子下方的6个探测点上各安装3个测量不同方向的红外线距离探测器,分别测量转子与定子距离x,转子与油管距离y,转子与地面距离h;转子上方探测点安装6个红外线距离探测器,测量转子与定子距离x*;设上方6个红外线探测器测量转子与定子距离为x* 1,x* 2,x* 3,x* 4,x* 5,x* 6,下方6个红外线探测器测量转子与定子距离为x1,x2,x3,x4,x5,x6;下方6个红外线探测器测量向内方向与油管距离为y1,y2,y3,y4,y5,y6,下方6个红外线探测器测量转子与地面距离为h1,h2,h3,h4,h5,h6;
步骤一:吊装前,测量定子半径和转子半径,定子半径设为F,转子半径设为A,转子上方探测点进入定子的时刻记为t0=0,在转子下方6个互相构成60度的探测点中任选一点为起始点,记为点1,按逆时针方向依次将与起始点相隔60度的点记为点2,与起始点相隔120度的点记为点3;
当Δx1=Δx2=Δx3=0后,调整吊绳下降速度恒为v,
步骤二:在吊装的t1时刻,设Δh=ht0-ht1,当时,若Δh1-v(t1-t0)>0,Δh2-v(t1-t0)>0,Δh3-v(t1-t0)>0,则步骤一中点1、点2、点3向上调整距离分别为Δh1-v(t1-t0),Δh2-v(t1-t0),Δh3-v(t1-t0),若Δh1-v(t1-t0)<0,Δh2-v(t1-t0)<0,Δh3-v(t1-t0)<0,则点1、点2、点3向下调整距离分别为|Δh1-v(t1-t0)|,|Δh2-v(t1-t0)|,|Δh3-v(t1-t0)|,
式中,v为吊绳下降速度,t1为当前吊装时刻,t0为吊装起始时刻,Δh1、Δh2、Δh3分别为t1时刻点1、点2、点3下降的实际距离,
步骤三:当转子在定子内部为水平状态时,以转子中心为原点,建立直角坐标系;根据测距结果,利用矢量相加法,外圈为定子,内圈为转子,测量点1、点2、点3、点4、点5、点6到转子中心的方向及距离记为dx1、dx2、dx3、dx4、dx5、dx6;
计算dx=dx1+dx2+dx3+dx4+dx5+dx6,dx为操作人员应该移动转子的方向及移动距离;
步骤四:当吊装完成吊装后进行检验;
若y1=y2=y3=y4=y5=y6=A,x1=x2=x3=x4=x5=x6=F-A,Δh1=Δh2=Δh3=Δh4=Δh5=Δh6,则吊装成功。
2.根据权利要求1所述的一种转子吊装监测方法,其特征在于:所述在转子下方选6个探测点,在所述6个探测点上方垂直向上相等10cm处再选取6个探测点。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011459140.7A CN112600373B (zh) | 2020-12-11 | 2020-12-11 | 一种转子吊装监测方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202011459140.7A CN112600373B (zh) | 2020-12-11 | 2020-12-11 | 一种转子吊装监测方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN112600373A CN112600373A (zh) | 2021-04-02 |
CN112600373B true CN112600373B (zh) | 2021-12-24 |
Family
ID=75192836
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202011459140.7A Active CN112600373B (zh) | 2020-12-11 | 2020-12-11 | 一种转子吊装监测方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN112600373B (zh) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113607071B (zh) * | 2021-08-06 | 2022-03-29 | 三峡高科信息技术有限责任公司 | 发电机转子吊装气隙监测与防护装置 |
Family Cites Families (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN203554237U (zh) * | 2013-11-11 | 2014-04-16 | 中国水利水电第七工程局有限公司 | 一种水轮发电机转子吊装定位装置 |
CN103546001B (zh) * | 2013-11-11 | 2016-01-13 | 中国水利水电第七工程局有限公司 | 一种水轮发电机转子吊装定位装置及其定位方法 |
CN103887931B (zh) * | 2014-04-01 | 2016-04-20 | 武汉轻工大学 | 电机数控装配装置及方法 |
CN110526120B (zh) * | 2019-08-01 | 2020-10-20 | 国网浙江省电力有限公司紧水滩水力发电厂 | 立式水轮发电机转子吊装辅助装置及吊装方法 |
CN111121701B (zh) * | 2019-12-05 | 2021-03-23 | 东南大学 | 一种用于发电机抽穿转子安全状态评估的方法 |
CN210741385U (zh) * | 2019-12-11 | 2020-06-12 | 国网东北分部绿源水力发电公司太平湾发电厂 | 转子吊装监测装置 |
-
2020
- 2020-12-11 CN CN202011459140.7A patent/CN112600373B/zh active Active
Also Published As
Publication number | Publication date |
---|---|
CN112600373A (zh) | 2021-04-02 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN101348213B (zh) | 厂房内行车滑触线安装方法 | |
CN112600373B (zh) | 一种转子吊装监测方法 | |
JP2020515483A (ja) | 絶縁型高所作業車及びその絶縁型作業床の自動幅制限方法 | |
CN107628138B (zh) | 一种检测电梯导轨多参数的攀爬机器人 | |
CN113090472B (zh) | 位移传感器、监测塔筒螺栓松动的方法及风力发电机组 | |
CN205352328U (zh) | 电梯导轨直线度在线测量系统 | |
CN112320568A (zh) | 一种用于行车垂直升降的平衡调整机构 | |
WO2016150184A1 (zh) | 海洋油气水下设备重量测量和重心检测方法 | |
CN113587985A (zh) | 一种钢索式巷道围岩收敛监测装置及监测方法 | |
CN107036522B (zh) | 一种中小跨桥梁水上结构竖向位移测量装置和方法 | |
CN216012253U (zh) | 超高烟囱滑模施工用垂直度检测装置 | |
CN110127522A (zh) | 一种用于塔式起重机的无需外部传感器的力矩检测方法 | |
CN108439140B (zh) | 一种改进曳引机结构的电梯平衡性实时监测方法和系统 | |
CN108699792A (zh) | 测量系统、腿部引导件、自升式平台 | |
KR102089730B1 (ko) | 와이어 로프의 결함 위치 감지 장치, 이를 포함하는 크레인, 및 와이어 로프의 결함 위치 감지 방법 | |
CN108545611B (zh) | 在用桥式起重机桥架腹板变形测量及判定方法 | |
CN213141059U (zh) | 一种电梯导轨动态检测装置 | |
CN110243298A (zh) | 一种检测提升机绳槽直径的方法装置 | |
CN216115821U (zh) | 一种用于托载水平基准粱的活动托架组件 | |
CN109183764B (zh) | 自升式平台的弦相位标定方法 | |
CN203772485U (zh) | 一种静平衡仪偏重检测装置 | |
CN220706815U (zh) | 一种工程建设监理质量验收实时测量装置 | |
CN216385459U (zh) | 一种封头平面度检验工装 | |
CN114301242B (zh) | 适用于伸缩臂叉装车专用电机安装的安装方法 | |
CN115600470B (zh) | 输电线路带电回路模拟判断方法、应用及安全预警方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |