CN112095441A - Construction process for connecting assembled reinforced concrete bridge pier column and capping beam - Google Patents

Construction process for connecting assembled reinforced concrete bridge pier column and capping beam Download PDF

Info

Publication number
CN112095441A
CN112095441A CN202010810446.6A CN202010810446A CN112095441A CN 112095441 A CN112095441 A CN 112095441A CN 202010810446 A CN202010810446 A CN 202010810446A CN 112095441 A CN112095441 A CN 112095441A
Authority
CN
China
Prior art keywords
bent cap
pier stud
grouting
connecting hole
concave cavity
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010810446.6A
Other languages
Chinese (zh)
Other versions
CN112095441B (en
Inventor
吴发红
支正东
朱华
赵乙丁
朱广富
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yancheng Institute of Technology
Original Assignee
Yancheng Institute of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yancheng Institute of Technology filed Critical Yancheng Institute of Technology
Priority to CN202010810446.6A priority Critical patent/CN112095441B/en
Publication of CN112095441A publication Critical patent/CN112095441A/en
Application granted granted Critical
Publication of CN112095441B publication Critical patent/CN112095441B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention provides a construction process for connecting an assembled reinforced concrete bridge pier stud with a capping beam, which comprises the following steps: and (3) prefabricating a cover beam with a concave cavity in the connecting hole: placing a mould in the bent cap reinforcement cage to form a connecting hole with a concave cavity after the cast concrete bent cap is cast, wherein the concave cavity radially extends along the circumferential surface of the connecting hole; the mold comprises a hollow sleeve and a rubber cylinder, and a wedge-shaped lug matched with the hollow part of the hollow sleeve is arranged on the whole body of the rubber cylinder; after the bent cap is poured, the rubber cylinder is taken out, so that the concave cavity is formed in the connecting hole of the bent cap; pouring the joint of the integrated bent cap and the pier stud: and hoisting the bent cap to enable a plurality of main ribs of the pier stud extending out of the top surface to be correspondingly inserted into a plurality of connecting holes of the bent cap, and then grouting and pouring in the connecting holes to finish the connection of the bent cap and the pier stud. By adopting the construction process, the bonding performance is better, so that the connection integral performance of the pier stud main reinforcement and the bent cap is better.

Description

Construction process for connecting assembled reinforced concrete bridge pier column and capping beam
Technical Field
The invention relates to the technical field of construction of an assembled RC structure, in particular to a connection construction process of main reinforcements and capping beams of an assembled reinforced concrete bridge pier stud.
Background
The reinforced concrete structure adopts a prefabricated construction mode, so that the site construction labor force can be greatly reduced, the construction speed is improved, the construction period is shortened, and the method has the advantages of easiness in ensuring the component quality, energy conservation, environmental protection and the like, accords with the development direction of building industrialization, and is a construction mode for buildings such as houses, municipal bridges and the like which are widely popularized in China at present.
The connecting technology of the main reinforcement of the prefabricated pier column of the prefabricated reinforced concrete bridge and the prefabricated capping beam is one of key technologies in the construction technology of the prefabricated bridge, and the connecting quality of the main reinforcement of the prefabricated pier column and the prefabricated capping beam directly influences the anti-seismic performance of the structure, so that the connecting technology is the important factor in each technology of the construction mode.
At present, the connection technology of main reinforcements of prefabricated pier columns of prefabricated reinforced concrete bridges and prefabricated bent caps in China mainly adopts grouting corrugated sleeve connection technology, and the technology mainly increases the bonding between the sleeves and the surrounding concrete by small-amplitude concave-convex parts of the peripheries of the corrugated sleeves in the use process, so that the diameter and the length of the sleeves need to be determined by a construction site test (according to the characteristics of the site concrete) to prevent the sleeves and slurry in the sleeves from being integrally pulled out of the bent caps.
Disclosure of Invention
The technical problem to be solved by the invention is to provide a construction process for connecting a main pier stud rib and a cover beam of an assembled reinforced concrete bridge, which has better connection performance, is simple and easy to implement, so that the connection between the main pier stud rib and the cover beam cannot be caused by the situation that the sleeve and slurry in the sleeve are integrally pulled out of the cover beam concrete.
In order to solve the technical problems, the technical scheme of the invention is as follows:
the utility model provides a construction technology that assembled reinforced concrete bridge pier stud is connected with bent cap which characterized in that: the method comprises the following steps:
and (3) prefabricating a cover beam with a concave cavity in the connecting hole: placing a mould in the bent cap reinforcement cage to form a connecting hole with a concave cavity after the cast concrete bent cap is cast, wherein the concave cavity radially extends along the circumferential surface of the connecting hole; the mold comprises a hollow sleeve and a rubber cylinder, and a wedge-shaped lug matched with the hollow part of the hollow sleeve is arranged on the whole body of the rubber cylinder; after the bent cap is poured, the rubber cylinder is taken out, so that the concave cavity is formed in the connecting hole of the bent cap;
pouring the joint of the integrated bent cap and the pier stud: and hoisting the bent cap to enable a plurality of main ribs of the pier stud extending out of the top surface to be correspondingly inserted into a plurality of connecting holes of the bent cap, and then grouting and pouring in the connecting holes to finish the connection of the bent cap and the pier stud.
And grouting from the grouting guide pipe opening, stopping grouting after slurry flows out of the slurry outlet guide pipe, and then plugging the grouting guide pipe and the slurry outlet guide pipe opening by using a rubber plug to finish the connection work of the cover beam and the pier stud.
When the bent cap is poured, a support is arranged in the rubber cylinder.
The support comprises 1 shaft, 3 supporting plates, a plurality of supporting rods, a plurality of hinges and 1 supporting plate; the supporting plates are parallel to the shaft and are hinged through a plurality of supporting rods, and the bottommost row of supporting rods are arranged at the lower ends of the supporting plates; the supporting plate is fixed at the lower part of the shaft and is tightly attached to the bottom row of supporting rods; the bottom row of support rods and the support plate are provided with corresponding bolt holes.
The supporting plates are parallel to the shaft and hinged through a plurality of supporting rods, and a certain distance is reserved between the 3 supporting plates, so that the 3 supporting plates can be retracted after moving relatively in the axial direction.
The whole special support becomes a geometric invariant system after the supporting plate and the bottommost row of supporting rods of the special support are connected by adopting bolt tightening. In addition, the supporting plate can prevent cement mortar from flowing into the inner cavity of the soft rubber cylinder during concrete pouring.
The invention has the advantages that:
compared with the similar technology, the construction process has the advantages that the manufactured grouting space is zigzag, the grouting material in the zigzag space can be directly bonded with the capping beam concrete, the bonding performance is better, and the sleeve and the whole slurry in the sleeve can not be pulled out of the capping beam concrete, so that the integral connection performance of the pier column main rib and the capping beam is better.
Drawings
FIG. 1 is a schematic view of a hollow sleeve of a soft rubber plug of the present invention.
FIG. 2 is a schematic sectional view of the present invention at 1-1.
Figure 3 is a top view of the dedicated support of the present invention.
Fig. 4 is a bottom view of the inventive customized support.
Fig. 5 is a schematic sectional view 2-2 of the present invention.
Fig. 6 is a schematic view of the pier stud and cap beam connection of the present invention.
In the upper diagram: 1. hollowing out the sleeve; 2. A soft rubber cylinder; 3. a wedge-shaped projection; 4. grouting a conduit; 5. a slurry outlet conduit; 6. a support plate; 7. a support bar; 8. hinging; 9. a support plate; 10. a shaft; 11. a bolt; 12. a capping beam; 13. grouting space; 14. pier column longitudinal steel bars; 15. and (5) pier studs.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Referring to fig. 1-6, the construction process for connecting the main reinforcement and the bent cap of the assembled reinforced concrete bridge pier stud of the invention is used for realizing the connection between the assembled reinforced concrete bridge pier stud 15 and the bent cap 12, wherein the prefabricated pier stud consists of a concrete column body and a plurality of pier stud longitudinal reinforcements 14 poured in the concrete column body, and the upper end parts of the pier stud longitudinal reinforcements 14 extend out of the top surface of the concrete column body; a plurality of grouting spaces 13 corresponding to the longitudinal reinforcements of the pier stud are arranged in the prefabricated capping beam 12. During on-site construction, the parts of the longitudinal steel bars 14 of the pier stud extending out of the top surface of the concrete column body are correspondingly inserted into the grouting spaces 13, then grouting is performed in the grouting spaces 13, and the connection between the prefabricated pier stud and the prefabricated capping beam is completed.
The construction process specifically comprises the following steps:
s1: the soft rubber cylinder 2 is plugged into the hollow sleeve 1, so that the wedge-shaped convex blocks protrude out of the circumferential surface of the hollow sleeve 1. The hollow sleeve 1 is characterized in that the upper opening is closed, and a plurality of regular square holes are formed in the whole body. The soft rubber cylinder 2 is characterized by being provided with a cavity, and wedge-shaped convex blocks 3 matched with square holes on the whole body of the hollow sleeve 1 are arranged on the whole body.
S2: the special support is folded, the special support is plugged into the cavity of the soft rubber cylinder 2 and then is unfolded, so that the support rods 7 at the bottom are tightly attached to the supporting plate 9, and finally the bolts 11 are screwed up for fixing.
S3: binding a cover beam reinforcement cage, and fixing a plurality of the hollow sleeves 1 subjected to the operation in the reinforcement cage according to the designed position.
S4: and (4) supporting the capping beam template, and then pouring capping beam concrete.
S5: after the cap beam concrete is initially set, the bolt 11 is unscrewed, then the special support is pulled downwards, and finally the soft rubber cylinder 2 is pulled downwards.
S6: and (3) transporting the bent cap to a construction site, firstly carrying out base grouting on the top surface of the installed pier stud, then hoisting the bent cap, correspondingly inserting a plurality of main ribs extending out of the top surface of the pier stud into a plurality of hollow sleeves 1 of the bent cap, and carrying out accurate positioning work on the bent cap.
S7: grouting from the opening of the grouting guide pipe 4, stopping grouting after slurry flows out of the slurry outlet guide pipe 5, and then plugging the openings of the grouting guide pipe 4 and the slurry outlet guide pipe 5 by using rubber plugs to finish the connection work of the capping beam and the pier stud.
The special support comprises 1 shaft 10, 3 support plates 6, a plurality of support rods 7, a plurality of hinges 8 and 1 supporting plate 9, wherein the support plates 6 are parallel to the shaft 10 and are connected with each other through the support rods 7 by the hinges 8, and the support rods 7 in the bottommost row are arranged at the lower ends of the support plates 6; the supporting plate 9 is fixed at the lower part of the shaft 10 and is tightly attached to the bottom row of supporting rods 7; the support rods 7 and the support plates 9 in the bottom row are provided with corresponding bolt holes.
Although embodiments of the present invention have been shown and described, it will be appreciated by those skilled in the art that changes, modifications, substitutions and alterations can be made in these embodiments without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (4)

1. The utility model provides a construction technology that assembled reinforced concrete bridge pier stud is connected with bent cap which characterized in that: the method comprises the following steps:
and (3) prefabricating a cover beam with a concave cavity in the connecting hole: placing a mould in the bent cap reinforcement cage to form a connecting hole with a concave cavity after the cast concrete bent cap is cast, wherein the concave cavity radially extends along the circumferential surface of the connecting hole; the mold comprises a hollow sleeve and a rubber cylinder, and a wedge-shaped lug matched with the hollow part of the hollow sleeve is arranged on the whole body of the rubber cylinder; after the bent cap is poured, the rubber cylinder is taken out, so that the concave cavity is formed in the connecting hole of the bent cap;
pouring the joint of the integrated bent cap and the pier stud: and hoisting the bent cap to enable a plurality of main ribs of the pier stud extending out of the top surface to be correspondingly inserted into a plurality of connecting holes of the bent cap, and then grouting and pouring in the connecting holes to finish the connection of the bent cap and the pier stud.
2. The construction process according to claim 1, wherein: grouting is carried out from the opening of the grouting guide pipe (4), grouting is stopped after slurry flows out from the slurry outlet guide pipe (5), then the openings of the grouting guide pipe (4) and the slurry outlet guide pipe (5) are blocked by rubber plugs, and the connection work of the bent cap and the pier stud is completed.
3. The construction process according to claim 1, wherein: when the bent cap is poured, a support is arranged in the rubber cylinder.
4. The construction process according to claim 3, wherein: the support comprises a shaft (10), three support plates (6), a plurality of support rods (7), a plurality of hinges (8) and a supporting plate (9); the supporting plates (6) are parallel to the shaft (10), the supporting plates and the shaft are connected through a plurality of supporting rods (7) by hinges (8), and the supporting rods (7) in the bottommost row are arranged at the lower ends of the supporting plates (6); the supporting plate (9) is fixed at the lower part of the shaft (10) and is tightly attached to the bottom row of supporting rods (7); the support rod (7) and the support plate (9) in the bottom row are provided with corresponding bolt holes.
CN202010810446.6A 2020-08-13 2020-08-13 Construction process for connecting assembled reinforced concrete bridge pier column and capping beam Active CN112095441B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010810446.6A CN112095441B (en) 2020-08-13 2020-08-13 Construction process for connecting assembled reinforced concrete bridge pier column and capping beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010810446.6A CN112095441B (en) 2020-08-13 2020-08-13 Construction process for connecting assembled reinforced concrete bridge pier column and capping beam

Publications (2)

Publication Number Publication Date
CN112095441A true CN112095441A (en) 2020-12-18
CN112095441B CN112095441B (en) 2022-01-28

Family

ID=73754550

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010810446.6A Active CN112095441B (en) 2020-08-13 2020-08-13 Construction process for connecting assembled reinforced concrete bridge pier column and capping beam

Country Status (1)

Country Link
CN (1) CN112095441B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113062203A (en) * 2021-03-01 2021-07-02 中铁大桥局上海工程有限公司 Construction method for splicing bridge prefabricated stand column and prefabricated capping beam

Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05318430A (en) * 1992-05-20 1993-12-03 Dantoo Kk Mold for dry molding of tile having dovetail groove for dry construction method
JP2005028648A (en) * 2003-07-09 2005-02-03 Meidensha Corp Manufacturing method for pressure-molded object of insert main body and manufacturing method for insert main body
JP2007331132A (en) * 2006-06-12 2007-12-27 Yokohama Rubber Co Ltd:The Manufacturing method of tire vulcanizing mold in gypsum casting method, and tire
KR100903417B1 (en) * 2008-10-10 2009-06-18 주식회사 케이피지 A packer structure using an elastic tube
CN202266018U (en) * 2011-10-24 2012-06-06 上海市第二市政工程有限公司 Template sealing structure for grouting of connecting sleeve
CN103276850A (en) * 2013-06-05 2013-09-04 盐城工学院 Prefabricated housing for making reinforced concrete beams and mould thereof.
CN103899044A (en) * 2014-04-10 2014-07-02 东南大学 Full-grouting sleeve embedded with cones
CN204326248U (en) * 2014-09-22 2015-05-13 中国建筑股份有限公司 A kind of steel reinforcement abutting joints with the concavo-convex rib of spirality connects grout sleeve
CN205599982U (en) * 2016-03-15 2016-09-28 盐城工学院 Drilling depth sleeve
CN106541490A (en) * 2016-12-22 2017-03-29 华侨大学 A kind of preparation facilitiess and its using method of prefabricated connecting hole
CN106994739A (en) * 2017-04-16 2017-08-01 北京工业大学 A kind of full grout sleeves of anticorrosive FRP and its practice
CN107447647A (en) * 2017-07-25 2017-12-08 武汉理工大学 Assembled bridge pier and its construction method
CN207077594U (en) * 2017-04-07 2018-03-09 华侨大学 A kind of assembled inverted trapezoidal connecting hole preparation facilities
CN207974374U (en) * 2018-03-08 2018-10-16 中冶建工集团有限公司 The grout sleeve sealing mechanism of assembled architecture
CN209114310U (en) * 2018-11-02 2019-07-16 内蒙古工业大学 A kind of assembled integral Reinforced Concrete Pier Column

Patent Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH05318430A (en) * 1992-05-20 1993-12-03 Dantoo Kk Mold for dry molding of tile having dovetail groove for dry construction method
JP2005028648A (en) * 2003-07-09 2005-02-03 Meidensha Corp Manufacturing method for pressure-molded object of insert main body and manufacturing method for insert main body
JP2007331132A (en) * 2006-06-12 2007-12-27 Yokohama Rubber Co Ltd:The Manufacturing method of tire vulcanizing mold in gypsum casting method, and tire
KR100903417B1 (en) * 2008-10-10 2009-06-18 주식회사 케이피지 A packer structure using an elastic tube
CN202266018U (en) * 2011-10-24 2012-06-06 上海市第二市政工程有限公司 Template sealing structure for grouting of connecting sleeve
CN103276850A (en) * 2013-06-05 2013-09-04 盐城工学院 Prefabricated housing for making reinforced concrete beams and mould thereof.
CN103899044A (en) * 2014-04-10 2014-07-02 东南大学 Full-grouting sleeve embedded with cones
CN204326248U (en) * 2014-09-22 2015-05-13 中国建筑股份有限公司 A kind of steel reinforcement abutting joints with the concavo-convex rib of spirality connects grout sleeve
CN205599982U (en) * 2016-03-15 2016-09-28 盐城工学院 Drilling depth sleeve
CN106541490A (en) * 2016-12-22 2017-03-29 华侨大学 A kind of preparation facilitiess and its using method of prefabricated connecting hole
CN207077594U (en) * 2017-04-07 2018-03-09 华侨大学 A kind of assembled inverted trapezoidal connecting hole preparation facilities
CN106994739A (en) * 2017-04-16 2017-08-01 北京工业大学 A kind of full grout sleeves of anticorrosive FRP and its practice
CN107447647A (en) * 2017-07-25 2017-12-08 武汉理工大学 Assembled bridge pier and its construction method
CN207974374U (en) * 2018-03-08 2018-10-16 中冶建工集团有限公司 The grout sleeve sealing mechanism of assembled architecture
CN209114310U (en) * 2018-11-02 2019-07-16 内蒙古工业大学 A kind of assembled integral Reinforced Concrete Pier Column

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
钱冠龙: "钢筋连接用灌浆套筒与应用", 《混凝土世界》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113062203A (en) * 2021-03-01 2021-07-02 中铁大桥局上海工程有限公司 Construction method for splicing bridge prefabricated stand column and prefabricated capping beam

Also Published As

Publication number Publication date
CN112095441B (en) 2022-01-28

Similar Documents

Publication Publication Date Title
CN109252727B (en) Shock insulation layer rubber support, column, beam and plate system integrated assembly node and method
CN110130580B (en) Steel pipe constraint type precast concrete column connecting structure and construction method
CN105780935A (en) Prefabricated assembling type steel pipe restrained energy-dissipation connection node and construction method
CN109267472B (en) Prefabricated spliced pile foundation pier and construction method thereof
CN109837831A (en) A kind of centrifugation prefabricated assembled concrete bridge pier and construction method
CN109457599B (en) Splicing structure of hollow pier and bearing platform and construction method
CN106284655A (en) Precast concrete beam stud connects node and method of attachment in succession
KR100862005B1 (en) Manufacturing method of segmental internally confined hollow concrete filled tube
CN111305051A (en) Pile type pier assembly structure and construction method
CN105970803B (en) The shearing resistance energy-dissipating device and construction method of assembled bridge pier
CN112095441B (en) Construction process for connecting assembled reinforced concrete bridge pier column and capping beam
CN205662838U (en) Prestressing force joint construction of pier is assembled to prefabricated segment
CN107313507B (en) Construction method for node structure of fabricated concrete frame overhead core column
CN109208823B (en) Quick-assembly built-in steel box type concrete filled steel tube column and production process thereof
CN103911989B (en) A kind of underwater casting base type foundation with retaining wall and construction method thereof
CN211848867U (en) Tooth groove type prefabricated bridge pier and bearing platform connecting structure
CN103147438A (en) Cast-in-place post-tensioning method-based I-shaped support pile and manufacturing method of support pile
CN112921789A (en) Structure structure of self-resetting socket-and-spigot type ECC (error correction code) mixed bridge pier and splicing method thereof
CN111719411A (en) Prefabricated hollow upright column structure and forming method thereof
CN103758207A (en) Semi-prefabricated semi-cast-in-place type frame structure of integrated building and construction method thereof
CN111576196A (en) On-site splicing pouring construction process for prefabricated pier column segment shell and bent cap
CN110653918A (en) Construction method for synchronously pouring large-span corrugated steel inclined web precast beam with toothed block on top and bottom plates by post-tensioning method
CN205975996U (en) Thick liquid anchor lap joint structure and wall body
CN115680116A (en) Assembled frame beam column connecting node and construction method thereof
CN103911990B (en) A kind of underwater casting formula tubing string with retaining wall and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant