CN111719411A - Prefabricated hollow upright column structure and forming method thereof - Google Patents

Prefabricated hollow upright column structure and forming method thereof Download PDF

Info

Publication number
CN111719411A
CN111719411A CN202010520986.0A CN202010520986A CN111719411A CN 111719411 A CN111719411 A CN 111719411A CN 202010520986 A CN202010520986 A CN 202010520986A CN 111719411 A CN111719411 A CN 111719411A
Authority
CN
China
Prior art keywords
upright post
hollow
vertical
reinforcement cage
prefabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010520986.0A
Other languages
Chinese (zh)
Inventor
闫兴非
周良
张涛
甘露
张斌
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Urban Construction Design Research Institute Group Co Ltd
Original Assignee
Shanghai Urban Construction Design Research Institute Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Urban Construction Design Research Institute Group Co Ltd filed Critical Shanghai Urban Construction Design Research Institute Group Co Ltd
Priority to CN202010520986.0A priority Critical patent/CN111719411A/en
Publication of CN111719411A publication Critical patent/CN111719411A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/02Piers; Abutments ; Protecting same against drifting ice
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28BSHAPING CLAY OR OTHER CERAMIC COMPOSITIONS; SHAPING SLAG; SHAPING MIXTURES CONTAINING CEMENTITIOUS MATERIAL, e.g. PLASTER
    • B28B23/00Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects
    • B28B23/02Arrangements specially adapted for the production of shaped articles with elements wholly or partly embedded in the moulding material; Production of reinforced objects wherein the elements are reinforcing members
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2101/00Material constitution of bridges
    • E01D2101/20Concrete, stone or stone-like material
    • E01D2101/24Concrete
    • E01D2101/26Concrete reinforced

Landscapes

  • Engineering & Computer Science (AREA)
  • Manufacturing & Machinery (AREA)
  • Chemical & Material Sciences (AREA)
  • Ceramic Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a prefabricated hollow upright post structure and a forming method thereof, wherein the structure comprises a hollow upright post and a reinforcement cage, the reinforcement cage at least comprises vertical stressed reinforcements and vertical erection reinforcements, a hollow core section of the hollow upright post penetrates through the whole bridge pier, the vertical stressed reinforcements are arranged on the outer side of the hollow upright post, the vertical erection reinforcements are arranged on the inner side of the hollow upright post, and connecting pieces are arranged on the vertical stressed reinforcements; simultaneously placing the reinforcement cage and the positioning plate into the outer template of the upright post; the invention can realize the accurate positioning of the vertically stressed steel bars and the vertically erected steel bars, and can not be displaced greatly in the pouring process in time; the inner template of the upright post can be taken out by adopting a drawing method, so that the inner template of the upright post can be conveniently recycled.

Description

Prefabricated hollow upright column structure and forming method thereof
Technical Field
The invention relates to the technical field of municipal engineering construction, in particular to a prefabricated hollow upright post structure and a forming method thereof.
Background
In the bridge construction, adopt hollow prefabricated pier can alleviate prefabricated construction weight, have better application prospect.
However, when the hollow upright column is prefabricated, the problems that the inner side steel bar is difficult to position and the inner side formwork is difficult to demould are solved, and the special design of the bottom plate positioning steel bar and the inner film structure is usually needed.
The person skilled in the art is dedicated to solving the above technical drawbacks.
Disclosure of Invention
In view of the above defects of the prior art, the invention provides a prefabricated hollow upright column structure and a forming method thereof, and aims to reduce the difficulty of construction of a prefabricated central pier, improve the demolding efficiency of an inner side template, reduce the construction cost of the prefabricated hollow pier and promote the application of the prefabricated hollow pier in the construction of various bridges.
In order to achieve the technical purpose, the invention provides a prefabricated hollow upright post structure, which comprises a hollow upright post and a reinforcement cage; the reinforcement cage at least comprises vertical stressed reinforcements and vertical erection reinforcements; the hollow section of hollow stand runs through whole pier, vertical atress reinforcing bar is arranged in the outside of hollow stand, the inboard of hollow stand is arranged vertical reinforcing bar that erects, be provided with the connecting piece on the vertical atress reinforcing bar.
Preferably, the hollow upright post is of a concrete structure.
Preferably, the top or the bottom of the hollow upright post is a solid section.
Preferably, the connecting piece adopts a sleeve or a corrugated pipe.
The invention also provides a forming method of the prefabricated hollow upright post structure, which comprises the following steps:
the method comprises the following steps: binding vertical stressed steel bars and vertically erecting the steel bars to form a steel bar cage, and fixing the steel bar cage by using a positioning plate;
step two: simultaneously placing the reinforcement cage and the positioning plate into the outer template of the upright post;
step three: installing an upright post inner template in the reinforcement cage;
step four: pouring concrete into the outer column formwork and the inner column formwork to form a prefabricated hollow column;
step five: after the strength of the poured concrete reaches enough strength, the outer template of the upright post is dismantled;
step six: and finally, dismantling the positioning plate and dismantling the inner template of the upright post by a drawing method.
Preferably, the inner template of the upright post adopts a combined structure.
The invention has the beneficial effects that:
due to the structural design, the vertical stressed steel bars and the vertically erected steel bars can be accurately positioned, and the steel bars cannot be displaced greatly in the pouring process in time;
the inner template of the upright post can be taken out by adopting a drawing method, so that the inner template of the upright post can be conveniently recycled.
Drawings
FIG. 1 is a schematic elevational view of the present invention;
FIG. 2 is a schematic sectional elevation view of the present invention;
FIG. 3 is a schematic cross-sectional view of the present invention;
FIG. 4 is a schematic view of a first step in the molding method of the present invention;
FIG. 5 is a schematic view of step two of the molding method of the present invention;
FIG. 6 is a schematic view of step three of the molding method of the present invention;
FIG. 7 is a schematic view of step four of the molding method of the present invention;
FIG. 8 is a schematic view of step five of the molding method of the present invention;
FIG. 9 is a schematic diagram of step six of the molding method of the present invention.
In the figure: the steel bar vertical type steel bar reinforced concrete column comprises a hollow upright column 1, vertical stressed steel bars 2, vertical erected steel bars 3, a steel bar cage 4, a positioning plate 5, an upright column outer formwork 6 and an upright column inner formwork 7.
Detailed Description
The conception, the specific structure and the technical effects of the present invention will be further described with reference to the accompanying drawings to fully understand the objects, the features and the effects of the present invention.
Example (b):
as shown in fig. 1-9, a prefabricated hollow column structure comprises a hollow column 1 and a reinforcement cage 4;
the reinforcement cage 4 at least comprises vertical stressed reinforcements 2 and vertical erection reinforcements 3;
the hollow core section of hollow stand 1 runs through whole pier, and vertical atress reinforcing bar 2 is arranged in the outside of hollow stand 1, and vertical reinforcing bar 3 that erects is arranged to the inboard of hollow stand 1, is provided with the connecting piece on the vertical atress reinforcing bar 2.
Specifically, the hollow upright column 1 is of a concrete structure.
Specifically, the top or the bottom of the hollow upright column 1 is a solid section, and the upright column inner template 7 can be taken out by adopting a drawing method as long as both ends are not sealed.
Specifically, the connecting piece adopts a sleeve or a corrugated pipe.
Specifically, vertical atress reinforcing bar 2 and vertical reinforcing bar 3 of erectting all need accurate location, ensure that hollow column 1 assembles precision and strict control concrete protective layer thickness.
A forming method of a prefabricated hollow upright post structure comprises the following steps:
the method comprises the following steps: binding the vertical stressed steel bars 2 and the vertical erection steel bars 3 to form a steel bar cage 4, and fixing the steel bar cage 4 by using a positioning plate 5;
step two: simultaneously placing the reinforcement cage 4 and the positioning plate 5 into the upright post outer template 6;
step three: an upright post inner template 7 is arranged in the reinforcement cage 4;
step four: concrete is poured into the upright post outer formwork 6 and the upright post inner formwork 7 to form a prefabricated hollow upright post 1;
step five: after the strength of the poured concrete reaches enough strength, the outer formwork 6 of the upright post is dismantled, and the prefabricated hollow upright post 1 is laid down;
step six: and finally, removing the positioning plate 5 and removing the inner template 7 of the upright post by a drawing method.
Specifically, the column inner formworks 7 adopt a combined structure, and the column inner formworks 7 can be disassembled into small blocks one by one.
Specifically, the on-site drawing equipment is strong enough, or the hollow upright column 1 is not high, and the upright column inner formwork 7 can be vertically drawn out without laying down the hollow upright column 1 during implementation.
The principle of the invention is as follows:
fixing the reinforcement cage 4 by using the positioning plate 5, and keeping the reinforcement cage 4 stable in the whole manufacturing process of the prefabricated hollow upright post 1; when the inner column formwork 7 is detached, the prefabricated hollow column 1 is laid down, so that the resistance between the inner column formwork 7 and the hollow column 1 can be overcome conveniently by a drawing method, and the inner column formwork 7 can be taken out.
The foregoing detailed description of the preferred embodiments of the invention has been presented. It should be understood that numerous modifications and variations could be devised by those skilled in the art in light of the present teachings without departing from the inventive concepts. Therefore, the technical solutions available to those skilled in the art through logic analysis, reasoning and limited experiments based on the prior art according to the concept of the present invention should be within the scope of protection defined by the claims.

Claims (6)

1. The utility model provides a prefabricated hollow column structure which characterized in that: comprises a hollow upright post and a reinforcement cage;
the reinforcement cage at least comprises vertical stressed reinforcements and vertical erection reinforcements;
the hollow section of hollow stand runs through whole pier, vertical atress reinforcing bar is arranged in the outside of hollow stand, the inboard of hollow stand is arranged vertical reinforcing bar that erects, be provided with the connecting piece on the vertical atress reinforcing bar.
2. The prefabricated hollow column structure of claim 1, wherein: the hollow upright posts are of a concrete structure.
3. The prefabricated hollow column structure of claim 1, wherein: the top or the bottom of the hollow upright post is a solid section.
4. The prefabricated hollow column structure of claim 1, wherein: the connecting piece adopts a sleeve or a corrugated pipe.
5. A forming method of a prefabricated hollow upright column structure is characterized in that: the method comprises the following steps:
the method comprises the following steps: binding vertical stressed steel bars and vertically erecting the steel bars to form a steel bar cage, and fixing the steel bar cage by using a positioning plate;
step two: simultaneously placing the reinforcement cage and the positioning plate into the outer template of the upright post;
step three: installing an upright post inner template in the reinforcement cage;
step four: pouring concrete into the outer column formwork and the inner column formwork to form a prefabricated hollow column;
step five: after the strength of the poured concrete reaches enough strength, the outer template of the upright post is dismantled;
step six: and finally, dismantling the positioning plate and dismantling the inner template of the upright post by a drawing method.
6. The method of forming a prefabricated hollow column structure according to claim 5, wherein: the inner template of the upright post adopts a combined structure.
CN202010520986.0A 2020-06-10 2020-06-10 Prefabricated hollow upright column structure and forming method thereof Pending CN111719411A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010520986.0A CN111719411A (en) 2020-06-10 2020-06-10 Prefabricated hollow upright column structure and forming method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010520986.0A CN111719411A (en) 2020-06-10 2020-06-10 Prefabricated hollow upright column structure and forming method thereof

Publications (1)

Publication Number Publication Date
CN111719411A true CN111719411A (en) 2020-09-29

Family

ID=72566290

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010520986.0A Pending CN111719411A (en) 2020-06-10 2020-06-10 Prefabricated hollow upright column structure and forming method thereof

Country Status (1)

Country Link
CN (1) CN111719411A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113216263A (en) * 2021-04-26 2021-08-06 哈尔滨工业大学(深圳) Active and passive dual-protection seawater sea sand reinforced concrete member and preparation method thereof
CN113954230A (en) * 2021-10-28 2022-01-21 浙江交工集团股份有限公司 Processing method of prefabricated hollow pier

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113216263A (en) * 2021-04-26 2021-08-06 哈尔滨工业大学(深圳) Active and passive dual-protection seawater sea sand reinforced concrete member and preparation method thereof
CN113954230A (en) * 2021-10-28 2022-01-21 浙江交工集团股份有限公司 Processing method of prefabricated hollow pier

Similar Documents

Publication Publication Date Title
CN111734031B (en) Fast-assembling and fast-disassembling formwork system of building multi-ribbed structure and construction process thereof
CN113293694B (en) Turnover formwork frame structure for efficient pier body construction and construction process
CN111719411A (en) Prefabricated hollow upright column structure and forming method thereof
CN211114425U (en) Prefabricated steel pipe concrete column
CN109267585B (en) Assembled prismatic table type foundation and column structure and assembling method
CN105839784B (en) Assembled jacking type construction techniques
CN109972655A (en) A kind of prefabricated piping lane machinery and Combined hydraulic type, which are integrally pacified, tears steel form and installation method open
CN114263275B (en) Construction method for same-layer construction of high-rise assembled steel structure-core tube
CN103911989B (en) A kind of underwater casting base type foundation with retaining wall and construction method thereof
CN112302255A (en) Frame column inverted insertion combined system and construction method
CN109208823B (en) Quick-assembly built-in steel box type concrete filled steel tube column and production process thereof
CN210315253U (en) Novel aquatic tie beam bracket device
CN212270652U (en) Prefabricated hollow upright column structure
CN103911990B (en) A kind of underwater casting formula tubing string with retaining wall and construction method thereof
CN112144412A (en) Construction method of prefabricated assembled intercolumnar tie beam
CN209082555U (en) A kind of prefabricated piping lane machinery and Combined hydraulic type, which are integrally pacified, tears steel form open
CN112095441B (en) Construction process for connecting assembled reinforced concrete bridge pier column and capping beam
CN211873406U (en) Precast concrete hollow wall structure
CN210658451U (en) Open cut method composite assembly formula underground structure
CN212025899U (en) Concrete pipe and pier structure
CN108755700B (en) Installation method of curved surface superposed ring beam device for supporting underground enclosure wall
CN113738157A (en) Temporary supports on two sides of post-cast strip of building and method for constructing constructional column by using temporary supports
CN210552011U (en) Take precast stair mould of concrete maintenance function
CN208294062U (en) A kind of concrete wall template and support combinations structure
CN220565258U (en) Adjustable rim of a cup basis template

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination