CN111425250A - Double-layer pressure-reducing water-proof and drainage system for karst water-rich tunnel and construction method of double-layer pressure-reducing water-proof and drainage system - Google Patents

Double-layer pressure-reducing water-proof and drainage system for karst water-rich tunnel and construction method of double-layer pressure-reducing water-proof and drainage system Download PDF

Info

Publication number
CN111425250A
CN111425250A CN202010326020.3A CN202010326020A CN111425250A CN 111425250 A CN111425250 A CN 111425250A CN 202010326020 A CN202010326020 A CN 202010326020A CN 111425250 A CN111425250 A CN 111425250A
Authority
CN
China
Prior art keywords
drainage
tunnel
layer
pipes
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010326020.3A
Other languages
Chinese (zh)
Other versions
CN111425250B (en
Inventor
王华牢
张鹏
田世宽
万飞
王占强
李唐军
胡波
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Tech University
Research Institute of Highway Ministry of Transport
Fourth Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Original Assignee
Nanjing Tech University
Research Institute of Highway Ministry of Transport
Fourth Engineering Co Ltd of CCCC First Highway Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Tech University, Research Institute of Highway Ministry of Transport, Fourth Engineering Co Ltd of CCCC First Highway Engineering Co Ltd filed Critical Nanjing Tech University
Priority to CN202010326020.3A priority Critical patent/CN111425250B/en
Publication of CN111425250A publication Critical patent/CN111425250A/en
Application granted granted Critical
Publication of CN111425250B publication Critical patent/CN111425250B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

本发明提供了一种岩溶富水隧道双层减压防排水系统及其施工方法,该系统设置在隧道初支与二衬之间,包括外侧排水层、减压层、内侧排水层、排水道。其中,外侧排水层包括外侧纵向排水盲管、外侧环向排水盲管、透水土工布;减压层包括三维双向土工格室、喷射式多孔轻骨料透水混凝土和内外排水盲管的垂直连接管;内侧排水层包括内侧纵向排水盲管、内侧环向排水盲管、施工缝止水条和透水土工布;排水道采用分布式集束排水管来扩大传统排水管通道。本发明旨在通过扩大储水容量、降低水头压力、提高排水效率来解决岩溶富水隧道在雨季中的高水压大流量防排水需求。

Figure 202010326020

The invention provides a double-layer decompression, prevention and drainage system for a karst water-rich tunnel and a construction method thereof. The system is arranged between the primary branch of the tunnel and the second lining, and includes an outer drainage layer, a decompression layer, an inner drainage layer and a drainage channel. . Among them, the outer drainage layer includes outer longitudinal drainage blind pipes, outer circumferential drainage blind pipes, and permeable geotextiles; the decompression layer includes three-dimensional two-way geocells, sprayed porous lightweight aggregate permeable concrete and vertical connection pipes of the inner and outer drainage blind pipes The inner drainage layer includes inner longitudinal drainage blind pipe, inner circumferential drainage blind pipe, construction joint water stop strip and permeable geotextile; the drainage channel adopts distributed cluster drainage pipe to expand the traditional drainage pipe channel. The invention aims to solve the high water pressure and large flow waterproofing and drainage requirements of the karst water-rich tunnel in the rainy season by expanding the water storage capacity, reducing the water head pressure and improving the drainage efficiency.

Figure 202010326020

Description

一种岩溶富水隧道双层减压防排水系统及其施工方法A double-layer decompression and drainage system for karst water-rich tunnel and its construction method

技术领域technical field

本发明涉及一种岩溶富水地层隧道防排水结构及其施工方法。属于隧道设计与施工领域。The invention relates to a waterproof and drainage structure for a tunnel in a karst water-rich stratum and a construction method thereof. It belongs to the field of tunnel design and construction.

背景技术Background technique

渗漏水是运营隧道最常见的病害,隧道渗流水不但加速隧道结构老化,缩短隧道结构的服役寿命,还增加了隧道运营维护成本,并威胁隧道的行车安全。《公路隧道设计规范》中规定:“隧道采用复合式衬砌时,在初期支护和二次衬砌之间应设置防水板及无纺布,防水板应采用易于焊接的防水卷材,厚度不小于1.0mm;沿衬砌背后环向应设置导水盲管,其纵向间距不大于20m”。隧道传统排水系统控制排水量大小是通过盲管与排水管来控制的,其施作方式只能保障常规地下水位赋存区的排水流量。Leakage water is the most common disease in operating tunnels. Tunnel seepage water not only accelerates the aging of the tunnel structure, shortens the service life of the tunnel structure, but also increases the cost of tunnel operation and maintenance, and threatens the safety of the tunnel. The "Code for Design of Highway Tunnels" stipulates: "When the tunnel adopts composite lining, waterproof boards and non-woven fabrics should be set between the primary support and the secondary lining, and the waterproof boards should be made of easily welded waterproof membranes with a thickness of not less than 1.0mm; blind pipes should be installed along the back of the lining, with a longitudinal spacing of not more than 20m”. The traditional drainage system of the tunnel controls the drainage volume through blind pipes and drainage pipes, and its implementation method can only guarantee the drainage flow in the conventional groundwater level occurrence area.

我国的岩溶发育地区面积接近国土面积的1/3,岩溶隧道的病害问题尤为严峻。其中岩溶隧道病害的主要来源就是岩溶地下水,一方面是岩溶地下水侵蚀性对隧道衬砌结构与防排水系统的危害,另一方面岩溶地下水与地表水文有着密切的联系,雨季岩溶地下水位暴涨,发生地下水突涌,使得传统防排水结构设计不能满足雨季瞬时大水量的排水需求,甚至衬砌结构承担高外水压力,从而危及隧道结构安全,甚至造成隧道结构开裂产生渗漏水病害,严重影响隧道的安全运营。因此,针对岩溶富水隧道季节性防排水需求差异,研发能够适应不同季节排水量需求的新型防排水系统结构已成为亟待解决的科学与工程问题。The area of karst development area in my country is close to 1/3 of the country's land area, and the disease problem of karst tunnels is particularly serious. Among them, the main source of karst tunnel diseases is karst groundwater. On the one hand, the erosiveness of karst groundwater is harmful to the tunnel lining structure and drainage system. On the other hand, karst groundwater is closely related to surface hydrology. The sudden surge makes the traditional waterproof and drainage structure design unable to meet the drainage demand of the instantaneous large amount of water in the rainy season, and even the lining structure bears high external water pressure, which endangers the safety of the tunnel structure, and even causes the tunnel structure to crack and cause water leakage, which seriously affects the safety of the tunnel. operation. Therefore, in view of the differences in seasonal waterproofing and drainage requirements of karst water-rich tunnels, it has become an urgent scientific and engineering problem to develop a new type of waterproofing and drainage system structure that can adapt to different seasonal drainage requirements.

发明内容SUMMARY OF THE INVENTION

技术问题:本发明的目的是提供一种岩溶富水隧道双层减压防排水系统及其施工方法,新型防排水结构能够满足不同季节不同排水量的需求,能够起到弹性增大排水量,降低隧道外水压力,削弱降雨突发涌水对衬砌结构的影响。Technical problem: The purpose of the present invention is to provide a double-layer decompression and drainage system for karst water-rich tunnels and a construction method thereof. The new waterproof and drainage structure can meet the needs of different drainage volumes in different seasons, and can increase the drainage volume elastically and reduce the amount of water in the tunnel. The external water pressure weakens the impact of sudden rainfall surges on the lining structure.

技术方案:本发明的一种岩溶富水隧道双层减压防排水系统包括在隧道初期支护与二次衬砌之间设置外侧排水层、减压层、内侧排水层和排水道,外侧排水层包括外侧纵向排水盲管、外侧环向排水盲管、透水土工布;减压层包括三维双向土工格室、喷射式多孔轻骨料透水混凝土和内外排水盲管的垂直连接管;内测排水层包括内侧纵向排水盲管、内侧环向排水盲管和透水土工布;排水道是在二次衬砌边墙与底板交接处局部采用分布式集束排水管来扩大传统排水管通道。Technical scheme: a double-layer decompression and drainage system for a karst water-rich tunnel of the present invention includes an outer drainage layer, a decompression layer, an inner drainage layer and a drainage channel between the initial support of the tunnel and the secondary lining, and the outer drainage layer is provided. Including the outer longitudinal drainage blind pipe, the outer circumferential drainage blind pipe, and the permeable geotextile; the decompression layer includes the three-dimensional two-way geocell, the sprayed porous light aggregate permeable concrete and the vertical connecting pipe of the inner and outer drainage blind pipes; the inner measurement drainage layer It includes inner longitudinal drainage blind pipe, inner circumferential drainage blind pipe and permeable geotextile; the drainage channel adopts distributed cluster drainage pipe at the junction of the secondary lining side wall and the bottom plate to expand the traditional drainage pipe channel.

其中:in:

所述的外侧排水层,在隧道初期支护表面沿隧道轴线方向等间隔环绕隧道断面布设外侧环向排水盲管,外侧纵向排水盲管沿着隧道轴线方向布置,分别在布设在隧道拱部、边墙和拱脚处,最后在隧道壁面上铺设一层透水土工布。For the outer drainage layer, at the initial stage of the tunnel, the outer circumferential drainage blind pipes are arranged around the tunnel section at equal intervals along the tunnel axis direction, and the outer longitudinal drainage blind pipes are arranged along the tunnel axis direction. At the side wall and arch foot, finally lay a layer of permeable geotextile on the tunnel wall.

所述的减压层,在透水土工布上铺设三维双向土工格室,在外侧环向排水盲管与外侧纵向排水盲管的交汇处垂直于隧道初期支护壁面安装内外排水盲管的连接管,最后在三维双向土工格室内喷射多孔轻骨料透水混凝土,透水混凝土的厚度刚好达到三维双向土工格室高度。For the decompression layer, a three-dimensional two-way geocell is laid on the permeable geotextile, and the connecting pipe of the inner and outer drainage blind pipes is installed perpendicular to the initial support wall of the tunnel at the intersection of the outer circumferential drainage blind pipe and the outer longitudinal drainage blind pipe. Finally, the porous lightweight aggregate permeable concrete is sprayed in the three-dimensional two-way geocell, and the thickness of the permeable concrete just reaches the height of the three-dimensional two-way geocell.

所述的内侧排水层,在透水混凝土表面铺设一层透水土工布,然后沿隧道轴线方向根据连通管位置等间隔布设内侧环向排水盲管和施工止水条,施工止水条的布设位置与二次衬砌施工缝对齐,内侧环向排水盲管布设在相邻施工止水条的中间;环向排水盲管与止水条之间由纵向排水盲管连接,纵向排水盲管布设在隧道拱部、边墙和拱脚处,保障内侧环向排水盲管与内侧纵向排水盲管的交汇处与内外排水盲管的连接管相连。For the inner drainage layer, a layer of permeable geotextile is laid on the surface of the permeable concrete, and then the inner circumferential drainage blind pipes and construction water stop strips are arranged at equal intervals along the tunnel axis direction according to the position of the connecting pipe. The secondary lining construction joints are aligned, and the inner circumferential drainage blind pipe is arranged in the middle of the adjacent construction waterstop; the longitudinal drainage blind pipe is connected between the circumferential drainage blind pipe and the waterstop, and the longitudinal drainage blind pipe is arranged in the tunnel arch. It is ensured that the intersection of the inner circumferential drainage dead pipe and the inner longitudinal drainage dead pipe is connected with the connecting pipe of the inner and outer drainage dead pipes.

所述的排水道,在二次衬砌结构的钢筋布置之后与混凝土浇筑之前,在隧道二次衬砌边墙与底板连接处原有布设传统排水管的混凝土浇筑局部区域布设分布式集束排水管,连接内侧排水层与隧道的排水边沟,来扩大传统排水管的排水通道;For the drainage channel, after the reinforcement of the secondary lining structure is arranged and before the concrete is poured, distributed cluster drainage pipes are arranged in the concrete pouring local area where the traditional drainage pipes are originally arranged at the connection between the secondary lining side wall and the bottom plate of the tunnel, and the connection is made. The inner drainage layer and the drainage side ditch of the tunnel to expand the drainage channel of the traditional drainage pipe;

本发明的岩溶富水隧道双层减压防排水系统的建造方法包括以下步骤:The construction method of the double-layer decompression and drainage system of the karst water-rich tunnel of the present invention comprises the following steps:

步骤1,紧贴隧道初期支护结构,沿隧道环向上布设外侧环向排水盲管,在隧道轴线上布设外侧纵向排水盲管;Step 1, close to the initial support structure of the tunnel, lay out the outer circumferential drainage dead pipe along the tunnel ring upward, and lay the outer longitudinal drainage dead pipe on the tunnel axis;

步骤2,围绕隧道环向在初期支护结构、外侧环向排水盲管和外侧纵向排水盲管的上面铺设透水土工布,使之覆盖隧道环向壁面;Step 2: Lay permeable geotextiles around the tunnel circumferential direction on the initial support structure, the outer circumferential drainage dead pipe and the outer longitudinal drainage dead pipe to cover the tunnel circumferential wall;

步骤3,在透水土工布上面安装固定三维双向土工格室,使之覆盖在透水土工布之上;Step 3, install and fix the three-dimensional two-way geocell on the permeable geotextile to cover the permeable geotextile;

步骤4,在外侧环向排水盲管和外侧纵向排水盲管的交叉点处,垂直隧道壁面设置内外排水盲管的连接管,并利用三维双向土工格室来固定,并且做好之后步骤5施作中可能造成连接管堵塞的保护工作;Step 4: At the intersection of the outer annular drainage dead pipe and the outer longitudinal drainage dead pipe, the connecting pipe of the inner and outer drainage dead pipes is arranged on the vertical tunnel wall, and fixed with a three-dimensional two-way geocell, and after the completion of step 5, the construction is in progress. Protection work that may cause blockage of the connecting pipe;

步骤5,采用喷射浇筑方式在三维双向土工格室内部填充多孔透水混凝土,达到填满整个格室;Step 5: Fill the interior of the three-dimensional two-way geocell with porous permeable concrete by means of spray pouring, so as to fill the entire cell;

步骤6,在充满多孔透水混凝土的三维双向土工格室的表面铺设透水土工布;Step 6, laying permeable geotextiles on the surface of the three-dimensional two-way geocell filled with porous permeable concrete;

步骤7,在步骤6的透水土工布的表面布设内侧环向排水盲管和内侧纵向排水盲管,内侧排水层盲管位置与外侧排水层盲管的位置平行,并将内侧环向排水盲管和内侧纵向排水盲管的交叉点与内外排水盲管的连接管连接;In step 7, the inner circumferential drainage dead pipe and the inner longitudinal drainage dead pipe are arranged on the surface of the permeable geotextile in step 6. The position of the inner drainage layer dead pipe is parallel to the position of the outer drainage layer dead pipe, and the inner circumferential drainage dead pipe is placed. The intersection point with the inner longitudinal drainage dead pipe is connected with the connecting pipe of the inner and outer drainage dead pipes;

步骤8,按照常规工艺施作隧道防水层;Step 8, applying the tunnel waterproof layer according to the conventional process;

步骤9,在防水层外侧进行二次衬砌结构的钢筋布置;Step 9, the reinforcement arrangement of the secondary lining structure is carried out on the outside of the waterproof layer;

步骤10,在隧道二次衬砌边墙与底板连接处原有布设传统排水管的局部区域,利用钢筋网布置间隙布设分布式集束排水管,并利用钢筋网使得分布式集束排水管固定;Step 10: In the local area where the traditional drainage pipes are originally laid at the connection between the secondary lining side wall and the bottom plate of the tunnel, the distributed cluster drainage pipes are arranged in the gaps of the reinforcement mesh, and the distributed cluster drainage pipes are fixed by using the reinforcement mesh;

步骤11,在防水层外浇注二衬混凝土。Step 11, pour the secondary lining concrete outside the waterproof layer.

有益效果:岩溶富水隧道双层减压防排水系统结构主要包括在隧道初期支护与二次衬砌之间设置外侧排水层、减压层、内侧排水层和排水道。外侧排水层紧贴隧道初期支护设置,外侧排水层与内侧排水层通过连接管相连通,外侧排水层与内侧排水层之间设置减压层,内侧排水层与二次衬砌之间设置防水层。外侧排水层主要功能主要是收集围岩裂隙水,起到旱季岩溶隧道常规排水效能;减压层主要功能是扩大储水容量、降低水头压力的作用,内侧排水层主要功能是收集减压层排水量;排水道的主要功能是加大排入排水边沟收水量;内外排水层的连通管提高了排水效率。本发明的施工方法简便有效,各个排水层功能明确,能够有效保障岩溶富水隧道雨季大流量排水需求。Beneficial effects: The structure of the double-layer decompression and drainage system of the karst water-rich tunnel mainly includes setting an outer drainage layer, a decompression layer, an inner drainage layer and a drainage channel between the initial support of the tunnel and the secondary lining. The outer drainage layer is set close to the initial support of the tunnel, the outer drainage layer and the inner drainage layer are connected by connecting pipes, a decompression layer is arranged between the outer drainage layer and the inner drainage layer, and a waterproof layer is arranged between the inner drainage layer and the secondary lining . The main function of the outer drainage layer is to collect water from surrounding rock fissures, which plays a role in the conventional drainage of karst tunnels in dry season; the main function of the decompression layer is to expand the water storage capacity and reduce the head pressure, and the main function of the inner drainage layer is to collect the drainage of the decompression layer. The main function of the drainage channel is to increase the amount of water discharged into the drainage side ditch; the connecting pipes of the inner and outer drainage layers improve the drainage efficiency. The construction method of the invention is simple and effective, the functions of each drainage layer are clear, and the demand for large-flow drainage in the rainy season of the karst water-rich tunnel can be effectively guaranteed.

附图说明Description of drawings

以下结合附图和实施案例对本发明作进一步说明。The present invention will be further described below with reference to the accompanying drawings and implementation cases.

图1是双层减压防排水系统示意图;Figure 1 is a schematic diagram of a double-layer decompression and drainage system;

以上图中有:分布式集束排水管1、内侧纵向排水盲管2、外侧纵向排水盲管3、外侧环向排水盲管4、内侧环向排水盲管5、外侧排水层与内侧排水层的连接管6、三维双向土工格室7、多孔透水混凝土8、初期支护9、外侧排水层10、减压层11、内侧排水层12、防水层13、二次衬砌14。In the above figure, there are: distributed cluster drainage pipe 1, inner longitudinal drainage blind pipe 2, outer longitudinal drainage blind pipe 3, outer annular drainage blind pipe 4, inner annular drainage blind pipe 5, the outer drainage layer and the inner drainage layer Connecting pipe 6 , three-dimensional two-way geocell 7 , porous permeable concrete 8 , initial support 9 , outer drainage layer 10 , decompression layer 11 , inner drainage layer 12 , waterproof layer 13 , secondary lining 14 .

具体实施方式Detailed ways

下面举例对本发明的技术方案进行详细说明:The following examples illustrate the technical scheme of the present invention in detail:

本发明的岩溶富水隧道双层减压防排水系统包括在隧道初期支护与二次衬砌之间设置外侧排水层、减压层、内侧排水层和排水道,外侧排水层包括外侧纵向排水盲管(80mm单壁打孔波纹管、洞顶边墙共5道)、外侧环向排水盲管(50mm单壁打孔波纹管、环向间隔12m设置)、透水土工布;减压层包括三维双向土工格室(格室高度50~100mm)、喷射式多孔轻骨料透水混凝土(厚度50~100mm和内外排水盲管的垂直连接管(80mm单壁波纹管,长50~100mm);内侧排水层包括内侧纵向排水盲管(80mm单壁打孔波纹管、洞顶边墙共5道)、内侧环向排水盲管(50mm单壁打孔波纹管、环向间隔12m设置)和透水土工布;排水道是在二次衬砌边墙与底板交接处局部采用分布式集束排水管(一组10个,单个排水管管径30mm)来扩大传统排水管通道。The double-layer decompression and drainage system of the karst water-rich tunnel of the present invention includes an outer drainage layer, a decompression layer, an inner drainage layer and a drainage channel arranged between the initial support of the tunnel and the secondary lining, and the outer drainage layer includes an outer longitudinal drainage blind Pipes (80mm single-wall perforated corrugated pipe, 5 tunnels on the top and side walls of the hole), outer annular drainage blind pipe (50mm single-wall perforated corrugated pipe, set at 12m circumferential interval), permeable geotextiles; the decompression layer includes three-dimensional Two-way geocell (cell height 50-100mm), sprayed porous lightweight aggregate permeable concrete (thickness 50-100mm and vertical connecting pipe of inner and outer drainage blind pipes (80mm single-wall corrugated pipe, length 50-100mm); inner drainage The layer includes inner longitudinal drainage blind pipes (80mm single-wall perforated corrugated pipes, 5 tunnels on the top side wall), inner circumferential drainage blind pipes (50mm single-wall perforated corrugated pipes, set at a circumferential interval of 12m) and permeable geotextiles ; Drainage is to use distributed cluster drainage pipes (a group of 10, the diameter of a single drainage pipe is 30mm) at the junction of the secondary lining side wall and the bottom plate to expand the traditional drainage pipe channel.

所述的外侧排水层,在隧道初期支护表面沿隧道轴线方向等间隔环绕隧道断面布设外侧环向排水盲管,外侧纵向排水盲管沿着隧道轴线方向布置,分别在布设在隧道拱部、边墙和拱脚处,纵向排水管在环向排水管两侧对称布置,呈V字型布置,且纵向排水管的坡度不低于2%,最后在隧道壁面上铺设一层透水土工布。For the outer drainage layer, at the initial stage of the tunnel, the outer circumferential drainage blind pipes are arranged around the tunnel section at equal intervals along the tunnel axis direction, and the outer longitudinal drainage blind pipes are arranged along the tunnel axis direction. At the side wall and arch foot, the longitudinal drainage pipes are arranged symmetrically on both sides of the annular drainage pipe in a V-shaped arrangement, and the slope of the longitudinal drainage pipes is not less than 2%. Finally, a layer of permeable geotextile is laid on the tunnel wall.

所述的减压层,在透水土工布上铺设三维双向土工格室,在外侧环向排水盲管与外侧纵向排水盲管的交汇处垂直于隧道初期支护壁面安装内外排水盲管的连接管(80mm单壁波纹管,长50~100mm),最后在三维双向土工格室内喷射多孔轻骨料透水混凝土(厚度50~100mm),透水混凝土的厚度刚好达到三维双向土工格室高度。For the decompression layer, a three-dimensional two-way geocell is laid on the permeable geotextile, and the connecting pipe of the inner and outer drainage blind pipes is installed perpendicular to the initial support wall of the tunnel at the intersection of the outer circumferential drainage blind pipe and the outer longitudinal drainage blind pipe. (80mm single-wall corrugated pipe, length 50-100mm), and finally spray porous lightweight aggregate permeable concrete (thickness 50-100mm) in the three-dimensional two-way geocell, and the thickness of the permeable concrete just reaches the height of the three-dimensional two-way geocell.

所述的内侧排水层,在透水混凝土表面铺设一层透水土工布,然后沿隧道轴线方向根据连通管位置等间隔布设内侧环向排水盲管和施工止水条,施工止水条的布设位置与二次衬砌施工缝对齐,内侧环向排水盲管布设在相邻施工止水条的中间;环向排水盲管与止水条之间由纵向排水盲管连接,纵向排水盲管布设在隧道拱部、边墙和拱脚处,保障内侧环向排水盲管与内侧纵向排水盲管的交汇处与内外排水盲管的连接管相连。For the inner drainage layer, a layer of permeable geotextile is laid on the surface of the permeable concrete, and then the inner circumferential drainage blind pipes and construction water stop strips are arranged at equal intervals along the tunnel axis direction according to the position of the connecting pipe. The secondary lining construction joints are aligned, and the inner circumferential drainage blind pipe is arranged in the middle of the adjacent construction waterstop; the longitudinal drainage blind pipe is connected between the circumferential drainage blind pipe and the waterstop, and the longitudinal drainage blind pipe is arranged in the tunnel arch. It is ensured that the intersection of the inner circumferential drainage dead pipe and the inner longitudinal drainage dead pipe is connected with the connecting pipe of the inner and outer drainage dead pipes.

所述的排水道,在二次衬砌结构的钢筋布置之后与混凝土浇筑之前,在隧道二次衬砌边墙与底板连接处原有布设传统排水管的混凝土浇筑局部区域布设分布式集束排水管(一组10个,单个排水管管径30mm),连接内侧排水层与隧道的排水边沟,来扩大传统排水管的排水通道;For the drainage channel, after the reinforcement of the secondary lining structure is arranged and before the concrete is poured, distributed cluster drainage pipes (one Group of 10, the diameter of a single drainage pipe is 30mm), connecting the inner drainage layer and the drainage side ditch of the tunnel to expand the drainage channel of the traditional drainage pipe;

岩溶富水隧道双层减压防排水系统结构与建造方法,包括以下步骤:Structure and construction method of double-layer decompression and drainage system for karst water-rich tunnel, including the following steps:

步骤1,紧贴隧道初期支护结构,沿隧道环向上布设外侧环向排水盲管,在隧道轴线上布设外侧纵向排水盲管,纵向排水管在环向排水管两侧对称布置,呈V字型布置,且纵向排水管的坡度不低于2%;Step 1: Adhere to the initial support structure of the tunnel, lay out the outer annular drainage blind pipe along the tunnel ring upward, and arrange the outer longitudinal drainage blind pipe on the tunnel axis. The longitudinal drainage pipes are symmetrically arranged on both sides of the annular drainage pipe in a V shape. type layout, and the slope of the longitudinal drainage pipe is not less than 2%;

步骤2,围绕隧道环向在初期支护结构、外侧环向排水盲管和外侧纵向排水盲管的上面铺设透水土工布,使之覆盖隧道环向壁面,透水土工布在两道环向排水盲管之间设置止水条;Step 2: Lay a permeable geotextile on the initial support structure, the outer circumferential drainage blind pipe and the outer longitudinal drainage blind pipe around the tunnel circumferential direction to cover the tunnel circumferential wall. Water stop strips are set between the pipes;

步骤3,在透水土工布上面安装固定三维双向土工格室(格室高度50~100mm),使之覆盖在透水土工布之上;Step 3, install and fix a three-dimensional two-way geocell (cell height 50-100mm) on the permeable geotextile to cover the permeable geotextile;

步骤4,在外侧环向排水盲管和外侧纵向排水盲管的交叉点处,垂直隧道壁面设置内外排水盲管的连接管(80mm单壁波纹管,长50~100mm),并利用三维双向土工格室来固定,并且做好后面步骤5施作中可能造成连接管堵塞的保护工作;Step 4: At the intersection of the outer annular drainage dead pipe and the outer longitudinal drainage dead pipe, the connecting pipe (80mm single-wall corrugated pipe, 50-100 mm long) of the inner and outer drainage dead pipes is set on the vertical tunnel wall, and three-dimensional two-way geotechnical The cell is fixed, and the protection work that may cause the blockage of the connecting pipe in the following step 5 is done well;

步骤5,采用喷射浇筑方式在三维双向土工格室内部填充多孔透水混凝土,达到填满整个格室(厚度50~100mm);Step 5: Fill the interior of the three-dimensional two-way geocell with porous permeable concrete by means of spray pouring to fill the entire cell (thickness 50-100mm);

步骤6,在充满多孔透水混凝土的三维双向土工格室的表面铺设透水土工布;Step 6, laying permeable geotextiles on the surface of the three-dimensional two-way geocell filled with porous permeable concrete;

步骤7,在步骤6的透水土工布的表面布设内侧环向排水盲管和内侧纵向排水盲管,内侧排水层盲管位置与外侧排水层盲管的位置平行,并将内侧环向排水盲管和内侧纵向排水盲管的交叉点与内外排水盲管的连接管连接;In step 7, the inner circumferential drainage dead pipe and the inner longitudinal drainage dead pipe are arranged on the surface of the permeable geotextile in step 6. The position of the inner drainage layer dead pipe is parallel to the position of the outer drainage layer dead pipe, and the inner circumferential drainage dead pipe is placed. The intersection point with the inner longitudinal drainage dead pipe is connected with the connecting pipe of the inner and outer drainage dead pipes;

步骤8,按照常规工艺施作隧道防水层;Step 8, applying the tunnel waterproof layer according to the conventional process;

步骤9,在防水层外侧进行二次衬砌结构的钢筋布置;Step 9, the reinforcement arrangement of the secondary lining structure is carried out on the outside of the waterproof layer;

步骤10,在隧道二次衬砌边墙与底板连接处原有布设传统排水管的局部区域,利用钢筋网布置间隙布设分布式集束排水管,并利用钢筋网使得分布式集束排水管(一组10个,单个排水管管径30mm)固定;Step 10: In the local area where the traditional drainage pipes were originally laid at the connection between the secondary lining side wall and the bottom plate of the tunnel, the distributed cluster drainage pipes were arranged in the gaps of the reinforcement mesh, and the distributed cluster drainage pipes (a group of 10 A single drain pipe with a diameter of 30mm) is fixed;

步骤11,在防水层外浇注二衬混凝土。Step 11, pour the secondary lining concrete outside the waterproof layer.

Claims (6)

1. The utility model provides a drainage system is prevented in double-deck decompression of rich water tunnel of karst which characterized in that: the method comprises the steps of arranging an outer side drainage layer, a decompression layer, an inner side drainage layer and a drainage channel between a tunnel primary support and a secondary lining, wherein the outer side drainage layer comprises an outer side longitudinal drainage blind pipe, an outer side circumferential drainage blind pipe and permeable geotextile; the pressure reduction layer comprises a three-dimensional bidirectional geocell, injection type porous lightweight aggregate permeable concrete and a vertical connecting pipe of an internal and external drainage blind pipe; the inner drainage layer comprises an inner longitudinal drainage blind pipe, an inner circumferential drainage blind pipe and a water-permeable geotextile; the drainage channel is formed by locally adopting distributed cluster drainage pipes at the joint of the secondary lining side wall and the bottom plate to enlarge the channel of the traditional drainage pipe.
2. The double-layer pressure-reducing water-proof and drainage system for the karst water-rich tunnel according to claim 1, wherein the outer drainage layers are characterized in that outer circumferential drainage blind pipes are arranged on the primary support surface of the tunnel at equal intervals along the axial direction of the tunnel around the section of the tunnel, outer longitudinal drainage blind pipes are arranged along the axial direction of the tunnel, and are respectively arranged at the arch part, the side wall and the arch foot of the tunnel, and finally a layer of permeable geotextile is laid on the wall surface of the tunnel.
3. The double-layer pressure-reducing, water-proof and drainage system for the karst water-rich tunnel according to claim 1, wherein the pressure-reducing layer is formed by laying three-dimensional bidirectional geocells on a permeable geotextile, connecting pipes of inner and outer drainage blind pipes are arranged at the intersection of an outer circumferential drainage blind pipe and an outer longitudinal drainage blind pipe and are perpendicular to the primary supporting wall surface of the tunnel, and finally porous light aggregate permeable concrete is sprayed in the three-dimensional bidirectional geocells, so that the thickness of the permeable concrete just reaches the height of the three-dimensional bidirectional geocells.
4. The double-layer pressure-reducing and water-preventing and draining system for the karst water-rich tunnel according to claim 1, wherein a layer of permeable geotextile is laid on the surface of the permeable concrete, inner annular drainage blind pipes and construction water stop bars are arranged at equal intervals along the axial direction of the tunnel according to the positions of the communicating pipes, the arrangement positions of the construction water stop bars are aligned with the construction joints of the secondary lining, and the inner annular drainage blind pipes are arranged in the middle of the adjacent construction water stop bars; the annular drainage blind pipes are connected with the water stop strips through longitudinal drainage blind pipes, the longitudinal drainage blind pipes are arranged at the arch parts, side walls and arch feet of the tunnels, and the junction of the inner annular drainage blind pipe and the inner longitudinal drainage blind pipe is connected with a connecting pipe of the inner drainage blind pipe and the outer drainage blind pipe.
5. The double-layer pressure-reducing and water-proof system for the karst water-rich tunnel according to claim 1, wherein the drainage channel is formed by arranging distributed bundled drainage pipes in a concrete pouring local area where conventional drainage pipes are originally arranged at the joint of the secondary lining side wall and the bottom plate of the tunnel after arranging reinforcing steel bars of the secondary lining structure and before pouring concrete, and connecting an inner drainage layer with a drainage side ditch of the tunnel to enlarge a drainage channel of the conventional drainage pipes.
6. The method for constructing the double-layer decompression waterproof and drainage system of the karst water-rich tunnel according to claim 1, characterized by comprising the following steps:
step 1, closely attaching to a tunnel primary support structure, arranging outer circumferential drainage blind pipes upwards along the circumferential direction of a tunnel, and arranging outer longitudinal drainage blind pipes on the axis of the tunnel;
step 2, paving permeable geotextile on the primary support structure, the outer circumferential drainage blind pipe and the outer longitudinal drainage blind pipe around the circumferential direction of the tunnel to cover the circumferential wall surface of the tunnel;
step 3, installing and fixing a three-dimensional bidirectional geocell on the permeable geotextile to cover the permeable geotextile;
step 4, arranging a connecting pipe of the inner and outer drainage blind pipes at the intersection point of the outer annular drainage blind pipe and the outer longitudinal drainage blind pipe, and fixing by using a three-dimensional bidirectional geocell, and performing protection work which can cause the blockage of the connecting pipe in the subsequent step 5;
step 5, filling porous pervious concrete in the three-dimensional bidirectional geocell by adopting a jet pouring mode to fill the whole geocell;
step 6, paving permeable geotextile on the surface of the three-dimensional bidirectional geocell filled with the porous permeable concrete;
step 7, laying an inner side circumferential drainage blind pipe and an inner side longitudinal drainage blind pipe on the surface of the permeable geotextile in the step 6, wherein the position of the inner side drainage layer blind pipe is parallel to that of the outer side drainage layer blind pipe, and connecting the intersection point of the inner side circumferential drainage blind pipe and the inner side longitudinal drainage blind pipe with a connecting pipe of the inner and outer drainage blind pipes;
step 8, constructing a tunnel waterproof layer according to a conventional process;
step 9, arranging reinforcing steel bars of a secondary lining structure on the outer side of the waterproof layer;
step 10, distributing distributed type cluster drainage pipes in a local area where traditional drainage pipes are originally distributed at the joint of the tunnel secondary lining side wall and the bottom plate by using reinforcing mesh arrangement gaps, and fixing the distributed type cluster drainage pipes by using the reinforcing mesh;
and 11, pouring secondary lining concrete outside the waterproof layer.
CN202010326020.3A 2020-04-23 2020-04-23 A double-layer decompression and drainage system for karst water-rich tunnel and its construction method Active CN111425250B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010326020.3A CN111425250B (en) 2020-04-23 2020-04-23 A double-layer decompression and drainage system for karst water-rich tunnel and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010326020.3A CN111425250B (en) 2020-04-23 2020-04-23 A double-layer decompression and drainage system for karst water-rich tunnel and its construction method

Publications (2)

Publication Number Publication Date
CN111425250A true CN111425250A (en) 2020-07-17
CN111425250B CN111425250B (en) 2022-04-12

Family

ID=71554441

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010326020.3A Active CN111425250B (en) 2020-04-23 2020-04-23 A double-layer decompression and drainage system for karst water-rich tunnel and its construction method

Country Status (1)

Country Link
CN (1) CN111425250B (en)

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112648011A (en) * 2021-01-25 2021-04-13 成都和拓土木工程有限公司 Siphon rapid drainage anti-crystallization blind pipe and installation method thereof
CN113153379A (en) * 2021-04-27 2021-07-23 重庆永昂实业有限公司 Tunnel water-proof and drainage system and construction process
CN114483082A (en) * 2022-01-26 2022-05-13 华设设计集团股份有限公司 Tunnel sewage interception and drainage prevention structure for downward-penetrating refuse landfill and construction method thereof
CN115110992A (en) * 2022-07-17 2022-09-27 西安泰晟智能科技有限公司 Tunnel drainage system construction method
CN115467707A (en) * 2022-10-10 2022-12-13 长江勘测规划设计研究有限责任公司 Duct piece drainage structure with longitudinal and transverse drainage capacity
CN115638022A (en) * 2022-11-03 2023-01-24 中铁第一勘察设计院集团有限公司 Tunnel hoop country rock laminating type prevents crystallization drainage blind pipe
WO2024212091A1 (en) * 2023-04-11 2024-10-17 大连理工大学 Tunnel groundwater recycling device based on dynamic regulation and control of ecological water requirements

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107178393A (en) * 2017-07-07 2017-09-19 中铁第四勘察设计院集团有限公司 A kind of Tunnel Second Lining water pressure control structure
CN206655716U (en) * 2017-04-21 2017-11-21 湖南城市学院 A kind of tunnel drainage structure
CN206874310U (en) * 2017-04-14 2018-01-12 长沙理工大学 Be applicable to high-pressure rich water district tunnel decompression drainage device
CN207513633U (en) * 2017-12-08 2018-06-19 四川省交通运输厅公路规划勘察设计研究院 The pressure limiting drainage system of tunnel anti-hydraulic pressure section
CN108533316A (en) * 2018-05-07 2018-09-14 中铁工程设计咨询集团有限公司 A kind of full packet pressure release waterproof/drainage structure in tunnel
CN108661674A (en) * 2018-07-19 2018-10-16 中国铁路设计集团有限公司 A kind of high hydraulic pressure tunnel sluicing voltage-dropping type is pre-buried to safeguard grouting device
CN108729932A (en) * 2018-05-22 2018-11-02 中铁二院工程集团有限责任公司 Tunnel lining structure solid waterproof and water drainage system
CN109751080A (en) * 2019-01-15 2019-05-14 西南交通大学 Supporting structure and construction method with waterproof and drainage function suitable for water-rich stratum
CN209212297U (en) * 2018-08-27 2019-08-06 中南大学 A water-proof, drainage and pressure-reducing system for tunnels in water-rich sections
CN209482090U (en) * 2018-12-11 2019-10-11 广东省长大公路工程有限公司 A kind of tunnel drainage pavement structure

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN206874310U (en) * 2017-04-14 2018-01-12 长沙理工大学 Be applicable to high-pressure rich water district tunnel decompression drainage device
CN206655716U (en) * 2017-04-21 2017-11-21 湖南城市学院 A kind of tunnel drainage structure
CN107178393A (en) * 2017-07-07 2017-09-19 中铁第四勘察设计院集团有限公司 A kind of Tunnel Second Lining water pressure control structure
CN207513633U (en) * 2017-12-08 2018-06-19 四川省交通运输厅公路规划勘察设计研究院 The pressure limiting drainage system of tunnel anti-hydraulic pressure section
CN108533316A (en) * 2018-05-07 2018-09-14 中铁工程设计咨询集团有限公司 A kind of full packet pressure release waterproof/drainage structure in tunnel
CN108729932A (en) * 2018-05-22 2018-11-02 中铁二院工程集团有限责任公司 Tunnel lining structure solid waterproof and water drainage system
CN108661674A (en) * 2018-07-19 2018-10-16 中国铁路设计集团有限公司 A kind of high hydraulic pressure tunnel sluicing voltage-dropping type is pre-buried to safeguard grouting device
CN209212297U (en) * 2018-08-27 2019-08-06 中南大学 A water-proof, drainage and pressure-reducing system for tunnels in water-rich sections
CN209482090U (en) * 2018-12-11 2019-10-11 广东省长大公路工程有限公司 A kind of tunnel drainage pavement structure
CN109751080A (en) * 2019-01-15 2019-05-14 西南交通大学 Supporting structure and construction method with waterproof and drainage function suitable for water-rich stratum

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112648011A (en) * 2021-01-25 2021-04-13 成都和拓土木工程有限公司 Siphon rapid drainage anti-crystallization blind pipe and installation method thereof
CN113153379A (en) * 2021-04-27 2021-07-23 重庆永昂实业有限公司 Tunnel water-proof and drainage system and construction process
CN113153379B (en) * 2021-04-27 2024-01-09 重庆永昂实业有限公司 Tunnel waterproof and drainage system and construction process
CN114483082A (en) * 2022-01-26 2022-05-13 华设设计集团股份有限公司 Tunnel sewage interception and drainage prevention structure for downward-penetrating refuse landfill and construction method thereof
CN115110992A (en) * 2022-07-17 2022-09-27 西安泰晟智能科技有限公司 Tunnel drainage system construction method
CN115467707A (en) * 2022-10-10 2022-12-13 长江勘测规划设计研究有限责任公司 Duct piece drainage structure with longitudinal and transverse drainage capacity
CN115638022A (en) * 2022-11-03 2023-01-24 中铁第一勘察设计院集团有限公司 Tunnel hoop country rock laminating type prevents crystallization drainage blind pipe
WO2024212091A1 (en) * 2023-04-11 2024-10-17 大连理工大学 Tunnel groundwater recycling device based on dynamic regulation and control of ecological water requirements

Also Published As

Publication number Publication date
CN111425250B (en) 2022-04-12

Similar Documents

Publication Publication Date Title
CN111425250B (en) A double-layer decompression and drainage system for karst water-rich tunnel and its construction method
CN106194255B (en) Tunnel waterproof and water drainage system and its method of construction
CN106638918B (en) Construction method of sponge urban rainwater collection system
CN103256052B (en) Construction method for integral straight middle wall type double-arch tunnel
CN202483588U (en) Self water-proof drainage system of tunnel lining
CN103147614B (en) Pool with multi-layer structure and building method thereof
CN101298782A (en) Method and system for basement engineering water proof and water drain
CN110878700A (en) Tunnel waterproof structure and construction method thereof
CN104846840B (en) A kind of shallow embedding reinforcement of soft soil integrated pipe canal device and construction method
CN108316354A (en) With waterproof, the underground pipe gallery structure of drain function and its construction method
CN109488371B (en) Waterproof system of full-enclosed waterproof station and dynamic setting and quantity-limiting drainage method
CN111911168A (en) Construction Method and Permanent Support System of Shallow Buried Long-Span Tunnel
CN110886303A (en) Anti-drainage integrated underground drainage system
CN105350581A (en) Advanced sealing structure for basement top slab settlement post-cast strips
CN207268009U (en) A drainage system of underground comprehensive pipe gallery based on the existing sewage channel
CN115949437A (en) Shallow cold-proof heat preservation, drainage structure that buries bias voltage tunnel
CN104846935B (en) Head-tank treating seepage remodeling method
CN113323017B (en) Construction method of side wall fertilizer groove foam concrete backfill system
CN205259214U (en) Assembled rainwater storage tank constructed by sinking method
CN112012763B (en) Construction method of double-layer primary support multi-arch tunnel structure
CN113464174A (en) Construction method of tunnel drainage waterproof comprehensive treatment system
CN111749073A (en) Water permeable reconstruction technology based on existing road base layer
CN102677660B (en) Quick pile-forming method and method for quickly building urban flyover by quick pile-forming method
CN112323658B (en) Landscape ecological structure and construction method of mountain roads based on corrugated plates
CN113186977B (en) A reverse sequence construction method for underground comprehensive utility gallery

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant