CN206655716U - A kind of tunnel drainage structure - Google Patents
A kind of tunnel drainage structure Download PDFInfo
- Publication number
- CN206655716U CN206655716U CN201720423734.XU CN201720423734U CN206655716U CN 206655716 U CN206655716 U CN 206655716U CN 201720423734 U CN201720423734 U CN 201720423734U CN 206655716 U CN206655716 U CN 206655716U
- Authority
- CN
- China
- Prior art keywords
- tunnel
- coat
- drainage structure
- skeleton
- pervious bed
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Expired - Fee Related
Links
Abstract
The utility model discloses a kind of tunnel drainage structure, belong to constructing tunnel construction applications, for solve the problems, such as more than working procedure and it is numerous and diverse, drainage effect is bad.It includes back-up coat, pervious bed, the back-up coat is outside construction section, and the pervious bed includes vault part, arch bottom point, and the vault part is poured in back-up coat inwall, the arch bottom point is laid in tunnel bottom surface, and the arch bottom partial interior is embedded with drainage pipeline along tunnel bearing of trend;The drainage pipeline includes skeleton, surface layer fabric, and the surface layer fabric is fixed on the outside of skeleton.The technical program is simple and reasonable, drainage effect is good.
Description
Technical field
The utility model belongs to constructing tunnel construction applications, is a kind of tunnel drainage structure specifically.
Background technology
At present, " slip casting+row leads " method is the guarded drainage method commonly used in tunnel.Rock grouting reinforcement after lining cutting, reduce rock
The infiltration coefficient of stone, prevent more direction of groundwater flow tunnels;Drainage system is being set between lining and two linings at the beginning of tunnel, will transmit through rock
Rock glacier enters the underground water discharge tunnel in tunnel, reduces effect of the underground water to tunnel double-lining, ensures tunnel structure safety.
The shortcomings that " slip casting+row leads " method is:Working procedure is more and numerous and diverse, drainage effect is bad etc..
Utility model content
The utility model purpose is intended to provide a kind of tunnel drainage structure simple and reasonable, drainage effect is good.
To realize above-mentioned technical purpose, the technical solution adopted in the utility model is as follows:
A kind of tunnel drainage structure, including back-up coat, pervious bed, the back-up coat are described permeable outside construction section
Layer includes vault part, arch bottom point, and the vault part is poured is laid in tunnel bottom in back-up coat inwall, the arch bottom point
Face, the arch bottom partial interior are embedded with drainage pipeline along tunnel bearing of trend;The drainage pipeline includes skeleton, top layer face
Material, the surface layer fabric are fixed on the outside of skeleton.
Further limit, the skeleton includes some arc ribs, lengthways of rod, and the arc rib is justified for half
Arc, some arc ribs are longitudinally evenly distributed, and the lengthways of rod is at least provided with three, three lengthways of rod difference
Both ends, top with arc rib are fixedly connected.
Further limit, the vault internal partial wall is additionally provided with waterproof layer, and the waterproof layer is by some waterproof Slab element phases
Mutually it is welded to form.
Further limit, reinforcement net is also embedded with the pervious bed.
Further limit, the permeable thickness 20cm-30cm.
Using the utility model of above-mentioned technical proposal, the back-up coat structural support overall as tunnel, the whole of tunnel is improved
Body structural strength;Pervious bed can use foam concrete to pour and form, and foam concrete has internal porous due to itself
Structure, it is easy to groundwater seepage, pervious bed is by vault part and the packet of arch bottom into the underground water that vault part is penetrated into can edge
Arc-shaped curved surface infiltration downwards is final to come together in arch bottom point, and arch is embedded with the draining being made up of skeleton and surface layer fabric in bottom point
In pipeline, surface layer fabric is made using the good asbestos cloth of anticorrosion ability or glass fabric, is advantageous to groundwater seepage, draining
It pipeline inner hollow, can also facilitate underground water discharge, improve drainage effect;Skeleton is by some arc ribs and lengthways of rod phase
Mutually it is composed of a fixed connection, forms the upward arcuate channels of a curved surface, is advantageous to the pressure of scattered top, prevents drainage pipeline from existing
In work progress, compressive deformation, its structural strength is improved;Vault internal partial wall is provided with waterproof layer, and waterproof layer is by some splash guards
Unit is welded to each other composition, and waterproof Slab element can use PVC plastic flitch, and it can mutually be spliced by the way of hot melt;Thoroughly
Pre-buried reinforcement net in water layer, improve the structural strength of pervious bed;
Above-mentioned technical proposal uses following construction procedure:
First, premeasuring:
Tunnel section radius are predefined using equipment, and mark the section radius position;
2nd, back-up coat is constructed:
1st, drill:The uniformly drilling at 20cm-30cm outside the tunnel radial location of mark using rig;
2nd, it is in the milk:By grouting equipment by concrete grout hand-hole;
3rd, solidify:Concrete grout can be permeated after pouring into along fabric, by fabric in process of osmosis
Rock, sandy soil bond the back-up coat to form an arch;
3rd, tunnel piercing:
Usage mining machinery carries out longitudinal driving, and tunnelling footage, which is no more than, reinforces layer depth 30cm;Construction radius is not more than
Back-up coat inwall 10cm;
3rd, pervious bed is constructed:
1st, prefabricated reinforcement net is implanted into back-up coat inwall, expansion bolt is hammered into back-up coat inwall, by reinforcement net
It is fixed on expansion bolt;
2nd, drainage pipeline is laid, some drainage pipelines are laid side by side, adjacent spaces 20-25cm;
3rd, the foam concrete matched injection is carried out by grouting equipment encircleing bottom point pouring;
4th, vault part pouring is carried out when encircleing bottom point and reaching technological requirement intensity 65%-70%;
5th, when vault part reaches technological requirement 80%, powder is carried out to vault internal partial wall using water-proof acrylic acid paint
Brush;
4th, construction of waterproof layer:
PVC plastic flitch is fixed by swell fixture and waterproof layer, hot melt is used between adjacent two PVC plastic flitch
Bonding.
The utility model is compared with prior art, simple and reasonable, drainage effect is good.
Brief description of the drawings
The utility model can be further illustrated by the nonlimiting examples that accompanying drawing provides;
Fig. 1 is a kind of structural representation of tunnel drainage structure of the utility model;
Fig. 2 is skeleton structure schematic diagram;
Fig. 3 is the sectional view of A-A in Fig. 1;
Main element symbol description is as follows:
Back-up coat 1, pervious bed 2, vault part 3, arch bottom point 4, drainage pipeline 5, skeleton 6, surface layer fabric 7, arched ribs
Bar 8, lengthways of rod 9, waterproof layer 10, reinforcement net 11.
Embodiment
In order that the utility model may be better understood in those skilled in the art, it is right with reference to the accompanying drawings and examples
Technical solutions of the utility model further illustrate.
As shown in Figure 1, Figure 2, Figure 3 shows, a kind of tunnel drainage structure, including back-up coat 1, pervious bed 2, back-up coat 1, which is located at, to be applied
Outside work section, pervious bed 2 includes vault part 3, arch bottom point 4, and vault part 3 is poured in the inwall of back-up coat 1, arch bottom point 4
Tunnel bottom surface is laid in, arch bottom is divided inside 4 is embedded with drainage pipeline 5 along tunnel bearing of trend;Drainage pipeline 5 include skeleton 6,
Surface layer fabric 7, surface layer fabric 7 are fixed on the outside of skeleton 6.
Preferably, skeleton 6 includes some arc ribs 8, lengthways of rod 9, and arc rib 8 is half circular arc, some
The longitudinal direction of arc rib 8 is evenly distributed, lengthways of rod 9 at least provided with three, three lengthways of rod 9 respectively with arc rib 8 two
End, top are fixedly connected.
Preferably, the inwall of vault part 3 is additionally provided with waterproof layer 10, and waterproof layer 10 is welded to each other group by some waterproof Slab elements
Into.
Preferably, reinforcement net 11 is also embedded with pervious bed 2.
Preferably, 2 thick 20cm-30cm of pervious bed.
A kind of tunnel drainage structure provided by the utility model is described in detail above.The explanation of specific embodiment
It is only intended to help and understands method and its core concept of the present utility model.It should be pointed out that the common skill for the art
For art personnel, on the premise of the utility model principle is not departed from, some improvement can also be carried out to the utility model and are repaiied
Decorations, these are improved and modification is also fallen into the protection domain of the utility model claims.
Claims (5)
1. a kind of tunnel drainage structure, including back-up coat, pervious bed, it is characterised in that:The back-up coat is located at outside construction section,
The pervious bed includes vault part, arch bottom point, and the vault part is poured in back-up coat inwall, the arch bottom point tiling
In tunnel bottom surface, the arch bottom partial interior is embedded with drainage pipeline along tunnel bearing of trend;The drainage pipeline include skeleton,
Surface layer fabric, the surface layer fabric are fixed on the outside of skeleton.
A kind of 2. tunnel drainage structure according to claim 1, it is characterised in that:The skeleton includes some arched ribs
Bar, lengthways of rod, the arc rib are half circular arc, and some arc ribs are longitudinally evenly distributed, the longitudinal direction
Rib is at least provided with three, and the both ends with arc rib, top are fixedly connected three lengthways of rod respectively.
A kind of 3. tunnel drainage structure according to claim 2, it is characterised in that:The vault internal partial wall is additionally provided with anti-
Water layer, the waterproof layer are welded to each other by some waterproof Slab elements and formed.
A kind of 4. tunnel drainage structure according to claim 3, it is characterised in that:Reinforcement is also embedded with the pervious bed
Muscle net.
A kind of 5. tunnel drainage structure according to claim 4, it is characterised in that:The permeable thickness 20cm-30cm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720423734.XU CN206655716U (en) | 2017-04-21 | 2017-04-21 | A kind of tunnel drainage structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201720423734.XU CN206655716U (en) | 2017-04-21 | 2017-04-21 | A kind of tunnel drainage structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN206655716U true CN206655716U (en) | 2017-11-21 |
Family
ID=60319417
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201720423734.XU Expired - Fee Related CN206655716U (en) | 2017-04-21 | 2017-04-21 | A kind of tunnel drainage structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN206655716U (en) |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109296389A (en) * | 2018-12-10 | 2019-02-01 | 潘晓东 | A kind of freeway tunnel jet printing type guarded drainage construction and method |
CN111425250A (en) * | 2020-04-23 | 2020-07-17 | 交通运输部公路科学研究所 | Double-layer pressure-reducing water-proof and drainage system for karst water-rich tunnel and construction method of double-layer pressure-reducing water-proof and drainage system |
-
2017
- 2017-04-21 CN CN201720423734.XU patent/CN206655716U/en not_active Expired - Fee Related
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN109296389A (en) * | 2018-12-10 | 2019-02-01 | 潘晓东 | A kind of freeway tunnel jet printing type guarded drainage construction and method |
CN109296389B (en) * | 2018-12-10 | 2022-09-23 | 潘晓东 | Spraying type waterproof and drainage structure and method for expressway tunnel |
CN111425250A (en) * | 2020-04-23 | 2020-07-17 | 交通运输部公路科学研究所 | Double-layer pressure-reducing water-proof and drainage system for karst water-rich tunnel and construction method of double-layer pressure-reducing water-proof and drainage system |
CN111425250B (en) * | 2020-04-23 | 2022-04-12 | 交通运输部公路科学研究所 | Double-layer pressure-reducing water-proof and drainage system for karst water-rich tunnel and construction method of double-layer pressure-reducing water-proof and drainage system |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN103590425B (en) | A kind of Peaty soft soil stratum subway station construction technology | |
CN204000956U (en) | A kind of basement bottom plate rear pouring tape structure | |
CN104499479B (en) | It is a kind of to pass through the dug pile construction method that sand gravel backfills layer | |
CN203034467U (en) | Combined steel pile cofferdam with water-proof fore shafts | |
CN110878700B (en) | Tunnel waterproof structure and construction method thereof | |
CN205977229U (en) | Arcading tunnel non - flushes entrance to a cave structure suitable for bias voltage condition | |
CN104612143A (en) | Bored composite pile structure under karst cave/soil cave geological condition | |
CN109488371B (en) | Waterproof system of full-enclosed waterproof station and dynamic setting and quantity-limiting drainage method | |
CN204080789U (en) | The preparing structure of underground continuous wall width breach | |
CN104847365B (en) | A kind of small interval Four-Lane Road Shallow-buried Large-span Tunnel construction method | |
CN107201908A (en) | A kind of construction method of the regional buried Central drain in tunnel of bitter cold | |
CN104099943A (en) | Underground diaphragm wall and deserted underground civil air defense engineering intersection processing method | |
CN108180025A (en) | A kind of circular cross section tunnel lining construction method three times | |
CN106120801A (en) | In water-rich sand layer, pipeline crosses the construction method at foundation ditch | |
CN201538975U (en) | Seepage-proofing joint of underground continuous wall | |
CN204940315U (en) | A kind of water-stopping system for the large-scale vertical shaft of region of FuShui | |
CN106609508A (en) | Construction technology and construction method for large-particle-size pebble stratum super-deep foundation pit in strong water permeation environment of Yellow River flood plain | |
CN101575859B (en) | Anti-seepage joint of underground continuous walls and construction method thereof | |
CN206655716U (en) | A kind of tunnel drainage structure | |
CN207862925U (en) | A kind of slip casting casing device | |
CN107587502A (en) | A kind of spiral-digging pore pressure pour water soil occlusion curtain pile construction method | |
CN108277800B (en) | Reinforced concrete pipe joint gravel pile with consolidated sand layer and construction method thereof | |
CN104153347B (en) | Preparing structure and the construction method thereof of underground continuous wall width breach | |
CN206158753U (en) | Shield constructs well end bassoon canopy system of consolidating based on major structure | |
JP3645773B2 (en) | Wastewater treatment method for underground wall and underground wall constructed by this method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant | ||
CF01 | Termination of patent right due to non-payment of annual fee |
Granted publication date: 20171121 Termination date: 20190421 |
|
CF01 | Termination of patent right due to non-payment of annual fee |