CN111422317A - 一种超大型上建总段整体建造方法 - Google Patents

一种超大型上建总段整体建造方法 Download PDF

Info

Publication number
CN111422317A
CN111422317A CN202010304871.8A CN202010304871A CN111422317A CN 111422317 A CN111422317 A CN 111422317A CN 202010304871 A CN202010304871 A CN 202010304871A CN 111422317 A CN111422317 A CN 111422317A
Authority
CN
China
Prior art keywords
building block
hoisting
construction
upper building
stage
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010304871.8A
Other languages
English (en)
Inventor
叶飞
徐占勇
王杰
蒋林勇
甘伯惠
陈小雨
王大明
王虎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Waigaoqiao Shipbuilding Co Ltd
Original Assignee
Shanghai Waigaoqiao Shipbuilding Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Waigaoqiao Shipbuilding Co Ltd filed Critical Shanghai Waigaoqiao Shipbuilding Co Ltd
Priority to CN202010304871.8A priority Critical patent/CN111422317A/zh
Publication of CN111422317A publication Critical patent/CN111422317A/zh
Pending legal-status Critical Current

Links

Images

Landscapes

  • Ship Loading And Unloading (AREA)

Abstract

本发明公开了一种超大型上建总段整体建造方法,包括:分段划分阶段:根据上建总段的重量、体积以及施工因素,将上建总段划分为多个分段进行制造;运输搁置阶段:采用搁置运输托盘作为中间媒介,在建造时,搁置运输托盘可以用来总段或总组搁置;在转运时,动力模块顶升搁置运输托盘,将搁置运输托盘顶起后从地台移运至码头;吊装阶段:使用吊排方式的吊装结构对上建总段进行吊装。本发明能够整合超大型上建总段整体建造,提高舾装完整性。

Description

一种超大型上建总段整体建造方法
技术领域
本发明涉及船舶建造领域,尤其涉及上建总段建造领域。
背景技术
上建全称上层建筑,用于船员或乘客居住以及船舶运行控制。其结构特点是,结构轻薄,强度较弱,且内部舾装内装等系统复杂,如一层层单独在船上安装,一来单独吊装结构损伤过多,二来舾装安装阶段后移,影响安装坞内效率。FPSO超大型上建整体尺寸和吨位均创历史新高,重量达1800吨,且内部结构舾装比常规船舶更为复杂,因此需要进行超大型上建总段整体建造。
发明内容
本发明的目的在于提供超大型上建总段整体建造方法,整合超大型上建总段整体建造,提高舾装完整性。
实现上述目的的技术方案是:
一种超大型上建总段整体建造方法,包括:
分段划分阶段:根据上建总段的重量、体积以及施工因素,将上建总段划分为多个分段进行制造;
运输搁置阶段:采用搁置运输托盘作为中间媒介,在建造时,搁置运输托盘可以用来总段总组搁置;在转运时,动力模块顶升搁置运输托盘,将搁置运输托盘顶起后从地台移运至码头;
吊装阶段:使用吊排方式的吊装结构对上建总段进行吊装。
优选的,所述的施工因素包括:海工建造场地的总组能力和运输能力,以及分段制造、翻身、涂装和搭载的施工要求。
优选的,搁置运输托盘的主尺度为47400mm×15700mm×600mm。
优选的,运输搁置阶段中,
运输过程中,针对在行进方向上出现的爬坡时受逆风作用情况,以及在垂直于行进方向上出现的受强力横风作用情况,结合风力和坡度因数,对运输稳定性进行计算。
优选的,在吊装之前,对吊装结构的强度进行校核。
优选的,在分段划分阶段至吊装阶段的过程中,收集数据。
本发明的有益效果是:本发明实现了超大型上建总段整体建造,解决建造过程中超大型上建的承载、运输、吊装问题。能够有利于降低结构变形程度,同时舾装安装工序前移,减少坞内安装周期。
附图说明
图1是本发明的超大型上建总段整体建造方法的流程图;
图2是本发明中搁置运输托盘的俯视图;
图3是本发明中搁置运输托盘的有限元模型示意图;
图4是本发明中上建总段运输时爬坡逆风受载示意图;
图5是本发明中上建总段运输时侧风受载示意图;
图6是本发明中吊排的示意图;
图7是本发明中吊装阶段一视角的受力分析示意图;
图8是本发明中吊装阶段另一视角的受力分析示意图。
具体实施方式
下面将结合附图对本发明作进一步说明。
请参阅图1,本发明的超大型上建总段整体建造方法,包括下列步骤:
步骤S1,分段划分阶段:根据上建总段的重量、体积以及施工因素,将上建总段划分为多个分段进行制造。其中,施工因素包括:海工建造场地的总组能力和运输能力,以及分段制造、翻身、涂装和搭载的施工要求。使得上层建筑可以满足基本的建造和运输要求。
步骤S2,运输搁置阶段:采用专门设计的搁置运输托盘作为中间媒介,在建造时,搁置运输托盘可以用来总段总组搁置;在转运时,动力模块顶升搁置运输托盘,动力模块每一轴线在搁置运输托盘上顶升受力,符合SPMT(自行式模块运输车)型平板运输装置运输要求。在吊运时,吊起搁置运输托盘。搁置运输托盘的主尺度为47400mm×15700mm×600mm,如图2所示,尺寸之大应当是国内首位。
另外,采用有限元软件PATRAN进行搁置运输托盘的计算。搁置运输托盘的有限元模型如图3所示,所有构件采用CQUAD4壳单元模拟,网格尺寸大致为200mm×200mm。从边缘位移和应力结果看,搁置运输托盘设计满足使用要求。
运输稳定性计算:总组结束后,上建总段置于搁置运输托盘之上,通过动力模块将搁置运输托盘顶起后从地台移运至码头。运输途中有爬坡路段,同时承受风力作用。运输过程中,在行进方向上可能出现的不利情况为爬坡时受逆风作用,如图4所示。在垂直于行进方向上可能出现的不利情况为受强力横风作用,如图5所示。本申请中超大型上建总段具有高、重的特点,以及在运输时需要爬坡,因此需要结合风力和坡度因数,对运输稳定性进行计算。
步骤S3,吊装阶段:使用吊排方式的吊装结构对上建总段进行吊装,使得吊装结构均布受力。如图6所示。在吊装之前,采用结构强度计算软件(有限元软件PATRAN)对吊装结构的强度进行校核,如图7、8所示。
在步骤S1至步骤S3的过程中,收集数据。经过对现场实施的跟踪,此超大型上层建筑总段成功完成了建造并吊装,为目前国内体积及吨位最大上层建筑。为平地托盘建造、陆地运输转运以及浮吊吊装提供了有力的实践依据。
以上实施例仅供说明本发明之用,而非对本发明的限制,有关技术领域的技术人员,在不脱离本发明的精神和范围的情况下,还可以作出各种变换或变型,因此所有等同的技术方案也应该属于本发明的范畴,应由各权利要求所限定。

Claims (6)

1.一种超大型上建总段整体建造方法,其特征在于,包括:
分段划分阶段:根据上建总段的重量、体积以及施工因素,将上建总段划分为多个分段进行制造;
运输搁置阶段:采用搁置运输托盘作为中间媒介,在建造时,搁置运输托盘可以用来总段总组搁置;在转运时,动力模块顶升搁置运输托盘,将搁置运输托盘顶起后从地台移运至码头;
吊装阶段:使用吊排方式的吊装结构对上建总段进行吊装。
2.根据权利要求1所述的超大型上建总段整体建造方法,其特征在于,所述的施工因素包括:海工建造场地的总组能力和运输能力,以及分段制造、翻身、涂装和搭载的施工要求。
3.根据权利要求1所述的超大型上建总段整体建造方法,其特征在于,搁置运输托盘的主尺度为47400mm×15700mm×600mm。
4.根据权利要求1所述的超大型上建总段整体建造方法,其特征在于,运输搁置阶段中,
运输过程中,针对在行进方向上出现的爬坡时受逆风作用情况,以及在垂直于行进方向上出现的受强力横风作用情况,结合风力和坡度因数,对运输稳定性进行计算。
5.根据权利要求1所述的超大型上建总段整体建造方法,其特征在于,在吊装之前,对吊装结构的强度进行校核。
6.根据权利要求1所述的超大型上建总段整体建造方法,其特征在于,在分段划分阶段至吊装阶段的过程中,收集数据。
CN202010304871.8A 2020-04-17 2020-04-17 一种超大型上建总段整体建造方法 Pending CN111422317A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010304871.8A CN111422317A (zh) 2020-04-17 2020-04-17 一种超大型上建总段整体建造方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010304871.8A CN111422317A (zh) 2020-04-17 2020-04-17 一种超大型上建总段整体建造方法

Publications (1)

Publication Number Publication Date
CN111422317A true CN111422317A (zh) 2020-07-17

Family

ID=71553981

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010304871.8A Pending CN111422317A (zh) 2020-04-17 2020-04-17 一种超大型上建总段整体建造方法

Country Status (1)

Country Link
CN (1) CN111422317A (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112623148A (zh) * 2020-12-23 2021-04-09 大连中远海运重工有限公司 船舶生活区建造及合拢工艺方法
CN113581419A (zh) * 2021-09-03 2021-11-02 上海外高桥造船有限公司 船舶承载装置
CN117184359A (zh) * 2023-08-07 2023-12-08 中交第四航务工程局有限公司 一种塔楼的吊装方法及吊装设备总成

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU472848A1 (ru) * 1973-04-09 1975-06-05 Предприятие П/Я А-7102 Способ изготовлени судовых надстроек
US4226203A (en) * 1978-09-25 1980-10-07 Pullman Incorporated Floatable concrete pallet for lifting and bearing heavy loads
CN103010404A (zh) * 2012-12-20 2013-04-03 广州中船黄埔造船有限公司 一种铝合金上层建筑分段总组方法
CN103057661A (zh) * 2011-10-21 2013-04-24 上海江南长兴重工有限责任公司 船舶上层建筑整体吊装工艺
CN109334858A (zh) * 2018-09-05 2019-02-15 中国葛洲坝集团机械船舶有限公司 一种船舶上层建筑建造的方法
CN110077520A (zh) * 2019-04-30 2019-08-02 上海外高桥造船有限公司 一种散货船上建分段翻身用主钩吊马布置结构

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU472848A1 (ru) * 1973-04-09 1975-06-05 Предприятие П/Я А-7102 Способ изготовлени судовых надстроек
US4226203A (en) * 1978-09-25 1980-10-07 Pullman Incorporated Floatable concrete pallet for lifting and bearing heavy loads
CN103057661A (zh) * 2011-10-21 2013-04-24 上海江南长兴重工有限责任公司 船舶上层建筑整体吊装工艺
CN103010404A (zh) * 2012-12-20 2013-04-03 广州中船黄埔造船有限公司 一种铝合金上层建筑分段总组方法
CN109334858A (zh) * 2018-09-05 2019-02-15 中国葛洲坝集团机械船舶有限公司 一种船舶上层建筑建造的方法
CN110077520A (zh) * 2019-04-30 2019-08-02 上海外高桥造船有限公司 一种散货船上建分段翻身用主钩吊马布置结构

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
叶飞等: "FPSO超大型上层建筑陆地转运方案分析", 《船海工程》 *
吕俊兵: "新型吊排在上层建筑吊装中的应用", 《中国水运》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112623148A (zh) * 2020-12-23 2021-04-09 大连中远海运重工有限公司 船舶生活区建造及合拢工艺方法
CN113581419A (zh) * 2021-09-03 2021-11-02 上海外高桥造船有限公司 船舶承载装置
CN117184359A (zh) * 2023-08-07 2023-12-08 中交第四航务工程局有限公司 一种塔楼的吊装方法及吊装设备总成

Similar Documents

Publication Publication Date Title
CN111422317A (zh) 一种超大型上建总段整体建造方法
US20090191028A1 (en) Loading/unloading system for container terminal
CN110466680A (zh) 一种双排舱型船总段的搭载方法
CN107244382A (zh) 绑扎桥与集装箱船的组装方法
CN102602712A (zh) 一种钢箱梁节段滚装装船的方法
CN110182313B (zh) 30万吨浮式生产储油轮艏货舱舷侧总段异地总组工艺
CN103693170A (zh) 一种漂浮式海上风电组装平台及用该平台组装海上风机的方法
CN103640909B (zh) 大型构件滚装装船方法
CN102530582A (zh) 用于大型装船机整机上岸的方法
CN203359820U (zh) 一种用于集装箱装卸的双层岸桥
CN115874594B (zh) 一种海洋升压站平移接载系统及其平移接载方法
CN202765875U (zh) 超大轨距起重机运输设备
CN105667709A (zh) 一种船体制造方法
CN103129984A (zh) 细长结构模块的叠加固定及运输工艺
CN106522095B (zh) 一种桁架节段场内多向运转方法
CN110937424A (zh) 海上升压站上部运输方法
CN104310235A (zh) 海工生活平台上建整体吊运方法
CN103693168B (zh) 海上lng储罐的水上运输系统
CN112706903A (zh) 船台及船舶转移方法
CN113799940B (zh) 利用集中力模拟集装箱载荷进行垂向静水剪力计算的方法
CN218664413U (zh) 一种华龙一号堆型装卸料机的试验台架
CN219447249U (zh) 一种适用于海上运输的组合式支墩结构
CN215972029U (zh) 底部连接结构
CN103303805A (zh) 一种用于集装箱装卸的双层岸桥
EP4053012A1 (en) Integrated disassembly system and disassembly method for large offshore structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20200717

RJ01 Rejection of invention patent application after publication