CN111411770A - Unit type jig frame sliding support frame - Google Patents

Unit type jig frame sliding support frame Download PDF

Info

Publication number
CN111411770A
CN111411770A CN201910011636.9A CN201910011636A CN111411770A CN 111411770 A CN111411770 A CN 111411770A CN 201910011636 A CN201910011636 A CN 201910011636A CN 111411770 A CN111411770 A CN 111411770A
Authority
CN
China
Prior art keywords
sliding
jig
frame
formwork
unit type
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910011636.9A
Other languages
Chinese (zh)
Inventor
张小平
张向洪
余震
马建光
王琅
迟宝新
张波
鲁英伟
王刚
徐刘净
王丽丽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Zhongtian North Construction Co.,Ltd.
Beijing Zhongwan Construction Co.,Ltd.
Hebei Yitian Construction Technology Co.,Ltd.
Original Assignee
Beijing Zhongwan Construction Co ltd
Hebei Yitian Construction Technology Co ltd
Zhongtian Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Zhongwan Construction Co ltd, Hebei Yitian Construction Technology Co ltd, Zhongtian Construction Group Co Ltd filed Critical Beijing Zhongwan Construction Co ltd
Priority to CN201910011636.9A priority Critical patent/CN111411770A/en
Publication of CN111411770A publication Critical patent/CN111411770A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G11/00Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs
    • E04G11/06Forms, shutterings, or falsework for making walls, floors, ceilings, or roofs for walls, e.g. curved end panels for wall shutterings; filler elements for wall shutterings; shutterings for vertical ducts
    • E04G11/20Movable forms; Movable forms for moulding cylindrical, conical or hyperbolical structures; Templates serving as forms for positioning blocks or the like
    • E04G11/22Sliding forms raised continuously or step-by-step and being in contact with the poured concrete during raising and which are not anchored in the hardened concrete; Arrangements of lifting means therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)

Abstract

The invention discloses a unit type jig frame sliding support frame, relates to the technical field of building construction formwork support frames, and is particularly suitable for a construction method of a roof formwork support frame system with an ultrahigh and ultra-thick frame structure. The method solves the technical problems that the efficiency of workers for building full formwork supporting frames on the top plate of the ultrahigh frame structure is seriously reduced, the workers are repeatedly built, the labor cost investment is large, and the method can save the engineering cost and shorten the construction period on the premise of ensuring the safety of a structural formwork supporting system. The technical scheme is characterized in that 1, the integral movement and turnover use of a formwork support are realized by arranging a sliding jig; 2. calculating and analyzing the stress and the strain of the section steel by adopting finite element software on the unit type sliding jig; 3. arranging a traction device to provide sliding power; 4. the arrangement of the formwork support frame needs to meet the requirement of sliding; the method is mainly used for construction of the top plate formwork support of the frame structure of the building engineering.

Description

Unit type jig frame sliding support frame
Technical Field
The invention relates to the technical field of building construction formwork support frames, in particular to a construction method of a roof formwork support frame system with an ultrahigh and ultra-thick frame structure.
Background
Along with the development of the building industry, structural design is changing to the direction of standardization, and the reproducibility is strong for structural design such as industrial factory buildings, garages, and the like, so how to improve the utilization ratio of turnover materials in construction for this type of project, and reducing the labor cost is the direction that construction enterprises need to explore, the construction of erecting full-hall formwork support frames is adopted for the framework structure roof formwork tradition, the turnover material input is huge, and need to be dismantled and erected many times, the labor cost is large, the construction efficiency of the full-hall formwork support frame worker for the ultrahigh framework structure roof is seriously reduced, and the labor cost is repeatedly erected, the labor cost input is larger, and the template support system which ensures the safety of the framework formwork support system is designed, the engineering cost is saved, and the engineering period is shortened.
Disclosure of Invention
The invention aims to solve the technical problem of providing a top plate formwork support sliding technology, which is simple and feasible in construction, safe and reliable in technology, capable of greatly saving turnover materials and labor input, greatly reducing the construction cost of engineering and shortening the construction period of the engineering.
In order to solve the technical problems, the invention adopts the following technical scheme: the utility model provides a unit formula bed-jig support frame that slides, includes unit formula bed-jig, a formwork system, traction equipment, the mode is set up to the formwork adoption console mode to set up adjustable oil support base under every pole setting, unit formula bed-jig adopts shaped steel to connect, unit formula bed-jig adopts the tanlet to provide the ability of sliding, unit formula bed-jig strong point adopts adjustable oil support to support, the formwork sets up the arrangement that needs carry out the bridging, guarantees support body overall stability, traction equipment adopts the hoist engine to provide horizontal pulling force.
Preferably, the unit type jig frame is connected by bolts by using section steel.
Preferably, the unit type jig and the small tank are fixed in a mechanical mode.
Preferably, the support points on the jig are bolted to the jig section steel.
Preferably, the supporting points on the jig frame are required to be arranged at the end parts of the cross rods of the formwork support body, so that the formwork support body is ensured not to deform in the sliding process.
The invention also provides a construction method of the unit type sliding support frame, which comprises the following steps:
the method comprises the following steps: and planning a sliding area and a sliding route according to a drawing, and arranging the formwork support.
Step two: and (3) adopting finite element software to calculate and analyze the stress and the strain of the unit type sliding jig frame.
Step three: and manufacturing a unit type sliding jig frame.
Step four: and (4) erecting a formwork support, and pouring the top plate concrete after acceptance inspection.
Step five: and after the strength of the concrete is set up to meet the design requirement, removing the upper frame body of the formwork support.
Step six: the sliding jig frame is installed in place, so that the formwork support body is suspended. And simultaneously, fixing the traction equipment and pulling and connecting the traction equipment with the jig frame.
Step seven: and (4) sliding according to a preset route, and performing next area construction after the sliding is finished, so that the circulation is realized.
According to the technical scheme, the unit type jig frames are integrally connected through the assembling bolts, field operation is convenient, integrity is good, integral stress analysis is carried out through finite element software, safety of the sliding support frame is guaranteed, stable sliding capacity is provided through the small tank, and the frame body is guaranteed to move stably. The application of the sliding formwork support technology reduces the input of turnover materials and labor cost, thereby greatly reducing the engineering construction cost.
Description of the drawings:
the invention is further described with reference to the accompanying drawings and the detailed description below:
FIG. 1 is a schematic plan view of an embodiment of the present invention;
FIG. 2 is a diagrammatic elevational view of an embodiment of the invention;
FIG. 3 is a node diagram according to an embodiment of the present invention;
fig. 4 is a schematic node diagram according to an embodiment of the present invention.
The parts in the drawings are numbered as follows: 1. i-shaped steel; 2. a small tank; 3. channel steel; 4. a connecting member; 5. an adjustable oil support; 6. connecting steel plates; 7. a bolt; 8. a fastener; 9. bolt holes.
Detailed Description
As shown in fig. 1, 2, 3, 4, a unit formula bed-jig support frame that slides, set up including unit formula bed-jig, formwork support, unit formula bed-jig adopts shaped steel 1, 3, carries out bolted connection 4, unit formula bed-jig adopts little tank 2 to provide the ability of sliding, fixes between little tank and the shaped steel, unit formula bed-jig strong point adopts adjustable oil support to support 5, and the collet adopts standard fastener 8 with shaped steel to be connected, adopt steel sheet 6 to reserve between the shaped steel girder and establish bolt hole 9, connect through bolt 7.
The invention also provides a construction method of the unit type sliding support frame, which comprises the following steps:
the method comprises the following steps: and planning a sliding area and a sliding route according to a drawing, and arranging the formwork support.
Step two: and (3) adopting finite element software to calculate and analyze the stress and the strain of the unit type sliding jig frame.
Step three: and manufacturing a unit type sliding jig frame.
Step four: and (4) erecting a formwork support, and pouring the top plate concrete after acceptance inspection.
Step five: and after the strength of the concrete is set up to meet the design requirement, removing the upper frame body of the formwork support.
Step six: the sliding jig frame is installed in place, so that the formwork support body is suspended. And simultaneously, fixing the traction equipment and pulling and connecting the traction equipment with the jig frame.
Step seven: and (4) sliding according to a preset route, and performing next area construction after the sliding is finished, so that the circulation is realized.

Claims (13)

1. The utility model provides a unit formula bed-jig support frame that slides, includes that unit formula bed-jig, a formwork set up, a formwork set adopts the console mode to set up the mode to set up adjustable oil and hold in the palm the base under every pole setting, unit formula bed-jig adopts shaped steel to connect, unit formula bed-jig adopts the little tank to provide the ability of sliding, unit formula bed-jig strong point adopts adjustable oil to hold in the palm and supports, a formwork set up the arrangement that needs to carry out the bridging, guarantees support body overall stability, traction equipment adopts the hoist engine to provide horizontal pulling force.
2. The unit type jig frame sliding support frame as claimed in claim 1, wherein: the unit type jig frame is connected by bolts by adopting section steel.
3. The unit type jig frame sliding support frame as claimed in claim 1, wherein: the unit type jig frame and the small tank are fixed in a mechanical mode.
4. The unit type jig frame sliding support frame as claimed in claim 1, wherein: and the supporting point position on the jig frame is in bolted connection with the jig frame section steel.
5. The unit type jig frame sliding support frame as claimed in claim 1, wherein: the supporting points on the jig frame need to be arranged at the end parts of the cross rods of the formwork support body.
6. The utility model provides a unit formula bed-jig support frame that slides which characterized in that includes following step:
the method comprises the following steps: and planning a sliding area and a sliding route according to a drawing, and arranging the formwork support.
7. Step two: and (3) adopting finite element software to calculate and analyze the stress and the strain of the unit type sliding jig frame.
8. Step three: and manufacturing a unit type sliding jig frame.
9. Step four: and (4) erecting a formwork support, and pouring the top plate concrete after acceptance inspection.
10. Step five: and after the strength of the concrete is set up to meet the design requirement, removing the upper frame body of the formwork support.
11. Step six: the sliding jig frame is installed in place, so that the formwork support body is suspended.
12. And simultaneously, fixing the traction equipment and pulling and connecting the traction equipment with the jig frame.
13. Step seven: and (4) sliding according to a preset route, and performing next area construction after the sliding is finished, so that the circulation is realized.
CN201910011636.9A 2019-01-07 2019-01-07 Unit type jig frame sliding support frame Pending CN111411770A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910011636.9A CN111411770A (en) 2019-01-07 2019-01-07 Unit type jig frame sliding support frame

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910011636.9A CN111411770A (en) 2019-01-07 2019-01-07 Unit type jig frame sliding support frame

Publications (1)

Publication Number Publication Date
CN111411770A true CN111411770A (en) 2020-07-14

Family

ID=71488733

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910011636.9A Pending CN111411770A (en) 2019-01-07 2019-01-07 Unit type jig frame sliding support frame

Country Status (1)

Country Link
CN (1) CN111411770A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115788034A (en) * 2022-11-14 2023-03-14 广东中凯建设工程有限公司 Be applied to base structure of high formwork

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201786002U (en) * 2010-06-02 2011-04-06 中建钢构有限公司 Sliding jig for construction of large-span steel structure
CN102691409A (en) * 2012-06-07 2012-09-26 浙江城建建设集团有限公司 HR (height regulation) heavy portal frame and temporary reinforced concrete column jointed formwork erecting device and construction method
CN106013783A (en) * 2016-07-27 2016-10-12 中国冶集团有限公司 Formwork support and erecting method thereof
WO2017084210A1 (en) * 2015-11-16 2017-05-26 苏文藏 Inner support wire saw lossless cutting and disassembling structure and construction method therefor

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN201786002U (en) * 2010-06-02 2011-04-06 中建钢构有限公司 Sliding jig for construction of large-span steel structure
CN102691409A (en) * 2012-06-07 2012-09-26 浙江城建建设集团有限公司 HR (height regulation) heavy portal frame and temporary reinforced concrete column jointed formwork erecting device and construction method
WO2017084210A1 (en) * 2015-11-16 2017-05-26 苏文藏 Inner support wire saw lossless cutting and disassembling structure and construction method therefor
CN106013783A (en) * 2016-07-27 2016-10-12 中国冶集团有限公司 Formwork support and erecting method thereof

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115788034A (en) * 2022-11-14 2023-03-14 广东中凯建设工程有限公司 Be applied to base structure of high formwork

Similar Documents

Publication Publication Date Title
CN111270852A (en) Construction method of novel formwork support system for reinforced concrete silo dome
CN110412206B (en) Movable space self-balancing reaction frame system for fire experiment and use method thereof
CN109914244B (en) Weak bracket system suitable for high-tower reinforced concrete combined beam steel structure installation and bottom and top plate concrete pouring and operation method thereof
CN111395532B (en) Installation and construction method for large-span half-opening elliptical spherical reticulated shell
CN111424822A (en) Support-free construction method for annular large cantilever cable bearing grid structure
CN113250468A (en) Construction method and construction structure of symmetrical cantilever steel truss of high-rise building
CN103498509A (en) Steel structure combined column system and connecting method thereof
CN111411770A (en) Unit type jig frame sliding support frame
CN203475310U (en) Formwork for concrete slabs of composite steel-concrete box girders
CN117569609A (en) Integral hoisting construction method for large-span beam string
CN109989590B (en) Auxiliary fixing device for mounting roof overlong steel beam and hoisting method of steel beam
CN214614569U (en) Steel beam column connection node for fine construction
CN212077591U (en) Component hoisting walking foundation under complex environment of large railway station house
CN211013830U (en) Be applicable to experimental loading device of T font beam column node
CN210395642U (en) Detachable assembly type steel structure building connecting node
CN110118014B (en) Exterior wall template system free of exterior scaffold and construction method thereof
CN211008666U (en) Tunnel middle partition wall template mounting structure based on top positioning device
CN210152320U (en) Bolt ball node type net rack jig frame
CN218931529U (en) Lifting device for column top steel beam
CN114351584B (en) Special-shaped steel ladle concrete upper tower column and construction method thereof
CN110593081A (en) Component hoisting walking foundation for large railway station house under complex environment and construction method
CN219386680U (en) High-speed railway station room quick column-beam connection node structure based on BIM
CN221256195U (en) Steel tower pre-assembled gap adjustable device
CN104652833A (en) Manufacturing method for fixing device for pulleys for installation and lifting of purlines of steel structure factory building
CN217998095U (en) Sectional type supports bottom shaped steel stand

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20210205

Address after: Room 266, 2nd floor, 9 Guangyuan West Street, Zhangjiawan Town, Tongzhou District, Beijing

Applicant after: Beijing Zhongtian North Construction Co.,Ltd.

Applicant after: Beijing Zhongwan Construction Co.,Ltd.

Applicant after: Hebei Yitian Construction Technology Co.,Ltd.

Address before: Dongyang, Zhejiang Province, No. 65 East Road, Wu Ning Road, Jinhua

Applicant before: ZHONGTIAN CONSTRUCTION GROUP Co.,Ltd.

Applicant before: Beijing Zhongwan Construction Co.,Ltd.

Applicant before: Hebei Yitian Construction Technology Co.,Ltd.