CN104652833A - Manufacturing method for fixing device for pulleys for installation and lifting of purlines of steel structure factory building - Google Patents

Manufacturing method for fixing device for pulleys for installation and lifting of purlines of steel structure factory building Download PDF

Info

Publication number
CN104652833A
CN104652833A CN201410856232.7A CN201410856232A CN104652833A CN 104652833 A CN104652833 A CN 104652833A CN 201410856232 A CN201410856232 A CN 201410856232A CN 104652833 A CN104652833 A CN 104652833A
Authority
CN
China
Prior art keywords
factory building
lifting
steel
structure factory
bodies
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201410856232.7A
Other languages
Chinese (zh)
Inventor
鲍文明
常冀阳
李永贵
魏新华
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Second Metallurgy Group Co Ltd
Original Assignee
China Second Metallurgy Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Second Metallurgy Group Co Ltd filed Critical China Second Metallurgy Group Co Ltd
Priority to CN201410856232.7A priority Critical patent/CN104652833A/en
Publication of CN104652833A publication Critical patent/CN104652833A/en
Pending legal-status Critical Current

Links

Landscapes

  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to a manufacturing method for a fixing device for pulleys for installation and lifting of purlines of a steel structure factory building. The manufacturing method is characterized by comprising the following steps of manufacturing four flange plate neck bodies, respectively connecting four bearing bars onto the four neck bodies, and respectively installing four right-angle couplers at the upper parts of the four bearing bars to form four longitudinal supporting bodies; fixedly connecting a hoisting plate with a hoisting hole onto the side wall of one end of one of two connecting rods to form a transverse supporting body; dividing the four longitudinal supporting bodies into pairs; fixing the flange plate neck bodies of two longitudinal supporting bodies in each longitudinal supporting body group onto a flange plate of an H-shaped steel beam of the steel structure factory building mouth to mouth, and connecting the two transverse supporting bodies with the two groups of longitudinal supporting bodies respectively through the right-angle couplers. The manufacturing method has the advantages that the application range is broad; the safety factor is high; the construction efficiency is high; the cost is low, and the construction of steel structure purlines is facilitated.

Description

The fastening devices preparation method of lifting tackle installed by steel-structure factory building purlin
Technical field
The present invention relates to the fastening devices preparation method that lifting tackle installed by a kind of steel-structure factory building purlin, belong to the realm of building construction.
Background technology
Steel-structure factory building is in work progress, and the installation of purlin adopts crane lifting, and cost is too high; Adopt pulley to lift general jig and cannot meet the fixing of all kinds pulley, cause lifting appliance scope of application when steel-structure factory building purlin promotes little, install, dismantle loaded down with trivial details problem, also happen occasionally because jig designs irrational work high above the ground accident.
Summary of the invention
The object of the invention is to solve lifting appliance scope of application when existing steel-structure factory building purlin promotes little, installing, dismantling loaded down with trivial details problem, providing a kind of steel-structure factory building purlin that the fastening devices preparation method of lifting tackle is installed.
The object of the invention is to adopt following technical scheme to realize:
The fastening devices preparation method of lifting tackle installed by steel-structure factory building purlin of the present invention, comprises the following steps:
1) make frange plate draw-in groove body, frange plate draw-in groove body is fixedly connected with bearing bar, right-angle coupler is set on the top of bearing bar, form longitudinal bracing body;
2) on the sidewall of a connecting rod one end, be fixedly connected with the lifting plate with lifting hole(eyelet), form cross binding body;
3) four longitudinal bracing bodies are one group between two, often organize the frange plate draw-in groove body of two longitudinal bracing bodies in longitudinal bracing body group by being fixed on the frange plate of steel-structure factory building H profile steel beam mouth to mouth, two cross binding bodies are connected with two groups of longitudinal bracing body groups respectively, connected mode is: one end without lifting plate of the connecting rod of cross binding body successively through two right-angle couplers in one group of longitudinal bracing body group, the bar that is rotatably connected make lifting plate plate face and horizontal plane downward.
Described two groups of longitudinal bracing body groups are arranged on same steel-structure factory building H profile steel beam, and the lifting plate of two cross binding bodies is positioned at the homonymy of steel-structure factory building H profile steel beam;
Described two groups of longitudinal bracing body groups are separately positioned on two parallel steel-structure factory building H profile steel beams, and one end that two cross binding bodies are provided with lifting plate is relative.
Advantage of the present invention is: adopt draw-in groove body as the fixture of fastening devices, using steel pipe as support member, steel-structure factory building H profile steel beam is as stressed member, again the mode that steel pipe, draw-in groove, girder steel are connected by grafting, welding, fastener is assembled, easy to assembly, connect compact, for convenience detach, recycle rate high, applied widely, safety factor is high, and efficiency of construction is high, cost is low, facilitates the construction of steelwork purlin bar.
Accompanying drawing explanation
Fig. 1 is the structural representation of invention step 1;
Fig. 2 is the structural representation of invention step 2.
Fig. 3 is the structural representation of invention step 3.
Fig. 4 is body of wall purlin mounting structure schematic diagram.
Fig. 5 is roof purline mounting structure schematic diagram.
In figure: 1-draw-in groove body; 2-bearing bar; 3-connecting rod, 4-lifts plate; 5-right-angle coupler.
Detailed description of the invention
With reference to accompanying drawing 1,2,3, the fastening devices preparation method of lifting tackle installed by steel-structure factory building purlin of the present invention, comprises the following steps:
1) make frange plate draw-in groove body 1, frange plate draw-in groove body is welded to connect bearing bar 2, connect right-angle coupler 5 at the upper weld of bearing bar, form longitudinal bracing body; Wherein: draw-in groove body plate body thickness d is identical with steel-structure factory building H profile steel beam flange plate thickness, draw-in groove height h is than 3 times of large 10mm ~ 20mm of draw-in groove body plate body thickness d, draw-in groove body width b is that the width of H profile steel beam flange plate deducts draw-in groove height h again divided by 2, draw-in groove body length L equals 1/2 of H profile steel beam flange plate width,, the centre distance bearing bar upper end 150mm of right-angle coupler;
2) on the sidewall of a connecting rod one end, be fixedly connected with the lifting plate with lifting hole(eyelet), form cross binding body; Wherein: lifting board size is the square orifice plate of the 100mmx100mm that thickness is identical with H profile steel beam flange plate thickness;
3) four longitudinal bracing bodies are one group between two, often organize the frange plate draw-in groove body of two longitudinal bracing bodies in longitudinal bracing body group by being fixed on the frange plate of steel-structure factory building H profile steel beam mouth to mouth, two cross binding bodies are connected with two groups of longitudinal bracing body groups respectively, connected mode is: one end without lifting plate of the connecting rod of cross binding body successively through two right-angle couplers in one group of longitudinal bracing body group, the bar that is rotatably connected make lifting plate plate face and horizontal plane downward; Wherein: the length that connecting rod stretches out right-angle coupler cover plate is 100mm ~ 150mm.
In the application, when promoting body of wall purlin, with reference to accompanying drawing 4, two groups of longitudinal bracing body groups are arranged on same steel-structure factory building H profile steel beam, and the lifting plate of two cross binding bodies is positioned at the homonymy of steel-structure factory building H profile steel beam, two pulleys are fixed with the lifting hole(eyelet) of lifting plate respectively, pulley just can be utilized to promote purlin.
When promoting roof purline, with reference to accompanying drawing 5, two groups of longitudinal bracing body groups are separately positioned on two parallel steel-structure factory building H profile steel beams, and one end that two cross binding bodies are provided with lifting plate is relative, two pulleys are fixed with the lifting hole(eyelet) of lifting plate respectively, pulley just can be utilized to promote purlin.
After purlin installation, fastening devices is removed.

Claims (3)

1. a fastening devices preparation method for lifting tackle installed by steel-structure factory building purlin, it is characterized in that: comprise the following steps:
1) make frange plate draw-in groove body, frange plate draw-in groove body is fixedly connected with bearing bar, right-angle coupler is set on the top of bearing bar, form longitudinal bracing body;
2) on the sidewall of a connecting rod one end, be fixedly connected with the lifting plate with lifting hole(eyelet), form cross binding body;
3) four longitudinal bracing bodies are one group between two, often organize the frange plate draw-in groove body of two longitudinal bracing bodies in longitudinal bracing body group by being fixed on the frange plate of steel-structure factory building H profile steel beam mouth to mouth, two cross binding bodies are connected with two groups of longitudinal bracing body groups respectively, connected mode is: one end without lifting plate of the connecting rod of cross binding body successively through two right-angle couplers in one group of longitudinal bracing body group, the bar that is rotatably connected make lifting plate plate face and horizontal plane downward.
2. the fastening devices preparation method of lifting tackle installed by steel-structure factory building purlin according to claim 1, it is characterized in that: described two groups of longitudinal bracing body groups are arranged on same steel-structure factory building H profile steel beam, and the lifting plate of two cross binding bodies is positioned at the homonymy of steel-structure factory building H profile steel beam.
3. the fastening devices preparation method of lifting tackle installed by steel-structure factory building purlin according to claim 1, it is characterized in that: described two groups of longitudinal bracing body groups are separately positioned on two parallel steel-structure factory building H profile steel beams, and one end that two cross binding bodies are provided with lifting plate is relative.
CN201410856232.7A 2014-12-28 2014-12-28 Manufacturing method for fixing device for pulleys for installation and lifting of purlines of steel structure factory building Pending CN104652833A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201410856232.7A CN104652833A (en) 2014-12-28 2014-12-28 Manufacturing method for fixing device for pulleys for installation and lifting of purlines of steel structure factory building

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201410856232.7A CN104652833A (en) 2014-12-28 2014-12-28 Manufacturing method for fixing device for pulleys for installation and lifting of purlines of steel structure factory building

Publications (1)

Publication Number Publication Date
CN104652833A true CN104652833A (en) 2015-05-27

Family

ID=53244416

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201410856232.7A Pending CN104652833A (en) 2014-12-28 2014-12-28 Manufacturing method for fixing device for pulleys for installation and lifting of purlines of steel structure factory building

Country Status (1)

Country Link
CN (1) CN104652833A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107503520A (en) * 2016-06-14 2017-12-22 五冶集团上海有限公司 A kind of auxiliary lifting apparatus for the lifting of steel structural plant roof system secondary member
CN112357743A (en) * 2020-10-30 2021-02-12 五冶集团上海有限公司 Manufacturing method of simple hoisting tool for purlines of factory building roof

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20090095944A1 (en) * 2007-09-26 2009-04-16 Gaines Robert G Lifting apparatus
CN201381196Y (en) * 2009-04-03 2010-01-13 中铁二十四局集团有限公司 Light hanging bracket
CN201952153U (en) * 2011-01-13 2011-08-31 中建钢构有限公司 Portable detachable hoisting equipment
CN203033703U (en) * 2012-11-30 2013-07-03 中国石油天然气股份有限公司 Detachable assembling type hanging tool
CN203333224U (en) * 2013-07-19 2013-12-11 安徽富煌钢构股份有限公司 Steel structural beam upward lifting tool

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20090095944A1 (en) * 2007-09-26 2009-04-16 Gaines Robert G Lifting apparatus
CN201381196Y (en) * 2009-04-03 2010-01-13 中铁二十四局集团有限公司 Light hanging bracket
CN201952153U (en) * 2011-01-13 2011-08-31 中建钢构有限公司 Portable detachable hoisting equipment
CN203033703U (en) * 2012-11-30 2013-07-03 中国石油天然气股份有限公司 Detachable assembling type hanging tool
CN203333224U (en) * 2013-07-19 2013-12-11 安徽富煌钢构股份有限公司 Steel structural beam upward lifting tool

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN107503520A (en) * 2016-06-14 2017-12-22 五冶集团上海有限公司 A kind of auxiliary lifting apparatus for the lifting of steel structural plant roof system secondary member
CN112357743A (en) * 2020-10-30 2021-02-12 五冶集团上海有限公司 Manufacturing method of simple hoisting tool for purlines of factory building roof

Similar Documents

Publication Publication Date Title
CN203594213U (en) Flexible assembling and disassembling bearing truss
CN109184189B (en) Construction method for conical shell silo top structure of large-diameter silo
CN203499229U (en) Operating platform for construction of elevator shaft
CN201417657Y (en) Installation device of indoor transformer
CN202627493U (en) Combined template for constructing elevator shaft
CN104358215B (en) Integrated prestress entirely assembles box module type steel trestle and makes assembly technology
CN203247868U (en) Large-span steel structure construction temporary supporting frame
CN103343639B (en) A kind of sliding mode system of efficient adjustment
CN204983173U (en) Steel construction beam -column connection node
CN202945798U (en) Overhanging type scaffold corner device
CN104652833A (en) Manufacturing method for fixing device for pulleys for installation and lifting of purlines of steel structure factory building
CN205257792U (en) Bridge crane with triangular support girder
CN202899639U (en) Concrete column structure
CN104372948A (en) Elevator shaft formwork lifting frame
CN203361596U (en) Auxiliary support of integrated lifting operation platform
CN205293909U (en) Mobilizable assembled transport auxiliary device
CN204980945U (en) Supplementary tower crane dismounting device
CN203247718U (en) Steel column butt-joint mounting device
CN210289075U (en) Adjustable elevator shaft operating platform system that can have enough to meet need
CN201952736U (en) Auxiliary pier movable bracket for assisting invariable-amplitude beam erecting crane in erecting steel box girder
CN107237515A (en) The support meanss and its application method of circular steel truss structure
CN202913356U (en) Load-bearing frame for bridge construction
CN202321919U (en) Metallic framework structure of escalator
CN202181614U (en) Steel pipe fixing device for joist steel
CN107780644B (en) Operation platform for elevator shaft construction and use method thereof

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20150527

WD01 Invention patent application deemed withdrawn after publication