CN1113282A - Method for connecting anchor-rod type supporting table - Google Patents
Method for connecting anchor-rod type supporting table Download PDFInfo
- Publication number
- CN1113282A CN1113282A CN 95106189 CN95106189A CN1113282A CN 1113282 A CN1113282 A CN 1113282A CN 95106189 CN95106189 CN 95106189 CN 95106189 A CN95106189 A CN 95106189A CN 1113282 A CN1113282 A CN 1113282A
- Authority
- CN
- China
- Prior art keywords
- former
- cushion cap
- supporting table
- rod type
- type supporting
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Images
Abstract
The joining method includes anchoring the longitudinal stressed reinforcing bars and structural reinforcing bars with bonding agent at the lateral side of the original foundation (original bearing platform) and installing an anchor-bar type bearing platform to join the original foundation and underpinnings. Advantage: no influence on the building and worker's safety, good construction quality, low construction cost, and wide application range.
Description
The present invention relates to the reinforcing of building foundation.
For the pile foundation or the excessive sedimentation of single footing generation of control built construction thing, often adopt the pile underpinning mode that the basis is reinforced.In pile underpinning, need to adopt certain method of attachment that original structure and underpinned pile are coupled together, the part-structure load is delivered on the underpinned pile reliably.More general method of attachment at present is bag pillar cushion cap method of attachment and the method for attachment of bottom-supported type cushion cap.The method of attachment of bag pillar cushion cap is the new cushion cap of casting a parcel pillar and extend to the underpinned pile top on former basis (former cushion cap), the part-structure load is delivered on the underpinned pile by new cushion cap, it is many that this method consumes material, and be only limited to former basis (former cushion cap) apart from the enough situations of ground level.The method of attachment of bottom-supported type cushion cap is that (former cushion cap) casts the new cushion cap being close to bottom, former basis (former cushion cap) and extending to the underpinned pile top below the bottom surface on former basis, the part-structure load is passed on the underpinned pile by new cushion cap, and this method cutting depth is big, construction is dangerous, quality be cannot say for sure card, construction costs height.
The objective of the invention is for pile underpinning provides a kind of construction safety, saves material, quality is easy to guarantee, cushion cap method of attachment applied widely.
Technical program of the present invention lies in: (former cushion cap) side sticks with glue agent anchoring longitudinal stress reinforcing bar and distributing bar on former basis, anchor-rod type supporting table is set connects former basis (former cushion cap) and underpinned pile.
The invention has the advantages that: construction period does not influence building and constructor's safety, and construction quality guarantees that easily construction costs is low, and the scope of application is extensive.
Further specify the operation of operating principle of the present invention and enforcement below by accompanying drawing.
Accompanying drawing 1 structure principle chart.
The K of accompanying drawing 2 accompanying drawings 1 is to view.
Among the figure: post 1, former basis (former cushion cap) 2, former stake 3, underpinned pile 4, concrete 5, longitudinal stress reinforcing bar 6, distributing bar 7, distribution reinforcement 8, new and old concrete interface 9.
Operating principle of the present invention is: the entire infrastructure load acts on former basic 2 by post 1, wherein fractional load is by the tension effect of longitudinal stress reinforcing bar 6, the pressurized effect at new and old concrete interface 9 and the effect of being cut are delivered to new cushion cap (anchor-rod type supporting table), longitudinal stress reinforcing bar 6 had both worked to be subjected to curved main muscle, work to suppress new and old concrete interface 9 crackings again, guarantee the continuity at new and old concrete interface, thereby anchor-rod type supporting table can bear and resist the moment of flexure that produces because of load action, scissors and flush shear force, and with Load Transfer to underpinned pile 4.
Enforcement operation of the present invention is as follows: the former basic side earthwork of excavation earlier, cut underpinned pile 4 pile crowns, and bore anchor hole, bury underground and anchoring longitudinal stress reinforcing bar 6 and distributing bar 7, cutter hair concrete interface 9, colligation distribution reinforcement 8, the 9 batches of cement pastes in concrete interface water and smash concrete, maintenance.
In practice of construction, former basis can sublevel or sublevel not; Former stake and underpinned pile can be various types of stakes (then not having former stake if former basis is the single footing); Anchor-rod type supporting table can all be connected with former basis at two ends, but in this case, anchoring longitudinal stress reinforcing bar should place top, and the anchoring structure reinforcing bar should place the bottom.
Claims (1)
1, a kind of method for connecting anchor-rod type supporting table is characterized in that: stick with glue agent anchoring longitudinal stress reinforcing bar and distributing bar in former basis (former cushion cap) side, anchor-rod type supporting table is set connects former basis (former cushion cap) and underpinned pile.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 95106189 CN1111627C (en) | 1995-05-17 | 1995-05-17 | Method for connecting anchor-rod type supporting table |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN 95106189 CN1111627C (en) | 1995-05-17 | 1995-05-17 | Method for connecting anchor-rod type supporting table |
Publications (2)
Publication Number | Publication Date |
---|---|
CN1113282A true CN1113282A (en) | 1995-12-13 |
CN1111627C CN1111627C (en) | 2003-06-18 |
Family
ID=5075783
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN 95106189 Expired - Fee Related CN1111627C (en) | 1995-05-17 | 1995-05-17 | Method for connecting anchor-rod type supporting table |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN1111627C (en) |
Cited By (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101922152B (en) * | 2009-06-11 | 2012-11-07 | 贵阳铝镁设计研究院有限公司 | Pile foundation structure of reinforcing pile |
CN103061364A (en) * | 2013-01-15 | 2013-04-24 | 广州市市政工程设计研究院 | Prestressed pile foundation underpinning structure and construction method thereof |
CN103726503A (en) * | 2014-01-08 | 2014-04-16 | 中铁十一局集团有限公司 | Anchor rod pile reinforcing bearing platform structure used for reinforcing deformed bridge pile and construction method thereof |
CN105155867A (en) * | 2015-09-30 | 2015-12-16 | 贵州正业工程技术投资有限公司 | Underpinning device for tunnel to pass through existing large-diameter pile building |
CN106351270A (en) * | 2016-11-16 | 2017-01-25 | 贵州正业工程技术投资有限公司 | Self-locking steel pile structure for deviation correction and reinforcement of underpinned pile foundation |
CN107237345A (en) * | 2017-06-15 | 2017-10-10 | 广州市胜特建筑科技开发有限公司 | A kind of method and system of quick control building settlement |
CN108457204A (en) * | 2018-02-10 | 2018-08-28 | 北京工业大学 | One kind carrying out bracing means for old Bridge Foundation Lack of support |
CN108532624A (en) * | 2018-05-31 | 2018-09-14 | 广东工业大学 | A kind of chemicals tank raft foundation ruggedized construction and its preparation process |
CN112343080A (en) * | 2020-10-22 | 2021-02-09 | 湖北中建昌龙建筑技术有限公司 | Reinforcement structure based on old plant infrastructure and construction method |
CN112921962A (en) * | 2021-01-25 | 2021-06-08 | 浙江鼎固建筑技术有限公司 | Pile foundation reinforcing method |
CN113863705A (en) * | 2021-09-14 | 2021-12-31 | 建研地基基础工程有限责任公司 | Method for underpinning and reinforcing existing building based on static pressure jet grouting steel pipe pile and application device |
Families Citing this family (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN100383349C (en) * | 2005-09-06 | 2008-04-23 | 贵阳铝镁设计研究院 | Method for reconstructing operation platform column foundation in existing workshop |
CN100396855C (en) * | 2005-09-07 | 2008-06-25 | 贵阳铝镁设计研究院 | Existing one-storied factory continuation end foundation construction method |
CN100464035C (en) * | 2007-10-17 | 2009-02-25 | 中铁十八局集团有限公司 | Metro engineering pile foundation underpinning construction method |
-
1995
- 1995-05-17 CN CN 95106189 patent/CN1111627C/en not_active Expired - Fee Related
Cited By (12)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN101922152B (en) * | 2009-06-11 | 2012-11-07 | 贵阳铝镁设计研究院有限公司 | Pile foundation structure of reinforcing pile |
CN103061364A (en) * | 2013-01-15 | 2013-04-24 | 广州市市政工程设计研究院 | Prestressed pile foundation underpinning structure and construction method thereof |
CN103726503A (en) * | 2014-01-08 | 2014-04-16 | 中铁十一局集团有限公司 | Anchor rod pile reinforcing bearing platform structure used for reinforcing deformed bridge pile and construction method thereof |
CN103726503B (en) * | 2014-01-08 | 2015-07-08 | 中铁十一局集团有限公司 | Anchor rod pile reinforcing bearing platform structure used for reinforcing deformed bridge pile and construction method thereof |
CN105155867A (en) * | 2015-09-30 | 2015-12-16 | 贵州正业工程技术投资有限公司 | Underpinning device for tunnel to pass through existing large-diameter pile building |
CN106351270A (en) * | 2016-11-16 | 2017-01-25 | 贵州正业工程技术投资有限公司 | Self-locking steel pile structure for deviation correction and reinforcement of underpinned pile foundation |
CN107237345A (en) * | 2017-06-15 | 2017-10-10 | 广州市胜特建筑科技开发有限公司 | A kind of method and system of quick control building settlement |
CN108457204A (en) * | 2018-02-10 | 2018-08-28 | 北京工业大学 | One kind carrying out bracing means for old Bridge Foundation Lack of support |
CN108532624A (en) * | 2018-05-31 | 2018-09-14 | 广东工业大学 | A kind of chemicals tank raft foundation ruggedized construction and its preparation process |
CN112343080A (en) * | 2020-10-22 | 2021-02-09 | 湖北中建昌龙建筑技术有限公司 | Reinforcement structure based on old plant infrastructure and construction method |
CN112921962A (en) * | 2021-01-25 | 2021-06-08 | 浙江鼎固建筑技术有限公司 | Pile foundation reinforcing method |
CN113863705A (en) * | 2021-09-14 | 2021-12-31 | 建研地基基础工程有限责任公司 | Method for underpinning and reinforcing existing building based on static pressure jet grouting steel pipe pile and application device |
Also Published As
Publication number | Publication date |
---|---|
CN1111627C (en) | 2003-06-18 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN1111627C (en) | Method for connecting anchor-rod type supporting table | |
CN101310078B (en) | Apparatus for fixing a wale | |
CN110130367A (en) | It is a kind of for the precast lattice beam of slope reinforcement and its production and construction method | |
US4558545A (en) | Foundation for a mast, supporting pillar, and the like | |
CN101010464A (en) | Foundation structure of steel tower | |
CN108518084A (en) | The additional structure and method that shear wall is removed in frame-shear-wall structure | |
CN102392416A (en) | Pier-beam temporary consolidation post-installed fastening system construction method | |
CN2756708Y (en) | Full length adhesive prestress anchor rod | |
CN1619063A (en) | Post stress method stake body prestressed antislid stake and construction method | |
CN100441782C (en) | Innovative prestressed scaffolding system | |
DK1402119T3 (en) | Foundation in water | |
JPH086291B2 (en) | Widening method of road bridge | |
ES8701273A1 (en) | Foundation arrangement. | |
CN211498887U (en) | Broken rock soil body cutting slope flexible retaining reinforced structure | |
CN1137088A (en) | Construction method for soil bulkhead structure | |
JP3760365B2 (en) | Core material erection device | |
CN109868837A (en) | A kind of rib column formula anchored bolt retaining wall of no cutting | |
CN109972673A (en) | Retaining wall reinforcement structure and the inclined active restorative procedure of retaining wall | |
CN1331366A (en) | High-pressure grouting technique for stiffening slope of anchor cable (rod) system | |
RU188064U1 (en) | The unit for coupling the reinforcement piles with the foundation plate | |
Rowan et al. | Olifants river bridge widening | |
KR20100029425A (en) | Concrete plate for reinforcing ground slope by using soil nail and reinforcing method using thereof | |
CN212836863U (en) | Combined supporting pile for civil engineering | |
JP2886376B2 (en) | Anchor structure of pile head | |
CN219261294U (en) | Assembled rainwater grate composite structure |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
C06 | Publication | ||
PB01 | Publication | ||
C14 | Grant of patent or utility model | ||
GR01 | Patent grant | ||
C19 | Lapse of patent right due to non-payment of the annual fee | ||
CF01 | Termination of patent right due to non-payment of annual fee |