CN108518084A - The additional structure and method that shear wall is removed in frame-shear-wall structure - Google Patents

The additional structure and method that shear wall is removed in frame-shear-wall structure Download PDF

Info

Publication number
CN108518084A
CN108518084A CN201810398545.0A CN201810398545A CN108518084A CN 108518084 A CN108518084 A CN 108518084A CN 201810398545 A CN201810398545 A CN 201810398545A CN 108518084 A CN108518084 A CN 108518084A
Authority
CN
China
Prior art keywords
shear wall
shear
wall
frame
reinforced beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810398545.0A
Other languages
Chinese (zh)
Inventor
戴中剑
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 2 Group Co Ltd
Original Assignee
Shanghai Construction No 2 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 2 Group Co Ltd filed Critical Shanghai Construction No 2 Group Co Ltd
Priority to CN201810398545.0A priority Critical patent/CN108518084A/en
Publication of CN108518084A publication Critical patent/CN108518084A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/08Wrecking of buildings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Working Measures On Existing Buildindgs (AREA)

Abstract

The additional structure and method removed the invention discloses shear wall in a kind of frame-shear-wall structure, the additional structure includes reinforced beam and several junction steel plates for being set to shear wall and structural slab to be removed and crossing below junction, by shear wall below the bottom surface absolute altitude of reinforced beam be left shear wall member-retaining portion after partial demolition more than the top surface absolute altitude of structural slab, the both ends of reinforced beam anchor into the frame column at shear wall both ends, the bottom of shear wall member-retaining portion and the bottom of reinforced beam are connected by junction steel plate, form composite construction beam, the junction steel plate along reinforced beam longitudinally spaced setting.By the way that armored concrete girder construction is arranged, it can not only play the role of supporting cantilevered plate after shear wall dismounting, it is supported without temperature pier is arranged, but also it can utilize part original structure that shear wall is maintained to remove front and back structure monolithic stability, so that each layer can construct simultaneously, to accelerate construction progress, economize on resources.

Description

The additional structure and method that shear wall is removed in frame-shear-wall structure
Technical field
The present invention is applicable in the additional knot that shear wall is removed in the realm of building construction more particularly to a kind of frame-shear-wall structure Structure and method.
Background technology
As urban modernization rapidly develops, people's living standards continue to improve, part Old building cannot be satisfied society It can develop and production and living needs adhere to lasting, Green Development target, occur increasingly under city integrated planning promotion More underpinning reconstructed projects.In skyscraper, when frame-shear-wall structure is transformed into frame structure, the dismounting of shear wall is as pass Key works, both difficult, is often also required to no small cost input.
Currently, the arrangement and method for construction that shear wall is removed in frame-shear-wall structure is all first will script and shear wall from top The structural slab being connected is reinforced with temporary support, then is removed top shear wall and doed for supplement frame structure, because with shear wall phase Plate even becomes cantilevered plate after shear wall dismounting, if take multilayer while removing the arrangement and method for construction of shear wall, upper layer is interim Support can not be again by understructure plate stress, therefore shear wall needs are from top to bottom successively removed, and one layer i.e. construction one is often removed Story frame structure, successively downwards.
Though such construction method is than more conventional, construction cost is larger, and the wasting of resources, the duration is longer, is mainly manifested in:① Before shear wall is removed, the structural slab lower section being connected with shear wall needs to be reinforced with temporary support.Structural slab after avoiding shear wall from removing Overhang stress, plate self structure is damaged.Temporary support is set comparatively under structural slab, needs to put into larger cost. 2. because the structural slab being connected with shear wall becomes cantilevered plate after shear wall dismounting, upper layer temporary support can not pass through lower layer again Cantilevered plate stress, thus shear wall needs from top to bottom successively remove, often remove one layer i.e. construction works as story frame structure, successively to Under.So repeatedly working procedure replaces operation, is unfavorable for working sources allotment.3. in such arrangement and method for construction, shear wall is merely able to It successively removes, and frame structure of successively constructing, i.e., need to successively set up structure stand, casting concrete simultaneously conserves, and finally removes branch Frame continues to construct to lower layer, and the overall flow duration is longer.
Therefore, how one kind is provided construction input when can remove shear wall in larger reduction frame-shear-wall structure, really The construction quality of reconstruction structure is protected, and with economizing on resources, is sheared in frame-shear-wall structure that accelerate the duration, low-carbon construction The additional structure that wall is removed is those skilled in the art's technical problem urgently to be resolved hurrily.
Invention content
The additional structure and method removed the purpose of the present invention is to provide shear wall in a kind of frame-shear-wall structure, energy It is enough effectively to reduce in frame-shear-wall structure construction input when removing shear wall, it is ensured that the construction quality of reconstruction structure, and have It economizes on resources, accelerates the duration, low-carbon construction social benefit.
To achieve the above object, the present invention adopts the following technical scheme that:
The invention discloses a kind of for removing the additional structure that shear wall is removed in frame-shear-wall structure, is used for frame Shear wall is removed to be transformed into frame structure in frame shear wall structure, including is set to shear wall and structural slab to be removed and is crossed company Connect place lower section reinforced beam and several junction steel plates, by shear wall below the bottom surface absolute altitude of reinforced beam with It is left shear wall member-retaining portion after partial demolition more than the top surface absolute altitude of structural slab, the both ends of the reinforced beam anchor into In the frame column at shear wall both ends, the bottom surface of the bottom surface and the reinforced beam of the shear wall member-retaining portion is neat Flat, the bottom of the shear wall member-retaining portion is connect with the bottom of the reinforced beam by the junction steel plate, is formed Composite construction beam, the junction steel plate along reinforced beam longitudinally spaced setting.
Preferably, in the additional structure that shear wall is removed in above-mentioned frame-shear-wall structure, the armored concrete The width of beam≤frame column width -+200 millimeters of shear wall's thickness, and width >=400 millimeter of reinforced beam.
Preferably, in the additional structure that shear wall is removed in above-mentioned frame-shear-wall structure, the junction steel plate Width is 300 millimeters, and length=shear wall's thickness+armored concrete beam width, junction steel plate passes through a diameter of 12~22 millimeters Chemical bolt is anchored on composite construction beam, the junction steel plate along reinforced beam longitudinal direction setting spacing be 800~ 1000 millimeters, chemical bolt 8 is set on every piece of junction steel plate.
Preferably, in the additional structure that shear wall is removed in above-mentioned frame-shear-wall structure, the armored concrete The design height of beam is calculated according to frame stressing and is determined.
Preferably, in the additional structure that shear wall is removed in above-mentioned frame-shear-wall structure, work as reinforced beam After the completion of construction and maintenance, shear wall is removed range and is terminated since armored concrete beam bottom to the plate face of understructure plate.
Preferably, in the additional structure that shear wall is removed in above-mentioned frame-shear-wall structure, the list of the shear wall Side or both sides are equipped with the structural slab.
The invention also discloses the construction methods that shear wall in a kind of frame-shear-wall structure is removed, and are used for shear force of frame Shear wall is removed to be transformed into frame structure in wall construction, is removed using shear wall in frame-shear-wall structure as described above Additional structure, this method include
Step 1, in the building of existing frame-shear-wall structure, on shear wall and structural slab with reinforced beam The position of contact carries out surface dabbing processing;On the frame column of shear wall both sides for connect the position of reinforced beam according to Corresponding bar planting is arranged in the reinforcing bar distributing position of reinforced beam;The reinforcing bar of assembling reinforcement beams of concrete simultaneously makes reinforced concrete The reinforcing bar of Tu Liang is fixedly connected with bar planting, pouring reinforcement concrete beam;
Step 2, reinforced beam construction complete, by below the bottom surface absolute altitude of reinforced beam with structural slab Shear wall more than top surface absolute altitude is removed, and shear wall member-retaining portion is left;
Step 3, after the completion of shear wall is removed, to the bottom surface of shear wall member-retaining portion need to install the position of junction steel plate into Row polishes flat, and according to the bolt hole on junction steel plate, carries out unwrapping wire positioning in composite construction beam bottom, and mark, Chemical bolt is planted in the position drilling of label, installs junction steel plate after the completion, and junction steel plate is applied with combination beam concrete contact site Brush steel bonding glue finally twists solid chemical bolt.
Preferably, in the construction method that shear wall is removed in frame-shear-wall structure as described above, the shear wall Before dismounting, when shear wall unilateral side is connect with structural slab, increase reinforced beam below junction;When shear wall both sides are equal When having structural slab connection, increase reinforced beam below the junction of both sides.
Preferably, in the construction method that shear wall is removed in frame-shear-wall structure as described above, the reinforcing bar is mixed Width≤frame column width -+200 millimeters of shear wall's thickness of solidifying Tu Liang, and width >=400 millimeter of reinforced beam, institute The height for stating reinforced beam determines by the following method:Shear wall removes the bottom surface of line and reinforced beam same On horizontal plane, shear wall removes line along shear wall and is divided into shear wall member-retaining portion and shear wall dismounting part, and shear wall is torn open Except line has a domain of walker, a value is determined in the domain of walker that shear wall removes line, meanwhile, in the width of reinforced beam After degree determines, whether requirement disclosure satisfy that according to the section Accounting Framework structure stress stability of reinforced beam;If discontented Foot requires, and the height that adjustment shear wall removes line recalculates review after adjusting armored concrete depth of beam, final to determine The cross-sectional sizes of reinforced beam.
Preferably, in the construction method that shear wall is removed in frame-shear-wall structure as described above, work as reinforced concrete After the completion of native beam construction and maintenance, the Demolition Construction of each story shear wall is carried out at the same time.
The additional structure that shear wall is removed in frame-shear-wall structure provided by the invention is transformed in frame-shear-wall structure At in frame structure construction, the appropriately sized reinforced beam of increase, additional below shear wall and plate to be removed junction Reinforced beam is combined into construction beam with the reinforcing of shear wall member-retaining portion, after shear wall is removed, it is ensured that improved frame Structure entirety stability under loading, to save the reinforced beam for newly doing larger cross-section after shear wall is all removed.As it can be seen that passing through Reinforced beam is set, structure safety can be ensured when shear wall is removed.In addition, additional reinforced beam can be each Story shear wall is all constructed before removing and is finished, i.e., each layer can construct simultaneously, and can play the role of support construction plate, each layer structure After the support by reinforced beam, each story shear wall can be removed plate simultaneously, not influence structure entirety stress, without another The supporting rack of setting structure plate accelerates construction progress to reduce construction cost again outside, economizes on resources, is applied with green low-carbon Work advantage, and then make it that there is easy to operate, work compared with shear wall Demolition Construction method in traditional frame-shear-wall structure The high feature of sequence simplification, reliability, implementation.
In conclusion the additional structure of shear wall dismounting and method and general prior art phase in this frame-shear-wall structure Than:
1, using the construction method of additional bar beams of concrete, with its structure stress, excellent convenient for the technological synthesis of construction Point, with traditional shear wall remove, Structural-transformconstruction construction method have it is easy to operate, low in resources consumption, process is simplified, reliability, The high feature of implementation.
2, in the utility model construction technology, increase reinforced beam setting, support is reinforced without being arranged under cantilevered plate, and In multilayer shear wall demolishing process, each layer each process can be carried out at the same time, between not by construction cross influence, be convenient for working sources Allotment.
3, in the utility model construction technology, in the composition of composite construction beam, the original shear wall structure of member-retaining portion is reduced to original Structured destruction connects into stress entirety by constructing steel plate with reinforced beam, preferably protects original structure, have Good economical synthesis benefit.
Description of the drawings
The additional structure that shear wall is removed in the frame-shear-wall structure of the present invention is provided by embodiment below and attached drawing.
Fig. 1 be one embodiment of the invention frame-shear-wall structure in the facade structures of additional structure removed of shear wall show It is intended to;
Fig. 2 is that the horizontal layout of junction steel plate in one embodiment of the invention, the reinforcing bar of reinforced beam and bar planting is shown It is intended to;
The step of Fig. 3 is the construction method that shear wall is removed in the frame-shear-wall structure using one embodiment of the invention one When structural schematic diagram;
The step of Fig. 4 is the construction method that shear wall is removed in the frame-shear-wall structure using one embodiment of the invention two When structural schematic diagram;
The step of Fig. 5 is the construction method that shear wall is removed in the frame-shear-wall structure using one embodiment of the invention three When structural schematic diagram.
In figure, 1, reinforced beam;2, shear wall to be removed;3, shear wall member-retaining portion;4, structural slab;5, shear wall Remove part;6, frame column;7, junction steel plate;8, chemical bolt;9, the reinforcing bar of reinforced beam;10, bar planting.
Specific implementation mode
The additional structure work removed to shear wall in the frame-shear-wall structure of the present invention is further retouched in detail below It states.
Please refer to Fig.1 to Fig. 2, the invention discloses it is a kind of for remove shear wall in frame-shear-wall structure remove it is attached Add structure, for removing the shear wall to be removed 2 in shear wall, that is, original structure in frame-shear-wall structure to be transformed into frame Structure, if including being set to reinforced beam 1 and involvement that shear wall 2 and structural slab 4 to be removed cross below junction Connect steel plate, by shear wall below the bottom surface absolute altitude of reinforced beam 1 with partial demolition more than the top surface absolute altitude of structural slab 4 It is left shear wall member-retaining portion 3 afterwards, the both ends of the reinforced beam 1 anchor into the frame column 6 at shear wall both ends, described to cut The bottom surface of power wall member-retaining portion 3 is flushed with the bottom surface of the reinforced beam 1, the bottom of the shear wall member-retaining portion 3 Portion is connect with the bottom of the reinforced beam 1 by the junction steel plate, and composite construction beam, the lower junction steel plate are formed Along the longitudinally spaced setting of reinforced beam 1.
The additional structure that shear wall is removed in the frame-shear-wall structure of the present invention, for being sheared in frame-shear-wall structure Wall 2 needs to remove the position 4 for being transformed into frame structure, is crossed under junction by being set to shear wall and structural slab 4 to be removed The reinforced beam 1 of side, the both ends of the reinforced beam 1 anchor into the frame column 6 at shear wall both ends, the reinforcing bar added Beams of concrete 1 can play the role of supporting cantilevered plate 5 and form frame entirety rock-steady structure.1 He of the reinforced beam 3 shear wall member-retaining portion 3 of shear wall member-retaining portion is attached by the junction steel plate 7 being arranged in its bottom.That is, steel Concrete Beam Reinforced 1 and 3 combination of shear wall member-retaining portion are whole to be connected into 1 bottom of beam and 3 bottom of shear wall setting steel plate 7 Body.Composite construction beam belongs to conjunction old and new concret, to ensure bond quality, reaches cooperative bearing effect, is connected using steel plate 7 Globality can be enhanced and play the stress characteristic of beam.
Preferably, in the additional structure that shear wall is removed in above-mentioned frame-shear-wall structure, the armored concrete The width of beam 1≤6 width of frame column -+200 millimeters of shear wall's thickness, and width >=400 millimeter of reinforced beam 1.Limitation The purpose of the section minimum widith of reinforced beam 1 is in order to which the shear wall 3 for ensureing reinforced beam 1 and not removing is constituted There is enough force stabilities after combination beam.The maximum width in 1 section of restraint beam is to ensure that reinforced beam 1 is anchored in frame On trestle 6, limitation beam-ends exceeds the overhanging section width of 6 width of frame column, avoids the eccentric force for causing frame column 6 too big, and Influence frame entirety stability.
Preferably, in the additional structure that shear wall is removed in above-mentioned frame-shear-wall structure, the junction steel plate 7 Width is 300 millimeters, length=1 width of shear wall's thickness+reinforced beam, under the premise of ensuring steel plate stiffness by itself, The usage amount of steel in junction steel plate 7 is reduced as far as possible.Junction steel plate 7 passes through 8 anchor of a diameter of 12~22 millimeters of chemical bolts It is fixed on composite construction beam, under the premise of ensureing that steel plate and combination beam there are enough anchor forces, reduce chemical bolt as far as possible 8 diameters.The junction steel plate 7 is 800~1000 millimeters along the longitudinal setting spacing of reinforced beam 1, every piece of connection Chemical bolt 8 is set on steel plate 7, is anchored in respectively in shear wall member-retaining portion 3 and reinforced beam 1, to ensure group Under the premise of closing beam entirety bond strength, the usage amount of junction steel plate 7 is reduced as far as possible.
Preferably, in the additional structure that shear wall is removed in above-mentioned frame-shear-wall structure, the armored concrete The design height of beam 1 is calculated according to frame stressing and is determined.Computing Principle is:Shear wall removes line and 1 lower end of reinforced beam In same level, and shear wall removes height with certain floating scalability, therefore removes height in shear wall and floating A value is determined in value, meanwhile, after the cross-sectional width of reinforced beam 1 determines, frame is calculated according to 1 section of reinforced beam Whether frame force stability disclosure satisfy that requirement.If being unsatisfactory for requiring, adjustment shear wall removes height, that is, adjusts armored concrete After depth of beam, review is recalculated, the final cross-sectional sizes for determining reinforced beam.
Preferably, after the completion of 1 construction and maintenance of reinforced beam, shear wall removes range from 1 bottom of reinforced beam Start to the plate face of understructure plate 4 to terminate, i.e., shear wall remove ranging from 1 bottom of reinforced beam to understructure plate 4 it Between.Multilayer shear wall, which is removed, repeats above range, and can be carried out at the same time, and saves the duration.
Preferably, in the additional structure that shear wall is removed in above-mentioned frame-shear-wall structure, the list of the shear wall 2 Side or both sides are equipped with the structural slab 4.It is cantilevered plate without the structural slab 4 under any holding state after shear wall is removed.Shearing Before wall 2 is removed, can there be above structure plate 4 in unilateral or both sides.2 unilateral side of shear wall has when being connect with structural slab 4, under junction Fang Zengjia reinforced beams 1.When there are the connection of structural slab 4 in 2 both sides of shear wall, increase reinforcing bar below the junction of both sides Beams of concrete 1 ensures that structure on two sides plate 4 has enough bearings after shear wall dismounting, maintains frame system stability.
In conclusion the additional structure that shear wall is removed in frame-shear-wall structure provided by the invention, in shear force of frame Wall construction is transformed into frame structure construction, increases appropriately sized reinforced concrete below 4 junction of shear wall 2 and plate to be removed Native beam 1, after shear wall is removed, additional bar beams of concrete 1 is combined into construction beam with the reinforcing of shear wall member-retaining portion 3, it is ensured that Improved frame structure entirety stability under loading, to save the armored concrete for newly doing larger cross-section after shear wall is all removed Beam.As it can be seen that by the way that reinforced beam 1 is arranged, structure safety can be ensured when shear wall is removed.In addition, additional reinforcing bar Beams of concrete 1 can all construction finishes before each story shear wall 2 is removed, i.e., each layer can construct simultaneously, and can play support construction The effect of plate, after the support by reinforced beam 1, each story shear wall can be removed each layer structural slab simultaneously, not influence Structure entirety stress, the supporting rack without other setting structure plate again are accelerated construction progress to reduce construction cost, are saved Resource has the advantages that green low-carbon construction, and then makes itself and shear wall Demolition Construction method in traditional frame-shear-wall structure Compared to having the characteristics that easy to operate, process is simplified, reliability, implementation are high.
It please refers to Fig.1 to Fig. 5, the invention also discloses the construction parties that shear wall in a kind of frame-shear-wall structure is removed Method, for removing shear wall in frame-shear-wall structure to be transformed into frame structure, using frame-shear wall as described above The additional structure that shear wall is removed in structure, this method include
Step 1 asks emphasis refering to Fig. 3, in the building of existing frame-shear-wall structure, on shear wall and structural slab The position contacted with reinforced beam carries out surface dabbing processing, is preferably contacted with original structure with sharp reinforced beam 1. For connecting the position of reinforced beam according to 9 distributing position of reinforcing bar of reinforced beam on the frame column of shear wall both sides Corresponding bar planting 10 is set;The reinforcing bar 9 of assembling reinforcement beams of concrete simultaneously makes the reinforcing bar 9 of reinforced beam be fixed with bar planting 10 Connection, pouring reinforcement concrete beam.Each layer can construct simultaneously completes reinforced beam 1, to improve construction efficiency.
Preferably, the width of reinforced beam 1≤frame column width -+200 millimeters of shear wall's thickness, and reinforced concrete Width >=400 millimeter of native beam 1.1 section minimum widith of restraint beam is the shear wall 3 for ensureing reinforced beam 1 and not removing There is enough force stabilities after constituting combination beam.The maximum width in 1 section of restraint beam is to ensure that reinforced beam 1 anchors In on frame column 6, limitation beam-ends exceeds the overhanging section width of 6 width of frame column, avoid causing frame column 6 too big it is eccentric by Power, and influence frame entirety stability.
Preferably, 1 design height of the reinforced beam is calculated according to frame stressing and is determined.Computing Principle is:Shearing Wall removes line and 1 lower end of reinforced beam in same level, and shear wall removes height and there is certain floating to adjust Property, therefore remove height in shear wall and determine a value in float value, meanwhile, after the cross-sectional width of reinforced beam 1 determines, Requirement whether is disclosure satisfy that according to 1 section Accounting Framework force stability of reinforced beam.If being unsatisfactory for requiring, adjustment shearing Wall removes height, that is, after adjusting armored concrete depth of beam, recalculates review, final to determine that the section of reinforced beam is big It is small.
Preferably, after the cantilevered plate refers to shear wall dismounting, without the structural slab under any holding state.Shear wall 2 is torn open Before removing, can there be above structure plate 4 in unilateral or both sides.2 unilateral side of shear wall has when being connect with structural slab 4, increases below junction Adding reinforced concrete beam 1.When there are the connection of structural slab 4 in 2 both sides of shear wall, increase reinforced concrete below the junction of both sides Native beam 1 ensures that structure on two sides plate 4 has enough bearings after shear wall dismounting, maintains frame system stability.
Step 2 asks emphasis refering to Fig. 4, and reinforced beam construction is completed, will be in the bottom surface absolute altitude of reinforced beam It is removed below with shear wall more than the top surface absolute altitude of structural slab, is left shear wall member-retaining portion 3.That is, reinforced concrete Tu Liang constructions are completed, and the overhead height for removing 5 range of shear wall is determined according to 1 bottom level of reinforced beam, remove shearing The bottom of 5 range of wall to understructure plate 4 top surface absolute altitude.Preferably, it after the completion of 1 construction and maintenance of reinforced beam, cuts Power wall is removed range and is terminated since 1 bottom of reinforced beam to 4 face of lower plywood, and multilayer shear wall, which is removed, repeats above range, And can be carried out at the same time, save the duration.
Step 3 asks emphasis refering to Fig. 5, after i.e. shear wall removes the dismounting of part 5 after the completion of shear wall is removed, to shear wall The position that the bottom surface of member-retaining portion 3 need to install junction steel plate 7 polishes flat, according to the bolt hole on junction steel plate 7, Composite construction beam bottom carries out unwrapping wire positioning, and marks, and in the position of label, chemical bolt 8 is planted in drilling, and installation after the completion connects Steel plate 7, junction steel plate 7 and combination beam concrete contact site brushing steel bonding glue are connect, solid chemical bolt 8 is finally twisted.
Preferably, reinforced beam 1 and 3 combination of shear wall member-retaining portion are in 3 bottom of 1 bottom of beam and shear wall Setting steel plate 7 connects integral.Combination beam belongs to conjunction old and new concret, to ensure bond quality, reaches cooperative bearing effect, The stress characteristic that can enhance globality and play beam is connected using steel plate 7.
Preferably, 1 bottom of the beam connects junction steel plate 7 used with 3 bottom of shear wall, and width is 300 millimeters, length 2 thickness of=shear wall+1 width of reinforced beam, under the premise of ensuring steel plate stiffness by itself, to reduce connection steel as far as possible The usage amount of steel in plate 7.Junction steel plate 7 is anchored in by 12~diameter of diameter, 22 chemical bolt 8 on composite construction beam, to protect Under the premise of card junction steel plate 7 there are enough anchor forces with combination beam, reduce chemical bolt diameter as far as possible.Junction steel plate 7 are arranged 800~1000 millimeters of spacing along beam direction, and every block of steel plate is arranged chemical bolt 8, is anchored in shear wall reserve part respectively Divide on 3 and reinforced beam 1, under the premise of ensuring combination beam entirety bond strength, to reduce junction steel plate as far as possible Usage amount.
Preferably, in the construction method that shear wall is removed in frame-shear-wall structure as described above, the shear wall Before dismounting, when shear wall unilateral side is connect with structural slab, increase reinforced beam below junction;When shear wall both sides are equal When having structural slab connection, increase reinforced beam below the junction of both sides.
Preferably, in the construction method that shear wall is removed in frame-shear-wall structure as described above, the reinforcing bar is mixed Width≤frame column width -+200 millimeters of shear wall's thickness of solidifying Tu Liang, and width >=400 millimeter of reinforced beam, institute The height for stating reinforced beam determines by the following method:Shear wall removes the bottom surface of line and reinforced beam same On horizontal plane, shear wall removes line along shear wall and is divided into shear wall member-retaining portion 3 and shear wall dismounting part 5, and shear wall Removing line has a domain of walker, and a value is determined in the domain of walker that shear wall removes line, meanwhile, in reinforced beam After width determines, whether requirement disclosure satisfy that according to the section Accounting Framework structure stress stability of reinforced beam;If no It meets the requirements, the height that adjustment shear wall removes line recalculates review after adjusting armored concrete depth of beam, final true Determine the cross-sectional sizes of reinforced beam.
Preferably, in the construction method that shear wall is removed in frame-shear-wall structure as described above, work as reinforced concrete After the completion of native beam construction and maintenance, the Demolition Construction of each story shear wall is carried out at the same time.
The additional structure that shear wall is removed in frame-shear-wall structure provided by the invention is transformed in frame-shear-wall structure At in frame structure construction, increase appropriately sized reinforced beam, shear wall below shear wall and plate to be removed junction After dismounting, additional bar beams of concrete is combined into construction beam with the reinforcing of shear wall member-retaining portion, it is ensured that improved frame knot Structure entirety stability under loading, to save the reinforced beam for newly doing larger cross-section after shear wall is all removed.As it can be seen that by setting Reinforced beam is set, structure safety can be ensured when shear wall is removed.In addition, additional reinforced beam can be in each layer Shear wall is all constructed before removing and is finished, i.e., each layer can construct simultaneously, and can play the role of support construction plate, each layer structural slab After the support by reinforced beam, each story shear wall can be removed simultaneously, not influence structure entirety stress, without in addition The supporting rack of setting structure plate again accelerates construction progress to reduce construction cost, economizes on resources, and has green low-carbon construction Advantage, and then make it that there is easy to operate, process compared with shear wall Demolition Construction method in traditional frame-shear-wall structure The high feature of simplification, reliability, implementation.
In conclusion in this frame-shear-wall structure shear wall remove construction method and additional constructing structure with it is general existing Technology is compared:
1, using the construction method of additional bar beams of concrete, with its structure stress, excellent convenient for the technological synthesis of construction Point, with traditional shear wall remove, Structural-transformconstruction construction method have it is easy to operate, low in resources consumption, process is simplified, reliability, The high feature of implementation.
2, in the utility model construction technology, increase reinforced beam setting, support is reinforced without being arranged under cantilevered plate, and In multilayer shear wall demolishing process, each layer each process can be carried out at the same time, between not by construction cross influence, be convenient for working sources Allotment.
3, in the utility model construction technology, in the composition of composite construction beam, the original shear wall structure of member-retaining portion is reduced to original Structured destruction connects into stress entirety by constructing steel plate with reinforced beam, need not newly do structure again, save money Also original structure engineering can be preferably protected while source, and there is economical synthesis benefit.
Obviously, various changes and modifications can be made to the invention without departing from essence of the invention by those skilled in the art God and range.In this way, if these modification and variation of the present invention belong to the range of the claims in the present invention and its equivalent technologies Within, then the present invention is also intended to include these modifications and variations.

Claims (10)

1. the additional structure that shear wall is removed in a kind of frame-shear-wall structure, for tearing shear wall in frame-shear-wall structure open Divided by it is transformed into frame structure, which is characterized in that cross below junction including being set to shear wall and structural slab to be removed Reinforced beam and several junction steel plates, the top by shear wall below the bottom surface absolute altitude of reinforced beam with structural slab It is left shear wall member-retaining portion after partial demolition more than face absolute altitude, the both ends of the reinforced beam anchor into shear wall both ends Frame column in, the bottom surface of the shear wall member-retaining portion is flushed with the bottom surface of the reinforced beam, the shearing The bottom of wall member-retaining portion is connect with the bottom of the reinforced beam by the junction steel plate, and composite construction beam is formed, The junction steel plate along reinforced beam longitudinally spaced setting.
2. the additional structure that shear wall is removed in frame-shear-wall structure according to claim 1, which is characterized in that described The width of reinforced beam≤frame column width -+200 millimeters of shear wall's thickness, and the width of reinforced beam >=400 are in the least Rice.
3. the additional structure that shear wall is removed in frame-shear-wall structure according to claim 1, which is characterized in that described The width of junction steel plate is 300 millimeters, length=shear wall's thickness+armored concrete beam width of the junction steel plate, connection Steel plate is anchored in by a diameter of 12~22 millimeters of chemical bolts on composite construction beam, and the junction steel plate is along reinforced beam Longitudinal setting spacing is 800~1000 millimeters.
4. the additional structure that shear wall is removed in frame-shear-wall structure according to claim 1, which is characterized in that described The design height of reinforced beam is calculated according to frame stressing and is determined.
5. the additional structure that shear wall is removed in frame-shear-wall structure according to claim 1, which is characterized in that work as steel After the completion of Concrete Beam Reinforced construction and maintenance, shear wall remove range since armored concrete beam bottom to the plate face of understructure plate Terminate.
6. the additional structure that shear wall is removed in frame-shear-wall structure according to claim 1, which is characterized in that described The unilateral side or both sides of shear wall are equipped with the structural slab.
7. the construction method that shear wall is removed in a kind of frame-shear-wall structure, which is characterized in that be used for frame-shear wall knot Shear wall is removed to be transformed into frame structure, using the frame-shear wall knot as described in any one of claim 1-6 in structure The additional structure that shear wall is removed in structure, this method include
Step 1, in the building of existing frame-shear-wall structure, to being contacted with reinforced beam on shear wall and structural slab Position carry out surface dabbing processing;For connecting the position of reinforced beam according to reinforcing bar on the frame column of shear wall both sides Corresponding bar planting is arranged in the reinforcing bar distributing position of beams of concrete;The reinforcing bar of assembling reinforcement beams of concrete simultaneously makes reinforced beam Reinforcing bar be fixedly connected with bar planting, pouring reinforcement concrete beam;
Step 2, reinforced beam construction is completed, by the top surface with structural slab below the bottom surface absolute altitude of reinforced beam Shear wall more than absolute altitude is removed, and shear wall member-retaining portion is left;
Step 3, after the completion of shear wall is removed, the position that junction steel plate need to be installed to the bottom surface of shear wall member-retaining portion is beaten It polishes whole, according to the bolt hole on junction steel plate, carries out unwrapping wire positioning in composite construction beam bottom, and mark, marking Position drilling plant chemical bolt, junction steel plate is installed after the completion, junction steel plate is viscous with the contact site brushing of combination beam concrete Steel glue finally twists solid chemical bolt.
8. the construction method that shear wall is removed in frame-shear-wall structure according to claim 7, which is characterized in that described Before shear wall is removed, when shear wall unilateral side is connect with structural slab, increase reinforced beam below junction;Work as shear wall When there are structural slab connection in both sides, increase reinforced beam below the junction of both sides.
9. the construction method that shear wall is removed in frame-shear-wall structure according to claim 7, which is characterized in that described The width of reinforced beam≤frame column width -+200 millimeters of shear wall's thickness, and the width of reinforced beam >=400 are in the least Rice, the height of the reinforced beam determine by the following method:Shear wall removes the bottom surface of line and reinforced beam In same level, shear wall removes line along shear wall and is divided into shear wall member-retaining portion and shear wall dismounting part, and cuts Power wall, which removes line, has a domain of walker, and a value is determined in the domain of walker that shear wall removes line, meanwhile, in armored concrete After the cross-sectional width of beam determines, wanted according to whether the section Accounting Framework structure stress stability of reinforced beam disclosure satisfy that It asks;If being unsatisfactory for requiring, adjustment shear wall removes the height of line, recalculates review, final to determine cutting for reinforced beam Face size.
10. the construction method that shear wall is removed in frame-shear-wall structure according to claim 7, which is characterized in that when After the completion of reinforced beam construction and maintenance, the Demolition Construction of each story shear wall is carried out at the same time.
CN201810398545.0A 2018-04-28 2018-04-28 The additional structure and method that shear wall is removed in frame-shear-wall structure Pending CN108518084A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810398545.0A CN108518084A (en) 2018-04-28 2018-04-28 The additional structure and method that shear wall is removed in frame-shear-wall structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810398545.0A CN108518084A (en) 2018-04-28 2018-04-28 The additional structure and method that shear wall is removed in frame-shear-wall structure

Publications (1)

Publication Number Publication Date
CN108518084A true CN108518084A (en) 2018-09-11

Family

ID=63429468

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810398545.0A Pending CN108518084A (en) 2018-04-28 2018-04-28 The additional structure and method that shear wall is removed in frame-shear-wall structure

Country Status (1)

Country Link
CN (1) CN108518084A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109838114A (en) * 2019-04-01 2019-06-04 吉林建筑大学 Reinforced concrete structure inversely removes temporary support conversion equipment and its operating method
CN111395799A (en) * 2020-03-25 2020-07-10 中国一冶集团有限公司 Low-disturbance basement communication port outer wall efficient dismantling construction method
CN112854293A (en) * 2020-12-31 2021-05-28 北京建工土木工程有限公司 Structure of wall door opening of subway station auxiliary and main body connecting section and construction process thereof
CN113482396A (en) * 2021-06-30 2021-10-08 上海宝冶集团有限公司 Static force dismantling construction method for indoor wall

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017008618A (en) * 2015-06-24 2017-01-12 株式会社フジタ Repair method of concrete structure
CN106760050A (en) * 2016-11-24 2017-05-31 大象建筑设计有限公司 The attachment structure and through processing method of shear wall and after-pouring concrete frame beam
CN106760049A (en) * 2016-11-24 2017-05-31 大象建筑设计有限公司 The attachment structure and its casting method of shear wall and after-pouring concrete secondary beam
CN107401232A (en) * 2017-08-22 2017-11-28 天津联鉴建筑质量鉴定检测有限公司 A kind of underpinning structure and construction method for replacing underproof shear wall concrete
CN208310283U (en) * 2018-04-28 2019-01-01 上海建工二建集团有限公司 The additional structure that shear wall is removed in frame-shear-wall structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2017008618A (en) * 2015-06-24 2017-01-12 株式会社フジタ Repair method of concrete structure
CN106760050A (en) * 2016-11-24 2017-05-31 大象建筑设计有限公司 The attachment structure and through processing method of shear wall and after-pouring concrete frame beam
CN106760049A (en) * 2016-11-24 2017-05-31 大象建筑设计有限公司 The attachment structure and its casting method of shear wall and after-pouring concrete secondary beam
CN107401232A (en) * 2017-08-22 2017-11-28 天津联鉴建筑质量鉴定检测有限公司 A kind of underpinning structure and construction method for replacing underproof shear wall concrete
CN208310283U (en) * 2018-04-28 2019-01-01 上海建工二建集团有限公司 The additional structure that shear wall is removed in frame-shear-wall structure

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
余兴华 等: "某在建工程部分剪力墙混凝土置换施工方案设计", 建筑技术开发 *
刘浩 等: "北京某既有建筑抗震加固改造设计与施工", 建筑结构 *
史明祥: "谈混凝土结构改造加固方法及方案优选", 山西建筑 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109838114A (en) * 2019-04-01 2019-06-04 吉林建筑大学 Reinforced concrete structure inversely removes temporary support conversion equipment and its operating method
CN109838114B (en) * 2019-04-01 2024-01-26 吉林建筑大学 Reinforced concrete structure reverse dismantling temporary support conversion device and operation method thereof
CN111395799A (en) * 2020-03-25 2020-07-10 中国一冶集团有限公司 Low-disturbance basement communication port outer wall efficient dismantling construction method
CN112854293A (en) * 2020-12-31 2021-05-28 北京建工土木工程有限公司 Structure of wall door opening of subway station auxiliary and main body connecting section and construction process thereof
CN113482396A (en) * 2021-06-30 2021-10-08 上海宝冶集团有限公司 Static force dismantling construction method for indoor wall

Similar Documents

Publication Publication Date Title
CN108518084A (en) The additional structure and method that shear wall is removed in frame-shear-wall structure
CN105887702B (en) A kind of method of pre-stressed carbon fiber plate and steel concrete reinforced concrete beam
CN101424075B (en) Concrete box girder bridge widening and reinforced structure and construction method thereof
CN101613997B (en) Method for widening steel-concrete combination
CN104652293A (en) Cable-stayed bridge structure used for reinforcing PSC (Pre-stressed Concrete) continuous box girder bridge and construction method
CN102995572B (en) The method of attachment of Thin-wall Hollow Pier and former pier stud and device thereof after bridge jacking
CN104847130A (en) Reinforcing structure of existing structural beam and construction method thereof
CN103088842A (en) Rubble retaining wall reinforced single-face pattern plate support system and construction method
CN102900241A (en) Integrated construction method for nodes of 'new beam and old column' in reconstruction of concrete structure
CN204098523U (en) Punch after a kind of reinforced concrete floor and add beam reinforced structure
CN107100062B (en) A kind of compound section steel box girder and its method of construction
CN208310283U (en) The additional structure that shear wall is removed in frame-shear-wall structure
CN104763161A (en) Beam-adding reinforced structure of a reinforced concrete floor with an opening and construction method
CN106499211B (en) Newly-increased outrigger frame Baogang anchor daraf(reciprocal of farad) structure
CN210797296U (en) Steel-concrete combination beam bridge floor flange plate bracket mounting structure
CN204782044U (en) Reinforced structure of existing structure roof beam
CN204780635U (en) Super wide nonprismatic continuous beam 0# piece concreties and relieves construction structures
CN102936953A (en) Construction method of bridging-arm stiffened steel structure template
CN207999071U (en) A kind of wall column root concrete capping tools
JP3695550B2 (en) Construction method of high-rise building supported by piles
CN108265998A (en) A kind of skyscraper supporting member flood method of replacing
CN211472128U (en) Continuity combination beam
CN106836641A (en) Side sticking steel plate formula Combined concrete coupling beam
CN102220808A (en) Beam lowering construction method of frame structure
CN207846167U (en) A kind of constructing device of auxiliary concrete road side form support

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination