CN211472128U - Continuity combination beam - Google Patents

Continuity combination beam Download PDF

Info

Publication number
CN211472128U
CN211472128U CN201921736089.2U CN201921736089U CN211472128U CN 211472128 U CN211472128 U CN 211472128U CN 201921736089 U CN201921736089 U CN 201921736089U CN 211472128 U CN211472128 U CN 211472128U
Authority
CN
China
Prior art keywords
prefabricated bridge
tendons
bridge pieces
construction
prefabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201921736089.2U
Other languages
Chinese (zh)
Inventor
冯赟杰
吴小平
段文军
范志勇
罗杭飞
刘昊
吴瑶
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Southwest Jiaotong University
China Railway Engineering Service Co Ltd
Original Assignee
Southwest Jiaotong University
China Railway Engineering Service Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Southwest Jiaotong University, China Railway Engineering Service Co Ltd filed Critical Southwest Jiaotong University
Priority to CN201921736089.2U priority Critical patent/CN211472128U/en
Application granted granted Critical
Publication of CN211472128U publication Critical patent/CN211472128U/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Landscapes

  • Bridges Or Land Bridges (AREA)

Abstract

本实用新型属于桥梁工程技术领域,具体涉及一种连续性组合梁施工方法。解决了现有技术中桥梁内部应力大,容易产生裂缝,使用寿命低的问题,技术方案是:包括数个预制桥梁片,所述数个预制桥梁片依次连接,预制桥梁片中设置有预应力筋,所述预应力筋伸出预制桥梁片的截面35~45cm,所述预应力筋与相邻预制桥梁片的预应力筋一一对应连接。本实用新型将一跨梁的预应力分为了多个节段,接缝处不受预应力影响,裂缝产生的几率大大降低,而且裂缝也不会向相邻的预制桥梁片发展,桥梁的使用寿命增加。本实用新型适用于对交通或者工期要求较高的桥梁的施工。

Figure 201921736089

The utility model belongs to the technical field of bridge engineering, in particular to a continuous composite beam construction method. The problems of high internal stress of bridges in the prior art, cracks are easily generated, and service life is low, the technical solution is: including several prefabricated bridge pieces, the several prefabricated bridge pieces are connected in sequence, and the prefabricated bridge pieces are provided with prestressed bridge pieces. The prestressed tendons extend out of the cross-section of the prefabricated bridge pieces by 35-45 cm, and the prestressed tendons are connected with the prestressed tendons of the adjacent prefabricated bridge pieces in a one-to-one correspondence. The utility model divides the prestress of a span beam into a plurality of segments, the joints are not affected by the prestress, the probability of cracks is greatly reduced, and the cracks will not develop to the adjacent prefabricated bridge pieces. increased lifespan. The utility model is suitable for the construction of bridges with high requirements on traffic or construction period.

Figure 201921736089

Description

一种连续性组合梁A continuous composite beam

技术领域technical field

本实用新型属于桥梁工程技术领域,具体涉及一种连续性组合梁。The utility model belongs to the technical field of bridge engineering, in particular to a continuous composite beam.

背景技术Background technique

连续梁是在建筑、施工、航空以及管道线路等工程中,具有三个或更多支承的梁。随着高速公路和高速铁路的快速建设,出现了很多大跨度的连续梁桥,一般采用的建设方式都是挂篮、满堂脚手架等,施工过程工艺复杂,需要现场进行全面浇筑施工,进度慢,时间长,往往成为整个工程进度的限制口。Continuous beams are beams with three or more supports in construction, construction, aviation, and pipeline projects. With the rapid construction of expressways and high-speed railways, many long-span continuous girder bridges have appeared. The commonly used construction methods are hanging baskets, scaffolding, etc. The construction process is complicated and requires comprehensive pouring construction on site. A long time often becomes the limit of the entire project progress.

国内的桥梁建设都是混凝土钢筋预应力桥梁,在施工中也大多采用挂篮式施工,满堂脚手架等施工技术。这样的施工技术为现在的普遍桥梁施工,能够保证桥梁结构的稳定性,并且施工完成后出现裂缝等的情况也很少,因此国内现在都是应有这种施工技术。但是,这种施工技术也有很多的弊端。如:施工时间很长,机器使用频率过高,使用寿命较短以及施工人员的工作量大等。The domestic bridge construction is all concrete reinforced prestressed bridges, and most of the construction techniques such as hanging basket construction and full house scaffolding are used in the construction. This kind of construction technology is a common bridge construction now, which can ensure the stability of the bridge structure, and there are few cases of cracks after the construction is completed. Therefore, this construction technology should be used in China now. However, this construction technique also has many drawbacks. Such as: the construction time is very long, the frequency of machine use is too high, the service life is short, and the workload of the construction personnel is heavy.

预制拼装法是将大量混凝土浇灌过程放在梁预制场进行工业化制作,在工程现场进行拼装,达到需要的预应力及内部结构,并进行少量的混凝土浇筑,实现整个连续梁的成型。可以将整个连续梁的主体工程放到预制场进行,减少现场工程量,能够将变截面的精度控制到较高水平,不仅可以提高质量,同时可以大大减少施工的时间,加快施工进度,也节省了大量的工程经费。The prefabrication assembly method is to put a large amount of concrete pouring process in the beam prefabrication field for industrial production, assemble at the project site to achieve the required prestress and internal structure, and perform a small amount of concrete pouring to realize the entire continuous beam. The main project of the entire continuous beam can be carried out in the prefabrication field, reducing the amount of on-site engineering, and can control the precision of the variable section to a higher level, which can not only improve the quality, but also greatly reduce the construction time, speed up the construction progress, and save money. A lot of engineering costs.

但是现有的连续梁预制拼装施工大多都是在拼装时对预制桥梁片和已经拼装好的桥梁之间施加预应力,随着预制桥梁片拼装数量的增加,预应力施加的长度增加,最后对一跨梁整体都施加上了预应力,这种施工方法会在桥梁整体内部产生巨大的应力,过大的应力容易使桥面产生很多裂缝,而且裂缝会从一个节段向相邻的节段发展,导致桥梁的使用寿命降低。However, most of the existing continuous beam prefabricated assembly construction is to apply prestressing between the prefabricated bridge pieces and the already assembled bridge during assembly. The entire span of the beam is prestressed. This construction method will generate huge stress inside the bridge as a whole. Excessive stress will easily cause many cracks in the bridge deck, and the cracks will go from one segment to the adjacent segment. development, resulting in a reduction in the service life of the bridge.

实用新型内容Utility model content

针对现有技术中桥梁内部应力大,容易产生裂缝,使用寿命低的问题,本实用新型提供一种连续性组合梁,其目的在于:将桥梁内部的应力分为多个节段,各节段的应力之间不连通,防止裂缝的发展,延长桥梁使用寿命。Aiming at the problems in the prior art that the internal stress of the bridge is large, cracks are easily generated, and the service life is low, the utility model provides a continuous composite beam, the purpose of which is to divide the internal stress of the bridge into a plurality of segments, and each segment The stress is not connected, preventing the development of cracks and prolonging the service life of the bridge.

本实用新型采用的技术方案如下:The technical scheme adopted by the utility model is as follows:

一种连续性组合梁,包括数个预制桥梁片,所述数个预制桥梁片依次连接,所述预制桥梁片中设置有预应力筋,所述预应力筋伸出预制桥梁片的截面35~45cm,所述预应力筋与相邻预制桥梁片的预应力筋一一对应连接,在预应力筋上设置有横向钢筋,所述预应力筋和横向钢筋的外侧浇筑有混凝土连接部,所述混凝土连接部的截面尺寸与预制桥梁片的截面尺寸相同。A continuous composite beam, comprising several prefabricated bridge pieces, the several prefabricated bridge pieces are connected in sequence, the prefabricated bridge pieces are provided with prestressed tendons, the prestressed tendons extend out of the cross section of the prefabricated bridge pieces by 35-35 mm. 45cm, the prestressed tendons are connected with the prestressed tendons of the adjacent prefabricated bridge pieces in one-to-one correspondence, the prestressed tendons are provided with transverse reinforcing bars, and the outer sides of the prestressed tendons and the transverse reinforcing bars are poured with concrete connecting parts. The section size of the concrete connection is the same as that of the prefabricated bridge piece.

现有技术中,预制拼装法施工一般都是预制好桥梁片,但是预制的时候不施加预应力,预制桥梁片中预留好预应力筋通道,预制桥梁片吊装到位后,将预应力筋穿入该预留通道中进行张拉,并对接缝处进行处理,就完成了一节预制桥梁片的拼装,重复上述操作,就完成了一跨梁的安装。这种方法会使得一跨梁中存在连续的预应力,预制桥梁片接缝处成为薄弱处,容易被压裂,在预应力的作用下,裂缝发展较快,而且裂缝会向相邻的预制桥梁片发展。In the prior art, the prefabricated assembling method generally involves prefabricating bridge pieces, but no prestressing is applied during prefabrication, and prestressed rib channels are reserved in the prefabricated bridge pieces. Enter the reserved channel for tensioning, and process the joints to complete the assembly of a section of prefabricated bridge pieces. Repeat the above operations to complete the installation of a span beam. This method will cause continuous prestressing in a span beam, and the joints of the prefabricated bridge pieces will become weak spots, which are easy to be fractured. Bridge piece development.

采用该技术方案后,只在每一片预制桥梁片中施加预应力,预制桥梁片之间的接缝处没有预应力,将一跨梁的预应力分为了多个节段,接缝处不受预应力影响,裂缝产生的几率大大降低,而且裂缝也不会向相邻的预制桥梁片发展,桥梁的使用寿命增加。而且这种方案大大缩短了桥梁的施工时间,提高了工程效率,降低了建设工程对于交通的不良影响。After adopting this technical solution, only prestress is applied to each prefabricated bridge piece, and there is no prestress at the joints between the prefabricated bridge pieces. Under the influence of prestress, the probability of cracks is greatly reduced, and the cracks will not develop to the adjacent prefabricated bridge pieces, and the service life of the bridge will be increased. Moreover, this solution greatly shortens the construction time of the bridge, improves the engineering efficiency, and reduces the adverse impact of the construction project on the traffic.

优选的,所述预制桥梁片的上部设置有两层预应力筋,其中下层的预应力筋设置为弧形且向上弯曲。Preferably, the upper part of the prefabricated bridge piece is provided with two layers of prestressed tendons, wherein the prestressed tendons of the lower layer are arranged in an arc shape and are bent upward.

采用该技术方案后,弧形钢筋连接方式在厚度方向和水平方向上受力都比较均匀,弧形钢筋连接方式对其两侧的预制桥梁片的影响更小,预制桥梁片更不易产生裂缝。After adopting this technical scheme, the force of the arc-shaped steel bar connection is relatively uniform in the thickness direction and the horizontal direction, the arc-shaped steel connection mode has less influence on the prefabricated bridge pieces on both sides, and the prefabricated bridge pieces are less prone to cracks.

优选的,上部的横向钢筋采用焊接连接,下部的横向钢筋绑扎连接。Preferably, the upper transverse reinforcement is connected by welding, and the lower transverse reinforcement is connected by binding.

采用该技术方案后,上部的焊接施工人员可以直接在桥面上进行操作,下部的绑扎施工人员可以在箱梁空腔和模板上进行操作,便于施工。After adopting this technical solution, the welding construction personnel in the upper part can directly operate on the bridge deck, and the binding construction personnel in the lower part can operate on the cavity of the box girder and the formwork, which is convenient for construction.

优选的,所述预制桥梁片的截面设置有粘结剂,所述粘结剂的厚度为0.5mm~1mm。Preferably, the cross section of the prefabricated bridge sheet is provided with an adhesive, and the thickness of the adhesive is 0.5 mm to 1 mm.

粘结剂涂抹过厚会造成溶剂的挥发速度过慢,强度增长慢,此时粘结剂仅仅起填充的作用,粘接力不强,如果粘结剂涂抹过薄容易造成缺胶,粘接面积减小。采用该技术方案后,粘结剂中的水分更加容易挥发,粘结剂的强度增长的更快,同时避免造成缺胶的情况。粘结剂能够使新浇筑的混凝土与预制桥梁片之间连接更加紧密,避免粘结剂与混凝土结合处成为桥梁受力的薄弱处,造成应力集中,避免裂缝在粘结剂与混凝土结合处产生,增加桥梁的稳定性和承载能力。If the adhesive is applied too thickly, the volatilization speed of the solvent will be too slow, and the strength will increase slowly. At this time, the adhesive only plays the role of filling, and the adhesive force is not strong. area is reduced. After adopting this technical solution, the moisture in the binder is more easily volatilized, the strength of the binder increases faster, and the situation of lack of glue is avoided at the same time. The binder can make the connection between the newly poured concrete and the prefabricated bridge piece more closely, avoid the joint between the binder and the concrete becoming the weak point of the bridge force, cause stress concentration, and avoid cracks in the joint between the binder and the concrete. , to increase the stability and bearing capacity of the bridge.

优选的,所述预应力筋之间的间距为35~45cm。Preferably, the spacing between the prestressed tendons is 35-45 cm.

采用该技术方案后,保证预制桥梁片内部有足够的预应力,同时施工人员在焊接施工时,焊接工具能有操作空间,便于施工。After adopting the technical scheme, it is ensured that the prefabricated bridge piece has sufficient prestress inside, and the construction personnel can have operating space for the welding tools during welding construction, which is convenient for construction.

优选的,所述预应力筋与相邻预制桥梁片的预应力筋焊接连接,焊接的搭接长度不小于10倍预应力筋的直径。Preferably, the prestressed rib is connected to the prestressed rib of the adjacent prefabricated bridge piece by welding, and the welding overlap length is not less than 10 times the diameter of the prestressed rib.

采用该技术方案后,保证预应力筋之间搭接处的搭接强度满足规范的要求,保证桥梁的抗弯、抗剪以及承载力满足要求。After adopting this technical solution, it is ensured that the lap strength of the lap joints between the prestressed tendons meets the requirements of the specification, and the bending resistance, shear resistance and bearing capacity of the bridge are guaranteed to meet the requirements.

本实用新型的连续性组合梁的施工方法包括以下步骤:The construction method of the continuous composite beam of the present invention comprises the following steps:

步骤[1]:制作预制桥梁片;Step [1]: Make prefabricated bridge pieces;

步骤[2]:搭建支架,支架间的距离大于桥墩的宽度和桥梁的跨度;Step [2]: Build the supports, the distance between the supports is greater than the width of the pier and the span of the bridge;

步骤[3]:桥墩的两侧分别设置有横梁,所述横梁安装于支架上;Step [3]: the two sides of the bridge pier are respectively provided with beams, and the beams are installed on the brackets;

步骤[4]:在横梁上安装起重设备,起重设备的数量与跨中的预制桥梁片的数量相同;Step [4]: Install lifting equipment on the beam, and the number of lifting equipment is the same as the number of prefabricated bridge pieces in the span;

步骤[5]:吊装预制桥梁片,首先吊装桥墩上的预制桥梁片,然后同时吊装跨中的预制桥梁片;Step [5]: Hoist the prefabricated bridge pieces, first hoist the prefabricated bridge pieces on the piers, and then hoist the prefabricated bridge pieces in the middle of the span at the same time;

步骤[6]:连接相邻的预制桥梁片接缝处的钢筋;Step [6]: Connect the reinforcing bars at the joints of adjacent prefabricated bridge pieces;

步骤[7]:对预制桥梁片的接缝处浇筑混凝土。Step [7]: Concrete is poured on the joints of the prefabricated bridge pieces.

所述步骤[1]中的预制桥梁片采用先张法预应力施工,并且两侧分别预留35cm~45cm 的预应力筋。The prefabricated bridge piece in the step [1] is prestressed by the pretensioning method, and 35cm-45cm of prestressed tendons are reserved on both sides.

步骤[2]中支架搭建前,先在搭建支架处开挖,然后浇筑混凝土作为支架基础。支架的基础更加稳定,防止在施工过程中由于支架基础沉降而造成质量事故或者安全事故。In step [2], before the support is built, excavate the place where the support is to be built, and then pour concrete as the support foundation. The foundation of the support is more stable, preventing quality accidents or safety accidents caused by the settlement of the support foundation during the construction process.

步骤[4]中的起重设备为龙门吊,所述龙门吊与横梁滑动连接。龙门吊能够移动,便于预制桥梁片在吊装过程中的移动和就位。The lifting equipment in step [4] is a gantry crane, and the gantry crane is slidingly connected with the beam. The gantry crane can move to facilitate the movement and positioning of the prefabricated bridge pieces during the hoisting process.

在步骤[6]与[7]之间,向预制桥梁片的截面上涂粘结剂,在涂粘结剂之前,将预制桥梁片截面处的松动混凝土清除,去除杂质并将预制桥梁片截面处的混凝土烘干。使粘结剂与混凝土之间结合的更加牢固,增加结构的承载能力和稳定性,避免裂缝的产生。Between steps [6] and [7], adhesive is applied to the sections of the prefabricated bridge pieces, and before the adhesive is applied, the loose concrete at the sections of the prefabricated bridge pieces is removed, impurities are removed, and the prefabricated bridge piece sections are concrete drying. Make the bond between the adhesive and the concrete stronger, increase the bearing capacity and stability of the structure, and avoid the occurrence of cracks.

粘结剂的厚度控制在0.5mm~1mm之间,并且粘结剂与混凝土之间的粘接强度大于混凝土的强度。能够避免粘结剂与混凝土结合处成为桥梁受力的薄弱处,造成应力集中,能够避免裂缝在粘结剂与混凝土结合处产生,增加桥梁的稳定性和承载能力。The thickness of the binder is controlled between 0.5mm and 1mm, and the bonding strength between the binder and the concrete is greater than that of the concrete. It can prevent the bond between the binder and the concrete from becoming the weak point of the bridge, resulting in stress concentration, and can avoid cracks from occurring at the bond between the binder and the concrete, and increase the stability and bearing capacity of the bridge.

在预制桥梁片的截面上涂粘结剂之后,对粘结剂施加2小时压力,压力为0.2Mpa。采用该技术方案后,粘结剂与混凝土面之间结合的更加紧密,粘结强度更高。After the adhesive is applied on the section of the prefabricated bridge sheet, a pressure of 0.2 Mpa is applied to the adhesive for 2 hours. After adopting the technical solution, the bonding agent and the concrete surface are more closely combined, and the bonding strength is higher.

粘结剂未凝固之前,在接缝处保持一个压应力,所述压应力不小于0.3Mpa。Before the adhesive is not solidified, a compressive stress is maintained at the joint, and the compressive stress is not less than 0.3Mpa.

采用该技术方案后,能够保证在预制桥梁片接缝处有一定的预应力,使桥梁的承载能力更高。After adopting the technical scheme, it can ensure that there is a certain prestress at the joints of the prefabricated bridge pieces, so that the bearing capacity of the bridge is higher.

综上所述,由于采用了上述技术方案,本实用新型的有益效果是:To sum up, due to the adoption of the above-mentioned technical solutions, the beneficial effects of the present utility model are:

1.大大缩短了桥梁的施工时间,提高了工程效率,降低了建设工程对于交通的不良影响,而且相对于现有的整体式预应力分布,这种分段式的预应力分布能够减少桥梁的裂缝,接缝处产生的裂缝更少,桥梁的使用寿命增加。1. The construction time of the bridge is greatly shortened, the engineering efficiency is improved, and the adverse impact of the construction project on the traffic is reduced. Compared with the existing integral prestress distribution, this segmented prestress distribution can reduce the bridge's impact. Cracks, fewer cracks are created at the joints, and the service life of the bridge is increased.

2.预制桥梁片的上部设置有两层预应力筋,其中下层的预应力筋设置为弧形且向上弯曲,弧形钢筋连接方式在厚度方向和水平方向上受力都比较均匀,弧形钢筋连接方式对其两侧的预制桥梁片的影响更小,预制桥梁片更不易产生裂缝。2. The upper part of the prefabricated bridge piece is provided with two layers of prestressed tendons, of which the prestressed tendons of the lower layer are set to be arc-shaped and curved upward. The connection method has less influence on the prefabricated bridge pieces on both sides, and the prefabricated bridge pieces are less prone to cracks.

3.上部的横向钢筋采用焊接连接,下部的横向钢筋绑扎连接,上部的焊接施工人员可以直接在桥面上进行操作,下部的绑扎施工人员可以在箱梁空腔和模板上进行操作,便于施工。3. The upper transverse steel bars are connected by welding, and the lower transverse steel bars are connected by binding. The welding construction personnel in the upper part can directly operate on the bridge deck, and the binding construction personnel in the lower part can operate on the box girder cavity and template, which is convenient for construction. .

4.预制桥梁片的截面设置有粘结剂,厚度为0.5mm~1mm,粘结剂的强度增长的更快,同时避免造成缺胶的情况。粘结剂能够使新浇筑的混凝土与预制桥梁片之间连接更加紧密,避免粘结剂与混凝土结合处成为桥梁受力的薄弱处,造成应力集中,避免裂缝在粘结剂与混凝土结合处产生,增加桥梁的稳定性和承载能力。4. The cross-section of the prefabricated bridge piece is provided with a binder, and the thickness is 0.5mm to 1mm. The strength of the binder increases faster, and at the same time, it avoids the lack of glue. The adhesive can make the connection between the newly poured concrete and the prefabricated bridge sheet more closely, avoid the bond between the adhesive and the concrete becoming the weak point of the bridge force, causing stress concentration, and avoiding cracks in the bonding of the adhesive and the concrete. , to increase the stability and bearing capacity of the bridge.

5.预应力筋间距为35~45cm,保证预制桥梁片内部有足够的预应力,同时施工人员在焊接施工时,焊接工具能有操作空间,便于施工。5. The spacing between the prestressed tendons is 35-45cm, which ensures that the prefabricated bridge pieces have sufficient prestressing, and the construction personnel can operate the welding tools during welding construction, which is convenient for construction.

6.搭接长度不小于10倍预应力筋的直径,保证预应力筋之间搭接处的搭接强度满足规范的要求,保证桥梁的抗弯、抗剪以及承载力满足要求。6. The lap length is not less than 10 times the diameter of the prestressed tendons, to ensure that the lap strength of the lap joints between the prestressed tendons meets the requirements of the specification, and the bending resistance, shear resistance and bearing capacity of the bridge meet the requirements.

附图说明Description of drawings

本实用新型将通过例子并参照附图的方式说明,其中:The present invention will be described by way of example and with reference to the accompanying drawings, wherein:

图1是实施例一的桥梁结构示意图;Fig. 1 is the bridge structure schematic diagram of Embodiment 1;

图2是①号预制桥梁片结构示意图;Figure 2 is a schematic diagram of the structure of the prefabricated bridge piece of No. 1;

图3是②号预制桥梁片结构示意图;Figure 3 is a schematic diagram of the structure of the prefabricated bridge piece of No. 2;

图4是③号预制桥梁片结构示意图;Fig. 4 is the structural schematic diagram of No. ③ prefabricated bridge piece;

图5是支架及龙门吊结构示意图;Figure 5 is a schematic diagram of the structure of the bracket and the gantry crane;

图6是接缝处钢筋布置图。Figure 6 is a diagram of the arrangement of reinforcement at the joint.

其中,1-①号预制桥梁片,2-②号预制桥梁片,3-③号预制桥梁片,4-桥墩,5-支架, 6-辅助支架,7-横梁,8-龙门吊,9-桥面,10-预应力筋,11-弧形钢筋,12-横向钢筋。Among them, prefabricated bridge pieces No. 1-①, prefabricated bridge pieces No. 2-②, prefabricated bridge pieces No. 3-③, 4-bridge pier, 5-support, 6-auxiliary support, 7-beam, 8-gantry crane, 9-bridge face, 10-prestressed tendons, 11-arc bars, 12-transverse bars.

具体实施方式Detailed ways

本说明书中公开的所有特征,或公开的所有方法或过程中的步骤,除了互相排斥的特征和/或步骤以外,均可以以任何方式组合。All features disclosed in this specification, or all disclosed steps in a method or process, may be combined in any way except mutually exclusive features and/or steps.

下面结合图1~图6对本实用新型作详细说明。The present utility model will be described in detail below with reference to FIGS. 1 to 6 .

一种连续性组合梁,包括数个预制桥梁片,所述数个预制桥梁片依次连接,所述预制桥梁片中设置有预应力筋10,所述预应力筋10伸出预制桥梁片的截面35~45cm,所述预应力筋10与相邻预制桥梁片的预应力筋10一一对应连接,在预应力筋10上设置有横向钢筋12,所述预应力筋10和横向钢筋12的外侧浇筑有混凝土连接部,所述混凝土连接部的截面尺寸与预制桥梁片的截面尺寸相同。A continuous composite beam includes several prefabricated bridge pieces, the several prefabricated bridge pieces are connected in sequence, the prefabricated bridge pieces are provided with prestressed ribs 10, and the prefabricated rib 10 extends out of the section of the prefabricated bridge pieces 35-45 cm, the prestressed tendons 10 are connected with the prestressed tendons 10 of the adjacent prefabricated bridge pieces in one-to-one correspondence, and transverse reinforcement bars 12 are arranged on the prestressed reinforcement bars 10. A concrete connection part is poured, and the cross-sectional dimension of the concrete connection part is the same as that of the prefabricated bridge piece.

所述预制桥梁片的上部设置有两层预应力筋10,其中下层的预应力筋10设置为弧形且向上弯曲。The upper part of the prefabricated bridge piece is provided with two layers of prestressed tendons 10 , wherein the prestressed tendons 10 of the lower layer are arranged in an arc shape and are bent upward.

上部的横向钢筋12采用焊接连接,下部的横向钢筋12绑扎连接。The upper transverse reinforcement 12 is connected by welding, and the lower transverse reinforcement 12 is connected by binding.

所述预制桥梁片的截面设置有粘结剂,所述粘结剂的厚度为0.5mm~1mm。The cross section of the prefabricated bridge sheet is provided with an adhesive, and the thickness of the adhesive is 0.5 mm˜1 mm.

所述预应力筋10之间的间距为35~45cm。The spacing between the prestressed tendons 10 is 35-45 cm.

所述预应力筋10与相邻预制桥梁片的预应力筋10焊接连接,焊接的搭接长度不小于 10倍预应力筋10的直径。The prestressed ribs 10 are connected by welding with the prestressed ribs 10 of the adjacent prefabricated bridge pieces, and the welded lap length is not less than 10 times the diameter of the prestressed ribs 10.

本实用新型连续性组合梁的施工方法包括以下步骤:The construction method of the continuous composite beam of the present invention comprises the following steps:

包括以下步骤:Include the following steps:

步骤[1]:制作预制桥梁片。本实施例中,共设置有三种规格的预制桥梁片,分别为①号预制桥梁片1、②号预制桥梁片2和③号预制桥梁片3,预制桥梁片的尺寸根据桥梁的具体情况设置。将混凝土浇筑过程设置在梁预制场进行工业化制作,预制桥梁片使用先张法预应力施工。本实施例中,预制桥梁片的钢筋直径为20cm,左右两侧预留出35cm的预应力筋10,并且对预留出来的预应力筋10通过钢筋拉直器拉直,并且两侧分别预留30cm~40cm 的预应力筋。桥面部分的预应力筋设置两层,其中下层的预应力筋设置成弧形,形成弧形钢筋11。Step [1]: Make prefabricated bridge pieces. In this embodiment, a total of three specifications of prefabricated bridge pieces are provided, namely No. 1 prefabricated bridge piece 1, No. 2 prefabricated bridge piece 2 and No. ③ prefabricated bridge piece 3, and the size of the prefabricated bridge piece is set according to the specific conditions of the bridge. The concrete pouring process is set in the beam prefabrication field for industrial production, and the prefabricated bridge pieces are constructed using the pretensioning method. In this embodiment, the diameter of the steel bars of the prefabricated bridge pieces is 20 cm, and 35 cm of prestressed bars 10 are reserved on the left and right sides. Leave 30cm ~ 40cm of prestressed tendons. The prestressed tendons of the bridge deck are provided with two layers, and the prestressed tendons of the lower layer are arranged in an arc shape to form an arc-shaped reinforcement bar 11 .

步骤[2]:搭建支架5,支架5间的距离大于桥墩4的宽度和桥梁的跨度。支架5搭建前,先在搭建支架处开挖基坑,基坑深度根据地基承载力经计算后确定,基坑的平面尺寸比支架5略大,然后在基坑中浇筑混凝土作为支架5的基础。然后在基础上开始支架5的搭建。Step [2]: Build supports 5, and the distance between the supports 5 is greater than the width of the pier 4 and the span of the bridge. Before the support 5 is built, excavate the foundation pit at the place where the support is built. The depth of the foundation pit is determined after calculation according to the bearing capacity of the foundation. The plane size of the foundation pit is slightly larger than that of the support 5, and then concrete is poured in the foundation pit as the foundation of the support 5. . Then start the construction of the bracket 5 on the basis.

步骤[3]:在支架5上安装横梁7并用扣件连接,横梁7互相平行且位于桥墩4的两侧。对于跨度较大的桥梁,在两个支架5之间搭设辅助支架6用于支撑对横梁7中部进行支撑,辅助支架6搭设前,同样需要对基础进行处理,使辅助支架6的基础满足承载力的要求。支架5和辅助支架5均采用扣件连接。Step [3]: Install the beams 7 on the bracket 5 and connect them with fasteners. The beams 7 are parallel to each other and located on both sides of the pier 4 . For bridges with large spans, an auxiliary bracket 6 is erected between the two brackets 5 to support the middle of the beam 7. Before the auxiliary bracket 6 is erected, the foundation also needs to be treated so that the foundation of the auxiliary bracket 6 can meet the bearing capacity. requirements. Both the bracket 5 and the auxiliary bracket 5 are connected by fasteners.

步骤[4]:在横梁上安装龙门吊8,横梁上设置有轨道,龙门吊8底部设置有滚轮与所述轨道配合。本实施例中,龙门吊8采用三组组合式的龙门吊,龙门吊8的额定载重量为200吨,一组龙门吊上布置两个起重小车,其中每个起重小车额定起重量为100吨。Step [4]: Install the gantry crane 8 on the beam, the beam is provided with a track, and the bottom of the gantry crane 8 is provided with rollers to cooperate with the track. In this embodiment, the gantry crane 8 adopts three sets of combined gantry cranes, the rated load of the gantry crane 8 is 200 tons, and two trolleys are arranged on one set of gantry cranes, wherein the rated lifting capacity of each hoist trolley is 100 tons.

步骤[5]:吊装预制桥梁片,首先使用位于两侧的两台龙门吊8分别吊装桥墩4上的①号预制桥梁片1,当①号预制桥梁片1安装稳固之后,使用三台龙门吊8同时吊装剩余的两个②号预制桥梁片2和一个③号预制桥梁片3,使②号预制桥梁片2和③号预制桥梁片3到达指定的位置,然后在预制桥梁片的下方搭设脚手架,并在脚手架上铺设隔板和模板为接缝施工做准备;Step [5]: Hoist the prefabricated bridge pieces. First, use two gantry cranes 8 on both sides to hoist the prefabricated bridge piece 1 on the pier 4 respectively. After the prefabricated bridge piece 1 is installed firmly, use three gantry cranes 8 at the same time Hoist the remaining two No. ② prefabricated bridge pieces 2 and one No. ③ prefabricated bridge piece 3, so that No. Lay bulkheads and formwork on scaffolding in preparation for joint construction;

步骤[6]:连接相邻的预制桥梁片接缝处的钢筋;本实施例中,接缝的宽度设置为45cm,预应力筋10的搭接长度为25cm,采用电渣焊焊接。桥面的预应力筋设置为双层,下层的预应力筋弯曲成弧形(即弧形钢筋11)。在预应力筋10和弧形钢筋11上铺设横向钢筋12。接缝处采取上部焊接,下部绑扎的方法,所以上部的焊接施工人员可以直接在桥面上进行,下部的绑扎施工人员可以在箱梁空腔和模板上进行操作。为了施工方便,使施工人员施工时候焊接工具能有空间操作,接缝处的钢筋布置间隔为40厘米,在截面处以40厘米的间距将钢筋布满,上部分布置两排钢筋,施工时只对上部分进行焊接,下部分只需要绑扎。Step [6]: Connect the reinforcing bars at the joints of adjacent prefabricated bridge pieces; in this embodiment, the width of the joints is set to 45cm, and the lap length of the prestressed tendons 10 is 25cm, which is welded by electroslag welding. The prestressed tendons of the bridge deck are set to be double-layered, and the prestressed tendons of the lower layer are bent into arcs (ie, arc-shaped reinforcing bars 11). Lay transverse reinforcement bars 12 on the prestressed reinforcement bars 10 and the arc-shaped reinforcement bars 11 . The joints are welded at the upper part and tied at the lower part, so the welding construction personnel at the upper part can directly carry out the operation on the bridge deck, and the binding construction personnel at the lower part can operate on the cavity of the box girder and the formwork. In order to facilitate the construction, the construction personnel can have space to operate the welding tools during construction. The steel bars at the joints are arranged at an interval of 40 cm, and the steel bars are covered with 40 cm intervals at the cross-section, and two rows of steel bars are arranged in the upper part. The upper part is welded, and the lower part only needs to be tied.

步骤[7]:将预制桥梁片截面处的松动混凝土清除,去除油污、灰尘等杂质,然后在接缝处浇筑混凝土,混凝土浇筑时采用分层法浇筑。Step [7]: Remove the loose concrete at the cross-section of the prefabricated bridge piece, remove impurities such as oil stains and dust, and then pour concrete at the joints, and use the layered method to pour the concrete.

在步骤[6]步骤[7]之间,向预制桥梁片截面处涂刷粘接剂。将预制桥梁片截面处的松动混凝土清除,去除油污、灰尘等杂质并将预制桥梁片截面处的混凝土烘干,然后在预制桥梁片的截面上涂粘结剂,本实施例采用的粘结剂为一种环氧树脂加水泥混合后做成的化学混凝土混合物,属于现有技术中常用的粘结剂。粘结剂涂抹均匀,厚度控制在0.5mm~1mm 之间,并且粘结剂与混凝土之间的粘接强度大于混凝土的强度。为了使粘结剂稳固在预制桥梁片的截面上,涂粘结剂之后,对粘结剂施加2小时压力,压力为0.2Mpa。在粘结剂尚未凝固之前,在接缝处保持一个最小临时压应力,压应力不小于0.3Mpa。然后在接缝处支模板并浇筑混凝土,混凝土浇筑时采用分层法浇筑。Between steps [6] and [7], apply adhesive to the section of the prefabricated bridge piece. Remove the loose concrete at the section of the prefabricated bridge piece, remove impurities such as oil stains and dust, and dry the concrete at the section of the prefabricated bridge piece, and then apply adhesive on the section of the prefabricated bridge piece. The adhesive used in this example The invention is a chemical concrete mixture made by mixing epoxy resin and cement, and belongs to the commonly used binder in the prior art. The adhesive is spread evenly, the thickness is controlled between 0.5mm and 1mm, and the bonding strength between the adhesive and the concrete is greater than that of the concrete. In order to stabilize the adhesive on the section of the prefabricated bridge sheet, after applying the adhesive, apply pressure to the adhesive for 2 hours, and the pressure is 0.2Mpa. Before the adhesive has solidified, maintain a minimum temporary compressive stress at the joint, and the compressive stress shall not be less than 0.3Mpa. Then, the formwork is supported at the joint and the concrete is poured, and the layered method is used for concrete pouring.

本实用新型通过先张法在每一片预制桥梁片中施加预应力,而在预制桥梁片之间的接缝处仅仅将两片预制桥梁片的预应力筋连接并浇筑混凝土,接缝处没有预应力。这样设置,将一跨梁的预应力分为了多个节段,接缝处不受预应力影响,裂缝产生的几率大大降低,而且裂缝也不会向相邻的预制桥梁片发展,桥梁的使用寿命增加。而且这种方案相比于现有的挂篮悬臂浇筑施工大大缩短了桥梁的施工时间,提高了工程效率,降低了建设工程对于交通的不良影响。The utility model applies prestressing to each prefabricated bridge piece by the pretensioning method, and only connects the prestressed tendons of the two prefabricated bridge pieces and pours concrete at the joint between the prefabricated bridge pieces, and there is no prestressing at the joint. stress. In this way, the prestress of a span beam is divided into multiple segments, the joints are not affected by the prestress, the probability of cracks is greatly reduced, and the cracks will not develop to the adjacent prefabricated bridge pieces. The use of bridges increased lifespan. Moreover, compared with the existing hanging basket cantilever pouring construction, this solution greatly shortens the construction time of the bridge, improves the engineering efficiency, and reduces the adverse impact of the construction project on traffic.

以上所述实施例仅表达了本申请的具体实施方式,其描述较为具体和详细,但并不能因此而理解为对本申请保护范围的限制。应当指出的是,对于本领域的普通技术人员来说,在不脱离本申请技术方案构思的前提下,还可以做出若干变形和改进,这些都属于本申请的保护范围。The above-mentioned embodiments only represent specific implementations of the present application, and the descriptions thereof are specific and detailed, but should not be construed as limiting the protection scope of the present application. It should be pointed out that for those of ordinary skill in the art, without departing from the concept of the technical solution of the present application, several modifications and improvements can be made, which all belong to the protection scope of the present application.

Claims (6)

1. A continuous composite beam, characterized by: including the prefabricated bridge piece of several, the prefabricated bridge piece of several connects gradually, be provided with prestressing tendons (10) in the prefabricated bridge piece, prestressing tendons (10) stretch out the cross-section 35 ~ 45cm of prefabricated bridge piece, prestressing tendons (10) are connected with prestressing tendons (10) one-to-one of adjacent prefabricated bridge piece, be provided with transverse reinforcement (12) on prestressing tendons (10), concrete connecting portion have been pour in the outside of prestressing tendons (10) and transverse reinforcement (12), the cross sectional dimension of concrete connecting portion is the same with the cross sectional dimension of prefabricated bridge piece.
2. A continuous composite girder according to claim 1, wherein the upper portion of the precast bridge segment is provided with two layers of tendons (10), wherein the tendons (10) of the lower layer are arranged in an arc shape and bent upward.
3. A continuous composite girder according to claim 1, wherein the upper transverse reinforcement (12) is welded and the lower transverse reinforcement (12) is bound.
4. A continuous composite girder according to claim 1, wherein a cross section of the precast bridge deck is provided with an adhesive having a thickness of 0.5mm to 1 mm.
5. A continuous composite beam as claimed in claim 1, characterised in that the spacing between the tendons (10) is 35-45 cm.
6. A continuous composite girder according to claim 1, wherein said tendons (10) are welded to the tendons (10) of the adjacent precast bridge segments with the welded overlapping length not less than 10 times the diameter of the tendons (10).
CN201921736089.2U 2019-10-16 2019-10-16 Continuity combination beam Active CN211472128U (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201921736089.2U CN211472128U (en) 2019-10-16 2019-10-16 Continuity combination beam

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201921736089.2U CN211472128U (en) 2019-10-16 2019-10-16 Continuity combination beam

Publications (1)

Publication Number Publication Date
CN211472128U true CN211472128U (en) 2020-09-11

Family

ID=72374802

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201921736089.2U Active CN211472128U (en) 2019-10-16 2019-10-16 Continuity combination beam

Country Status (1)

Country Link
CN (1) CN211472128U (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114892552A (en) * 2022-07-01 2022-08-12 安徽省公路桥梁工程有限公司 Box girder type bridge reconstruction construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114892552A (en) * 2022-07-01 2022-08-12 安徽省公路桥梁工程有限公司 Box girder type bridge reconstruction construction method
CN114892552B (en) * 2022-07-01 2023-11-21 安徽省公路桥梁工程有限公司 Box girder type bridge reconstruction construction method

Similar Documents

Publication Publication Date Title
CN106677049B (en) Assembled steel-concrete combined structure bridge and construction method
CN110700103B (en) Construction method of continuous composite beam
CN103276662B (en) Large-cantilever steel web spinal box beam segment
CN102146658B (en) Locally uncombined suspension bridge steel-concrete combined bridge deck system and construction method of combined bridge deck system
CN109440623B (en) Temporary splicing structure of precast bridge of concrete segment
CN103046463B (en) Assembly type saddle-shell-shaped bottom plate continuous box girder bridge and construction method thereof
CN205100082U (en) Prefabricated assembled steel-concrete composite beam bridge
CN109024225A (en) Ultra-high performance concrete truss arch blade unit, truss arch piece bridge and construction method
CN102704406B (en) Roadbed slab non-tensile stress construction method based on combined channel girder
CN106337361B (en) A kind of separate type FRP- concrete-steel combination beam bridge structure and construction method
CN112281633A (en) Back-loading cantilever arm of spine beam bridge and longitudinal joint structure thereof
CN114775404B (en) Steel beam-ultra-high performance concrete slab combined bent cap and construction method thereof
CN205399184U (en) A combination steel case roof beam for high -speed railway
CN105064196A (en) Prefabricated and assembled fish-belly I-shaped prestressed steel-concrete composite simple supported girder bridge and construction method thereof
CN108374356A (en) A kind of old hollow slab bridge of hinge seam longitudinal prestressing reinforcing single hole constructs and construction method
CN108316164B (en) Structure for reinforcing old assembled hollow slab girder bridge by using new girder and construction method
CN204570446U (en) The T-shaped simply supported beam of a kind of precast assembly
CN106758773A (en) A kind of shear connector of steel reinforced concrete composite beam bridge
CN217974005U (en) Combined box girder structure
CN105735099B (en) Construction time uses the simple supported-to-continuous girder bridge and its construction method of external prestressing
CN211472128U (en) Continuity combination beam
CN203307719U (en) Large-cantilever steel web carinal box girder section
CN202227268U (en) Concrete box beam structure capable of widening steel cantilever beam
CN108411801A (en) One kind reinforcing the old hollow slab bridge construction of single hole and construction method by real abdomen Bars In Poured Concrete Slab
CN105088962B (en) A kind of integral hoisting method of Wavelike steel webplate part

Legal Events

Date Code Title Description
GR01 Patent grant
GR01 Patent grant