CN110835998A - Method for improving epoxy construction efficiency of cast-in-situ floor waffle holes - Google Patents
Method for improving epoxy construction efficiency of cast-in-situ floor waffle holes Download PDFInfo
- Publication number
- CN110835998A CN110835998A CN201911159372.8A CN201911159372A CN110835998A CN 110835998 A CN110835998 A CN 110835998A CN 201911159372 A CN201911159372 A CN 201911159372A CN 110835998 A CN110835998 A CN 110835998A
- Authority
- CN
- China
- Prior art keywords
- epoxy
- hole
- waffle
- coating
- balloon
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F21/00—Implements for finishing work on buildings
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F13/00—Coverings or linings, e.g. for walls or ceilings
- E04F13/02—Coverings or linings, e.g. for walls or ceilings of plastic materials hardening after applying, e.g. plaster
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04F—FINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
- E04F15/00—Flooring
- E04F15/12—Flooring or floor layers made of masses in situ, e.g. seamless magnesite floors, terrazzo gypsum floors
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Working Measures On Existing Buildindgs (AREA)
Abstract
The invention relates to the field of electronic factory building construction, in particular to a method for improving epoxy construction efficiency of a cast-in-situ floor waffle hole; the method is characterized in that: polishing the concrete base layer on the upper surface of the waffle hole by using a grinding machine or a double-sided stone grinding machine; ensuring the integral flatness of the concrete base layer on the upper surface of the waffle hole to be +/-8 mm/2 m; performing epoxy primary coating construction to play a role in curing; after the bottom coat is solidified, inflating the PVC balloon and embedding the PVC balloon into the waffle hole; after the PVC balloon is embedded, firstly, coating epoxy resin with quartz sand trowel to scrape epoxy quartz mortar twice, after the mortar layer is solidified, coating epoxy soil twice, sealing the sand hole and the air hole, and taking out the PVC balloon after the middle coating is solidified; polishing the epoxy middle coat, and coating the epoxy surface twice. Compared with the traditional method for leveling the waffle hole opening by only relying on manpower, the method greatly improves the working efficiency and effectively ensures the quality of epoxy construction.
Description
Technical Field
The invention relates to the field of electronic factory building construction, in particular to a method for improving epoxy construction efficiency of a cast-in-place floor waffle hole.
Background
At present, the state strongly supports the semiconductor industry, and the construction projects of various electronic factory buildings are inexhaustible. Most of electronic factory buildings relate to the construction of clean rooms, and new technologies such as waffle cylinders are applied. For the epoxy construction of the waffle cone floor floors and the bottom surfaces, the traditional construction method comprises the following steps: the hole of the waffle hole is leveled only manually, the manual work efficiency is only 8-10 holes/day/person, and the hole is arc-shaped, so the hole is uneven after leveling, and more than 90% of the epoxy mortar can cause the phenomenon of sagging of the inner wall of the waffle hole in the troweling process, so the hole is extremely difficult to clean. The process completely depends on great labor resources to carry out careful polishing, cleaning and repairing work on the upper and lower holes of the waffle hole, so that the epoxy flatness of the hole of the waffle hole can meet the requirement as much as possible, but the process is usually done with half the effort and cannot achieve the expected effect.
Disclosure of Invention
The invention aims to overcome the defects and provide a cast-in-place construction method capable of effectively improving the work efficiency and quality of the bottom layer and surface layer epoxy construction of the waffle hole.
In order to achieve the above object, the present invention is realized by:
a method for improving epoxy construction efficiency of cast-in-situ floor waffle holes comprises
Step 1, checking the flatness of the floor and ceiling of a concrete building by using a 2-meter guiding rule, recording a clearance value, and marking the over-high positions and over-low positions of the floor and ceiling of the building;
step 2, polishing the concrete base layer on the upper surface of the waffle hole by using a grinding machine or a double-sided stone grinding machine, polishing key points if the concrete base layer is too high in the step 1, and repairing the too low parts by using quartz sand to ensure that the integral flatness of the concrete base layer on the upper surface of the waffle hole is +/-8 mm/2 m;
step 3, performing epoxy primer coating construction, and adopting roller coating or blade coating to fully soak the concrete to play a role in curing;
step 4, after the bottom coat is solidified, inflating a PVC balloon with a lifting ring or a handle and a wall thickness of not less than 0.5mm, and embedding the PVC balloon into the waffle hole, wherein the PVC balloon is customized according to the diameter of the waffle hole, the diameter of the balloon is slightly larger than the diameter of the waffle hole when the inflation amount reaches 80%, and the lifting ring is upward during embedding;
step 5, after embedding the PVC balloon, firstly coating epoxy resin with a quartz sand trowel to scrape epoxy quartz mortar twice, after the mortar layer is solidified, coating epoxy soil twice, sealing the sand hole and the air hole, and taking out the PVC balloon after the middle coating is solidified;
step 6, polishing the epoxy primer coat, and coating the epoxy primer coat on the epoxy primer coat;
and 7, finishing the operation.
Compared with the traditional method for leveling the waffle hole opening by only relying on manpower, the method greatly improves the working efficiency and effectively ensures the quality of epoxy construction. The method is characterized in that the special manual treatment of the waffle holes is not needed, the construction can be carried out according to the normal epoxy procedure by filling PVC balloons into the waffle holes, the work efficiency is 300-350 square meters/day/person, and the method has a dramatic progress compared with the efficiency of 8-10 holes/day/person in the traditional process.
Detailed Description
The invention is further illustrated by the following specific examples.
A method for improving epoxy construction efficiency of cast-in-situ floor waffle holes comprises
Step 1, checking the flatness of the floor and ceiling of a concrete building by using a 2-meter guiding rule, recording a clearance value, and marking the over-high positions and over-low positions of the floor and ceiling of the building;
step 2, polishing the concrete base layer on the upper surface of the waffle hole by using a grinding machine or a double-sided stone grinding machine, polishing key points if the concrete base layer is too high in the step 1, and repairing the too low parts by using quartz sand to ensure that the integral flatness of the concrete base layer on the upper surface of the waffle hole is +/-8 mm/2 m;
step 3, performing epoxy primer coating construction, and adopting roller coating or blade coating to fully soak the concrete to play a role in curing;
step 4, after the bottom coat is solidified, inflating a PVC balloon with a lifting ring or a handle and a wall thickness of not less than 0.5mm, and embedding the PVC balloon into the waffle hole, wherein the PVC balloon is customized according to the diameter of the waffle hole, the diameter of the balloon is slightly larger than the diameter of the waffle hole when the inflation amount reaches 80%, and the lifting ring is upward during embedding;
step 5, after embedding the PVC balloon, firstly coating epoxy resin with a quartz sand trowel to scrape epoxy quartz mortar twice, after the mortar layer is solidified, coating epoxy soil twice, sealing the sand hole and the air hole, and taking out the PVC balloon after the middle coating is solidified;
step 6, polishing the epoxy primer coat, and coating the epoxy primer coat on the epoxy primer coat;
and 7, finishing the operation.
Compared with the traditional method for leveling the waffle hole opening by only relying on manpower, the method greatly improves the working efficiency and effectively ensures the quality of epoxy construction. The method is characterized in that the special manual treatment of the waffle holes is not needed, the construction can be carried out according to the normal epoxy procedure by filling PVC balloons into the waffle holes, the work efficiency is 300-350 square meters/day/person, and the method has a dramatic progress compared with the efficiency of 8-10 holes/day/person in the traditional process.
Claims (1)
1. A method for improving the epoxy construction efficiency of a cast-in-situ floor waffle hole is characterized by comprising the following steps: comprises that
Step 1, checking the flatness of the floor and ceiling of a concrete building by using a 2-meter guiding rule, recording a clearance value, and marking the over-high positions and over-low positions of the floor and ceiling of the building;
step 2, polishing the concrete base layer on the upper surface of the waffle hole by using a grinding machine or a double-sided stone grinding machine, polishing key points if the concrete base layer is too high in the step 1, and repairing the too low parts by using quartz sand to ensure that the integral flatness of the concrete base layer on the upper surface of the waffle hole is +/-8 mm/2 m;
step 3, performing epoxy primer coating construction, and adopting roller coating or blade coating to fully soak the concrete to play a role in curing;
step 4, after the bottom coat is solidified, inflating a PVC balloon with a lifting ring or a handle and a wall thickness of not less than 0.5mm, and embedding the PVC balloon into the waffle hole, wherein the PVC balloon is customized according to the diameter of the waffle hole, the diameter of the balloon is slightly larger than the diameter of the waffle hole when the inflation amount reaches 80%, and the lifting ring is upward during embedding;
step 5, after embedding the PVC balloon, firstly coating epoxy resin with a quartz sand trowel to scrape epoxy quartz mortar twice, after the mortar layer is solidified, coating epoxy soil twice, sealing the sand hole and the air hole, and taking out the PVC balloon after the middle coating is solidified;
step 6, polishing the epoxy primer coat, and coating the epoxy primer coat on the epoxy primer coat;
and 7, finishing the operation.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911159372.8A CN110835998A (en) | 2019-11-22 | 2019-11-22 | Method for improving epoxy construction efficiency of cast-in-situ floor waffle holes |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911159372.8A CN110835998A (en) | 2019-11-22 | 2019-11-22 | Method for improving epoxy construction efficiency of cast-in-situ floor waffle holes |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110835998A true CN110835998A (en) | 2020-02-25 |
Family
ID=69577041
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201911159372.8A Pending CN110835998A (en) | 2019-11-22 | 2019-11-22 | Method for improving epoxy construction efficiency of cast-in-situ floor waffle holes |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110835998A (en) |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6061993A (en) * | 1995-10-13 | 2000-05-16 | Safety Rail System As | Construction module, method for producing such modules and the use of the module |
CN102433996A (en) * | 2011-09-29 | 2012-05-02 | 中国建筑第八工程局有限公司 | Method for constructing wafer board with SMC (Sheet Molding Compound) hole forming mould |
CN107023104A (en) * | 2017-06-05 | 2017-08-08 | 中建八局第建设有限公司 | A kind of wafer board construction technology for clean room |
CN107130796A (en) * | 2017-06-05 | 2017-09-05 | 中建八局第建设有限公司 | A kind of clean room wafer board flatness control methods |
CN108756035A (en) * | 2018-05-31 | 2018-11-06 | 上海宝冶集团有限公司 | A kind of waffle board construction method that whole cylinder is removable |
CN109184148A (en) * | 2018-09-30 | 2019-01-11 | 信息产业电子第十设计研究院科技工程股份有限公司 | A kind of toilet's wafer board wafer cone flooring epoxy construction improvement engineering method |
CN109322501A (en) * | 2018-11-14 | 2019-02-12 | 中建八局第建设有限公司 | A kind of aperture SMC epoxy construction protecting device |
CN209443812U (en) * | 2018-11-14 | 2019-09-27 | 中建八局第一建设有限公司 | A kind of aperture SMC epoxy construction protecting device |
-
2019
- 2019-11-22 CN CN201911159372.8A patent/CN110835998A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US6061993A (en) * | 1995-10-13 | 2000-05-16 | Safety Rail System As | Construction module, method for producing such modules and the use of the module |
CN102433996A (en) * | 2011-09-29 | 2012-05-02 | 中国建筑第八工程局有限公司 | Method for constructing wafer board with SMC (Sheet Molding Compound) hole forming mould |
CN107023104A (en) * | 2017-06-05 | 2017-08-08 | 中建八局第建设有限公司 | A kind of wafer board construction technology for clean room |
CN107130796A (en) * | 2017-06-05 | 2017-09-05 | 中建八局第建设有限公司 | A kind of clean room wafer board flatness control methods |
CN108756035A (en) * | 2018-05-31 | 2018-11-06 | 上海宝冶集团有限公司 | A kind of waffle board construction method that whole cylinder is removable |
CN109184148A (en) * | 2018-09-30 | 2019-01-11 | 信息产业电子第十设计研究院科技工程股份有限公司 | A kind of toilet's wafer board wafer cone flooring epoxy construction improvement engineering method |
CN109322501A (en) * | 2018-11-14 | 2019-02-12 | 中建八局第建设有限公司 | A kind of aperture SMC epoxy construction protecting device |
CN209443812U (en) * | 2018-11-14 | 2019-09-27 | 中建八局第一建设有限公司 | A kind of aperture SMC epoxy construction protecting device |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN102061798B (en) | Construction method of epoxy self-leveling floor with concrete sealing curing agent and thereof | |
US20160083967A1 (en) | Method for finishing a composite surface and a grounting pan for finishing a composite surface | |
CN101457581A (en) | Construction method for auto-flowing floor | |
CN102251455A (en) | Vibration-free anti-slip lane and construction method thereof | |
KR102363802B1 (en) | The construction method of terrazzo | |
CN112459395A (en) | High-strength wear-resistant floor and construction method thereof | |
CN203783173U (en) | Mold-proof structure for wall surface repair construction | |
CN110306819B (en) | Method for repairing red brick outer wall of historic building | |
CN113152841A (en) | Epoxy self-leveling ground construction method for concrete sealing curing agent | |
CN110835998A (en) | Method for improving epoxy construction efficiency of cast-in-situ floor waffle holes | |
CN105178562A (en) | Inorganic crystal grindstone integrated terrace system and construction process thereof | |
CN111734085A (en) | Floating integral terrace and construction method thereof | |
US8898994B1 (en) | Method for sealing wood subfloors | |
CN110821181A (en) | Ground leveling method | |
CN201908415U (en) | Wall decorative board layer structure | |
KR20160016350A (en) | The construction method of floor covering materials using concrete stain | |
CN110130615B (en) | Indoor composite floor based on phosphorus-magnesium material and self-leveling gypsum and construction method thereof | |
KR20140109022A (en) | Functionality special mortar composition use Method of water proofing | |
CN209742297U (en) | Terrace coating structure of carborundum wear-resistant paint for garage | |
CN109853906B (en) | Construction process of ceramic sand terrace | |
JP4364003B2 (en) | Surface repair method for lightweight cellular concrete panels | |
CN109763573B (en) | Water stop ridge and construction method thereof | |
TW201710584A (en) | Construction method of post-fabricating old building wall surface into exposed concrete without needs of templates and grouting, thereby reducing cost and increasing construction efficiency | |
CN111021775A (en) | Repairing method for local cracks of hardened terrace | |
CN212836509U (en) | Floating integral terrace |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |