CN110630277A - Protective structure and construction method for existing tunnel under short-distance crossing working condition of shield - Google Patents

Protective structure and construction method for existing tunnel under short-distance crossing working condition of shield Download PDF

Info

Publication number
CN110630277A
CN110630277A CN201911022433.6A CN201911022433A CN110630277A CN 110630277 A CN110630277 A CN 110630277A CN 201911022433 A CN201911022433 A CN 201911022433A CN 110630277 A CN110630277 A CN 110630277A
Authority
CN
China
Prior art keywords
pressure relief
glass fiber
fiber reinforced
reinforced plastic
shield
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201911022433.6A
Other languages
Chinese (zh)
Other versions
CN110630277B (en
Inventor
魏纲
齐永洁
吴华君
章丽莎
蒋吉清
尹鑫晟
陈建兰
吴俊峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yiwu Industrial and Commercial College
Zhejiang University City College ZUCC
Original Assignee
Yiwu Industrial and Commercial College
Zhejiang University City College ZUCC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yiwu Industrial and Commercial College, Zhejiang University City College ZUCC filed Critical Yiwu Industrial and Commercial College
Priority to CN201911022433.6A priority Critical patent/CN110630277B/en
Publication of CN110630277A publication Critical patent/CN110630277A/en
Application granted granted Critical
Publication of CN110630277B publication Critical patent/CN110630277B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • E21D20/021Grouting with inorganic components, e.g. cement
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • E21D21/0026Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection characterised by constructional features of the bolts
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/06Making by using a driving shield, i.e. advanced by pushing means bearing against the already placed lining

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Geology (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Inorganic Chemistry (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a protective structure and a construction method of an existing tunnel under the working condition of short-distance crossing of a shield, belonging to the technical field of subway tunnel structure reinforcement and protection, wherein the protective structure is arranged at a segment grouting hole; the protective cover is fixed on the inner surface of the pipe piece, and the pumping pipe is communicated with the protective cover and the vacuum pump; an opening metal sleeve is arranged in the protective cover, the top end of the opening metal sleeve is contacted with the protective cover, the bottom of the opening metal sleeve is connected with one end of a metal pipe section, the metal pipe section is embedded in the grouting hole, and a pressure relief opening is arranged on the opening metal sleeve in the circumferential direction at a position close to the grouting hole; a pressure spring is arranged in the opening metal sleeve, the top end of the pressure spring is fixed on the protective cover, and the bottom end of the pressure spring is connected with a pressure relief piston; the pressure relief piston is arranged in the metal pipe section; outside the tunnel, one end of the glass fiber reinforced plastic hollow anchor rod is connected with a metal pipe section in the grouting hole, and a reserved small hole is formed in the surface of the glass fiber reinforced plastic hollow anchor rod in the annular direction. The invention has the dual functions of water pressure relief and soil pressure relief, and utilizes the glass fiber reinforced plastic hollow anchor rod for connection and reinforcement.

Description

Protective structure and construction method for existing tunnel under short-distance crossing working condition of shield
Technical Field
The invention belongs to the technical field of subway tunnel structure reinforcement and protection, and particularly relates to a protective structure and a construction method of an existing tunnel under the working condition of short-distance crossing of a shield, which are suitable for protecting the structure of the existing tunnel under the working condition of short-distance crossing of the shield, and are particularly suitable for deformation prevention and control under the action of uneven grouting and soil extrusion additional load applied to the annular direction of the existing tunnel.
Background
The urban subway is convenient to go out, urban traffic congestion can be effectively relieved, and many domestic cities begin subway engineering construction. With the development of subway wire nets, more and more working conditions that the shield passes through the existing tunnel in a short distance appear in the urban shallow stratum space.
The shield is large in construction risk in short-distance crossing, and the stratum is often reinforced by adopting an advanced pre-grouting method. The grout injected into the soil layer has high control requirement, the injection amount is too small to achieve the expected reinforcing effect, the injection amount is too large to easily cause the grout to flow randomly, and the diffusion process, the diffusion range and the filling compaction degree of the grout are difficult to accurately control. Therefore, in practical engineering, the short-distance crossing of the shield often has deformation influence on the existing tunnel in the circumferential direction and the longitudinal direction due to advanced grouting, and certain protective measures need to be taken to protect the existing tunnel. The existing tunnel protection measures which are applied more at present comprise measures of reinforcing by annular grouting, arranging a fixed anchor rod, a pressure relief hole and the like. The diffusion range of the annular grouting is difficult to control, and a large amount of grout is often injected to reinforce a certain area, so that additional pollution is caused to the environment; the arrangement of the anchor rods under the multi-line overlapping working condition can influence the subsequent excavation of the newly-built shield tunnel; set up the pressure release hole and often just let out water pressure, alleviate the come-up deformation of shield tunnel, and pressure relief device itself is simple, can further develop in the functionality.
In summary, the prior art generally has the problems of poor protection effect, influence on subsequent adjacent shield excavation, incomplete functions and the like, and needs to be solved by improving the technology urgently.
Disclosure of Invention
The invention aims to overcome the defects in the prior art and provides a protective structure and a construction method of an existing tunnel under the working condition of short-distance crossing of a shield.
In order to realize the technical purpose, the invention adopts the following technical scheme:
a shield constructs the protective structure of the existing tunnel under the short-range crossing working condition, the protective structure is set up in the grouting hole of the segment; the device comprises a protective cover, a pressure spring, a pumping pipe, an opening metal sleeve, a pressure relief opening, a pressure relief piston, a metal pipe section, a glass fiber reinforced plastic hollow anchor rod, a reserved small hole and a vacuum pump;
in the tunnel, a protective cover is fixed on the inner surface of the segment and covers the grouting holes, one end of the pumping pipe is communicated with the protective cover, and the other end of the pumping pipe is communicated with a vacuum pump; an opening metal sleeve is arranged in the protective cover, the top end of the opening metal sleeve is contacted with the protective cover, the bottom of the opening metal sleeve is connected with one end of a metal pipe section, the metal pipe section is embedded in the grouting hole, and a pressure relief opening is arranged on the opening metal sleeve in the circumferential direction at a position close to the grouting hole; a pressure spring is arranged in the opening metal sleeve, the top end of the pressure spring is fixed on the protective cover, and the bottom end of the pressure spring is connected with a pressure relief piston; the pressure relief piston is arranged in the metal pipe section;
outside the tunnel, one end of the glass fiber reinforced plastic hollow anchor rod is connected with a metal pipe section in the grouting hole, and a reserved small hole is formed in the surface of the glass fiber reinforced plastic hollow anchor rod in the annular direction.
Preferably, a plurality of polyurethane waterproof rings are arranged at the contact part of the outer surface of the metal pipe section and the pipe piece.
Preferably, the other end of the glass fiber reinforced plastic hollow anchor rod is provided with a metal anchor tip, and the glass fiber reinforced plastic hollow anchor rod and the metal anchor tip can be connected through threads.
Preferably, the anchor tip is made of a hard metal material.
Preferably, the pressure relief piston is cylindrical, the height of the pressure relief piston is the same as the wall thickness of the pipe piece, and the outer diameter of the pressure relief piston is slightly smaller than the inner diameter of the metal pipe section.
Preferably, the pressure relief piston comprises an upper solid sealing layer and a lower glued transparent stone layer, and the two layers can be fixed through gluing.
Preferably, the metal pipe section is embedded in the grouting hole, the outer diameter of the metal pipe section is slightly smaller than the inner diameter of the grouting hole, the metal pipe section is in threaded connection with the glass fiber reinforced plastic hollow anchor rod and the opening metal sleeve, the outer diameter of the pressure relief piston is slightly smaller than the inner diameters of the metal pipe section and the opening metal sleeve, and the pressure relief piston slides in the metal pipe section and the opening metal sleeve.
Preferably, each ring of the glass fiber reinforced plastic hollow anchor rod is provided with 3-4 rings, and the distance between every two rings is 10-20 cm.
Preferably, the protective cover is fixed inside the pipe piece through a rivet, the protective cover is fully attached to the pipe piece, and certain sealing treatment is carried out at a gap. The protective cover material can be toughened transparent glass.
The second purpose of the invention is to provide a construction method of the existing tunnel protection structure under the shield short-distance crossing working condition, which comprises the following steps:
1) marking the position of a grouting hole to be treated on a duct piece in advance before construction; a plurality of grouting holes are distributed in the tunnel annularly, multiple rings are taken from the left and the right respectively by taking the central axis of penetration of the shield as the center, and reinforcement protection is carried out by the rings or the spacing rings one by one;
2) installing the glass fiber reinforced plastic hollow anchor rod: connecting a metal pipe section to the tail part of the glass fiber reinforced plastic hollow anchor rod through threads, driving the treated glass fiber reinforced plastic hollow anchor rod into a wall rear soil layer through a grouting hole by utilizing pressing-in equipment, and filling cement mortar into an annular gap between the metal pipe section and the grouting hole for sealing;
3) grouting and reinforcing the glass fiber reinforced plastic hollow anchor rod: after the glass fiber reinforced plastic hollow anchor rod is installed, cement mortar is directly injected to fill the glass fiber reinforced plastic hollow anchor rod, and a surrounding soil layer is reinforced;
4) installing an internal protection structure: a pressure relief piston is required to be arranged inside a metal pipe section close to a grouting hole on one side through which the shield passes, then an opening metal sleeve is fixed on the metal pipe section through threaded connection, and a protective cover is arranged in place after the initial elasticity of a pressure spring is adjusted;
5) the pressure relief device works: connecting the pumping pipe to a vacuum pump, and starting the vacuum pump to work in the shield crossing process;
6) and (3) post-processing: after the influence caused by the penetration of the shield is stable, the vacuum pump is closed, the protective cover, the pressure spring, the pumping pipe, the opening metal sleeve and the pressure relief piston are removed, cement mortar is directly injected to fill the glass fiber reinforced plastic hollow anchor rod, and the grouting hole is sealed.
The invention has the beneficial effects that:
1) perfecting pressure relief device and regulating water and soil pressure
The protection structure integrates the functions of water pressure relief and soil pressure relief, and adopts a two-stage pressure relief mode. Along with the contraction of the pressure spring, the pressure relief piston moves upwards, the solid sealing layer is separated from the inner surface of the pipe piece, the rubber permeable stone layer is exposed, the water in the soil layer begins to be discharged, and the pressure relief of the excess pore water pressure is carried out; if the soil and water pressure on the outside of the segment is too high, and the requirement cannot be met only by the sluicing pressure, the pressure spring can be further compressed, the pressure relief piston continues to move upwards until the glued permeable rock layer is completely separated from the inner surface of the segment, the whole pressure relief piston is exposed, soil particles and moisture begin to be discharged, and the soil pressure and the water pressure in the outside soil layer are released simultaneously; after the external water and soil pressure recovers to be normal, the pressure spring rebounds gradually under the action of initial elastic force, the pressure relief piston is pressed back to the inside of the grouting hole, and the automatic pressure relief process is completed.
2) Specially designed glass fiber reinforced plastic anchor rod beneficial to pressure relief and reinforcement
The glass fiber reinforced plastic hollow anchor rod is provided with a reserved small hole along the annular direction and extends into a soil layer, and the soil layer in a certain range of the annular direction of the existing tunnel can be subjected to adjustment of super-pore water pressure and soil layer additional stress in the pressure relief process; and in the slip casting process, reserve the aperture and regard as the slip casting hole, shunt into the aperture slip casting with the centralized slip casting mode originally, during the grout of injection can evenly permeate to surrounding soil layer, make glass steel hollow anchor rod better with the reinforcement effect of surrounding soil layer, avoid the secondary influence of slip casting simultaneously. In addition, the glass fiber reinforced plastic anchor rod is used as an environment-friendly material and left in a soil body, so that the environment cannot be polluted, and the material is easy to cut. The glass fiber reinforced plastic anchor rod is adopted to replace a conventional anchor rod, so that the purpose of reinforcing the existing tunnel can be achieved, and influence on subsequent adjacent shield pipeline excavation can be avoided.
3) The reinforcing structure is preset to reduce the crossing hazard
No matter the pressure relief device or the anchor rod structure is installed before the shield penetrates, the flexible design and the collocation can be carried out according to the requirements of actual working conditions, the effects of pressure buffering, tensile strength and soil layer reinforcement are respectively achieved in the penetrating process, and the influence and the harm to the existing tunnel caused by the short-distance penetration of the shield are reduced.
4) The assembly is quick and convenient to recover
The protective cover, the pressure spring, the pumping pipe, the opening metal sleeve and the pressure relief piston are all prefabricated in a factory, the field assembly is rapid, the construction is convenient, and after the shield passes through the shield stably, all or part of the shield can be recycled, so that the cost is saved.
Drawings
FIG. 1 is a schematic view of the overall structure of the present invention;
FIG. 2 is a schematic view of a partial structure of a pressure relief device;
3-5 are schematic views of the working process of the pressure relief device;
FIG. 6 is a schematic diagram of an existing tunnel reinforcing scheme under a shield short-distance upward-passing working condition;
FIG. 7 is a schematic diagram of an existing tunnel reinforcing scheme under a shield short-distance downward-penetrating working condition;
FIG. 8 is a schematic view of the arrangement of the reinforcing structure of the present invention along the longitudinal direction of an existing tunnel;
FIG. 9 is a schematic view of the pressure relief process of the present invention;
description of reference numerals: a protective cover 1; a pressure spring 2; a pumping pipe 3; a rivet 4; an open metal sleeve 5; a polyurethane waterproof ring 6; a pressure relief port 7; a pressure relief piston 8; a solid sealing layer 9; cementing a permeable stone layer 10; a metal tube segment 11; a glass fiber reinforced plastic hollow anchor rod 12; a reserved small hole 13; an anchor tip 14; a grouting hole 15; a vacuum pump 16.
Detailed Description
The present invention will be further described with reference to the following examples. The following examples are set forth merely to aid in the understanding of the invention. It should be noted that, for those skilled in the art, it is possible to make various improvements and modifications to the present invention without departing from the principle of the present invention, and those improvements and modifications also fall within the scope of the claims of the present invention.
In addition, technical solutions between various embodiments may be combined with each other, but must be realized by a person skilled in the art, and when the technical solutions are contradictory or cannot be realized, such a combination should not be considered to exist, and is not within the protection scope of the present application.
As shown in fig. 1 to 8, the protection structure for an existing tunnel under a shield short-distance crossing condition provided in this embodiment is disposed at a segment grouting hole 15; the device comprises a protective cover 1, a pressure spring 2, a pumping pipe 3, a rivet 4, an opening metal sleeve 5, a polyurethane waterproof ring 6, a pressure relief opening 7, a pressure relief piston 8, a solid sealing layer 9, a glued permeable stone layer 10, a metal pipe section 11, a glass fiber reinforced plastic hollow anchor rod 12, a reserved small hole 13, an anchor tip 14, a grouting hole 15 and a vacuum pump 16; in the tunnel, a protective cover 1 is fixed on the inner surface of a segment through rivets 4 and covers a grouting hole 15, one end of a pumping pipe 3 is connected with the protective cover 1, and the other end of the pumping pipe is connected with a vacuum pump 16; an opening metal sleeve 5 is arranged in the protective cover 1, the top end of the opening metal sleeve 5 is in contact with the protective cover 1, the bottom of the opening metal sleeve 5 is connected with a metal pipe section 11, and a rectangular pressure relief opening 7 is arranged on the opening metal sleeve 5 in the position close to the grouting hole 15 along the annular direction; a pressure spring 2 is arranged in the opening metal sleeve 5, the top end of the pressure spring 2 is fixed on the protective cover 1, and the bottom end of the pressure spring is connected with a pressure relief piston 8; the metal pipe section 11 is embedded in the grouting hole 15; outside the tunnel, one end of the glass fiber reinforced plastic hollow anchor rod 12 is connected with the metal pipe section 11 in the grouting hole 15, the other end is provided with a metal anchor tip 14, and the surface of the glass fiber reinforced plastic hollow anchor rod 12 is annularly provided with a reserved small hole 13.
Before the shield passes through the inner surface of the pipe piece in a short distance, a structure shown in figure 1 is installed in advance. When the pressure relief piston 8 is under the action of external excess pore water pressure and soil additional load, the lower surface of the pressure relief piston 8 is extruded, the pressure spring 2 is compressed, and the pressure relief piston 8 moves upwards; because the upper layer of the pressure relief piston 8 is a solid sealing layer 9, water and soil are not allowed to pass through, the lower layer is a glued permeable rock layer 10, water can be allowed to permeate, and the two layers are fixed through gluing. When the solid sealing layer 9 on the upper layer of the pressure relief piston 8 is completely exposed out of the inner surface of the duct piece, the vacuum pump 16 is started, water is partially divided into the protective cover 1 under the action of external pressure and is discharged through the pumping pipe 2, the excess pore water pressure outside the duct piece begins to drop, when the pure water pressure cannot meet the requirement, the external pressure continues to compress the pressure spring 2, and the pressure relief piston 8 further moves upwards; when the glued permeable rock layer 10 is completely exposed out of the inner surface of the segment, water pressure and soil pressure are released simultaneously, and water and soil pressed in from the outside are discharged through the pumping pipe 2; after pressure relief, the water and soil pressure outside the segment is reduced to a normal level, and under the action of the initial stress of the pressure spring 2, the pressure relief piston 8 returns to the original position again to block the grouting hole 15; after the influence caused by penetration is stable, the recovery pressure relief device is dismantled, cement mortar is injected to fill the glass fiber reinforced plastic hollow anchor rod 12, and the grouting hole 15 is sealed and filled.
As shown in fig. 1, the metal pipe section 11 is embedded and fixed in the grouting hole 15, and two polyurethane isolating rings 6 are annularly arranged on the contact surface of the metal pipe section and the grouting hole for preventing water; the outside of the metal pipe section 11 is connected with the glass fiber reinforced plastic hollow anchor rod 12 through threads, the top of the metal pipe section is connected with the opening metal sleeve 5 through threads, and the pressure relief piston 8 can move up and down in the opening metal sleeve 5 and the metal pipe section 11 according to the change of external pressure; the protective cover 1 is fixed on the surface of the inner wall of the pipe piece through a rivet 4, an opening metal sleeve 5 and a pressure spring 2 are connected inside the protective cover 1, a small hole is reserved on the side surface of the protective cover 1 and is connected with a pumping pipe 3 and a vacuum pump 16, so that soil particles and water discharged into the protective cover 1 can be conveniently pumped subsequently; the top of the glass fiber reinforced plastic hollow anchor rod 12 is provided with an anchor tip 14, the surface of the glass fiber reinforced plastic hollow anchor rod is provided with reserved small holes 13 at intervals along the circumferential direction, the reserved small holes 13 are used as pressure relief holes in the front stage and are used as grouting holes in the back stage internal grouting process.
As shown in fig. 2, the open metal sleeve 5, the pressure relief piston 8 and the metal pipe segment 11 are separated from each other. A plurality of rectangular pressure relief ports 7 are arranged at the lower position of the upper opening metal pipe sleeve 5 along the annular direction; two polyurethane waterproof rings 6 are arranged on the surface of the lower metal pipe section 11 along the annular direction, and the lower part of the lower metal pipe section is connected with the glass fiber reinforced plastic hollow anchor rod 12 through threads; the upper opening metal sleeve 5 is connected with the lower metal pipe section 11 through threads, and the inner diameters of the upper opening metal sleeve and the lower opening metal sleeve are slightly larger than the outer diameter of the pressure relief piston 8.
As shown in fig. 3, when an external soil layer is affected by adjacent shield excavation, the excess pore water pressure in the soil body and the additional load of the soil body extrude the lower surface of the internal pressure relief piston 8 through the reserved small hole 13 on the surface of the glass fiber reinforced plastic hollow anchor rod 12, when the external pressure is greater than the initial pressure of the pressure spring 2, the pressure spring 2 starts to contract, and the pressure relief piston 8 moves upwards; when the upper solid sealing layer 9 of the pressure relief piston 8 is not completely exposed out of the inner surface of the pipe piece, the whole pressure relief device is still in a closed state.
As shown in fig. 4, when the external pressure continues to increase, the compression spring 2 continues to be compressed, the pressure relief piston 8 further moves upwards, after the solid sealing layer 9 completely exposes out of the inner wall of the duct piece, the glued permeable stone layer 10 contacts with the inner wall, and under the action of the external pressure, moisture can flow into the protective cover 1 through the glued permeable stone layer 10; at this time, the vacuum pump 16 is turned on to pump out the discharged water through the pumping pipe 3, thereby reducing the excess pore water pressure outside the segment.
As shown in fig. 5, when the requirement cannot be met only by the drainage pressure, the compression spring 2 will be compressed continuously, the pressure relief piston 8 will move further upward, and after the glued permeable stone layer 10 is exposed out of the inner wall of the segment, part of the moisture and soil particles will be pressed into the protective cover 1 under the action of external pressure; at this time, the vacuum pump 16 pumps out part of the discharged water and soil particles through the pumping pipe 3, thereby reducing the water and soil pressure outside the segment.
The construction method of the existing tunnel protection structure under the shield short-distance crossing working condition, as shown in fig. 9, includes the following steps:
1) and (3) designing a reinforcing scheme: as shown in fig. 6, under the working condition that the shield penetrates the existing tunnel at a short distance, 6 grouting holes 15 are analyzed according to the ring direction of the segment, and the segment is sequentially named as a, b, c, d, e and f in the clockwise direction. The grouting holes 15 at the positions b, c and d are provided with corresponding pressure relief devices, and the pressure relief devices comprise a protective cover 1 and pressure relief devices inside the grouting holes 15 and are used for buffering excess pore water pressure and soil additional load caused by tunneling of an upper shield; a. and e, only installing the glass fiber reinforced plastic hollow anchor rod 12 in the grouting holes 15 at the three positions of f and e, and then directly injecting cement mortar to fill the glass fiber reinforced plastic hollow anchor rod 12, wherein the small reserved holes 13 are formed in the surface of the glass fiber reinforced plastic hollow anchor rod 12, so that the injected slurry can uniformly permeate into the surrounding soil layer, and the reinforcing effect of the glass fiber reinforced plastic hollow anchor rod 12 and the surrounding soil layer is better.
As shown in fig. 7, under the working condition that the shield penetrates the existing tunnel at a short distance, 6 grouting holes 15 are analyzed according to the annular direction of the segment, and the analysis is sequentially named as a, b, c, d, e and f in the clockwise direction. The grouting holes 15 at the three positions a, b and f are provided with corresponding protection structures for buffering the excess pore water pressure and the soil body additional load caused by the lower shield tunneling; c. d, the slip casting hole 15 of three department of e only installs glass steel hollow anchor 12, later directly pours into cement mortar and fills glass steel hollow anchor 12 into, because glass steel hollow anchor 12 surface sets up reservation aperture 13, the grout of pouring into can evenly permeate to in the soil layer around, makes glass steel hollow anchor 12 and the reinforcing effect of soil layer around better.
As shown in fig. 8, five-ring segments are taken along the longitudinal direction of the existing tunnel as reference, the protection structure related to the invention is arranged at intervals of one ring, each ring segment is provided with six grouting holes, glass fiber reinforced plastic hollow anchor rods 12 are respectively arranged, and a protection cover 1 and a corresponding protection structure are arranged at the designed position according to the reinforcing scheme; because the pipe sheet rings are assembled in a staggered joint mode, the grouting holes 15 are not in the uniform position, and the installed glass fiber reinforced plastic hollow anchor rods 12 are arranged in the soil layer in a staggered mode, so that the pressure relief and grouting effects are better; taking the shield penetrating through the central axis as a center, respectively taking 5 rings from the left and the right, and reinforcing and protecting the rings one by one or spacing rings.
2) Construction preparation: before construction, preparing enough structural accessories such as a protective cover 1, a pressure relief piston 8, a glass fiber reinforced plastic hollow anchor rod 12 and the like, installing two polyurethane waterproof rings 6 on the surface of a metal pipe section 11 in advance along the annular direction, completing assembly of the protective cover 1, a pressure spring 2, a pumping pipe 3, an opening metal sleeve 5 and the pressure relief piston 8 in advance, and placing the protective cover 1, the pressure spring 2, the pumping pipe 3, the opening metal sleeve 5 and the pressure relief piston 8 at a specified position near a construction;
3) positioning and paying off: according to the design of the reinforcing scheme, the positions of grouting holes to be treated are marked on the duct piece in advance before construction. During paying off, the positions of existing instruments and equipment in the existing tunnel are paid attention to, and the instruments and the equipment are reasonably arranged, so that influence on construction in the later period is avoided;
4) installing the glass fiber reinforced plastic hollow anchor rod 12: connecting a metal anchor tip 14 with the top of a glass fiber reinforced plastic hollow anchor rod 12 in a threaded manner, connecting a metal pipe section 11 with the tail of the glass fiber reinforced plastic hollow anchor rod 12 in a threaded manner, driving the processed glass fiber reinforced plastic hollow anchor rod 12 into a soil layer behind a wall through a grouting hole 15 by using pressing-in equipment, slowly pressing in, checking whether the driven angle is deviated constantly, finding that the deviation is timely corrected, just installing and embedding the metal pipe section 11 into the grouting hole 15 of a pipe sheet ring after the glass fiber reinforced plastic hollow anchor rod 12 is completely driven in, and filling certain cement mortar into an annular gap between the metal pipe section 11 and the grouting hole 15 for sealing after checking that the installation position is correct;
5) grouting and reinforcing the glass fiber reinforced plastic hollow anchor rod 12: according to the reinforcing scheme, after the glass fiber reinforced plastic hollow anchor rod 12 is installed, cement mortar is directly injected into the partial grouting holes 15 to fill the glass fiber reinforced plastic hollow anchor rod 12, and the injected slurry can uniformly permeate into the surrounding soil layer due to the reserved small holes 13 formed in the surface of the glass fiber reinforced plastic hollow anchor rod 12, so that the reinforcing effect of the glass fiber reinforced plastic hollow anchor rod 12 and the surrounding soil layer is better;
6) installing an internal protection structure: according to the reinforcing scheme, a protection structure is arranged at a specified position, firstly, a pressure relief piston 8 is arranged inside a metal pipe section 11, then, an opening metal sleeve 5 is fixed on the metal pipe section 11 through threaded connection, after the initial elasticity of a pressure spring is adjusted, a transparent protective cover 1 is arranged in place and fixed on the inner wall of the pipe section by rivets 4;
7) pressure relief work: the pumping pipe 3 is connected to a vacuum pump 16, the vacuum pump 16 is started in the process of passing through the shield, and a pressure relief device starts to work, so that the influence of excess pore water pressure caused by passing through the shield and additional load generated by soil layer extrusion is reduced;
8) post-processing and component part recovery: after the shield penetration is stable, the vacuum pump 16 is closed, pressure relief device components such as the protective cover 1, the pressure spring 2, the pumping pipe 3, the opening metal sleeve 5, the pressure relief piston 8 and the like are removed, then cement mortar is directly injected to fill the glass fiber reinforced plastic hollow anchor rod 12, the grouting hole 15 is sealed, and finally, certain recovery processing is carried out on the components after the components are detached.
The above description is only a preferred embodiment of the present invention, and not intended to limit the scope of the present invention, and all modifications of equivalent structures and equivalent processes, which are made by using the contents of the present specification and the accompanying drawings, or directly or indirectly applied to other related technical fields, are included in the scope of the present invention.

Claims (10)

1. A shield constructs the protective structure of the existing tunnel under the short-range crossing working condition, the protective structure is set up in the grouting hole of the segment; the device is characterized by comprising a protective cover, a pressure spring, a pumping pipe, an opening metal sleeve, a pressure relief opening, a pressure relief piston, a metal pipe section, a glass fiber reinforced plastic hollow anchor rod, a reserved small hole and a vacuum pump;
in the tunnel, a protective cover is fixed on the inner surface of the segment and covers the grouting holes, one end of the pumping pipe is communicated with the protective cover, and the other end of the pumping pipe is communicated with a vacuum pump; an opening metal sleeve is arranged in the protective cover, the top end of the opening metal sleeve is contacted with the protective cover, the bottom of the opening metal sleeve is connected with one end of a metal pipe section, the metal pipe section is embedded in the grouting hole, and a pressure relief opening is arranged on the opening metal sleeve in the circumferential direction at a position close to the grouting hole; a pressure spring is arranged in the opening metal sleeve, the top end of the pressure spring is fixed on the protective cover, and the bottom end of the pressure spring is connected with a pressure relief piston; the pressure relief piston is arranged in the metal pipe section;
outside the tunnel, one end of the glass fiber reinforced plastic hollow anchor rod is connected with a metal pipe section in the grouting hole, and a reserved small hole is formed in the surface of the glass fiber reinforced plastic hollow anchor rod in the annular direction.
2. The protective structure for the existing tunnel under the shield short-distance crossing working condition according to claim 1, wherein the pressure relief piston comprises an upper solid sealing layer and a lower glued permeable stone layer.
3. The protective structure for the existing tunnel under the shield short-distance crossing working condition according to claim 1, wherein a plurality of polyurethane waterproof rings are arranged at the contact part of the outer surface of the metal pipe section and the pipe piece.
4. The protective structure for the existing tunnel under the working condition of close range crossing of the shield according to claim 1, wherein a metal anchor tip is arranged at the other end of the glass fiber reinforced plastic hollow anchor rod.
5. The protective structure for the existing tunnel under the shield short-distance crossing working condition according to claim 1, wherein the anchor tip is made of hard metal material.
6. The protective structure for the existing tunnel under the shield short-distance crossing working condition according to claim 1, wherein the pressure relief piston is cylindrical and has the same height as the wall thickness of the duct piece.
7. The protective structure for the existing tunnel under the shield short-distance crossing working condition according to claim 1, wherein the metal pipe section is in threaded connection with the glass fiber reinforced plastic hollow anchor rod and the open metal sleeve, and the pressure relief piston slides in the metal pipe section and the open metal sleeve.
8. The protective structure for the existing tunnel under the shield short-distance crossing working condition according to claim 1, wherein 3-4 rings of the glass fiber reinforced plastic hollow anchor rods are arranged, and the distance between each two rings is 10-20 cm.
9. The protective structure for the existing tunnel under the shield short-distance crossing working condition according to claim 1, wherein the protective cover is fixed inside the segment through rivets, the protective cover and the segment are fully attached, and certain sealing treatment is performed at a gap.
10. A construction method of an existing tunnel protection structure under the working condition of short-distance crossing of a shield is characterized by comprising the following steps: the method comprises the following steps:
1) marking the position of a grouting hole to be treated on a duct piece in advance before construction; a plurality of grouting holes are distributed in the tunnel annularly, multiple rings are taken from the left and the right respectively by taking the central axis of penetration of the shield as the center, and reinforcement protection is carried out by the rings or the spacing rings one by one;
2) installing the glass fiber reinforced plastic hollow anchor rod: connecting a metal pipe section to the tail part of the glass fiber reinforced plastic hollow anchor rod through threads, driving the treated glass fiber reinforced plastic hollow anchor rod into a wall rear soil layer through a grouting hole by utilizing pressing-in equipment, and filling cement mortar into an annular gap between the metal pipe section and the grouting hole for sealing;
3) grouting and reinforcing the glass fiber reinforced plastic hollow anchor rod: after the glass fiber reinforced plastic hollow anchor rod is installed, cement mortar is directly injected to fill the glass fiber reinforced plastic hollow anchor rod, and a surrounding soil layer is reinforced;
4) installing an internal protection structure: a pressure relief piston is required to be arranged inside a metal pipe section close to a grouting hole on one side through which the shield passes, then an opening metal sleeve is fixed on the metal pipe section through threaded connection, and a protective cover is arranged in place after the initial elasticity of a pressure spring is adjusted;
5) the pressure relief device works: connecting the pumping pipe to a vacuum pump, and starting the vacuum pump to work in the shield crossing process;
6) and (3) post-processing: after the influence caused by the penetration of the shield is stable, the vacuum pump is closed, the protective cover, the pressure spring, the pumping pipe, the opening metal sleeve and the pressure relief piston are removed, cement mortar is directly injected to fill the glass fiber reinforced plastic hollow anchor rod, and the grouting hole is sealed.
CN201911022433.6A 2019-10-25 2019-10-25 Protection structure of existing tunnel under shield short-distance crossing working condition and construction method Active CN110630277B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911022433.6A CN110630277B (en) 2019-10-25 2019-10-25 Protection structure of existing tunnel under shield short-distance crossing working condition and construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911022433.6A CN110630277B (en) 2019-10-25 2019-10-25 Protection structure of existing tunnel under shield short-distance crossing working condition and construction method

Publications (2)

Publication Number Publication Date
CN110630277A true CN110630277A (en) 2019-12-31
CN110630277B CN110630277B (en) 2024-05-14

Family

ID=68977680

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911022433.6A Active CN110630277B (en) 2019-10-25 2019-10-25 Protection structure of existing tunnel under shield short-distance crossing working condition and construction method

Country Status (1)

Country Link
CN (1) CN110630277B (en)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113638750A (en) * 2021-07-13 2021-11-12 江苏思行达信息技术有限公司 Intelligent safety protection equipment for pit and tunnel operation and safety protection method
CN113898375A (en) * 2021-10-09 2022-01-07 大连地铁集团有限公司 Shield segment outer osmometer installation structure and method capable of preventing water seepage
CN115839244A (en) * 2023-02-13 2023-03-24 中铁五局集团电务工程有限责任公司 Short-distance subway shield tunnel crossing operation supporting equipment and method

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102828761A (en) * 2012-09-05 2012-12-19 淮南市顺辉锚固有限公司 Full-thread glass fiber composite hollow grouting anchor rod
KR101260292B1 (en) * 2012-08-28 2013-05-15 양재이엔지 주식회사 Grouting device and tunnel reinforce method
CN203809012U (en) * 2014-03-12 2014-09-03 广州地铁设计研究院有限公司 Shield tunnel foundation base reserved grouting and processing system
CN206397527U (en) * 2016-12-29 2017-08-11 中交第四公路工程局有限公司 A kind of supporting construction of Soft Rock Highway Tunnel
CN207554077U (en) * 2017-11-16 2018-06-29 河南理工大学 The passive harmonious supporting construction of extreme rockburst tunnel master
CN108708742A (en) * 2018-08-30 2018-10-26 沈阳建筑大学 Combined retaining structure for concrete pipe sheet anchor pole deviation
CN208184748U (en) * 2018-05-03 2018-12-04 唐钱龙 Wear the ruggedized construction of building in a kind of shield tunnel short distance side
CN109488334A (en) * 2018-10-25 2019-03-19 中铁第勘察设计院集团有限公司 Deep hole grouting reinforcement means and equipment in shield tunnel
CN209430235U (en) * 2018-11-28 2019-09-24 中国水利水电第一工程局有限公司 Wall Rock of Tunnel bracing means under a kind of complex geological condition
CN110331999A (en) * 2019-07-24 2019-10-15 古小辉 A kind of automatic decompression type grouted anchor bar
CN211397573U (en) * 2019-10-25 2020-09-01 浙江大学城市学院 Protective structure for shield to pass through existing tunnel under working condition in short distance

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101260292B1 (en) * 2012-08-28 2013-05-15 양재이엔지 주식회사 Grouting device and tunnel reinforce method
CN102828761A (en) * 2012-09-05 2012-12-19 淮南市顺辉锚固有限公司 Full-thread glass fiber composite hollow grouting anchor rod
CN203809012U (en) * 2014-03-12 2014-09-03 广州地铁设计研究院有限公司 Shield tunnel foundation base reserved grouting and processing system
CN206397527U (en) * 2016-12-29 2017-08-11 中交第四公路工程局有限公司 A kind of supporting construction of Soft Rock Highway Tunnel
CN207554077U (en) * 2017-11-16 2018-06-29 河南理工大学 The passive harmonious supporting construction of extreme rockburst tunnel master
CN208184748U (en) * 2018-05-03 2018-12-04 唐钱龙 Wear the ruggedized construction of building in a kind of shield tunnel short distance side
CN108708742A (en) * 2018-08-30 2018-10-26 沈阳建筑大学 Combined retaining structure for concrete pipe sheet anchor pole deviation
CN109488334A (en) * 2018-10-25 2019-03-19 中铁第勘察设计院集团有限公司 Deep hole grouting reinforcement means and equipment in shield tunnel
CN209430235U (en) * 2018-11-28 2019-09-24 中国水利水电第一工程局有限公司 Wall Rock of Tunnel bracing means under a kind of complex geological condition
CN110331999A (en) * 2019-07-24 2019-10-15 古小辉 A kind of automatic decompression type grouted anchor bar
CN211397573U (en) * 2019-10-25 2020-09-01 浙江大学城市学院 Protective structure for shield to pass through existing tunnel under working condition in short distance

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113638750A (en) * 2021-07-13 2021-11-12 江苏思行达信息技术有限公司 Intelligent safety protection equipment for pit and tunnel operation and safety protection method
CN113638750B (en) * 2021-07-13 2023-12-05 江苏思行达信息技术有限公司 Pit tunnel operation safety protection intelligent equipment and safety protection method
CN113898375A (en) * 2021-10-09 2022-01-07 大连地铁集团有限公司 Shield segment outer osmometer installation structure and method capable of preventing water seepage
CN115839244A (en) * 2023-02-13 2023-03-24 中铁五局集团电务工程有限责任公司 Short-distance subway shield tunnel crossing operation supporting equipment and method
CN115839244B (en) * 2023-02-13 2023-04-18 中铁五局集团电务工程有限责任公司 Short-distance subway shield tunnel crossing operation supporting equipment and method

Also Published As

Publication number Publication date
CN110630277B (en) 2024-05-14

Similar Documents

Publication Publication Date Title
CN112030964B (en) Positioning grouting anchor rod suitable for engineering seepage damage prevention and control and construction method thereof
CN110700857B (en) Composite tunnel supporting system and construction method
CN101761084B (en) Method for forming anchor in shielding manner in fluidized sand layer
CN102777189A (en) Intermediate-jacking-station-free jacking construction device of ultra-long pipe roof and method thereof
CN110630277A (en) Protective structure and construction method for existing tunnel under short-distance crossing working condition of shield
CN109440951B (en) Waterproof structure for joint of new and old concrete structures and construction process
WO2020151347A1 (en) Prefabricated prestressed anchor structure
CN105422128A (en) Method for preventing goaf gas leakage in deep shaft gob-side entry driving
CN207079627U (en) A kind of assembled underground pipe gallery member connecting structure
CN211397573U (en) Protective structure for shield to pass through existing tunnel under working condition in short distance
CN205171547U (en) Recoverable miniature stock wall
CN103603337A (en) Grouting precast pile and grouting method
CN108266207B (en) Pipe jacking in-out hole water stopping method and device suitable for deep water-rich sand layer area
KR101469603B1 (en) Pipe for piperoof with multipurpose solidarizing tube and construction method using this pipe
CN104018858A (en) Novel water stopping structure for tunneling seam in permafrost region
CN202108052U (en) Imbedding recoverable soil nail
CN103967004A (en) Supporting and protecting composite anti-slide pile suitable for high-attitude and high-intensity regions
CN208347789U (en) A kind of more joint fissure breaking surrounding rocks tunnel allows pressure type composite lining structure
CN203569575U (en) Plastic blind ditch pipe sandless precipitation well
KR102522769B1 (en) Fixing construction method of high-strength GFRP hollow bar for tunnel and ground reinforcement and its construction device
CN100417856C (en) Pressure-resistant culvert pipe with small section and circumferential stress and preparation process thereof
CN211081908U (en) Waterproof device for tunnel construction
CN205778909U (en) The pipe-plate lining structure of sluicing blood pressure lowering
CN203729290U (en) Grouting precast pile
CN220503984U (en) Anti-floating structure for basement reinforcement

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant