CN110331671A - 一种无称重平衡的转体桥转体施工方法 - Google Patents
一种无称重平衡的转体桥转体施工方法 Download PDFInfo
- Publication number
- CN110331671A CN110331671A CN201910699491.6A CN201910699491A CN110331671A CN 110331671 A CN110331671 A CN 110331671A CN 201910699491 A CN201910699491 A CN 201910699491A CN 110331671 A CN110331671 A CN 110331671A
- Authority
- CN
- China
- Prior art keywords
- block
- construction
- reinforcing bar
- swivel
- symmetrical
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
- E01D21/08—Methods or apparatus specially adapted for erecting or assembling bridges by rotational movement of the bridge or bridge sections
Abstract
本发明公开了一种无称重平衡的转体桥转体施工方法,该方法从施工规划阶段开始对转体体系进行设计,在保证以球铰为中心的转体体系的力矩平衡,从而不必预先调整体系的质量分布,就可以保证转体体系的平稳转动。该方法有效的解决了传统称重后平衡方法带来的诸多问题,减少施工成本和时间。
Description
技术领域
本发明涉及一种桥梁施工工艺,更具体地,涉及一种无称重平衡的转体桥转体施工方法。
背景技术
转体桥即采用转体法施工的桥梁。桥梁转体施工是指将桥梁结构在非设计轴线位置制作(浇注或拼接)成形后,通过转体就位的一种施工方法。它可以将在障碍上空的作业转化为岸上或近地面的作业。根据桥梁结构的转动方向,它可分为竖向转体施工法、水平转体施工法(简称竖转法和平转法)以及平转与竖转相结合的方法,其中以平转法应用最多。主要应用于上跨峡谷、河流、铁路、高速公路等不能做支撑的情况。转体桥的转体系统由下转盘、上转盘、球铰、滑道、牵引系统组成,转体过程一般通过千斤顶对拉牵引索,形成旋转力偶而实现转体。
桥梁采用转体施工时,沿梁轴线的竖平面内,由于球铰体系的制作安装误差和梁体质量分布差异以及拉索、预应力张拉的程度差异,导致两侧梁段刚度不同,质量分布不同,从而产生不平衡力矩,使得悬臂梁段下挠程度不同。为了保证转体过程中,体系平稳转动,要求预先调整体系的质量分布,使其质量处于平衡状态。以球铰为矩心,顺、反时针力矩之和为零,使转动体系能平衡转动,当结构本身力矩不能平衡时,需加配重使之平衡。以上为转体桥梁需要称重的原因。
决定转体桥梁倾覆的主要因素是以球铰为矩心两端梁体混凝土及钢筋用量的不平衡重所致,转体称重后反而增加了转体旋转的摩阻系数,因为目前的称重方法采用千斤顶应力传感器的方案,球铰两侧的千斤顶在工作时,向上的顶力打破了原有上下球铰的平衡状态,致使转体旋转过程摩阻加大。
发明内容
本发明的目的在于克服现有技术存在的上述缺陷,提供一种无称重平衡的转体桥转体施工方法,通过从施工规划阶段开始对转体体系进行设计,在保证以球铰为中心的转体体系的力矩平衡,从而不必预先调整体系的质量分布,就可以保证转体体系的平稳转动。
为实现上述目的,本发明的技术方案如下:
一种无称重平衡的转体桥转体施工方法,其特征在于,包括以下步骤
步骤S1:分型号、分直径进行钢筋下料,同一型号及直径的钢筋下料长度一致;
步骤S2:以球铰旋转中心为中心,进行上承台、墩柱施工和0号块钢筋绑扎;
步骤S3:依次进行一侧1号块段至末号块段和另一侧1号块段至末号块段的钢筋绑扎施工,施工前对对称的两块段所用钢筋过秤,记录两端各块段的钢筋重量,其中k取值为1到末号;
步骤S4:依次进行一侧1号块段至末号块段和另一侧1号块段至末号块段的模板支护加工,其中k取值为1到末号,模板安装前进行模板称重,记录两端各块段的模板重量;
步骤S5:依次进行一侧1号块段至末号块段和另一侧1号块段至末号块段的混凝土浇筑施工,对每车混凝土进行称重并记录;
步骤S6:对两端各对称块段进行配重,根据步骤S3~S5记录的两端各对称块段的钢筋重量、模板重量和混凝土重量,计算并施加两端各对称块段的配重,保证两侧的各对称块段整体重量一致,其中k取值为1到末号;
步骤S7:按照现有工艺完成转体施工。
优选地,所述步骤S3中,进行一侧1号块段至末号块段和另一侧1号块段至末号块段的钢筋绑扎施工时,施工前使对称的两块段所用的钢筋重量相同或相差误差小于等于10%。
优选地,所述步骤S4中,进行一侧1号块段至末号块段和另一侧1号块段至末号块段的模板支护加工时,施工前使对称的两块段所用的模板尺寸相同或相差误差小于等于10%。
从上述技术方案可以看出,本发明通过开工前统筹规划,并在施工过程中控制相关参数达到以球铰为中心的两端接近平衡,再通过对一侧1号块段至末号块段或另一侧1号块段至末号块段钢筋、模板和混凝土称重参数相加,通过对左侧1号块段至末号块段减或被减右侧1号块段至末号块段的值,根据值的参数进行合理配重,保证两端各对称块段以及两端整体重量相等,在不增加任何投入,方便快捷,也不会打破球铰的原有平衡,保证转体旋转自然无额外模组。因此,本发明具有减少施工时间和成本的显著特点。
附图说明
图1是本发明的以球铰为中心的转体结构示意图。
图中,1是下承台,2是上承台,3是球铰,4是0号块段,5是1号块段,6是末号块段。
具体实施方式
下面结合附图,对本发明的具体实施方式作进一步的详细说明。
需要说明的是,在下述的具体实施方式中,在详述本发明的实施方式时,为了清楚地表示本发明的结构以便于说明,特对附图中的结构不依照一般比例绘图,并进行了局部放大、变形及简化处理,因此,应避免以此作为对本发明的限定来加以理解。在以下的具体描述中,“左”和“右”的定义对应附图1中的方位,并不是任何时候的本发明的施工方位。
在以下本发明的具体实施方式中,参考图1,图1是本发明结构示意图,包括以下步骤
步骤S1:开工前统筹规划,分型号、分直径进行钢筋下料,同一型号及直径的钢筋下料长度一致,以减少两端不平衡重。
步骤S2:以球铰旋转中心为中心,进行上承台、墩柱施工和0号块钢筋绑扎。
步骤S3:依次进行左侧1号块段至末号块段和右侧1号块段至末号块段的钢筋绑扎施工,施工前对对称的两块段所用钢筋过秤,详细记录两端各块段钢筋重量,其中k取值为1到末号。优选地,施工前使左侧k号块段和右侧k号块段所用的钢筋重量基本一致,尽量做到一致,如果实在不能一致,相差误差小于等于10%,在步骤S6的配重环节,可以将重量差值抹平。
步骤S4:依次进行左侧1号块段至末号块段和右侧1号块段至末号块段的定型钢模板加工,其中k取值为1到末号;定型钢模板安装前进行再次称重,详细记录两端各对称块段定型钢模板重量。该过程中,施工前尽量使左侧k号块段和右侧k号块段所用的支护模板尺寸一致,尽量做到一致,如果实在不能一致,相差误差小于等于10%,在步骤S6的配重环节,可以将重量差值抹平。
步骤S5:依次进行左侧1号块段至末号块段和右侧1号块段至末号块段的混凝土浇筑施工,对每车混凝土进行称重并记录。
步骤S6:对两端各对称块段进行配重,根据步骤S3~S5记录的两端各对称块段的钢筋重量、模板重量和混凝土重量,计算并施加两端各对称块段的配重,保证左侧和右侧的各对称块段整体重量一致,其中k取值为1到末号。
步骤S6:按照现有工艺进行转体体系的其它施工,直至完成转体桥转体施工过程。
以上所述,仅为本发明较佳的具体实施方式,但本发明的保护范围并不局限于此,任何熟悉本技术领域的技术人员在本发明揭露的技术范围内,根据本发明的技术方案及其发明构思加以等同替换或改变,都应涵盖在本发明的保护范围之内。
Claims (3)
1.一种无称重平衡的转体桥转体施工方法,其特征在于,包括以下步骤
步骤S1:分型号、分直径进行钢筋下料,同一型号及直径的钢筋下料长度一致;
步骤S2:以球铰旋转中心为中心,进行上承台、墩柱施工和0号块钢筋绑扎;
步骤S3:依次进行一侧1号块段至末号块段和另一侧1号块段至末号块段的钢筋绑扎施工,施工前对对称的两块段所用钢筋过秤,记录两端各块段的钢筋重量,其中k取值为1到末号;
步骤S4:依次进行一侧1号块段至末号块段和另一侧1号块段至末号块段的模板支护加工,其中k取值为1到末号,模板安装前进行模板称重,记录两端各块段的模板重量;
步骤S5:依次进行一侧1号块段至末号块段和另一侧1号块段至末号块段的混凝土浇筑施工,对每车混凝土进行称重并记录;
步骤S6:对两端各对称块段进行配重,根据步骤S3~S5记录的两端各对称块段的钢筋重量、模板重量和混凝土重量,计算并施加两端各对称块段的配重,保证两侧的各对称块段整体重量一致,其中k取值为1到末号;
步骤S7:按照现有工艺完成转体施工。
2.根据权利要求1所述的方法,其特征在于,所述步骤S3中,进行一侧1号块段至末号块段和另一侧1号块段至末号块段的钢筋绑扎施工时,施工前使对称的两块段所用的钢筋重量相同或相差误差小于等于10%。
3.根据权利要求1所述的方法,其特征在于,所述步骤S4中,进行一侧1号块段至末号块段和另一侧1号块段至末号块段的模板支护加工时,施工前使对称的两块段所用的模板尺寸相同或相差误差小于等于10%。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910699491.6A CN110331671B (zh) | 2019-07-31 | 2019-07-31 | 一种无称重平衡的转体桥转体施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910699491.6A CN110331671B (zh) | 2019-07-31 | 2019-07-31 | 一种无称重平衡的转体桥转体施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110331671A true CN110331671A (zh) | 2019-10-15 |
CN110331671B CN110331671B (zh) | 2021-04-16 |
Family
ID=68148101
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910699491.6A Active CN110331671B (zh) | 2019-07-31 | 2019-07-31 | 一种无称重平衡的转体桥转体施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110331671B (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111593772A (zh) * | 2020-05-12 | 2020-08-28 | 中铁上海设计院集团有限公司 | 一种基于桩基应力测量的转体桥梁称重方法 |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100711086B1 (ko) * | 2004-10-05 | 2007-04-24 | (주) 철도안전연구소 | 철도 교량용 판형교의 거더 개량용 가설장비 및 개량 공법 |
CN104452603A (zh) * | 2014-12-16 | 2015-03-25 | 中铁大桥局集团有限公司 | 一种箱梁桥水平转体施工的平衡称重结构及方法 |
CN108193604A (zh) * | 2017-11-28 | 2018-06-22 | 中交二航局第二工程有限公司 | 箱梁t构平衡转体过程中的称重配重方法 |
CN108589556A (zh) * | 2018-05-04 | 2018-09-28 | 中铁二十三局集团有限公司 | 跨运营线低净空转体桥施工工法 |
CN108677747A (zh) * | 2018-06-30 | 2018-10-19 | 中铁二十局集团第工程有限公司 | 斜拉桥平面转体施工方法 |
-
2019
- 2019-07-31 CN CN201910699491.6A patent/CN110331671B/zh active Active
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100711086B1 (ko) * | 2004-10-05 | 2007-04-24 | (주) 철도안전연구소 | 철도 교량용 판형교의 거더 개량용 가설장비 및 개량 공법 |
CN104452603A (zh) * | 2014-12-16 | 2015-03-25 | 中铁大桥局集团有限公司 | 一种箱梁桥水平转体施工的平衡称重结构及方法 |
CN108193604A (zh) * | 2017-11-28 | 2018-06-22 | 中交二航局第二工程有限公司 | 箱梁t构平衡转体过程中的称重配重方法 |
CN108589556A (zh) * | 2018-05-04 | 2018-09-28 | 中铁二十三局集团有限公司 | 跨运营线低净空转体桥施工工法 |
CN108677747A (zh) * | 2018-06-30 | 2018-10-19 | 中铁二十局集团第工程有限公司 | 斜拉桥平面转体施工方法 |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111593772A (zh) * | 2020-05-12 | 2020-08-28 | 中铁上海设计院集团有限公司 | 一种基于桩基应力测量的转体桥梁称重方法 |
CN111593772B (zh) * | 2020-05-12 | 2021-06-04 | 中铁上海设计院集团有限公司 | 一种基于桩基应力测量的转体桥梁称重方法 |
Also Published As
Publication number | Publication date |
---|---|
CN110331671B (zh) | 2021-04-16 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
Zheng et al. | Concrete-filled steel tube arch bridges in China | |
CN107905109A (zh) | 跨越式桥梁现浇平台模拟等荷载分段预压施工方法 | |
CN105908902B (zh) | 预制墩柱钢筋笼用定位架及墩柱钢筋笼施工方法 | |
CN101323418A (zh) | 巨型异形钢构件单机翻身吊装方法 | |
CN108677747B (zh) | 斜拉桥平面转体施工方法 | |
CN106121236B (zh) | 楼板钢筋保护层及结构标高综合控制方法 | |
CN106758871A (zh) | 一种全悬臂施工预应力混凝土连续刚构桥及其施工方法 | |
CN206448176U (zh) | 可调式牛腿现浇悬臂梁零号段施工装置 | |
CN110205938A (zh) | 下承式梁拱组合桥的钢管拱安装方法 | |
CN110439301A (zh) | 一种可精准调节角度倾斜钢管混凝土柱与环形梁的施工方法 | |
CN109898425A (zh) | 一种用斜拉扣挂悬臂浇筑混凝土拱桥拱圈的施工方法 | |
Akl et al. | Deflection of in-span hinges in prestressed concrete box girder bridges during construction | |
CN110331671A (zh) | 一种无称重平衡的转体桥转体施工方法 | |
CN112195797A (zh) | 一种连续梁桥合龙施工方法 | |
CN108060634A (zh) | 双工字形超高性能混凝土-普通混凝土组合梁桥梁结构及其施工方法 | |
CN109944160A (zh) | 一种分离式开口组合梁混凝土桥面板叠合精度控制方法 | |
CN211250705U (zh) | 一种用于装配式桥梁预制墩柱模板的翻身装置 | |
CN109162204A (zh) | 一种桥梁下部结构横向分块快速组拼的施工方法 | |
CN106906750B (zh) | 一种多功能跨铁路线平转桥梁合龙施工模架及其施工方法 | |
CN110029580A (zh) | 一种长短线结合匹配预制节段装配式桥面板施工方法 | |
JP4057724B2 (ja) | 押出し工法における橋桁の支持構造 | |
CN215366842U (zh) | 一种平转桥梁拉压临时锁定结构 | |
CN110184943A (zh) | 一种多跨连续梁预应力砼桥合拢施工方法 | |
CN208167566U (zh) | 基于悬挑简支板结构的拼宽桥梁 | |
CN208649896U (zh) | 一种拼装式钢筋绑扎胎架 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
TA01 | Transfer of patent application right |
Effective date of registration: 20210302 Address after: No.88, chenjiaji Avenue, Jiang'an District, Wuhan City, Hubei Province, 430000 Applicant after: Huazhong Engineering Co.,Ltd. of CCCC tunnel Bureau Applicant after: CCCC TUNNEL ENGINEERING Co.,Ltd. Address before: 100102 room 607, 101-1-8 / F, building 2, yard 2, Lize East 2nd Road, Chaoyang District, Beijing Applicant before: CCCC TUNNEL ENGINEERING Co.,Ltd. |
|
TA01 | Transfer of patent application right | ||
GR01 | Patent grant | ||
GR01 | Patent grant |