CN110295627A - Road inspection well construction method - Google Patents

Road inspection well construction method Download PDF

Info

Publication number
CN110295627A
CN110295627A CN201910573957.8A CN201910573957A CN110295627A CN 110295627 A CN110295627 A CN 110295627A CN 201910573957 A CN201910573957 A CN 201910573957A CN 110295627 A CN110295627 A CN 110295627A
Authority
CN
China
Prior art keywords
walling crib
integrated board
well bore
template
road
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910573957.8A
Other languages
Chinese (zh)
Other versions
CN110295627B (en
Inventor
周其胜
吴倩
刘文仕
崔玉华
吴长端
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC20 Group Corp Ltd
Shanghai Ershiye Construction Co Ltd
Original Assignee
China MCC20 Group Corp Ltd
Shanghai Ershiye Construction Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC20 Group Corp Ltd, Shanghai Ershiye Construction Co Ltd filed Critical China MCC20 Group Corp Ltd
Priority to CN201910573957.8A priority Critical patent/CN110295627B/en
Publication of CN110295627A publication Critical patent/CN110295627A/en
Application granted granted Critical
Publication of CN110295627B publication Critical patent/CN110295627B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/12Manhole shafts; Other inspection or access chambers; Accessories therefor

Landscapes

  • Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Road Paving Structures (AREA)
  • Sampling And Sample Adjustment (AREA)

Abstract

The present invention relates to a kind of road inspection well construction methods, comprising the following steps: production armored concrete walling crib integrated board template;In-situ precast armored concrete walling crib integrated board;Inspection shaft basis and well bore construction;Well bore periphery backfilling of earthwork;The installation of armored concrete walling crib integrated board;Road base layer construction;Road surface construction.The present invention is conducive to improve the construction efficiency of inspection shaft, and well bore is avoided to form the risk that the problems in stress collection and inspection shaft ground are impregnated by rainwater, be conducive to extend inspection shaft using durable.

Description

Road inspection well construction method
Technical field
The invention belongs to the technical fields of road inspection well construction, more particularly to a kind of road inspection well construction method.
Background technique
All kinds of inspection shafts on outdoor road are set, under vehicular load and rainwater repeated action, stress collection can be generated It is middle to destroy, including the breakoff phenomenons such as well week sagging, pavement cracking, walling crib rupture, well lid protuberance, it is comfortable to seriously affect driving Degree and safety.It after such disease occurs in inspection shaft, has to carry out it excavation processing, result often causes room Outer road is temporarily paralysed, and influences traffic, while inspection shaft is dealt with improperly and will affect outdoor road beauty, especially occurs in city Similar problems can destroy the image in city, therefore prevent from road inspection well from destroying, improve inspection shaft useful life longevity to be to need at present The construction technology problem of solution.
Summary of the invention
Technical problem to be solved by the invention is to provide a kind of road inspection well construction methods, improve construction efficiency, have Conducive to extension inspection shaft using durable.
The technical solution adopted by the present invention to solve the technical problems is to provide a kind of road inspection well construction method, including Following steps:
(1) make armored concrete walling crib integrated board template: the template includes square template, circular shuttering and bed die Plate, the end template are the mattess tilted down from periphery to center, and the center of the end template is reserved and finished product well The circular hole that narrow circle outer diameter matches is enclosed, outer diameter and the wide circle internal diameter of finished product walling crib of the circular shuttering match;
(2) in-situ precast armored concrete walling crib integrated board: the position of square shaped template carries out unwrapping wire on end template, will The narrow circle retaining ring of finished product walling crib is in the center hole of end template, by circular shuttering encapsulation in the wide circle inner hole of finished product walling crib, Square template is installed according to unwrapping wire and square template is identical as circular shuttering upper end absolute altitude, between square template and circular shuttering Assembling reinforcement and casting concrete plate, demoulding obtains armored concrete walling crib integrated board after intensity is up to standard;
(3) inspection shaft basis and well bore construction: inspection shaft basis is poured on ground, on inspection shaft basis after intensity is up to standard Top builds well bore;
(4) back-filling in layers well bore periphery backfilling of earthwork: is carried out to the earthwork of well bore periphery;
(5) armored concrete walling crib integrated board is installed: being carried out leveling to the top of well bore, is trapped among reinforcing bar outside to well bore Backfill in concrete walling crib integrated board fitting limit carries out flatness and compactness processing so that the backfill surface with Well bore top flushes, and armored concrete walling crib integrated board is mounted on well bore top;
(6) Road base layer construction: Paving roadways base course, the surface level and armored concrete of the Road base The outer rim absolute altitude of walling crib integrated board is consistent;
(7) Road surface construction: Paving roadways supercrust, the surface level and armored concrete of the Road surface layer The top absolute altitude of walling crib integrated board is consistent.
The center hole depth of the end template is greater than the height of the narrow circle of finished product walling crib.
The surface slope of the end template is 2~5 °.
It will check that the synchronous installation of staircase is in place in the building construction of the well bore.
In the step (5) when being installed to armored concrete walling crib integrated board, finished product walling crib is biased to check and is helped The direction installation of ladder.
The thickness of each layer backfill of control is no more than 200mm in the step (4), and each layer backfill is carried out close using cutting ring Solidity sample detection.
Using cement mortar to progress leveling at the top of well bore in the step (6).
Beneficial effect
First, in the present invention, by the armored concrete walling crib one for obtaining integral structure to walling crib casting concrete Body plate can be realized the installation to walling crib by installing armored concrete walling crib integrated board when construction, avoid in the prior art Walling crib installation needs supporting module, and being conducive to simplify to construct reduces cost.And armored concrete walling crib integrated board in-situ precast, energy Enough progress synchronous with well construction is checked are conducive to improve construction efficiency shortening construction period.
Second, compared with prior art walling crib stress directly acts on the situation that well bore be easy to cause stress to concentrate, this hair Bright middle walling crib and concrete slab form armored concrete walling crib integrated board, and bottom bearing area greatly increases, and by well bore and outside It encloses the soil body and bears upper load jointly, avoid the formation of the problems in well bore stress collection, be conducive to avoid inspection shaft broken by stress It is bad, improve the durability of inspection shaft.
Third, armored concrete walling crib integrated board upper surface are the structure that outer rim tilts down, and form drainage grade, use The ponding of upper surface can be discharged to outside armored concrete walling crib integrated board range in the process, advantageously reduce the incident of inspection shaft ground By the risk that rainwater impregnates, be conducive to the durability for improving inspection shaft.
Detailed description of the invention
Fig. 1 is the formwork structure schematic diagram of armored concrete walling crib integrated board.
Fig. 2 is the structural schematic diagram of armored concrete walling crib integrated board.
Fig. 3 is the structural schematic diagram on inspection shaft basis and well bore.
Fig. 4 is the mounting plane figure of armored concrete walling crib integrated board.
Fig. 5 is the A-A sectional view of Fig. 4.
Specific embodiment
Present invention will be further explained below with reference to specific examples.It should be understood that these embodiments are merely to illustrate the present invention Rather than it limits the scope of the invention.In addition, it should also be understood that, after reading the content taught by the present invention, those skilled in the art Member can make various changes or modifications the present invention, and such equivalent forms equally fall within the application the appended claims and limited Range.
A kind of road inspection well construction method, comprising the following steps:
(1) armored concrete walling crib integrated board template is made: as shown in Figure 1, template includes square template 1-1, circular mode Plate 1-2 and end template.Square template 1-1 is square, and is made of 4 pieces of strip templates, and strip template length is finished product walling crib 2-1 The narrow circle outer diameter R2+800mm in top, is highly 80mm-100mm.The outer diameter and finished product walling crib 2-1 lower part Kuan Quan of circular shuttering 1-2 Internal diameter matches.End template is mattess, is tilted down from periphery to being centrally formed 2 °, the center of end template it is reserved with The circular hole that the narrow circle outer diameter in the top finished product walling crib 2-1 matches, depth 100mm-200mm, greater than the narrow circle of finished product walling crib 2-1 Highly.
(2) in-situ precast armored concrete walling crib integrated board: the position of square shaped template 1-1 is put on end template Line, by the narrow circle back-off in the top of finished product walling crib 2-1 in the center hole of end template, by circular shuttering 1-2 encapsulation in finished product well It encloses in the wide circle inner hole of 2-1.Square template 1-1, and square template 1-1 and the upper end circular shuttering 1-2 absolute altitude are installed according to unwrapping wire It is identical, the assembling reinforcement between square template 1-1 and circular shuttering 1-2.It is poured between square template 1-1 and circular shuttering 1-2 Concrete slab 3 is built, strength grade of concrete is not less than C25, and maintenance is no less than 7d, obtains the knot of armored concrete walling crib integrated board Structure is as shown in Figure 2.Concrete strength not less than design strength 75% after form removal, concentrate pile up, armored concrete walling crib The concrete strength of integrated board can be installed after reaching 100%.Armored concrete walling crib integrated board can be using building rubbish Rubbish is made in advance, is not take up the construction period, and environmentally protective.
(3) inspection shaft basis and well bore construction: after the completion of basement process, inspection shaft basis 4 is poured, inspection shaft basis 4 is C20 concrete, thickness are not less than 100mm.4 concrete strengths of inspection shaft basis carry out the building construction of well bore 5 after reaching 75%, 5 groups of blocks of well bore are not less than the cement mortar of M7.5 using intensity, and building block is not less than the solid concrete brick of Mu20, well using intensity It will check that the synchronous installation of staircase 6 is in place in 5 building process of body, as shown in Figure 3.Covering in time after the completion of well bore 5 is built, prevents rain Leaching carries out next process construction after placing 7d.If 5 local environment of well bore is very moist or water level located underground is hereinafter, in well 5 outer wall of body should carry out waterproof disposition.
(4) well bore periphery backfilling of earthwork: well bore 5 is built complete and check and accept and pass through after, carry out peripheral backfilling of earthwork.The earthwork point Layer backfill, lift height are no more than 200mm, and every layer of backfill is all made of cutting ring sample detection, it is ensured that backfill compactness.If Road Base 8-1 design is thicker than armored concrete walling crib integrated board, and first construct one layer of Road base 8-1, and thickness is not less than 100mm, Less than 100mm, backfilling of earthwork thickness is reduced, reduces backfill height hj=100+h0-h1, wherein h0 is integrated plate thickness, H1 is roadbase thickness.
(5) armored concrete walling crib integrated board is installed:
Using with the equicohesive cement mortar of armored concrete walling crib integrated board to carrying out leveling at the top of well bore 5.It is right Backfill surface smoothness and compactness in armored concrete walling crib integrated board fitting limit are checked that flatness is not met It is required that can be handled by the thin sand bed compacting that paves, compactness, which is unsatisfactory for requirement, should first carry out compacting processing, then reasonable with gradation Sandstone are backfilled to integrated board mounting height.
Armored concrete walling crib integrated board is mounted on the top of well bore 5, armored concrete walling crib integrated board outer rim absolute altitude with The upper surface Road base 8-1 absolute altitude is identical, and inspection shaft internal diameter is 100mm-300mm bigger than well lid 2-2 outer diameter.For convenient for inspection shaft Maintenance, when armored concrete walling crib integrated board is installed, finished product walling crib 2-1 is biased to check the direction installation of staircase 6, finished product well The minimum range of circle 2-1 internal diameter to 5 inner wall of well bore should be controlled in 0-100mm.
(6) Road base layer construction: being repeated several times step (3) to step (5), and completion needs all inspection shafts on construction road Construction, by design requirement Paving roadways base course 8-1, the surface level and armored concrete walling crib one of Road base 8-1 The outer rim absolute altitude of body plate is identical.
(7) Road surface construction: Paving roadways supercrust 8-2, the surface level and reinforced concrete of Road surface layer 8-2 The top absolute altitude of native walling crib integrated board is consistent.

Claims (7)

1. a kind of road inspection well construction method, comprising the following steps:
(1) make armored concrete walling crib integrated board template: the template include square template (1-1), circular shuttering (1-2) and End template, the end template are the mattess tilted down from periphery to center, the center of the end template it is reserved at The narrow circular hole that matches of circle outer diameter of product walling crib (2-1), in the wide circle of the outer diameter and finished product walling crib (2-1) of the circular shuttering (1-2) Diameter matches;
(2) in-situ precast armored concrete walling crib integrated board: the position of square shaped template (1-1) carries out unwrapping wire on end template, By the narrow circle retaining ring of finished product walling crib (2-1) in the center hole of end template, by circular shuttering (1-2) encapsulation in finished product walling crib In the wide circle inner hole of (2-1), according to unwrapping wire installation square template (1-1) and square template (1-1) and the upper end circular shuttering (1-2) Absolute altitude is identical, and assembling reinforcement and casting concrete plate (3) between square template (1-1) and circular shuttering (1-2), intensity is up to standard Demoulding obtains armored concrete walling crib integrated board afterwards;
(3) inspection shaft basis and well bore construction: inspection shaft basis (4) is poured on ground, on inspection shaft basis after intensity is up to standard (4) top builds well bore (5);
(4) back-filling in layers well bore periphery backfilling of earthwork: is carried out to the earthwork of well bore (5) periphery;
(5) armored concrete walling crib integrated board is installed: being carried out leveling to the top of well bore (5), is trapped among steel outside to well bore (5) Backfill in reinforced concrete walling crib integrated board fitting limit carries out flatness and compactness processing, so that the backfill surface It is flushed with well bore (5) top, armored concrete walling crib integrated board is mounted on well bore (5) top;
(6) Road base layer construction: Paving roadways base course (8-1), the surface level and reinforcing bar of the Road base (8-1) The outer rim absolute altitude of concrete walling crib integrated board is consistent;
(7) Road surface construction: Paving roadways supercrust (8-2), the surface level and reinforcing bar of the Road surface layer (8-2) The top absolute altitude of concrete walling crib integrated board is consistent.
2. a kind of road inspection well construction method according to claim 1, it is characterised in that: the center circle of the end template Hole depth is greater than the height of finished product walling crib (2-1) narrow circle.
3. a kind of road inspection well construction method according to claim 1, it is characterised in that: incline on the surface of the end template Gradient is 2~5 °.
4. a kind of road inspection well construction method according to claim 1, it is characterised in that: the masonry of the well bore (5) It will check that staircase (6) synchronous installation is in place in construction.
5. a kind of road inspection well construction method according to claim 4, it is characterised in that: right in the step (5) When armored concrete walling crib integrated board is installed, finished product walling crib (2-1) is biased to check that the direction of staircase (6) is installed.
6. a kind of road inspection well construction method according to claim 1, it is characterised in that: control in the step (4) The thickness of each layer backfill is no more than 200mm, and each layer backfill carries out compactness sample detection using cutting ring.
7. a kind of road inspection well construction method according to claim 1, it is characterised in that: used in the step (6) Cement mortar is to progress leveling at the top of well bore (5).
CN201910573957.8A 2019-06-28 2019-06-28 Construction method of road inspection well Active CN110295627B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910573957.8A CN110295627B (en) 2019-06-28 2019-06-28 Construction method of road inspection well

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910573957.8A CN110295627B (en) 2019-06-28 2019-06-28 Construction method of road inspection well

Publications (2)

Publication Number Publication Date
CN110295627A true CN110295627A (en) 2019-10-01
CN110295627B CN110295627B (en) 2021-01-01

Family

ID=68029345

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910573957.8A Active CN110295627B (en) 2019-06-28 2019-06-28 Construction method of road inspection well

Country Status (1)

Country Link
CN (1) CN110295627B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111733887A (en) * 2020-06-15 2020-10-02 中国一冶集团有限公司 Construction method of asphalt concrete road inspection well first-rising structure
CN111827040A (en) * 2020-07-23 2020-10-27 湖北烜豪建筑工程有限公司 Construction process for well road with pipeline
CN113622234A (en) * 2020-05-09 2021-11-09 北京建工路桥集团有限公司 Method for synchronously constructing road base and inspection well
CN113944219A (en) * 2021-09-14 2022-01-18 北京市政建设集团有限责任公司 Construction process for prefabricating gutter inlet

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001336168A (en) * 2000-05-30 2001-12-07 Inoac Corp Fixing ring for flexible joint for connecting pipe of manhole
CN205369311U (en) * 2016-01-06 2016-07-06 深圳市路桥建设集团有限公司 A walling crib for reinforcing or inspection shaft on maintenance town road
CN207469309U (en) * 2017-11-23 2018-06-08 中铁二十局集团市政工程有限公司 A kind of rectangular prefabricated assembled inspection shaft
CN108487323A (en) * 2018-03-21 2018-09-04 天津炬实科技发展股份有限公司 Inspection shaft manhole lid device construction technology on a kind of road
CN208455793U (en) * 2018-04-30 2019-02-01 安徽省公路桥梁工程有限公司 Heavy Traffic road inspection well walling crib
CN109695258A (en) * 2019-01-24 2019-04-30 陈方 A kind of band bell and spigot antiseep inspection shaft and construction method

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2001336168A (en) * 2000-05-30 2001-12-07 Inoac Corp Fixing ring for flexible joint for connecting pipe of manhole
CN205369311U (en) * 2016-01-06 2016-07-06 深圳市路桥建设集团有限公司 A walling crib for reinforcing or inspection shaft on maintenance town road
CN207469309U (en) * 2017-11-23 2018-06-08 中铁二十局集团市政工程有限公司 A kind of rectangular prefabricated assembled inspection shaft
CN108487323A (en) * 2018-03-21 2018-09-04 天津炬实科技发展股份有限公司 Inspection shaft manhole lid device construction technology on a kind of road
CN208455793U (en) * 2018-04-30 2019-02-01 安徽省公路桥梁工程有限公司 Heavy Traffic road inspection well walling crib
CN109695258A (en) * 2019-01-24 2019-04-30 陈方 A kind of band bell and spigot antiseep inspection shaft and construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113622234A (en) * 2020-05-09 2021-11-09 北京建工路桥集团有限公司 Method for synchronously constructing road base and inspection well
CN111733887A (en) * 2020-06-15 2020-10-02 中国一冶集团有限公司 Construction method of asphalt concrete road inspection well first-rising structure
CN111827040A (en) * 2020-07-23 2020-10-27 湖北烜豪建筑工程有限公司 Construction process for well road with pipeline
CN113944219A (en) * 2021-09-14 2022-01-18 北京市政建设集团有限责任公司 Construction process for prefabricating gutter inlet

Also Published As

Publication number Publication date
CN110295627B (en) 2021-01-01

Similar Documents

Publication Publication Date Title
CN110295627A (en) Road inspection well construction method
CN107059667B (en) Door shape assembled armored concrete box culvert and its construction method
CN107338801B (en) Prestressing force assembled Complex retaining wall structure and construction method
CN107246005A (en) Super-large diameter bores and buries steel pipe hollow foundation pile and its construction method
CN206495233U (en) Door shape assembled armored concrete box culvert
CN107816056A (en) Filled type concrete gravity retaining wall and its construction technology
CN108035379B (en) Comprehensive pipe gallery and construction method thereof
CN106801384A (en) Assembled steel reinforced concrete aliform type culvert opening and construction method
CN107059904A (en) A kind of underground pipe gallery ponding well excavation method
CN204662494U (en) Highway retaining wall reinforced structure
CN106988337B (en) It is a kind of for reducing the reinforcement means of bar shaped shallow foundation house differential settlement
CN206529712U (en) Assembled steel reinforced concrete aliform type culvert opening
CN112681376A (en) Construction method of shaft type underground stereo garage
CN209555967U (en) A kind of H-type concrete slab assembled ecology retaining wall
CN109681212B (en) Excavation construction method of small-section loess tunnel
CN109137972A (en) A kind of assembled integral basement structure and its safely and fast construction method
CN201381518Y (en) Standard integral outdoor equipment well
CN211498929U (en) Street lamp basis prefabricated construction
CN109267578A (en) A kind of inclined-plane plain concrete construction and its construction method
CN103015457A (en) Method for building rural brick buried sewage treatment facility
CN112854409A (en) Road rainwater well lifting device and lifting construction method
CN207121898U (en) Super-large diameter bores and buries steel pipe hollow foundation pile
CN111549784A (en) Construction process of foundation pit adjacent to building
CN211285674U (en) General prefabricated template device of basement cushion cap and grade beam
CN109457725B (en) H-shaped concrete plate assembled ecological retaining wall

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant