CN109137972A - A kind of assembled integral basement structure and its safely and fast construction method - Google Patents

A kind of assembled integral basement structure and its safely and fast construction method Download PDF

Info

Publication number
CN109137972A
CN109137972A CN201810996404.9A CN201810996404A CN109137972A CN 109137972 A CN109137972 A CN 109137972A CN 201810996404 A CN201810996404 A CN 201810996404A CN 109137972 A CN109137972 A CN 109137972A
Authority
CN
China
Prior art keywords
prefabricated
basement
bottom plate
cast
concrete
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810996404.9A
Other languages
Chinese (zh)
Inventor
樊军伟
杨仕教
陈文昭
彭成
江俊设
胡萍
龙慧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
University of South China
Original Assignee
University of South China
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by University of South China filed Critical University of South China
Priority to CN201810996404.9A priority Critical patent/CN109137972A/en
Publication of CN109137972A publication Critical patent/CN109137972A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/16Arrangement or construction of joints in foundation structures
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/02Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
    • E02D31/025Draining membranes, sheets or fabric specially adapted therefor, e.g. with dimples

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Environmental & Geological Engineering (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

本发明公开了一种装配整体式地下室结构及其快速安全施工方法,快速安全施工方法包括:在预定地基上设置素混凝土垫层并铺贴防水卷材;在防水卷材上安装预制底板。将预制底板之间纵横向连接;将外边缘预制底板与预制外墙连接;将地下室预制顶板梁与现浇混凝土柱连接;将地下室预制顶板与预制顶板梁连接。预制构件节点连接完成后在其一侧现浇混凝土叠合层。本发明能够地下室施工过程中通过预制构件快速安全施工以节省大笔资金、缩短工期,同时通过预制底板板面及预制外墙墙面上预留的孔洞沟通联系地下室内外水力平衡以满足施工期间极端情况下地下室抗浮稳定要求并适时完成预制构件叠合层的施工以满足地下室使用期间防水抗渗要求。

The invention discloses an assembled integral basement structure and a fast and safe construction method thereof. The fast and safe construction method comprises: arranging a plain concrete cushion on a predetermined foundation and laying a waterproofing membrane; installing a prefabricated bottom plate on the waterproofing membrane. Connect the prefabricated bottom plates vertically and horizontally; connect the outer edge prefabricated bottom plates with the prefabricated outer walls; connect the basement prefabricated roof beams with the cast-in-place concrete columns; connect the basement prefabricated top plates with the prefabricated roof beams. After the connection of the precast member nodes is completed, the superimposed layer of cast-in-place concrete is placed on one side. The invention can quickly and safely construct the basement through prefabricated components to save a large amount of money and shorten the construction period. Under the circumstance, the anti-floating stability of the basement is required and the construction of the prefabricated member superimposed layer is completed in time to meet the waterproof and anti-seepage requirements during the use of the basement.

Description

A kind of assembled integral basement structure and its safely and fast construction method
Technical field
The present invention relates to field of civil engineering, specifically, in particular to a kind of assembled integral basement structure and its Safely and fast construction method.
Background technique
The nearly more than ten years with reform and opening-up further in-depth, the development of China's economic crossover formula driven urbanization into Journey.The quickening of urbanization process also brings a series of problem, for example urban population is intensive, traffic deterioration, environmental pollution etc. "urban disease".To solve problems faced in above-mentioned urbanization process, large-scale develops and utilizes the underground space and become city and determine Inevitable the wanted problems faced of plan person.
The attached formula basement of building of civil buildings is one of the Main way greatly developed in current China's urban construction.Due to ground Lower room is completely or partially embedded under earth's surface in the Rock And Soil of certain depth, and level of ground water rising or ground are met in work progress Basement stability against floating requirement when table water pours into foundation pit, the basement after building up will meet water proof anti-seepage requirement, therefore at present Lower room is usually made cast-in-situ steel reinforced concrete enclosed construction, and basement takes necessary measure of anti float in the construction process, and adopts With water-proof concrete, waterproof roll, water-repellent paint, drainage systems, bentonite waterproof material, waterproof mortar and metal splash guard Etc. modes come water proof anti-seepage requirement during meeting use.
There are monolithic reinforced concrete structure materials to be easy, with material rationally, durability, fire resistance, normability, globality etc. Advantage, therefore largely it is widely used in construction industry field.However there is also from great, crack resistance for monolithic reinforced concrete structure Shortcomings, the especially cast-in-place concretes such as difference, heat-and sound-insulating performance difference and construction period pollution environment are poured smash after need it is longer The maintenance of time, it is also contemplated that construction period underground water rises and surface water pours into basement stability against floating problem after foundation pit.This Inevitable schedule delays increase cost.
Summary of the invention
To solve existing cast-in-situ steel reinforced concrete basement technical problem, it is whole that the embodiment of the invention provides a kind of assembly Formula basement structure and its fast and safe construction method.The technical solution is as follows:
On the one hand, a kind of assembled integral basement structure is provided, comprising: plain concrete cushion layer, prefabricated panel, prefabricated Exterior wall;
The plain concrete cushion layer and paving waterproof roll are set on predetermined ground;It is installed on the waterproof roll described pre- Bottom plate processed;The prefabricated panel vertically and horizontally connects;The outer edge prefabricated panel is connect with the precast facade;The prefabricated bottom Plate lower surface is provided with grouting behind shaft or drift lining concrete, and the prefabricated panel upper surface is provided with cast-in-place concrete bottom plate overlapping layers.
Further, the prefabricated panel vertical and horizontal section can be made "-", " ︺ ", " transversal I ", " ︹ " form or other Form, vertically and horizontally side steel bar stress uses the bottom plate overlapping layers of cast-in-place concrete in due course after sleeve mechanical connection to prefabricated panel.
Further, reserving hole is provided in the prefabricated panel plate face.
Further, basement outer edge prefabricated panel section is made " ﹂ " form, and the form of fracture of outer wall of basement can To be " I ", " ︱ ", " [" or "] " or other forms, and the reserving hole on its metope, by outer edge prefabricated panel and prefabricated outer The steel bar stress of wall passes through slip casting sleeve connection, and setting seat is starched at joint face.
Further, between the precast facade by casing by cast-in-situ concrete columns again after stress main reinforcement mechanical connection, It completes between precast facade and after the connection of cast-in-situ concrete columns, then in due course cast-in-place concrete exterior wall overlapping layers.
On the other hand, a kind of assembled integral basement fast and safe construction method is provided, comprising:
Plain concrete cushion layer and paving waterproof roll are set on predetermined ground;
Prefabricated panel is installed on setting waterproof roll;
The outer edge prefabricated panel is connect with precast facade;
The precast facade is connected by cast-in-situ concrete columns;
Prefabricated top plate beam is connect with the cast-in-situ reinforced concrete column;
Prefabricated top plate beam is connect with the prefabricated top plate of the basement.
Further, the size of above-mentioned prefabricated panel, precast facade, prefabricated top plate beam and prefabricated top plate can be according to column away from big Small determination.
Further, the step of installing prefabricated panel on waterproof roll is set described specifically:
The prefabricated panel, the vertical muscle of cast-in-situ reinforced concrete column and basis wait cast-in-place coagulation after being mechanically connected using casing The construction of earth pillar;
Vertically and horizontally side steel bar stress is mechanically connected the prefabricated panel using sleeve;
Reserving hole is set in the prefabricated panel plate face, is infused by reserving hole on prefabricated panel in the suitable time Concrete grout fills the space being recessed below prefabricated panel, then the cast-in-place concrete bottom plate overlapping layers above prefabricated panel;
Wherein, the suitable time are as follows: when basement structure meets construction period stability against floating requirement.
Further, by the basement outer edge prefabricated panel and precast facade Connection Step specifically:
The outer edge prefabricated panel and the precast facade pass through the laggard horizontal high voltage slip casting of slip casting sleeve connection;
The needs for meeting stability against floating during basement construction, the reserving hole on precast facade metope are reserved in prefabricated Hole on outer surface of wall can link up hydraulic equilibrium inside and outside connection basement;
Complete the connection of precast facade and cast-in-situ concrete columns;
Finally complete the construction of cast-in-place concrete exterior wall overlapping layers in due course in the side of precast facade.
Technical solution provided in an embodiment of the present invention has the benefit that
To solve formula basement of building attached at present using the longer curing time of monolithic reinforced concrete structure needs, construction time Between face many engineering roadblocks such as underground structure stability against floating, the requirements such as water proof anti-seepage are met during basement use and propose one Kind assembled integral basement fast and safe construction method.
Relative to cast-in-situ steel reinforced concrete integral basement structure, a kind of assembled integral basement structure of the present invention have with Lower advantage: 1. prefabricated components are produced in batches in PC factory, high-efficient, quality is guaranteed;2. a large amount of construction templates are saved at scene; 3. reducing labour, cross-operation is convenient, accelerates construction progress, construction is not affected by the weather;4. installation accuracy is high, matter of constructing It measures guaranteed;5. energy-saving and emission-reduction, reducing environmental pollution 6. can significantly save the cost when basement is larger;6. prefabricated structure Part (prefabricated panel and precast facade) reserving hole on plate (or wall) face in production, it is anti-to meet construction period underground structure Floating stability requirement;7. prefabricated components are installed afterwards in due course in the side cast-in-place concrete overlapping layers of prefabricated components, therefore underground Cell structure has good globality, bearing capacity characteristics, anti-seismic performance and during being able to satisfy construction period stability against floating and use Water proof anti-seepage requirement.
The present invention can assembled integral is attached build formula basement construction during fast and safely being applied by prefabricated components Work can also be passed through reserved with saving extensive fund, shortening the construction period in prefabricated panel plate face and on precast facade metope The mode of hole links up inside and outside connection construction period basement hydraulic equilibrium to meet the anti-of the basement structure under extreme case Floating stability requirement, in suitable time (when basement structure meets construction period stability against floating requirement) completion prefabricated panel and in advance The cast-in-place concrete overlapping layers of exterior wall processed is with water proof anti-seepage requirement during meeting basement use.Therefore the present invention is a kind of is worth It promotes, the extensive basement fast and safe construction method of application prospect.
Detailed description of the invention
To describe the technical solutions in the embodiments of the present invention more clearly, make required in being described below to embodiment Attached drawing is briefly described, it should be apparent that, drawings in the following description are only some embodiments of the invention, for For those of ordinary skill in the art, without creative efforts, it can also be obtained according to these attached drawings other Attached drawing.
Fig. 1 is that the prefabricated panel of the embodiment of the present invention one vertically and horizontally connects drawing;
Fig. 2 is that the basement outer edge prefabricated panel of the embodiment of the present invention one connect drawing with precast facade;
Fig. 3 is precast facade connection drawing (top view) of the embodiment of the present invention one.
Specific embodiment
To make the object, technical solutions and advantages of the present invention clearer, below in conjunction with attached drawing to embodiment party of the present invention Formula is described in further detail.
Embodiment one
The present invention provides a kind of assembled integral basement structure and its fast and safe construction methods, referring to Fig. 1-3, packet It includes: plain concrete cushion layer 2, prefabricated panel 5, precast facade 10;
The plain concrete cushion layer 2 and paving waterproof roll are set on predetermined Foundation Pit bottom ground 1;On the waterproof roll The prefabricated panel 5 is installed;It is vertically and horizontally connected between the prefabricated panel 5;The outer edge prefabricated panel 5 with it is described prefabricated outer Wall 10 connects;5 lower surface of prefabricated panel is provided with grouting behind shaft or drift lining concrete 3, and 5 upper surface of prefabricated panel is provided with cast-in-place Concrete floor overlapping layers 6.
Further, 5 vertical and horizontal section of prefabricated panel can be made "-", " ︺ ", " transversal I ", " ︹ " form or other shapes Formula, the cast-in-place concrete bottom plate overlapping layers 6 in due course after vertically and horizontally side steel bar stress is mechanically connected using sleeve 7 by prefabricated panel.
Further, reserving hole 4 is provided in the prefabricated panel plate face to exist to meet construction period basement structure Stability against floating requirement under extreme case.
Further, basement outer edge prefabricated panel section is made into " ﹂ " form, the section of basement precast facade 10 Form can be " I ", " ︱ ", " [" or "] " form and the reserving hole in its plate face, by outer edge prefabricated panel 5 and prefabricated outer The steel bar stress of wall is connected by slip casting sleeve 8, and setting seat starches 9 at joint face.
Further, stress main reinforcement is mechanically connected by cast-in-situ concrete columns 12 by casing 7 between precast facade 10, completed Between precast facade and after the connection of cast-in-situ concrete columns, then in due course cast-in-place concrete exterior wall overlapping layers 11.
Embodiment two
On the other hand, a kind of assembled integral basement fast and safe construction method is provided, comprising:
Plain concrete cushion layer and paving waterproof roll are set on predetermined ground;
Prefabricated panel is mounted and connected on the good waterproof roll of paving.
Basement outer edge prefabricated panel is connected with precast facade;
Basement precast facade is connected by cast-in-situ concrete columns;
The prefabricated top plate beam of basement is connect with cast-in-situ concrete columns;
The prefabricated top plate of basement is connect with prefabricated top plate beam.
Further, on the waterproof roll set the step of installation overlapping bottom plate specifically:
Prefabricated panel, the vertical muscle of cast-in-situ reinforced concrete column and basis wait cast-in-place concrete section after being mechanically connected using casing Point connection and the construction of cast-in-situ concrete columns;
Vertically and horizontally side steel bar stress is mechanically connected prefabricated panel using sleeve;
Reserving hole is set in prefabricated panel plate face, (basement structure meets construction in the suitable time by hole Period stability against floating require when) grouting behind shaft or drift lining Concrete Filled prefabricated panel lower recess space, then in due course on prefabricated panel Square cast-in-place concrete bottom plate overlapping layers.
Further, the step of connection basement outer edge overlapping bottom plate and outside overlap wall specifically:
Outer edge prefabricated panel and precast facade, which will pass through slip casting sleeve, to carry out high pressure injection again after stress main reinforcement mechanical connection Slurry;
To meet basement construction period stability against floating needs, the reserving hole on precast facade metope, reserving hole energy Link up hydraulic equilibrium inside and outside connection basement;
Complete the connection between precast facade with cast-in-situ concrete columns;
Finally in due course in precast facade side cast-in-place concrete exterior wall overlapping layers.
Specifically, in the present embodiment, a kind of assembled integral basement fast and safe construction method of the present invention is mainly solved Between basement prefabricated panel, between basement outer edge overlapping bottom plate and overlapping exterior wall and between basement overlapping exterior wall and now Quick, the safe and reliable connection of pouring concrete column.Detailed work progress has following steps:
Step 1: plain concrete cushion layer and paving waterproof roll are arranged on predetermined ground, pour and smash reinforced concrete foundation (mainly including the basis of pile foundation, isolated footing, strip footing or other forms).Need the above process that can adjust according to construction Its whole process;
Step 2: prefabricated panel is installed on the waterproof roll set, prefabricated panel, cast-in-situ reinforced concrete column and base Plinth, which is indulged, waits the connection of cast-in-place concrete node and the construction of cast-in-situ concrete columns after muscle is mechanically connected using casing, overlap bottom Plate transverse and longitudinal section can be made " ~ "," transversal I ",Form or other forms, prefabricated panel vertically and horizontally side Side steel bar stress is mechanically connected using sleeve.Prefabricated bottom is filled by the in due course grouting concrete of the hole being reserved on prefabricated panel The space of plate lower recess, finally the cast-in-place concrete bottom plate overlapping layers (being specifically shown in attached drawing 1) above prefabricated panel.
Step 3: the connection of basement outer edge prefabricated panel and precast facade.Basement outer edge prefabricated panel section It is madeForm, outer wall of basement form of fracture can be " I ", " ︱ ", " [" "] " or other forms.The prefabricated bottom of outer edge Plate and precast facade, which will pass through slip casting sleeve, to carry out high-pressure slip-casting (being specifically shown in attached drawing 2) again after stress main reinforcement mechanical connection.Underground Room meets the needs of construction period stability against floating, considers the reserving hole on precast facade metope, the hole on precast facade metope Hole can link up inside and outside connection basement hydraulic equilibrium to meet the requirement of construction period stability against floating, then complete precast facade it Between connection (being specifically shown in attached drawing 3) with cast-in-situ concrete columns, it is last that complete precast facade side cast-in-place concrete exterior wall in due course folded Close layer;
Step 4: the prefabricated top plate beam of connection basement and cast-in-situ concrete columns, detailed process is with reference on assembled integral The connection type of portion's structure;
Step 5: the connection of the connection prefabricated top plate of basement and prefabricated top plate beam, detailed process refer to assembled integral The connection type of superstructure;
When there are multi-storey basement, it is repeatedly performed the connection of above-mentioned prefabricated components and the overlapping layers of cast-in-place concrete in due course, According to construction need can appropriate adjustment structure connection sequencing.The one of the plate faces of above-mentioned prefabricated components, metope or precast beam Side should reserve overlapping reinforcing bar facilitate lifting transport and make prefabricated panel, precast facade or precast beam and rear pouring concrete overlapping layers it Between connect firm cooperative bearing.
Technical solution provided in an embodiment of the present invention has the benefit that
To solve formula basement of building attached at present using the longer curing time of monolithic reinforced concrete structure needs, construction time Between face many engineering roadblocks such as underground structure stability against floating, the requirements such as water proof anti-seepage propose a kind of dress during basement use With monoblock type basement fast and safe construction method.
Relative to cast-in-situ steel reinforced concrete integral basement structure, a kind of assembled integral basement structure of the present invention have with Lower advantage: 1. prefabricated components are produced in batches in PC factory, high-efficient, quality is guaranteed;2. a large amount of construction templates are saved at scene; 3. reducing labour, cross-operation is convenient, accelerates construction progress, construction is not affected by the weather;4. installation accuracy is high, matter of constructing It measures guaranteed;5. energy-saving and emission-reduction, reducing environmental pollution 6. can significantly save the cost when basement is larger;6. prefabricated structure When part (prefabricated panel and precast facade) produces on plate (or wall) face reserving hole, it is anti-to meet construction period basement structure Floating stability requirement;7. prefabricated components be installed after in one side cast-in-place concrete overlapping layers, therefore underground structure have it is good Globality, bearing capacity characteristics, anti-seismic performance and meet operation use during waterproof impervious characteristic.
The present invention can be saved during assembled integral basement construction by the rapid construction of prefabricated components big Fund shortens the construction period, while can also pass through the reserving hole ditch communications and liaison in prefabricated panel plate face and on precast facade metope It is that hydraulic equilibrium is and in due course existing to meet the basement structure stability against floating requirement under extreme case inside and outside construction period basement The overlapping layers of prefabricated panel and precast facade is poured with water proof anti-seepage requirement during meeting basement use.Therefore the present invention is a kind of It is worthy to be popularized, the extensive basement fast and safe construction method of application prospect.
The foregoing is merely a prefered embodiment of the invention, is not intended to limit the invention, all in the spirit and principles in the present invention Within, any modification, equivalent replacement, improvement and so on should all be included in the protection scope of the present invention.

Claims (8)

1.一种装配整体式地下室结构,其特征在于,包括:素混凝土垫层、预制底板、预制外墙;1. an assembled integral basement structure, is characterized in that, comprises: plain concrete cushion, prefabricated bottom plate, prefabricated outer wall; 预定地基上设置所述素混凝土垫层并铺贴防水卷材;所述防水卷材上安装所述预制底板;所述预制底板之间纵横向连接;所述外边缘预制底板与所述预制外墙连接;所述预制底板下表面设置有后注浆混凝土,所述预制底板上表面设置有现浇混凝土底板叠合层。The plain concrete cushion is set on the predetermined foundation and the waterproof membrane is covered; the prefabricated bottom plate is installed on the waterproof membrane; the prefabricated bottom plates are connected vertically and horizontally; the outer edge prefabricated bottom plate and the prefabricated outer wall connection; the lower surface of the prefabricated base plate is provided with post-grouting concrete, and the upper surface of the prefabricated base plate is provided with a cast-in-place concrete base plate superimposed layer. 2.如权利要求1所述的装配整体式地下室结构,其特征在于,所述预制底板纵横断面可以作成“—”、“︺”、“横向I”、“︹”形式或其他形式,将预制底板之间纵横向侧边受力钢筋采用套筒机械连接后适时注浆并现浇混凝土底板叠合层。2. The assembled integral basement structure according to claim 1 is characterized in that, the longitudinal and cross sections of the prefabricated bottom plate can be made into "—", "︺", "horizontal I", "︹" form or other forms, and the prefabricated The longitudinal and lateral side stressed reinforcement bars between the bottom plates are mechanically connected by sleeves and then grouted in a timely manner and the superimposed layer of the cast-in-place concrete bottom plate. 3.如权利要求2所述的装配整体式地下室结构,其特征在于,所述预制底板板面上设置有预留孔洞。3 . The assembled integral basement structure according to claim 2 , wherein the prefabricated bottom plate is provided with reserved holes on the surface. 4 . 4.如权利要求3所述的装配整体式地下室结构,其特征在于,地下室外边缘预制底板断面作成“﹂”形式,地下室外墙的断面形式可以是“I”、“︱”、“[”或“]”或其他形式,并在其墙面上预留孔洞,并将外边缘预制底板与预制外墙受力钢筋通过注浆套筒连接,其连接面处设置座浆。4. The assembled integral basement structure as claimed in claim 3 is characterized in that, the section of the prefabricated bottom plate on the outer edge of the basement is made in the form of "﹂", and the section form of the outer wall of the basement can be in the form of "I", "︱", "[" Or "]" or other forms, and reserve holes on the wall, and connect the outer edge prefabricated bottom plate and the prefabricated outer wall stressed steel bars through a grouting sleeve, and set the seat slurry at the connection surface. 5.如权利要求4所述的装配整体式地下室结构,其特征在于,所述预制外墙之间通过套管将受力主筋机械连接后再现浇混凝土柱,完成预制外墙之间与现浇混凝土柱的连接后,再适时现浇混凝土外墙叠合层。5. The assembled integral basement structure according to claim 4, wherein the prefabricated outer walls are mechanically connected with the main reinforcement bars through casings, and then the concrete columns are reproduced to complete the connection between the prefabricated outer walls and the existing ones. After the connection of the poured concrete columns, the superimposed layer of the concrete outer wall is poured in time. 6.一种装配整体式地下室安全快速施工方法,其特征在于,包括:6. A safe and rapid construction method for an assembled integral basement, characterized in that, comprising: 在预定基坑坑底地基上设置素混凝土垫层并铺贴防水卷材;Set up a plain concrete cushion on the bottom of the predetermined foundation pit and lay a waterproof membrane; 在设置好防水卷材上安装预制底板;Install the prefabricated bottom plate on the set waterproof membrane; 将所述外边缘预制底板和预制外墙连接;connecting the outer edge prefabricated bottom plate and the prefabricated outer wall; 将所述预制外墙通过现浇混凝土柱连接;connecting the prefabricated outer walls through cast-in-place concrete columns; 将预制顶板梁与所述现浇钢筋混凝土柱连接;connecting the prefabricated roof beams with the cast-in-place reinforced concrete columns; 将预制顶板与所述地下室预制顶板梁连接。Connect the prefabricated roof to the basement prefabricated roof beams. 7.如权利要求6所述的方法,其特征在于,在所述设置好防水卷材上安装预制底板的步骤具体为:7. The method according to claim 6, wherein the step of installing a prefabricated bottom plate on the set waterproofing membrane is specifically: 所述预制底板、现浇钢筋混凝土柱与基础纵筋采用套管机械连接后等待现浇混凝土柱的施工;The prefabricated bottom plate, the cast-in-place reinforced concrete column and the foundation longitudinal bars are mechanically connected by casing and wait for the construction of the cast-in-place concrete column; 所述预制底板纵横向侧边受力钢筋采用套筒机械连接;The longitudinal and lateral side stress bars of the prefabricated bottom plate are mechanically connected by sleeves; 在所述预制底板板面上设置预留孔洞,通过预制底板上的预留孔洞在合适的时间后注浆混凝土填充预制底板下凹陷的空间,然后在预制底板上方现浇混凝土底板叠合层;A reserved hole is arranged on the surface of the prefabricated bottom plate, and the recessed space under the prefabricated bottom plate is filled with concrete after a suitable time through the reserved hole on the prefabricated bottom plate, and then the superimposed layer of the concrete bottom plate is cast in place above the prefabricated bottom plate; 其中,所述合适的时间为:地下室结构满足施工期间抗浮稳定要求时。Wherein, the suitable time is when the basement structure meets the anti-floating stability requirements during construction. 8.如权利要求7所述的方法,其特征在于,将所述地下室外边缘预制底板与预制外墙的连接步骤具体为:8. The method of claim 7, wherein the step of connecting the basement outer edge prefabricated bottom plate and the prefabricated outer wall is as follows: 所述外边缘预制底板与所述预制外墙通过注浆套筒连接后再进行高压注浆;The outer edge prefabricated bottom plate and the prefabricated outer wall are connected by a grouting sleeve before high-pressure grouting; 根据地下室施工期间抗浮稳定的需要,在预制外墙墙面上预留孔洞,预留的孔洞能沟通联系地下室内外水力平衡以满足施工期间地下室的抗浮稳定要求;According to the needs of anti-floating stability during the construction of the basement, holes are reserved on the prefabricated exterior walls, and the reserved holes can communicate with the hydraulic balance between the indoor and outdoor basement to meet the anti-floating stability requirements of the basement during construction; 然后完成预制外墙之间与现浇混凝土柱的连接;Then complete the connection between the prefabricated outer walls and the cast-in-place concrete columns; 最后适时在预制外墙一侧完成现浇混凝土叠合层的施工。Finally, the construction of the cast-in-place concrete superimposed layer was completed on one side of the prefabricated outer wall in due course.
CN201810996404.9A 2018-08-29 2018-08-29 A kind of assembled integral basement structure and its safely and fast construction method Pending CN109137972A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810996404.9A CN109137972A (en) 2018-08-29 2018-08-29 A kind of assembled integral basement structure and its safely and fast construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810996404.9A CN109137972A (en) 2018-08-29 2018-08-29 A kind of assembled integral basement structure and its safely and fast construction method

Publications (1)

Publication Number Publication Date
CN109137972A true CN109137972A (en) 2019-01-04

Family

ID=64829096

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810996404.9A Pending CN109137972A (en) 2018-08-29 2018-08-29 A kind of assembled integral basement structure and its safely and fast construction method

Country Status (1)

Country Link
CN (1) CN109137972A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113062164A (en) * 2021-03-05 2021-07-02 武汉理工大学 Double-layer composite full-prefabricated assembly type pavement and construction method
CN114687377A (en) * 2020-12-30 2022-07-01 上海建工二建集团有限公司 Large-bottom-plate modular structure under time-limited condition and construction method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101914925A (en) * 2008-11-19 2010-12-15 兰州南特数码科技股份有限公司 Basement by using optimized composite prefabricated arch wall as external wall
KR101301079B1 (en) * 2012-09-10 2013-09-03 안창일 Box construction method
CN105201012A (en) * 2015-10-27 2015-12-30 国网福建省电力有限公司 Casting cable trench after assembly of L-shaped precast concrete and construction method of casting cable trench
CN106013228A (en) * 2016-06-24 2016-10-12 中国建筑股份有限公司 Overlapping integral type prefabricated assembly structure for comprehensive pipe gallery and construction method thereof
CN106013237A (en) * 2016-07-20 2016-10-12 湖北宇辉新型建筑材料有限公司 Precast concrete component assembly type subway station and installation method
CN106894445A (en) * 2017-04-11 2017-06-27 吉林森煌建筑材料集团有限公司 One kind assembling superposed type pipe gallery and its method of construction
CN108149706A (en) * 2017-12-05 2018-06-12 中建五局第三建设有限公司 Prefabricated assembled comprehensive pipe gallery spliced by cast-in-place hidden beams and laminated slabs and construction method thereof
CN209412856U (en) * 2018-08-29 2019-09-20 南华大学 An assembled integral basement structure that meets the requirements of anti-floating stability

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101914925A (en) * 2008-11-19 2010-12-15 兰州南特数码科技股份有限公司 Basement by using optimized composite prefabricated arch wall as external wall
KR101301079B1 (en) * 2012-09-10 2013-09-03 안창일 Box construction method
CN105201012A (en) * 2015-10-27 2015-12-30 国网福建省电力有限公司 Casting cable trench after assembly of L-shaped precast concrete and construction method of casting cable trench
CN106013228A (en) * 2016-06-24 2016-10-12 中国建筑股份有限公司 Overlapping integral type prefabricated assembly structure for comprehensive pipe gallery and construction method thereof
CN106013237A (en) * 2016-07-20 2016-10-12 湖北宇辉新型建筑材料有限公司 Precast concrete component assembly type subway station and installation method
CN106894445A (en) * 2017-04-11 2017-06-27 吉林森煌建筑材料集团有限公司 One kind assembling superposed type pipe gallery and its method of construction
CN108149706A (en) * 2017-12-05 2018-06-12 中建五局第三建设有限公司 Prefabricated assembled comprehensive pipe gallery spliced by cast-in-place hidden beams and laminated slabs and construction method thereof
CN209412856U (en) * 2018-08-29 2019-09-20 南华大学 An assembled integral basement structure that meets the requirements of anti-floating stability

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
张燕等编: "《装配式混凝土结构设计》", 31 July 2007, 中央广播电视大学出版社, pages: 226 - 64 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114687377A (en) * 2020-12-30 2022-07-01 上海建工二建集团有限公司 Large-bottom-plate modular structure under time-limited condition and construction method
CN114687377B (en) * 2020-12-30 2023-08-08 上海建工二建集团有限公司 Large bottom plate modularized structure under time-limited condition and construction method
CN113062164A (en) * 2021-03-05 2021-07-02 武汉理工大学 Double-layer composite full-prefabricated assembly type pavement and construction method

Similar Documents

Publication Publication Date Title
CN101914925B (en) Basement by using optimized composite prefabricated arch wall as external wall
CN105178357B (en) Prefabricated subsurface structure under foundation trench open cutting condition and construction method for prefabricated subsurface structure under foundation trench open cutting condition
CN106013228B (en) A kind of overlapping monoblock type pipe gallery prefabricated assembly structural and its construction method
CN102182325B (en) Storey adding method for existing building basement with frame structure and independent foundation
CN107313517B (en) Connecting node for laminated wall and laminated floor slab in middle layer
CN206070562U (en) Subassembly formula underground structure
CN106854873A (en) A kind of engineering method and garage parking in precast spliced sinking type garage parking
CN101418569B (en) Optimization complex arch wall combining prefabricated arch leaf, support and major structure
AU4388901A (en) Pre-fabricated bathroom
CN108005399A (en) Add the construction method for building multi-layer underground space under a kind of existing building group
CN107012871B (en) A kind of suspension type goes along with sb. to guard him the deep reversed construction method for greatly enhancing foundation pit fabricated construction
CN103306497B (en) Shock prevention and strengthening construction method for existing brickwork dwelling house fabricated structure
CN108035379B (en) Comprehensive pipe gallery and construction method thereof
CN109137972A (en) A kind of assembled integral basement structure and its safely and fast construction method
CN106193120B (en) Basement is encorbelmented, and bottom plate is inverse to make structure and construction method
CN213143117U (en) Assembled keyway basis retaining wall structure
CN105735352A (en) Fabricated structure based on foundation pit retaining pile for basement exterior walls, and construction method
CN206956949U (en) Overlap wall and intermediate layer laminated floor slab connecting node
RU55388U1 (en) SPATIAL REINFORCED CONCRETE FOUNDATION PLATFORM FOR SMALL-STOREY BUILDINGS FOR CONSTRUCTION IN SPECIAL GROUND CONDITIONS AND SEISMICITY IN ASSEMBLY AND MONOLITHIC OPTIONS
CN110904992B (en) Elevator foundation member for integrally assembling elevator and construction method thereof
CN209555967U (en) An H-shaped concrete slab assembled ecological retaining wall
KR20210133384A (en) Apartment remodeling construction method for construction duration reduction
CN207597914U (en) Add the construction stress structure for building multi-layer underground space under a kind of existing building group
CN217758906U (en) Assembled anti-settlement beam slab foundation structure
CN205502069U (en) Basement outer wall fabricated construction based on excavation supporting stake

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190104