CN107816056A - Filled type concrete gravity retaining wall and its construction technology - Google Patents

Filled type concrete gravity retaining wall and its construction technology Download PDF

Info

Publication number
CN107816056A
CN107816056A CN201711049295.1A CN201711049295A CN107816056A CN 107816056 A CN107816056 A CN 107816056A CN 201711049295 A CN201711049295 A CN 201711049295A CN 107816056 A CN107816056 A CN 107816056A
Authority
CN
China
Prior art keywords
wall
longitudinal side
construction
retaining wall
cavity
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201711049295.1A
Other languages
Chinese (zh)
Inventor
张宏博
岳红亚
宋修广
李为传
杨振宇
于锦涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong University
Original Assignee
Shandong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong University filed Critical Shandong University
Priority to CN201711049295.1A priority Critical patent/CN107816056A/en
Publication of CN107816056A publication Critical patent/CN107816056A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/02Retaining or protecting walls

Abstract

The invention discloses a kind of filled type concrete gravity retaining wall and its construction technology, it solves the problems, such as that retaining wall consumes the non-renewable resources such as a large amount of sandstones, the use of sandstone material can be greatly reduced, realize the recycling of waste and scrap, whole structural stability is improved, has and economizes on resources, it is green, the advantage such as applied widely, its technical scheme are:Multistage retaining wall body including being arranged in order setting, the retaining wall body include being arranged at the basis of bottom, and the basic top sets wall body structure, top plate is set at the top of wall body structure;The wall body structure includes multistage closed-in construction, and two longitudinal side walls are comprised at least per one-level closed-in construction, set crossbeam to connect two longitudinal side walls at the top of longitudinal side wall, cavity is provided between longitudinal side wall, filler is filled with cavity.

Description

Filled type concrete gravity retaining wall and its construction technology
Technical field
The present invention relates to road engineering technical field, and in particular to a kind of slope supporting structure, is filled out more particularly to one kind Fill formula concrete gravity retaining wall and its construction technology.
Background technology
Retaining wall is as a kind of important land consolidation technology, and its security is good, construction is simple, economical and practical, in highway Possesses wide application prospect in engineering construction.As the development of highway in China building cause, particularly high-grade highway are quick Development, retaining wall are being saved the area, and the advantage for reducing cost etc. is more and more significant.Gravity retaining wall is put down by deadweight Heng Qiang carries on the back filler lateral pressure, reaches the purpose that slope supported ensures slope stability.Because its structure type is simple, cost is low, The advantages such as construction is simple, especially it is widely used in slope support engineering in the area that building stones enrich, such as highway Engineering, railway engineering, hydraulic engineering etc..Traditional gravity retaining wall is mostly masonry structure, using block stone, slabstone, coagulation Earth building blocks are by grouting or laid dry mode forms gravity retaining wall.But existing gravity retaining wall is solid construction, by It is larger in size, it is necessary to consume the non-renewable resources such as substantial amounts of sandstone material, while sandstone material also can in recovery process Inevitably bring problem of environmental pollution.In addition the not reproducible use of existing masonry structure retaining wall, in highway reconstruction and expansion work Often fill to form new road structure jointly with newly-built roadbed filling in journey, build new retaining wall again in side slope position, Cause the wasting of resources.Current Green Development has become " 13 " and the from now on basic concept of socio-economic development.It is green public More focus on implementing and implementing for requirements such as " resources conservations, environment-friendly " as the point of penetration for promoting green traffic development in road. Therefore to promote the construction of green highway, should be used from control resource, push structure is innovated angularly, improves gravity retaining wall Structure type, reach the purpose of resources conservation and environmental protection.
Certain Chinese patent gives a kind of Form Gravity Breast Wall, and it is by basis, concrete slab, graded broken stone and cemented rock Composition, although the retaining wall reduces the use of sandstone material to a certain extent, the structure is still solid construction, is only saved About limited sandstone material.Further, since the structure is splicing structure, retaining wall resistance to overturning is low, in special road section (such as height Side slope, earthquake territory) the problem of facing stability deficiency when using.
In summary, the problem of consuming the non-renewable resources such as a large amount of sandstones for retaining wall in the prior art, still lacks Effective solution.
The content of the invention
In order to overcome the above-mentioned deficiencies of the prior art, the invention provides a kind of filled type concrete gravity retaining wall, its The use of sandstone material can be greatly reduced, realize the recycling of waste and scrap, improve whole structural stability, have and save money Source, green, the advantage such as applied widely;
Further, the present invention uses following technical proposals:
A kind of filled type concrete gravity retaining wall, including it is arranged in order the multistage retaining wall body of setting, the earth-retaining Wall body includes being arranged at the basis of bottom, and the basic top sets wall body structure, top plate is set at the top of wall body structure;It is described Wall body structure includes multistage closed-in construction, and two longitudinal side walls are comprised at least per one-level closed-in construction, are set at the top of longitudinal side wall Put crossbeam and connect two longitudinal side walls, cavity is provided between longitudinal side wall, filler is filled with cavity.
Further, cavity filler spilled water hole is set on the longitudinal side wall, first row is set in cavity filler spilled water hole Water pipe.
Further, correspond on the inside of the longitudinal side wall and geotextiles are set at cavity filler spilled water hole.
Further, the both ends of the longitudinal side wall are provided with lateral sidewalls.
Further, the closed-in construction is additionally provided with the second drainpipe for penetrating whole longitudinal side walls, and longitudinal side wall is corresponding Roadbed filling spilled water hole is set at the second drainpipe.
Further, correspond on the inside of the longitudinal side wall and geotextiles are set at roadbed filling spilled water hole.
Further, the filler is soil or building waste or industrial waste.
Further, subsiding crack and expansion joint are set between the adjacent two sections retaining wall bodies.
Further, the subsiding crack and the overall width at expansion joint are 10~20mm.
Further, the wall body structure is faces upward inclined structure or bow inclined structure or upright structures.
Further, the inclined structural wall back slope degree of bowing is (1:0.1)~(1:0.4).
Further, the inclined structural wall back slope degree of facing upward is more than 1:0.25.
Further, the upright structures and inclined structural wall height of bowing are less than 5m.
Further, the inclined structural wall height of facing upward is less than 8m.
Further, the length of the retaining wall body is 5~10m, and adjacent two sections of retaining wall bodies discrepancy in elevation is less than 1.2m.
Further, the basic thickness is more than 0.6m, the wall thickness of the longitudinal side wall and lateral sidewalls for 0.15~ 0.20m。
Further, the top plate is reinforced concrete structure, and its width is not less than 0.5m, and thickness is not less than 0.2m, steel Muscle diameter is not less than
Further, the crossbeam is reinforced concrete structure, and bar diameter is not less thanAlong wall between crossbeam High spacing is 2~3m, and thickness is not less than 0.15m.
Further, the spacing between the cavity filler spilled water hole and roadbed filling spilled water hole is 2~3m.
A kind of construction technology of filled type concrete gravity retaining wall, comprises the following steps:
Step 1:According to roadbed side slope supporting height, calculate and determine retaining wall body geometric parameter;
Step 2:Smooth construction site, excavation pit simultaneously carry out a section drainage measure, and the planar dimension at foundation ditch bottom is more than basis 0.5~1.0m of outer rim;
Step 3:Template is set up in foundation ditch, pours basic and first order closed-in construction longitudinal side wall and lateral sidewalls simultaneously Conserved;
Step 4:When first order closed-in construction intensity reaches the 70% of setting intensity, template of dismantling is filled in cavity fills out Material, and compaction in layers is carried out, and carry out the measurement per roadbed;
Step 5:When filling to beam height, crossbaring reinforcing bar, template is set up, carry out pouring for next stage closed-in construction Build and conserved;
Step 6:When next stage closed-in construction intensity reaches the 70% of setting intensity, template of dismantling is filled in cavity fills out Material, and compaction in layers is carried out, and carry out the measurement per roadbed;
Step 7:Repeat step 5,6, until filling to top setting height, set up template and carry out the arrangement of reinforcement of top plate and pour Build.
Compared with prior art, the beneficial effects of the invention are as follows:
1st, compared with existing masonry gravity retaining wall, the present invention enhances retaining wall by concreting technology Bulk strength and stability, preventing bricklaying wall body, wall body is ftractureed and failure by shear, supporting construction are pacified because puzzle joint intensity deficiency causes Full property improves.
2nd, it is cavity structure inside wall body compared with existing gravity retaining wall, masonry material is replaced by filler filling, Reach the purpose by dead-weight balanced soil lateral pressure.Therefore the usage amount of the non-renewable resources material such as sandstone is greatly reduced. And retaining wall is made up of the retaining wall body of sectional construction, it is easy to move integrally transport, can recycles.
3rd, filler can fill the obsolete materials such as building waste, industrial waste in wall cavity of the present invention, realize waste and old Material recycling and forever depositing admittedly, avoids the environmental issues such as the soil pollution brought during waste and scrap landfill and water pollution, Be advantageous to environmental protection.
4th, compared with existing masonry gravity retaining wall, the concrete of retaining walls body of the present invention is internal to pour to be formed Filler fills through compacting, enormously simplify the construction technology of retaining wall, substantial amounts of manpower consumption when avoiding masonry structure construction.
Brief description of the drawings
The Figure of description for forming the part of the application is used for providing further understanding of the present application, and the application's shows Meaning property embodiment and its illustrate be used for explain the application, do not form the improper restriction to the application.
Fig. 1 is to face upward inclined concrete gravity retaining wall side view;
Fig. 2 is vertical type concrete gravity retaining wall side view;
Fig. 3 is inclined concrete gravity retaining wall side view of bowing;
Fig. 4 is filled type concrete gravity retaining wall front view of the present invention;
In figure, 1, basis, 2, longitudinal side wall, 3, crossbeam, 4, roadbed filling spilled water hole, 5, geotextiles, 6, cavity, 7, cavity Filler spilled water hole, 8, top plate, 9, lateral sidewalls, 10, subsiding crack, 11, retaining wall body.
Embodiment
It is noted that described further below is all exemplary, it is intended to provides further instruction to the application.It is unless another Indicate, all technologies used herein and scientific terminology are with usual with the application person of an ordinary skill in the technical field The identical meanings of understanding.
It should be noted that term used herein above is merely to describe embodiment, and be not intended to restricted root According to the illustrative embodiments of the application.As used herein, unless the context clearly indicates otherwise, otherwise singulative It is also intended to include plural form, additionally, it should be understood that, when in this manual using term "comprising" and/or " bag Include " when, it indicates existing characteristics, step, operation, device, component and/or combinations thereof.
As background technology is introduced, retaining wall in the prior art be present and consume the non-renewable resources such as a large amount of sandstones Problem, in order to solve technical problem as above, present applicant proposes a kind of filled type concrete gravity retaining wall and its construction work Skill.
In a kind of typical embodiment of the application, as shown in Fig. 4,1, there is provided a kind of filled type concrete gravity gear Cob wall, including the multistage retaining wall body 11 of setting is arranged in order, retaining wall body 11 is made up of concrete, and its intensity is not less than C20;The segmentation of retaining wall body 11 is built, and for 5~10m, (length direction of retaining wall body is Fig. 4 to the length of retaining wall body Middle horizontal direction), adjacent two sections of retaining wall bodies discrepancy in elevation is less than 1.2m.
The retaining wall body 11 includes being arranged at the basis 1 of bottom, and basic 1 top sets wall body structure, wall Structural top sets top plate 8;The wall body structure includes multistage closed-in construction, and from top to bottom successively adjoining is set multistage closed-in construction Put, two longitudinal side walls 2 are comprised at least per one-level closed-in construction, the top of longitudinal side wall 2 sets crossbeam 3 to connect two longitudinal side walls 2, cavity 6 is provided between longitudinal side wall 2, filler is filled with cavity 6.
Cavity filler spilled water hole 7 is set on the longitudinal side wall 2, for cavity filler draining, in cavity filler spilled water hole 7 First drainpipe is set.Cavity filler spilled water hole 7 is set along wall is high with wall length.First drainpipe can use pvc pipe.
The inner side of longitudinal side wall 2, which corresponds to, sets geotextiles 5 at cavity filler spilled water hole 7, prevent sluicing hole plug.It is vertical It is close to the side of filler to the inner side of side wall 2.
The closed-in construction is additionally provided with the second drainpipe for penetrating whole longitudinal side walls 2, and longitudinal side wall 2 corresponds to second row Roadbed filling spilled water hole 4 is set at water pipe.Second drainpipe can use pvc pipe.
The inner side of longitudinal side wall 2, which corresponds to, sets geotextiles 5 at roadbed filling spilled water hole 4, prevent sluicing hole plug.
Spacing between the cavity filler spilled water hole and roadbed filling spilled water hole is 2~3m.
The both ends of the longitudinal side wall 2 are provided with lateral sidewalls 9.
The filler is soil or building waste or industrial waste, filler compaction in layers, is 0.2m per thickness degree, compactness is not Less than 90%.
Subsiding crack 10 and expansion joint, subsiding crack 10 and expansion joint is set to close between adjacent two sections of retaining wall bodies 11 And set, the overall width at subsiding crack and expansion joint is 10~20mm.
The wall body structure can face upward inclined structure or as shown in Figure 3 bow inclined structure or such as Fig. 1 for as shown in Figure 1 Shown upright structures.
The inclined structural wall back slope degree of bowing is (1:0.1)~(1:0.4).
The inclined structural wall back slope degree of facing upward is more than 1:0.25.
The upright structures and inclined structural wall height of bowing are less than 5m.
The inclined structural wall height of facing upward is less than 8m.
The basic thickness is more than 0.6m, and the wall thickness of the longitudinal side wall and lateral sidewalls is 0.15~0.20m.
The top plate is reinforced concrete structure, and its width is not less than 0.5m, and thickness is not less than 0.2m, and bar diameter is not small In
The crossbeam is reinforced concrete structure, and bar diameter is not less thanIt is along the high spacing of wall between crossbeam 2~3m, thickness are not less than 0.15m.
In the typical embodiment of another kind of the application, there is provided a kind of filled type concrete weight for slope retaining The construction technology of power formula retaining wall, comprises the following steps:
The first step:Calculating is designed according to roadbed side slope supporting height and cavity filler type, determines retaining wall geometry Parameter, including specific retaining wall size, sidewall thickness, crossbeam position, width, sluicing hole site etc.;
Second step:Smooth construction site, excavation pit simultaneously carry out a section drainage measure, and it is high that excavation of foundation pit height should meet design Degree requires, excavation of foundation pit size should meet the requirement of the construction of basis 1, the planar dimension at foundation ditch bottom be preferably greater than the outer rim 0.5 of basis 1~ 1.0m is in order to the erection of template;
3rd step:Set up longitudinal side wall 2 and lateral sidewalls 9 that template pours earth-retaining foundation of wall 1 and first order closed-in construction And conserved, roadbed filling spilled water hole 4 and the hole of cavity filler spilled water hole 7 should be reserved in casting process and dispose pvc pipe and Geotextiles 5;
4th step:When basis 1 and the intensity of longitudinal side wall 2 and the concrete of lateral sidewalls 9 reach the 70% of final strength, Template of dismantling fills filler in cavity 6, carries out compaction in layers using vibrating rammer, is 0.2m per thickness degree, and carries out every The measurement of roadbed, the next step construction is carried out after compactness reaches requirement;
5th step:When filling to the first order 3 height of crossbeam, the reinforcing bar of crossbaring 3, template is set up, carry out second level frame Formula structure longitudinal side wall 2 and lateral sidewalls 9 and crossbeam 3 pouring and being conserved;
6th step:When the second level, side wall concrete strength reaches the 70% of final strength, template of dismantling is filled cavity 6 and filled out Material, compaction in layers is carried out using vibrating rammer, and carry out the measurement per roadbed, and the reserved He of roadbed filling spilled water hole 4 Cavity filler spilled water hole 7, pvc pipe and geotextiles 5 are installed;
7th step:Multilevel cavity such as be present and answer repeat step 6 and highly set up template until filling to top design and pushed up The arrangement of reinforcement of plate 8 and pour.
In order that the technical scheme of the application can clearly be understood by obtaining those skilled in the art, below with reference to tool The embodiment of body describes the technical scheme of the application in detail.
Embodiment 1
As shown in figure 1, facing upward inclined concrete gravity retaining wall, retaining wall size, earth-retaining are determined according to specific supporting height The wall wall body gradient should not be delayed in 1:0.25;It is first according to that design requirement carries out the arrangement in place and excavation of foundation pit and guarded drainage are arranged Apply.Then the concreting that template carries out basis and first order side wall is set up.After maintenance is completed, filler is filled in cavity And be compacted, spilled water hole is set.Then carry out crossbeam arrangement of reinforcement and second level side wall concreting and conserved, concrete strength Reach and filler in the cavity of the second level is carried out after requirement fill and spilled water hole is set.Finally carry out the arrangement of reinforcement of top plate and pouring for concrete Build and conserve.
Embodiment 2
As shown in Fig. 2 vertical type concrete gravity retaining wall, determines retaining wall size, first according to specific supporting height Arrangement and excavation of foundation pit and the waterproof and drain measure in place are carried out according to design requirement.Then set up template and carry out basis and first The concreting of level side wall.After maintenance is completed, filler is filled in cavity and is compacted, spilled water hole is set.Then carry out horizontal Beam arrangement of reinforcement and second level side wall concreting are simultaneously conserved, and concrete strength after reaching requirement fill out in the cavity of the second level Material fills and sets spilled water hole.Finally carry out the arrangement of reinforcement of top plate and pouring and conserving for concrete.
Embodiment 3
As shown in figure 3, inclined formula concrete gravity retaining wall of bowing, determines retaining wall size according to specific supporting height, bows The inclined gradient is 1:0.2.It is first according to arrangement and excavation of foundation pit and waterproof and drain measure that design requirement carries out place.Then it is false If template carries out the concreting of basis and first order side wall.After maintenance is completed, filler is filled in cavity and is compacted, if Put spilled water hole.Then carry out crossbeam arrangement of reinforcement and second level side wall concreting and conserved, concrete strength reaches requirement Filler in the cavity of the second level is carried out afterwards to fill and set spilled water hole.Finally carry out the arrangement of reinforcement of top plate and pouring and supporting for concrete Shield.
The preferred embodiment of the application is the foregoing is only, is not limited to the application, for the skill of this area For art personnel, the application can have various modifications and variations.It is all within spirit herein and principle, made any repair Change, equivalent substitution, improvement etc., should be included within the protection domain of the application.

Claims (10)

1. a kind of filled type concrete gravity retaining wall, it is characterized in that, including it is arranged in order the multistage retaining wall body of setting, institute Stating retaining wall body includes being arranged at the basis of bottom, and the basic top sets wall body structure, top is set at the top of wall body structure Plate;The wall body structure includes multistage closed-in construction, and two longitudinal side walls, longitudinal side wall are comprised at least per one-level closed-in construction Top sets crossbeam to connect two longitudinal side walls, and cavity is provided between longitudinal side wall, filler is filled with cavity.
2. Form Gravity Breast Wall as claimed in claim 1, it is characterized in that, cavity filler spilled water hole is set on the longitudinal side wall, First drainpipe is set in cavity filler spilled water hole.
3. Form Gravity Breast Wall as claimed in claim 2, it is characterized in that, cavity filler is corresponded on the inside of the longitudinal side wall and is sluiced Geotextiles are set at hole.
4. Form Gravity Breast Wall as claimed in claim 1, it is characterized in that, the both ends of the longitudinal side wall are provided with cross side Wall.
5. Form Gravity Breast Wall as claimed in claim 1, it is characterized in that, the closed-in construction is additionally provided with the whole longitudinal side walls of insertion The second drainpipe, longitudinal side wall correspond to the second drainpipe at set roadbed filling spilled water hole;It is right on the inside of the longitudinal side wall Geotextiles should be set at roadbed filling spilled water hole.
6. Form Gravity Breast Wall as claimed in claim 1, it is characterized in that, the filler is soil or building waste or industrial waste.
7. Form Gravity Breast Wall as claimed in claim 1, it is characterized in that, sedimentation is set between adjacent two sections of retaining wall bodies Seam and expansion joint;The subsiding crack and the overall width at expansion joint are 10~20mm.
8. Form Gravity Breast Wall as claimed in claim 1, it is characterized in that, the wall body structure is faces upward inclined structure or inclined knot of bowing Structure or upright structures;
The inclined structural wall back slope degree of bowing is (1:0.1)~(1:0.4);The inclined structural wall back slope degree of facing upward is more than 1: 0.25。
9. Form Gravity Breast Wall as claimed in claim 1, it is characterized in that, the length of the retaining wall body is 5~10m, adjacent Two sections of retaining wall body discrepancy in elevation are less than 1.2m;The top plate is reinforced concrete structure;The crossbeam is reinforced concrete structure.
10. the construction technology of the Form Gravity Breast Wall as described in claim any one of 1-9, it is characterized in that, comprise the following steps:
Step 1:According to roadbed side slope supporting height, calculate and determine retaining wall body geometric parameter;
Step 2:Smooth construction site, excavation pit simultaneously carry out a section drainage measure, and the planar dimension at foundation ditch bottom is more than basic outer rim 0.5~1.0m;
Step 3:Template is set up in foundation ditch, basic and first order closed-in construction longitudinal side wall and lateral sidewalls is poured and carries out Maintenance;
Step 4:When first order closed-in construction intensity reaches the 70% of setting intensity, template of dismantling fills filler in cavity, And compaction in layers is carried out, and carry out the measurement per roadbed;
Step 5:When filling to beam height, crossbaring reinforcing bar, template is set up, carry out pouring simultaneously for next stage closed-in construction Conserved;
Step 6:When next stage closed-in construction intensity reaches the 70% of setting intensity, template of dismantling fills filler in cavity, And compaction in layers is carried out, and carry out the measurement per roadbed;
Step 7:Repeat step 5,6, until filling to top setting height, set up template and carry out the arrangement of reinforcement of top plate and pour.
CN201711049295.1A 2017-10-31 2017-10-31 Filled type concrete gravity retaining wall and its construction technology Pending CN107816056A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201711049295.1A CN107816056A (en) 2017-10-31 2017-10-31 Filled type concrete gravity retaining wall and its construction technology

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201711049295.1A CN107816056A (en) 2017-10-31 2017-10-31 Filled type concrete gravity retaining wall and its construction technology

Publications (1)

Publication Number Publication Date
CN107816056A true CN107816056A (en) 2018-03-20

Family

ID=61603046

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201711049295.1A Pending CN107816056A (en) 2017-10-31 2017-10-31 Filled type concrete gravity retaining wall and its construction technology

Country Status (1)

Country Link
CN (1) CN107816056A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108360557A (en) * 2018-05-02 2018-08-03 莱芜钢铁集团粉末冶金有限公司 A kind of segmented retaining Wall
CN108797636A (en) * 2018-09-06 2018-11-13 中铁二院北方勘察设计有限责任公司 A kind of upper font retaining wall structure and its construction method
CN110284518A (en) * 2019-07-17 2019-09-27 上海勘测设计研究院有限公司 A kind of tilting empty van barricade
CN110644297A (en) * 2019-10-31 2020-01-03 中铁二院工程集团有限责任公司 Anti-bulging supporting structure of ballastless track high-speed railway and construction method
CN111663564A (en) * 2020-06-03 2020-09-15 安徽省交通规划设计研究总院股份有限公司 UHPC-C environment-friendly retaining wall and construction method thereof

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN203716176U (en) * 2013-12-13 2014-07-16 中国水电顾问集团贵阳勘测设计研究院有限公司 Integrated framework type plate column soil retaining wall for full-filling of filling area
JP5816420B2 (en) * 2010-07-30 2015-11-18 ランデス株式会社 Retaining wall construction water storage block
CN105544600A (en) * 2015-12-30 2016-05-04 中铁第四勘察设计院集团有限公司 Segmented precast open-web retaining wall building block and retaining wall structure
CN106930319A (en) * 2017-05-03 2017-07-07 中冶沈勘工程技术有限公司 A kind of high slope framed revetment and its construction method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP5816420B2 (en) * 2010-07-30 2015-11-18 ランデス株式会社 Retaining wall construction water storage block
CN203716176U (en) * 2013-12-13 2014-07-16 中国水电顾问集团贵阳勘测设计研究院有限公司 Integrated framework type plate column soil retaining wall for full-filling of filling area
CN105544600A (en) * 2015-12-30 2016-05-04 中铁第四勘察设计院集团有限公司 Segmented precast open-web retaining wall building block and retaining wall structure
CN106930319A (en) * 2017-05-03 2017-07-07 中冶沈勘工程技术有限公司 A kind of high slope framed revetment and its construction method

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108360557A (en) * 2018-05-02 2018-08-03 莱芜钢铁集团粉末冶金有限公司 A kind of segmented retaining Wall
CN108797636A (en) * 2018-09-06 2018-11-13 中铁二院北方勘察设计有限责任公司 A kind of upper font retaining wall structure and its construction method
CN110284518A (en) * 2019-07-17 2019-09-27 上海勘测设计研究院有限公司 A kind of tilting empty van barricade
CN110644297A (en) * 2019-10-31 2020-01-03 中铁二院工程集团有限责任公司 Anti-bulging supporting structure of ballastless track high-speed railway and construction method
CN111663564A (en) * 2020-06-03 2020-09-15 安徽省交通规划设计研究总院股份有限公司 UHPC-C environment-friendly retaining wall and construction method thereof

Similar Documents

Publication Publication Date Title
CN107816056A (en) Filled type concrete gravity retaining wall and its construction technology
CN204059124U (en) A kind of sand drain strong rammer grouting behind shaft or drift lining foundation reinforcing structure
CN206553852U (en) A kind of geosynthetic reinforced pile supported embankments on soft soil
CN203729324U (en) Anchor rod lattice type retaining wall structure
CN105804119A (en) Underground corridor structure with dual-purpose pile foundations and construction method of underground corridor structure
CN205399090U (en) On stride highway's pile foundation reinforced concrete railway roadbed structure
CN109750571B (en) Road collapse emergency and permanent retaining integrated structure and construction method
CN108547641A (en) The bottom stab ilization system and its construction method in rich water soft stratum heavy haul railway tunnel
CN105672450A (en) Laying method for large-aperture water draining pipeline parallel to upper part of existing metro tunnel structure
CN210194361U (en) Splicing structure for widening new and old roadbeds on road
CN104762956B (en) Method for forming pile based on construction waste recycled aggregate
CN104480956B (en) A kind of minor diameter mold-bagged concrete pile composite foundation
CN105926391B (en) A kind of curb method for widening of existing railway roadbed
CN103215950B (en) Pile foundation extension construction method in backfilling area
CN203334154U (en) Embankment structure for preventing bearing platform of pile foundation from stretching in roadbed under viaduct
CN111188355A (en) Super-gravity type anchorage shallow-buried foundation and construction method
CN105155575B (en) Non-excavation cantilever retaining wall with embedded steel pipe and construction method of non-excavation cantilever retaining wall
CN106836034B (en) High-fill cover plate culvert flexible load shedding system and construction method
CN110805049B (en) Construction method of mountain slope ultra-thickness spray anchor permanent supporting structure
CN105804101B (en) Reduce off-loading supporting and retaining system system and construction method and the application of retaining structure stress
CN204825867U (en) As composite pile structure of secretly digging garage stand
CN106245546A (en) A kind of corrugated steel Pipe rack
CN110055845A (en) A kind of construction method that highway bridge and culvert two sides are soft soil roadbed
CN103866788A (en) Retaining wall reformation method for column type bridge abutment foreslope
CN210507517U (en) Combined member suitable for retaining wall heightening

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180320