CN110158602A - 一种软土地质深基坑支护开挖施工结构及施工方法 - Google Patents
一种软土地质深基坑支护开挖施工结构及施工方法 Download PDFInfo
- Publication number
- CN110158602A CN110158602A CN201910494700.3A CN201910494700A CN110158602A CN 110158602 A CN110158602 A CN 110158602A CN 201910494700 A CN201910494700 A CN 201910494700A CN 110158602 A CN110158602 A CN 110158602A
- Authority
- CN
- China
- Prior art keywords
- foundation pit
- pile
- block
- section
- region
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/10—Deep foundations
- E02D27/12—Pile foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/10—Deep foundations
- E02D27/12—Pile foundations
- E02D27/14—Pile framings, i.e. piles assembled to form the substructure
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/02—Sheet piles or sheet pile bulkheads
- E02D5/03—Prefabricated parts, e.g. composite sheet piles
- E02D5/04—Prefabricated parts, e.g. composite sheet piles made of steel
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
- E02D5/46—Concrete or concrete-like piles cast in position ; Apparatus for making same making in situ by forcing bonding agents into gravel fillings or the soil
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Chemical & Material Sciences (AREA)
- Composite Materials (AREA)
- Piles And Underground Anchors (AREA)
Abstract
Description
Claims (10)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910494700.3A CN110158602B (zh) | 2019-06-10 | 2019-06-10 | 一种软土地质深基坑支护开挖施工结构及施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910494700.3A CN110158602B (zh) | 2019-06-10 | 2019-06-10 | 一种软土地质深基坑支护开挖施工结构及施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN110158602A true CN110158602A (zh) | 2019-08-23 |
CN110158602B CN110158602B (zh) | 2020-09-29 |
Family
ID=67627857
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910494700.3A Active CN110158602B (zh) | 2019-06-10 | 2019-06-10 | 一种软土地质深基坑支护开挖施工结构及施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110158602B (zh) |
Cited By (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110777835A (zh) * | 2019-10-31 | 2020-02-11 | 安徽省路港工程有限责任公司 | 钢管桩支护桩基承台支模体系的施工方法 |
CN110984170A (zh) * | 2019-11-25 | 2020-04-10 | 上海水务建设工程有限公司 | 半自动基坑钢支撑安装方法及钢支撑安装辅助装置 |
CN111535332A (zh) * | 2020-05-13 | 2020-08-14 | 福建岩土工程勘察研究院有限公司 | 一种软土地区钢板桩基坑支护结构失稳的加固方法 |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100720321B1 (ko) * | 2005-04-19 | 2007-05-25 | 주식회사 서영엔지니어링 | 작용하중에 따라 발생되는 변위와 반력을 직접회복 및상쇄하도록 제어하는 자동싱크로나이즈지지시스템 및 이의설치방법 |
CN104947682A (zh) * | 2015-05-06 | 2015-09-30 | 中国地质大学(武汉) | 一种基坑支护施工方法及其装置 |
CN105604576A (zh) * | 2016-01-20 | 2016-05-25 | 中铁隆工程集团有限公司 | 一种软岩地层暗挖大断面隧道施工方法及支护体系 |
CN107476313A (zh) * | 2017-08-22 | 2017-12-15 | 江苏省岩土工程公司 | 一种斜抛撑支护系统及与基础底板同时施工的方法 |
CN109403333A (zh) * | 2018-11-02 | 2019-03-01 | 福建工程学院 | 一种上软下硬富水地层深基坑逆作施工方法 |
CN109778866A (zh) * | 2018-12-20 | 2019-05-21 | 上海建工集团股份有限公司 | 用于基坑中心岛盆式开挖的组合支护体系及其施工方法 |
-
2019
- 2019-06-10 CN CN201910494700.3A patent/CN110158602B/zh active Active
Patent Citations (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
KR100720321B1 (ko) * | 2005-04-19 | 2007-05-25 | 주식회사 서영엔지니어링 | 작용하중에 따라 발생되는 변위와 반력을 직접회복 및상쇄하도록 제어하는 자동싱크로나이즈지지시스템 및 이의설치방법 |
CN104947682A (zh) * | 2015-05-06 | 2015-09-30 | 中国地质大学(武汉) | 一种基坑支护施工方法及其装置 |
CN105604576A (zh) * | 2016-01-20 | 2016-05-25 | 中铁隆工程集团有限公司 | 一种软岩地层暗挖大断面隧道施工方法及支护体系 |
CN105604576B (zh) * | 2016-01-20 | 2018-08-21 | 中铁隆工程集团有限公司 | 一种软岩地层暗挖大断面隧道施工方法 |
CN107476313A (zh) * | 2017-08-22 | 2017-12-15 | 江苏省岩土工程公司 | 一种斜抛撑支护系统及与基础底板同时施工的方法 |
CN109403333A (zh) * | 2018-11-02 | 2019-03-01 | 福建工程学院 | 一种上软下硬富水地层深基坑逆作施工方法 |
CN109778866A (zh) * | 2018-12-20 | 2019-05-21 | 上海建工集团股份有限公司 | 用于基坑中心岛盆式开挖的组合支护体系及其施工方法 |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110777835A (zh) * | 2019-10-31 | 2020-02-11 | 安徽省路港工程有限责任公司 | 钢管桩支护桩基承台支模体系的施工方法 |
CN110777835B (zh) * | 2019-10-31 | 2021-04-27 | 安徽省路港工程有限责任公司 | 钢管桩支护桩基承台支模体系的施工方法 |
CN110984170A (zh) * | 2019-11-25 | 2020-04-10 | 上海水务建设工程有限公司 | 半自动基坑钢支撑安装方法及钢支撑安装辅助装置 |
CN111535332A (zh) * | 2020-05-13 | 2020-08-14 | 福建岩土工程勘察研究院有限公司 | 一种软土地区钢板桩基坑支护结构失稳的加固方法 |
Also Published As
Publication number | Publication date |
---|---|
CN110158602B (zh) | 2020-09-29 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US11384501B2 (en) | Method for sealing post-cast strip in foundation with no gap | |
CN208917858U (zh) | 预制拼装式内腔型沉井装置 | |
CN107059667A (zh) | 门形装配式钢筋混凝土箱型涵洞及其施工方法 | |
CN110158602A (zh) | 一种软土地质深基坑支护开挖施工结构及施工方法 | |
CN106320377A (zh) | 一种富水软土地区深基坑盖挖逆作施工方法 | |
CN109695250A (zh) | 一种深厚软土地层大直径沉井施工方法 | |
CN113502828B (zh) | 一种深基坑预警的处理方法 | |
CN209855277U (zh) | 一种用于既有建筑地下增层的转换层结构 | |
CN109826224A (zh) | 一种用于沙漠地带输电线路铁塔的沉井护壁掏挖基础及其施工方法 | |
CN116856932B (zh) | 一种含玻纤筋部的大直径预应力装配竖井结构及施工方法 | |
CN108222054A (zh) | 塔吊基础结构及其施工方法 | |
JPH0610344A (ja) | 場所打ち杭の支持力の確認と増加方法 | |
JP6475554B2 (ja) | 立坑の構築方法および地下式貯槽の構築方法 | |
CN111962522A (zh) | 一种倾斜楔形桩与竖直管桩的组合支护结构及其构建方法 | |
CN110093945B (zh) | 一种加装电梯钢结构底坑 | |
CN210946927U (zh) | 桅杆吊臂架下铰点基座的修复结构 | |
CN211172070U (zh) | 一种拼装型钢筋混凝土构件装配式悬壁挡土墙结构 | |
CN111472363A (zh) | 一种位于既有建构筑物地下空间的基坑围护结构施工方法 | |
CN111236311A (zh) | 用于密集既有建筑群地下空间开发的施工平台及施工方法 | |
CN212656215U (zh) | 一种十字形预制钢砼桩与钢管柱组合的装配式管架 | |
CN110656576A (zh) | 一种桥墩结构及其施工方法 | |
CN212506308U (zh) | 一种倾斜管桩与竖直楔形桩的组合支护结构 | |
KR101658826B1 (ko) | 테두리부 구조물로 토압을 지지하는 지하구조물 구축구조 및 공법 | |
CN216338977U (zh) | 桥梁加跨改建装置以及桥梁 | |
CN212506305U (zh) | 倾斜楔形桩与竖直楔形桩的组合支护结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant | ||
TR01 | Transfer of patent right |
Effective date of registration: 20220208 Address after: 430048 No. 11 Jinyinhu Road, Dongxihu District, Wuhan City, Hubei Province Patentee after: CCCC SECOND HARBOR ENGINEERING Co.,Ltd. Patentee after: CCCC WUHAN HARBOUR ENGINEERING DESIGN AND RESEARCH Co.,Ltd. Address before: No.11, Dongxihu Road, Jinyinhu District, Wuhan City, Hubei Province Patentee before: CCCC SECOND HARBOR ENGINEERING Co.,Ltd. |
|
TR01 | Transfer of patent right | ||
TR01 | Transfer of patent right |
Effective date of registration: 20220907 Address after: Room 1311, 13th Floor, Building 7#8#, Zixin Yuhuwan, No. 199 Wenyuan East Road, Gaotangling Street, Wangcheng District, Changsha City, Hunan Province 410203 Patentee after: CCCC (Changsha) Construction Co.,Ltd. Address before: 430048 No. 11 Jinyinhu Road, Dongxihu District, Wuhan City, Hubei Province Patentee before: CCCC SECOND HARBOR ENGINEERING Co.,Ltd. Patentee before: CCCC WUHAN HARBOUR ENGINEERING DESIGN AND RESEARCH Co.,Ltd. |
|
TR01 | Transfer of patent right |