CN110027987A - A kind of arc cantilever steel girder construction method for hanging - Google Patents
A kind of arc cantilever steel girder construction method for hanging Download PDFInfo
- Publication number
- CN110027987A CN110027987A CN201910360931.5A CN201910360931A CN110027987A CN 110027987 A CN110027987 A CN 110027987A CN 201910360931 A CN201910360931 A CN 201910360931A CN 110027987 A CN110027987 A CN 110027987A
- Authority
- CN
- China
- Prior art keywords
- temporary support
- girder
- cantilever steel
- steel girder
- steel
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C13/00—Other constructional features or details
- B66C13/04—Auxiliary devices for controlling movements of suspended loads, or preventing cable slack
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B66—HOISTING; LIFTING; HAULING
- B66C—CRANES; LOAD-ENGAGING ELEMENTS OR DEVICES FOR CRANES, CAPSTANS, WINCHES, OR TACKLES
- B66C13/00—Other constructional features or details
- B66C13/18—Control systems or devices
- B66C13/48—Automatic control of crane drives for producing a single or repeated working cycle; Programme control
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/20—Design optimisation, verification or simulation
- G06F30/23—Design optimisation, verification or simulation using finite element methods [FEM] or finite difference methods [FDM]
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Geometry (AREA)
- Theoretical Computer Science (AREA)
- General Physics & Mathematics (AREA)
- Computer Hardware Design (AREA)
- Evolutionary Computation (AREA)
- General Engineering & Computer Science (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Architecture (AREA)
- Automation & Control Theory (AREA)
- Structural Engineering (AREA)
- Computational Mathematics (AREA)
- Mathematical Analysis (AREA)
- Mathematical Optimization (AREA)
- Pure & Applied Mathematics (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
The invention discloses a kind of arc cantilever steel girder construction method for hanging, belong to construction technical field.The present invention is the following steps are included: step 1. application BIM technology creates cantilever steel girder three-dimensional visualization model;Step 2. calculates girder steel weight and length, selects crane, wirerope etc.;Step 3. selects suitable suspension centre and temporary support point using finite element analysis cantilever steel girder, temporary support and hoisting process force analysis, and it is quasi- based on BIM technology to carry out dynamic lifting simulation, unloading simulation, temporary support peace demoulding;Step 4. girder steel is marched into the arena, and temporary support installation, crane is in place, and examination is hung, lifting;Step 5. cantilever steel girder is in place, and girder steel and the installation of support tie point are fixed, and overhanging end is fixed on temporary support;Step 6. wirerope gradually unloads, and temporary support is removed.The present invention effectively improves the security and stability of unilateral support cantilever steel girder hoisting process, obtains preferable Social benefit and economic benefit.
Description
Technical field
The present invention relates to construction technical fields, more specifically to a kind of arc cantilever steel girder lifting construction side
Method.
Background technique
The arc cantilever steel girder of the more and more unilateral support of the medium-and-large-sized Stadium of engineering construction, and cantilever steel girder master
When beam is constructed, secondary beam and connecting elements are not yet constructed, and only unilateral support, structure are extremely unstable, it is necessary to be taken corresponding
Measure is reinforced.
Summary of the invention
1. technical problems to be solved by the inivention
In view of the defects existing in the prior art with deficiency, the present invention provides a kind of arc cantilever steel girder lifting construction sides
It is quasi- hang loading, unloading simulation, temporary support peace demoulding to cantilever steel girder based on BIM technology, effectively improves unilateral branch for method
The security and stability for supportting cantilever steel girder hoisting process, obtains preferable Social benefit and economic benefit.
2. technical solution
In order to achieve the above objectives, technical solution provided by the invention are as follows:
A kind of arc cantilever steel girder construction method for hanging of the invention, comprising the following steps:
Step 1. application BIM technology creates cantilever steel girder three-dimensional visualization model;
Step 2. calculates girder steel weight and length, selects crane, wirerope etc.;Using a kind of self-control fixed frame to overhanging end
Carry out temporary support;
For step 3. using finite element analysis cantilever steel girder, temporary support and hoisting process force analysis, selection is suitable
Suspension centre and temporary support point, and it is quasi- based on BIM technology to carry out dynamic lifting simulation, unloading simulation, temporary support peace demoulding;
Step 4. girder steel is marched into the arena, and temporary support installation, crane is in place, and examination is hung, lifting;
Step 5. cantilever steel girder is in place, and girder steel and the installation of support tie point are fixed, and temporary support is fixed at overhanging end
On;
Step 6. wirerope gradually unloads, and temporary support is removed.
3. beneficial effect
Using technical solution provided by the invention, compared with prior art, have the following beneficial effects:
The present invention is based on finite elements to reinforce support to unilateral support cantilever steel girder overhanging end to using fixing support rack, uses
Finite element analysis cantilever steel girder, temporary support and hoisting process force analysis hang cantilever steel girder based on BIM technology
Loading, unloading simulation, temporary support peace demoulding are quasi-, effectively improve the safety and stability of unilateral support cantilever steel girder hoisting process
Property, obtain preferable Social benefit and economic benefit.
Detailed description of the invention
Fig. 1 is construction process figure of the invention.
Specific embodiment
The invention will be further described with reference to the accompanying drawings and examples:
Embodiment 1
It will be seen from figure 1 that a kind of arc cantilever steel girder construction method for hanging of the present embodiment, comprising the following steps:
Step 1. application BIM technology creates cantilever steel girder three-dimensional visualization model;Girder steel total height 53m, total length 67m,
Fixed section vertical length 43m overhangs end length 24m, radius of the radian R4.7m;
Step 2. using a kind of self-control fixed frame to overhanging end carry out temporary support, this fixed frame be it is detachable, by one
Section segment type steel is assembled;With the preparatory casting concrete base in ground junction, pre-embedded anchoring bolts, it is ensured that firm;Calculate steel
Beam weight and length select crane, wirerope etc.;Single girder steel weight 18t, length 67m, select 150t crawler crane 1
Platform, suspension centre select 2,2, wirerope;
For step 3. using finite element analysis cantilever steel girder, temporary support and hoisting process force analysis, selection is suitable
Suspension centre and temporary support point, and it is quasi- based on BIM technology to carry out dynamic lifting simulation, unloading simulation, temporary support peace demoulding;
Step 4. girder steel is marched into the arena, and temporary support installation, crane is in place, and examination is hung, lifting;The whole liftoff 20cm of girder steel, hangs
Vehicle suspends 5 minutes;In lifting, every raising 5m carries out absolute altitude monitoring;
Step 5 cantilever steel girder is in place, and girder steel and the installation of support tie point are fixed, and overhanging end is fixed on temporary support;
Crane suspention, while overhanging end and being fixed on temporary support, keep girder steel completely in place, the connection for carrying out girder steel and support is pacified
Dress;
Step 6. wirerope gradually unloads, and temporary support is removed.
Schematically the present invention and embodiments thereof are described above, description is not limiting, institute in attached drawing
What is shown is also one of embodiments of the present invention, and actual method is not limited thereto.So if the common skill of this field
Art personnel are enlightened by it, without departing from the spirit of the invention, are not inventively designed and the technical solution
Similar frame mode and embodiment, are within the scope of protection of the invention.
Claims (1)
1. a kind of arc cantilever steel girder construction method for hanging, it is characterised in that: the following steps are included:
Step 1. application BIM technology creates cantilever steel girder three-dimensional visualization model;
Step 2. calculates girder steel weight and length, selects crane, wirerope etc.;Overhanging end is carried out using a kind of self-control fixed frame
Temporary support;
Step 3. selects suitable suspension centre using finite element analysis cantilever steel girder, temporary support and hoisting process force analysis
And temporary support point, and it is quasi- based on BIM technology to carry out dynamic lifting simulation, unloading simulation, temporary support peace demoulding;
Step 4. girder steel is marched into the arena, and temporary support installation, crane is in place, and examination is hung, lifting;
Step 5. cantilever steel girder is in place, and girder steel and the installation of support tie point are fixed, and overhanging end is fixed on temporary support;
Step 6. wirerope gradually unloads, and temporary support is removed.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910360931.5A CN110027987A (en) | 2019-04-30 | 2019-04-30 | A kind of arc cantilever steel girder construction method for hanging |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910360931.5A CN110027987A (en) | 2019-04-30 | 2019-04-30 | A kind of arc cantilever steel girder construction method for hanging |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110027987A true CN110027987A (en) | 2019-07-19 |
Family
ID=67240928
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910360931.5A Pending CN110027987A (en) | 2019-04-30 | 2019-04-30 | A kind of arc cantilever steel girder construction method for hanging |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110027987A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110713117A (en) * | 2019-09-02 | 2020-01-21 | 上海二十冶建设有限公司 | Sintering machine primary mixer and secondary mixer hoisting method |
CN110950267A (en) * | 2019-11-07 | 2020-04-03 | 广西电网有限责任公司桂林供电局 | Hoisting method of transformer |
CN111851296A (en) * | 2020-06-22 | 2020-10-30 | 中铁北京工程局集团(天津)工程有限公司 | Steel beam hoisting method |
CN115787996A (en) * | 2022-12-05 | 2023-03-14 | 中建八局第二建设有限公司 | Overhung construction method and overhung frame for super-high building |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102619170A (en) * | 2012-03-20 | 2012-08-01 | 中铁四局集团钢结构有限公司 | Large-span flexible arch skew back joining construction method |
CN102936962A (en) * | 2012-11-20 | 2013-02-20 | 永升建设集团有限公司 | Construction method of slanting cantilever steel structure supported by temporary steel frame |
CN106894639A (en) * | 2017-04-27 | 2017-06-27 | 中国建筑第八工程局有限公司 | The hanging reverse construction method of installation of steel construction under a kind of |
CN109372267A (en) * | 2018-11-20 | 2019-02-22 | 中国三冶集团有限公司 | A kind of modularization steel structure frame preassembling construction method |
CN109441127A (en) * | 2018-12-05 | 2019-03-08 | 中铁二局第三工程有限公司 | A kind of virtual emulation in-site installation construction method across overhanging steel structure greatly |
-
2019
- 2019-04-30 CN CN201910360931.5A patent/CN110027987A/en active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN102619170A (en) * | 2012-03-20 | 2012-08-01 | 中铁四局集团钢结构有限公司 | Large-span flexible arch skew back joining construction method |
CN102936962A (en) * | 2012-11-20 | 2013-02-20 | 永升建设集团有限公司 | Construction method of slanting cantilever steel structure supported by temporary steel frame |
CN106894639A (en) * | 2017-04-27 | 2017-06-27 | 中国建筑第八工程局有限公司 | The hanging reverse construction method of installation of steel construction under a kind of |
CN109372267A (en) * | 2018-11-20 | 2019-02-22 | 中国三冶集团有限公司 | A kind of modularization steel structure frame preassembling construction method |
CN109441127A (en) * | 2018-12-05 | 2019-03-08 | 中铁二局第三工程有限公司 | A kind of virtual emulation in-site installation construction method across overhanging steel structure greatly |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110713117A (en) * | 2019-09-02 | 2020-01-21 | 上海二十冶建设有限公司 | Sintering machine primary mixer and secondary mixer hoisting method |
CN110950267A (en) * | 2019-11-07 | 2020-04-03 | 广西电网有限责任公司桂林供电局 | Hoisting method of transformer |
CN110950267B (en) * | 2019-11-07 | 2021-07-20 | 广西电网有限责任公司桂林供电局 | Hoisting method of transformer |
CN111851296A (en) * | 2020-06-22 | 2020-10-30 | 中铁北京工程局集团(天津)工程有限公司 | Steel beam hoisting method |
CN115787996A (en) * | 2022-12-05 | 2023-03-14 | 中建八局第二建设有限公司 | Overhung construction method and overhung frame for super-high building |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110027987A (en) | A kind of arc cantilever steel girder construction method for hanging | |
CN102561788B (en) | Guide track series for helicopter assemblage power transmission line iron tower | |
CN102071798B (en) | Hydraulic climbing system for wall-attached support frame | |
CN106836498A (en) | A kind of super-span Stadium roof system steel truss lifting construction engineering method | |
CN110056197A (en) | A kind of overhanging three-dimension curved surface steel cage canopy integral hoisting construction method | |
CN102230313B (en) | Bridge thin-wall hollow-pier chain block hoisting operation platform and construction method thereof | |
CN108179816A (en) | A kind of deviation sliding and lifting device and method | |
CN202131824U (en) | Serial guide rail used for helicopter assembly transmission line iron tower | |
CN208884362U (en) | A kind of Construction of continuous beam bracket | |
CN106042173A (en) | Bridge production system | |
CN111622781A (en) | Construction equipment and method for suspension bridge tunnel anchor chamber vault secondary lining | |
CN204847755U (en) | Guide rail hoist and mount frock | |
CN208454282U (en) | A kind of suspender for precast-concrete form overturning and handling | |
CN104692261A (en) | Symmetrical dismounting construction method for attachment device of tower crane | |
CN105780659A (en) | Lifting appliance special for erection of large-tonnage steel box beam segment in non-stayed cable area of cable-stayed bridge | |
CN205442393U (en) | Posture that falls suspension system | |
JP6098453B2 (en) | Jib hanger | |
CN106351125B (en) | A kind of cable wire tower entirety turn-over method | |
CN205296017U (en) | Anticollision barrier template moving as a whole device | |
CN106012861B (en) | The construction method of the mounting and positioning device of Wavelike steel webplate and the Wavelike steel webplate | |
CN204198229U (en) | A kind ofly realize joining the lifting beam device hanging segmentation tread flaking | |
CN108797380B (en) | Suspension construction device and construction method for suspension irrigation continuous beam bracket | |
CN110040632A (en) | A kind of segmental hoisting construction method of large span section steel beam | |
CN203127986U (en) | Adjustable lifting tool for T joist steel formwork of high-speed rail | |
CN204940916U (en) | A kind of Super High Core Walls Structure emergency escape passage |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190719 |
|
RJ01 | Rejection of invention patent application after publication |