CN109372267A - A kind of modularization steel structure frame preassembling construction method - Google Patents

A kind of modularization steel structure frame preassembling construction method Download PDF

Info

Publication number
CN109372267A
CN109372267A CN201811381068.3A CN201811381068A CN109372267A CN 109372267 A CN109372267 A CN 109372267A CN 201811381068 A CN201811381068 A CN 201811381068A CN 109372267 A CN109372267 A CN 109372267A
Authority
CN
China
Prior art keywords
preassembling
frame unit
frame
steel structure
component
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811381068.3A
Other languages
Chinese (zh)
Inventor
刘群杰
张琳
景安闯
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Third Metallurgical Group Co Ltd
Original Assignee
China Third Metallurgical Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Third Metallurgical Group Co Ltd filed Critical China Third Metallurgical Group Co Ltd
Priority to CN201811381068.3A priority Critical patent/CN109372267A/en
Publication of CN109372267A publication Critical patent/CN109372267A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/162Handles to carry construction blocks
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/14Conveying or assembling building elements
    • E04G21/16Tools or apparatus
    • E04G21/18Adjusting tools; Templates
    • E04G21/1841Means for positioning building parts or elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The present invention relates to a kind of modularization steel structure frame preassembling construction methods, comprising: 1) entire steel structure frame is resolved into several frame units;2) preassembling moulding bed is set up in ground on the scene;3) frame unit is carried out on preassembling moulding bed pre-splicing;4) each component is fastenedly connected with connector;5) overall dimensions data outside frame unit are measured;6) measurement data is imported into tekla model and is compared with designing a model;7) frame unit after analysis is qualified on inspection disintegrates to each component, is marked during disintegration to each monomer members, sits in the right seat when being easily installed.The method that the present invention is checked using work factory assemply, computer simulation can be avoided component assembled various drawbacks at the scene, guarantee the installation accuracy of steel structure frame entirety, reduce site operation difficulty, raising installation effectiveness and quality.

Description

A kind of modularization steel structure frame preassembling construction method
Technical field
The present invention relates to steel structure frame technical field of construction more particularly to a kind of modularization steel structure frame preassembling to apply Work method.
Background technique
In recent years, as China's industry is grown rapidly, the widely applied concrete structure frame of the manufacturing enterprises such as petrochemical industry Frame is gradually replaced metal structure frame.The steel structure frame of these large-scale superelevation by conventional bulk during installation if made Industry is no longer satisfied engineering construction demand.To adapt to the requirement efficiently constructed, if steel structure frame would generally be assembled into advance Then dry frame unit is installed.But scene carries out situations such as assembly is if there is component geometric dimension error, Construction speed can seriously be delayed by returning to depot level maintenance, and increase production cost, reduce installation effectiveness.
Summary of the invention
The present invention provides a kind of modularization steel structure frame preassembling construction methods, using work factory assemply, calculate The method that machine simulation is checked can be avoided component assembled various drawbacks at the scene, guarantee that the installation of steel structure frame entirety is smart Degree reduces site operation difficulty, improves installation effectiveness and quality.
In order to achieve the above object, the present invention is implemented with the following technical solutions:
A kind of modularization steel structure frame preassembling construction method, includes the following steps:
1) before carrying out preassembling to steel structure frame, entire steel structure frame is first resolved into several frame units, Each frame unit forms one group of component by column, beam and support, carries out preassembling respectively according to the frame unit of decomposition;
2) one piece of area is selected to be greater than the place of preassembling frame unit area in on-site, preassembling is set up in ground on the scene Moulding bed, preassembling moulding bed chock and steel flat support guarantee that its top surface is smooth and do not sink, and can adjust its top surface level;
3) pre-splicing, the master during pre-splicing is being carried out on preassembling moulding bed according to actual size when installing to frame unit Guarantee straightness, spacing, the depth of parallelism, the diagonal error of column, then carries out the pre-splicing of beam and support, be also easy to produce deformation Position adds interim Auxiliary support;
4) frame unit after pre-splicing meets on inspection after installation dimension requires, and is fastened by connector to each component Connection, guarantees the through-hole rate of bolt;
5) after the preassembling of single frame unit is fully completed, with detecting instrument to overall dimensions data outside frame unit It measures, selects a datum mark to measure every a distance when measurement, and record measurement data;
6) measurement data measured by each datum mark is imported into tekla model, is compared with designing a model, point Whether the every installation dimension for analysing the frame unit of preassembling is exceeded;
7) frame unit after analysis is qualified on inspection disintegrates to each component, to each list during disintegration Body component is marked, and sits in the right seat when being easily installed.
Compared with prior art, the beneficial effects of the present invention are:
The method checked using work factory assemply, computer simulation can be avoided component assembled various disadvantages at the scene End guarantees the installation accuracy of steel structure frame entirety, reduces site operation difficulty, improves installation effectiveness and quality.
Specific embodiment
A kind of modularization steel structure frame preassembling construction method of the present invention, includes the following steps:
1) before carrying out preassembling to steel structure frame, entire steel structure frame is first resolved into several frame units, Each frame unit forms one group of component by column, beam and support, carries out preassembling respectively according to the frame unit of decomposition;
2) one piece of area is selected to be greater than the place of preassembling frame unit area in on-site, preassembling is set up in ground on the scene Moulding bed, preassembling moulding bed chock and steel flat support guarantee that its top surface is smooth and do not sink, and can adjust its top surface level;
3) pre-splicing, the master during pre-splicing is being carried out on preassembling moulding bed according to actual size when installing to frame unit Guarantee straightness, spacing, the depth of parallelism, the diagonal error of column, then carries out the pre-splicing of beam and support, be also easy to produce deformation Position adds interim Auxiliary support;
4) frame unit after pre-splicing meets on inspection after installation dimension requires, and is fastened by connector to each component Connection, guarantees the through-hole rate of bolt;
5) after the preassembling of single frame unit is fully completed, with detecting instrument to overall dimensions data outside frame unit It measures, selects a datum mark to measure every a distance when measurement, and record measurement data;
6) measurement data measured by each datum mark is imported into tekla model, is compared with designing a model, point Whether the every installation dimension for analysing the frame unit of preassembling is exceeded;
7) frame unit after analysis is qualified on inspection disintegrates to each component, to each list during disintegration Body component is marked, and sits in the right seat when being easily installed.
The foregoing is only a preferred embodiment of the present invention, but scope of protection of the present invention is not limited thereto, Anyone skilled in the art in the technical scope disclosed by the present invention, according to the technique and scheme of the present invention and its Inventive concept is subject to equivalent substitution or change, should be covered by the protection scope of the present invention.

Claims (1)

1. a kind of modularization steel structure frame preassembling construction method, which comprises the steps of:
1) before carrying out preassembling to steel structure frame, entire steel structure frame is first resolved into several frame units, each Frame unit forms one group of component by column, beam and support, carries out preassembling respectively according to the frame unit of decomposition;
2) one piece of area is selected to be greater than the place of preassembling frame unit area in on-site, preassembling tire is set up in ground on the scene Frame, preassembling moulding bed chock and steel flat support guarantee that its top surface is smooth and do not sink, and can adjust its top surface level;
3) pre-splicing, the main guarantor during pre-splicing is being carried out on preassembling moulding bed according to actual size when installing to frame unit Straightness, spacing, the depth of parallelism, the diagonal error of column are demonstrate,proved, the pre-splicing of beam and support is then carried out, at the position for being also easy to produce deformation Add interim Auxiliary support;
4) frame unit after pre-splicing meets on inspection after installation dimension requires, and carries out fastening company to each component by connector It connects, guarantees the through-hole rate of bolt;
5) after the preassembling of single frame unit is fully completed, overall dimensions data outside frame unit are carried out with detecting instrument Measurement selects a datum mark to measure when measurement, and records measurement data every a distance;
6) measurement data measured by each datum mark is imported into tekla model, is compared with designing a model, analysis is pre- Whether every installation dimension of assembled frame unit is exceeded;
7) frame unit after analysis is qualified on inspection disintegrates to each component, to each monomer structure during disintegration Part is marked, and sits in the right seat when being easily installed.
CN201811381068.3A 2018-11-20 2018-11-20 A kind of modularization steel structure frame preassembling construction method Pending CN109372267A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811381068.3A CN109372267A (en) 2018-11-20 2018-11-20 A kind of modularization steel structure frame preassembling construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811381068.3A CN109372267A (en) 2018-11-20 2018-11-20 A kind of modularization steel structure frame preassembling construction method

Publications (1)

Publication Number Publication Date
CN109372267A true CN109372267A (en) 2019-02-22

Family

ID=65389586

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811381068.3A Pending CN109372267A (en) 2018-11-20 2018-11-20 A kind of modularization steel structure frame preassembling construction method

Country Status (1)

Country Link
CN (1) CN109372267A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110027987A (en) * 2019-04-30 2019-07-19 中国十七冶集团有限公司 A kind of arc cantilever steel girder construction method for hanging
CN111550059A (en) * 2020-04-30 2020-08-18 中冶(上海)钢结构科技有限公司 Accumulative circulating pre-assembly method for special-shaped steel structure

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110027987A (en) * 2019-04-30 2019-07-19 中国十七冶集团有限公司 A kind of arc cantilever steel girder construction method for hanging
CN111550059A (en) * 2020-04-30 2020-08-18 中冶(上海)钢结构科技有限公司 Accumulative circulating pre-assembly method for special-shaped steel structure

Similar Documents

Publication Publication Date Title
CN109372267A (en) A kind of modularization steel structure frame preassembling construction method
CN103557837B (en) On-line tower inclination monitoring method capable of correcting installation error of sensor
CN103174166A (en) Recreation facility embedded part integrally arranged in complete-set mode and installation method thereof
CN104567670A (en) Mounting and detection method of multi-roll mill
CN210321628U (en) Correction device for detecting deformation of fiber bragg grating
CN206233595U (en) Pump line sliding support
CN108731574B (en) Ship generator set cushion block data measuring device and measuring method thereof
CN106140831B (en) Milling train tilts and the correction locating measurement method of skew
CN210195734U (en) Vertical shaft laser measuring device
CN204672699U (en) The frock of the installation accuracy of the large base of inspection high speed wire rod finishing block
CN201874586U (en) Positioner used for installing tunnel arch center
CN107720543A (en) 45 degree of dissection type leveling wheel group On-line construction methods of bridge crane
CN110287609B (en) Computing system and method for through-flow gap data of all cylinders of million nuclear power unit cylinder
CN103042382A (en) Elimination method for guide rail assembling errors
CN203534503U (en) Dial gauge rack for rotation device transmission shaft coaxiality single gauge alignment method
CN208231636U (en) The means for correcting of vertical machining centre nut seat
CN203452395U (en) Multifunctional angle square
CN203380610U (en) Novel pentahedral Z transverse beam structure of fixed-beam gantry
CN101988823B (en) Method for adjusting installation position error of T-shaped truss
CN206514834U (en) A kind of new exclusive height-gauge
CN109019323A (en) It is a kind of to gnaw the wheel alignment and installation method that rail is corrected for driving a vehicle
CN211621217U (en) Prestressed pipeline positioning tool
CN206590067U (en) A kind of adjustment instrument installed for ship steering engine
CN205373586U (en) Window centering degree measuring tool of vertical finishing mill of hot rolling
CN201828251U (en) Box type part measuring equipment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20190222