Overhung construction method and overhung frame for super-high building Download PDFInfo
- Publication number
- CN115787996A CN115787996A CN202211549424.4A CN202211549424A CN115787996A CN 115787996 A CN115787996 A CN 115787996A CN 202211549424 A CN202211549424 A CN 202211549424A CN 115787996 A CN115787996 A CN 115787996A
- Authority
- CN
- China
- Prior art keywords
- construction
- cantilever
- frame
- building
- triangular truss
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Landscapes
- Conveying And Assembling Of Building Elements In Situ (AREA)
Abstract
Description
技术领域technical field
本发明涉及建筑悬挑施工的技术领域,尤其是涉及一种超高建筑悬挑施工方法及悬挑架。The invention relates to the technical field of building cantilever construction, in particular to a super-high building cantilever construction method and a cantilever frame.
背景技术Background technique
超高层建筑外立面也根据建筑师先进的设计理念,展现出不同的建筑风格,造型新颖奇特,尤其是不同种类的核心筒偏心立面悬挑,极大地丰富了超高层建筑的设计内涵,外立面悬挑结构具备上述优点的同时,给超高层施工建造也带来了难度,在核心筒架体爬升、悬挑结构施工周边防护以及局部反坎施工等方面,均造成了较大影响。The facades of super high-rise buildings also show different architectural styles according to the architect's advanced design concepts, with novel and unique shapes, especially the different types of core tubes with eccentric facade overhangs, which greatly enrich the design connotation of super high-rise buildings. While the cantilevered structure of the facade has the above advantages, it also brings difficulties to the construction of super high-rise buildings. It has a great impact on the climbing of the core tube frame, the surrounding protection of the cantilevered structure construction, and the local anti-sill construction. .
当前施工中,低层悬挑施工可以采用搭设在地面的悬挑结构支撑架进行施工,但是高层建筑的高层施工时,悬挑结构支撑架搭设高度受限,采用吊笼进行施工时,由于吊笼容易晃动,影响施工人员的操作。In the current construction, low-rise cantilevered construction can be carried out with cantilevered structural support frames erected on the ground. However, in the high-rise construction of high-rise buildings, the height of the cantilevered structural support frame is limited. When using a hanging cage for construction, due to the It is easy to shake and affect the operation of construction personnel.
发明内容Contents of the invention
为了解决高空施工时施工平台搭设困难的问题,降低建筑悬挑施工难度,本发明提供一种超高建筑悬挑施工方法及悬挑架。In order to solve the problem of difficulty in setting up a construction platform during high-altitude construction and reduce the difficulty of building cantilevered construction, the invention provides a superhigh building cantilevered construction method and a cantilever frame.
一方面,本发明提供的一种超高建筑悬挑施工方法采用如下的技术方案:On the one hand, a kind of cantilevered construction method of a super high building provided by the present invention adopts the following technical scheme:
一种超高建筑悬挑施工方法,包括以下施工方法:A cantilevered construction method for super high buildings, comprising the following construction methods:
步骤一:通过BIM技术和施工现场实地测量,根据测量结果设计悬挑架各受力杆件型号,并进行仿真预拼装;Step 1: Through BIM technology and on-site measurement at the construction site, design the model of each stressed member of the cantilever frame according to the measurement results, and carry out simulation pre-assembly;
步骤二:按照设计图纸及各构件编号在施工现场安装悬挑架,将悬挑架的主体三角桁架吊装至顶部一侧对齐结构梁顶面,将附着连接件与结构对接安装;Step 2: Install the cantilever frame on the construction site according to the design drawings and the serial numbers of each component, hoist the main triangular truss of the cantilever frame to the top side and align it with the top surface of the structural beam, and connect the attached connector to the structure;
步骤三:根据建筑悬挑高度,在悬挑架上安装施工平台和护栏,并根据悬挑结构支撑架体方案,搭设模板支撑体系,进行悬挑混凝土结构施工;Step 3: According to the building cantilever height, install the construction platform and guardrail on the cantilever frame, and set up the formwork support system according to the cantilever structure support frame plan, and carry out the cantilever concrete structure construction;
步骤四:建筑悬挑结构施工完成且混凝土结构强度达到拆除要求后,拆除悬挑架并吊装至下一层施工位置;Step 4: After the construction of the building cantilever structure is completed and the strength of the concrete structure meets the demolition requirements, the cantilever frame is removed and hoisted to the construction position of the next floor;
步骤五:所述吊装完成后清理施工作业面,填补安装孔洞。Step 5: After the hoisting is completed, the construction work surface is cleaned, and the installation holes are filled.
通过采用上述技术方案,通过安装悬挑架为建筑悬挑施工提供施工操作平台,同时给施工中的建筑悬挑提供临时依托,防止施工中的建筑悬挑因为混凝土未干和安装不合理导致的变形或脱落,悬挑架通过可活动连接件安装在建筑主体上,方便安拆,整体小巧适合多种施工场景的运用,悬挑架整体为拼装结构,吊装或搬运方便。By adopting the above technical scheme, the construction operation platform is provided for the building cantilever construction by installing the cantilever frame, and at the same time, it provides temporary support for the building cantilever under construction, so as to prevent the building cantilever under construction from being damaged due to wet concrete and unreasonable installation. Deformation or falling off, the cantilever frame is installed on the main body of the building through movable connectors, which is convenient for installation and disassembly. The overall compactness is suitable for the use of various construction scenarios.
优选的,步骤一所述悬挑架包括附墙式和附梁式两种类型悬挑支撑操作平台,所述悬挑架为直角三角形桁架。Preferably, the cantilever frame in
通过采用上述技术方案,根据建筑框架的特点,结构梁和建筑立柱是承受力的主要结构,因此需要设置两种安装结构的悬挑架,以适应不同间距大小的建筑立柱。By adopting the above technical scheme, according to the characteristics of the building frame, structural beams and building columns are the main structures to bear the force, so it is necessary to set up cantilever frames with two installation structures to adapt to building columns with different spacing sizes.
优选的,步骤一所述仿真预拼装包括碰撞仿真和受力有限元分析。Preferably, the simulated pre-assembly in
通过采用上述技术方案,通过碰撞仿真分析,设计使悬挑架安装合理,通过受理仿真,检查悬挑架的受力程度,防止安装或使用时出现故障,整体提高对悬挑架的设计效率。By adopting the above-mentioned technical scheme, through collision simulation analysis, the design makes the installation of the suspension frame reasonable, and through accepting the simulation, checks the stress degree of the suspension frame, prevents failures during installation or use, and improves the design efficiency of the suspension frame as a whole.
优选的,步骤二所述预埋连接结构为竖直内嵌螺杆,安装三角桁架与结构柱连接时,通过平台挂座和销轴将悬挑架与结构柱连接固定。Preferably, the pre-embedded connection structure described in
通过采用上述技术方案,预埋连接节点用于连接固定悬挑架,安装牢固程度高,减去植筋的麻烦,减少对建筑主体的破坏。By adopting the above-mentioned technical scheme, the pre-buried connection nodes are used to connect and fix the cantilever frame, which has a high degree of installation firmness, reduces the trouble of planting bars, and reduces damage to the main body of the building.
优选的,步骤二所述悬挑架通过单独型钢加工制作,各型钢构件之间通过销栓连接,并在现场进行拼装。Preferably, the cantilever frame described in
通过采用上述技术方案,悬挑架为拼装结构,方便运输和存放,同时安装方便,方便拆卸和吊运。By adopting the above technical scheme, the suspension frame is an assembled structure, which is convenient for transportation and storage, and at the same time, it is convenient for installation, disassembly and lifting.
优选的,步骤三所述施工平台安装步骤包括:Preferably, the construction platform installation step described in
在悬挑架上利用螺栓安装固定分布梁,所述分布梁与悬挑架底部支撑架相互垂直;Bolts are used to install and fix the distribution beam on the cantilever frame, and the distribution beam and the bottom support frame of the cantilever frame are perpendicular to each other;
在分布梁上利用螺栓安装固定平台板,所述平台板为分块拼接结构,所述平台板安装方向与分布梁相互垂直。Bolts are used to install and fix the platform plate on the distribution beam. The platform plate is a block splicing structure, and the installation direction of the platform plate is perpendicular to the distribution beam.
通过采用上述技术方案,分布梁将悬挑架连接成一个整体,防止悬挑架偏斜,并为平台板提供依托,平台板方便施工人员站立和操作。By adopting the above technical solution, the distribution beam connects the cantilever frame into a whole, prevents the cantilever frame from deflecting, and provides support for the platform board, which is convenient for construction personnel to stand and operate.
优选的,步骤三所述施工平台安装完成后在施工平台上安装悬挑结构支撑架,所述悬挑结构支撑架上捆扎安全绳。Preferably, after the installation of the construction platform described in
通过采用上述技术方案,悬挑结构支撑架上捆扎安全绳有利于保护施工人员的安全防止坠落。By adopting the above technical scheme, the safety rope tied on the cantilever structure support frame is beneficial to protect the safety of construction personnel and prevent falling.
优选的,步骤四所述吊装悬挑架时,通过塔吊和卷扬机共同完成吊装,所述卷扬机设置在待安装楼层。Preferably, when the suspension frame is hoisted in step 4, the hoisting is completed by a tower crane and a hoist, and the hoist is set on the floor to be installed.
通过采用上述技术方案,塔吊用于将悬挑架吊起,卷扬机用于将悬挑架拉至安装位置,方便施工人员将悬挑架安装固定。By adopting the above technical solution, the tower crane is used to hoist the suspension frame, and the winch is used to pull the suspension frame to the installation position, which is convenient for construction personnel to install and fix the suspension frame.
另一方面,本发明提供一种超高建筑悬挑施工用悬挑架采用如下技术方案:On the other hand, the present invention provides a cantilever frame for cantilever construction of a super high building adopting the following technical scheme:
一种超高建筑悬挑施工用悬挑架,其特征在于:包括三角桁架、护栏和悬挑结构支撑架,所述三角桁架的附着连接件通过螺栓安装固定在结构梁的水平面上或结构柱立面上,所述三角桁架远离建筑侧设置有护栏,所述三角桁架上安装有悬挑结构支撑架,所述三角桁架通过工字钢拼接成三角结构,所述三角桁架与悬挑结构支撑架之间设置有平台板,所述平台板通过分布梁安装固定在三角桁架上。A cantilever frame for overhanging construction of a super-high building, characterized in that it includes a triangular truss, a guardrail and a cantilevered structural support frame, and the attached connectors of the triangular truss are installed and fixed on the horizontal plane of a structural beam or a structural column by bolts On the facade, the triangular truss is provided with a guardrail away from the side of the building, and a cantilevered structural support frame is installed on the triangular truss. The triangular truss is spliced into a triangular structure through I-beams. A platform plate is arranged between the frames, and the platform plate is installed and fixed on the triangular truss through distribution beams.
通过采用上述技术方案,三角形的架体有利于整体稳固性,护栏有利于防止施工人员和施工机械掉落,分布梁将悬挑架连接成一个整体,防止悬挑架偏斜,并为平台板提供依托,平台板方便施工人员站立和操作。By adopting the above technical scheme, the triangular frame body is beneficial to the overall stability, the guardrail is beneficial to prevent construction personnel and construction machinery from falling, the distribution beam connects the cantilever frame into a whole, prevents the cantilever frame from deflecting, and provides a platform for the Provide support, and the platform board is convenient for construction personnel to stand and operate.
优选的,所述三角桁架内设置有斜撑杆,所述三角桁架仅顶部与结构梁或结构柱连接固定。Preferably, diagonal braces are arranged inside the triangular truss, and only the top of the triangular truss is connected and fixed with structural beams or structural columns.
通过采用上述技术方案,斜撑杆有利于进一步加强悬挑架的支撑强度。By adopting the above technical solution, the diagonal brace is beneficial to further strengthen the support strength of the cantilever frame.
综上所述,本发明具有如下的有益技术效果:In summary, the present invention has the following beneficial technical effects:
1、通过安装悬挑架为建筑悬挑施工提供施工操作平台,同时给施工中的建筑悬挑提供临时依托,防止施工中的建筑悬挑因为混凝土未干和安装不合理导致的变形或脱落,悬挑架通过可活动连接件安装在建筑主体上,方便安拆,整体小巧适合多种施工场景的运用,悬挑架整体为拼装结构,吊装或搬运方便。1. Provide a construction operation platform for the building cantilever construction by installing the cantilever frame, and at the same time provide a temporary support for the building cantilever under construction to prevent the building cantilever under construction from being deformed or falling off due to wet concrete and unreasonable installation. The cantilever frame is installed on the main body of the building through movable connectors, which is convenient for installation and disassembly. The overall compactness is suitable for the use of various construction scenarios.
2、根据建筑框架的特点,结构梁和建筑立柱是承受力的主要结构,因此需要设置两种安装结构的悬挑架,以适应不同间距大小的建筑立柱,通过碰撞仿真分析,设计使悬挑架安装合理,通过受理仿真,检查悬挑架的受力程度,防止安装或使用时出现故障,整体提高对悬挑架的设计效率。2. According to the characteristics of the building frame, structural beams and building columns are the main structures to bear the force. Therefore, it is necessary to set up cantilever frames of two installation structures to adapt to building columns with different spacing sizes. Through collision simulation analysis, the design makes the cantilever The installation of the suspension frame is reasonable, and the stress degree of the suspension frame is checked by accepting the simulation, so as to prevent failures during installation or use, and improve the design efficiency of the suspension frame as a whole.
3、预埋连接节点用于连接固定悬挑架,安装牢固程度高,减去植筋的麻烦,减少对建筑主体的破坏,悬挑架为拼装结构,方便运输和存放,同时安装方便,方便拆卸和吊运。3. The pre-embedded connection nodes are used to connect and fix the cantilever frame, which has a high degree of firmness, reduces the trouble of planting bars, and reduces damage to the main body of the building. The cantilever frame is an assembled structure, which is convenient for transportation and storage, and is convenient and convenient to install Disassembly and lifting.
4、分布梁将悬挑架连接成一个整体,防止悬挑架偏斜,并为平台板提供依托,平台板方便施工人员站立和操作,悬挑结构支撑架上捆扎安全绳有利于保护施工人员的安全防止坠落,塔吊用于将悬挑架吊起,卷扬机用于将悬挑架拉至安装位置,方便施工人员将悬挑架安装固定。4. The distribution beam connects the cantilever frame into a whole, prevents the cantilever frame from deflecting, and provides a support for the platform plate. The platform plate is convenient for construction personnel to stand and operate, and the safety rope tied on the cantilever structure support frame is beneficial to protect the construction personnel. The safety prevents falling, the tower crane is used to lift the suspension frame, and the hoist is used to pull the suspension frame to the installation position, which is convenient for the construction personnel to install and fix the suspension frame.
5、三角形的架体有利于整体稳固性,护栏有利于防止施工人员和施工机械掉落,分布梁将悬挑架连接成一个整体,防止悬挑架偏斜,并为平台板提供依托,平台板方便施工人员站立和操作,斜撑杆有利于进一步加强悬挑架的支撑强度。5. The triangular frame is conducive to the overall stability, and the guardrail is beneficial to prevent construction personnel and construction machinery from falling. The distribution beam connects the cantilever frame into a whole, prevents the cantilever frame from deflecting, and provides support for the platform board. The platform The board is convenient for construction personnel to stand and operate, and the diagonal brace is conducive to further strengthening the support strength of the cantilever frame.
附图说明Description of drawings
图1为本发明悬挑架安装侧面示意图;Fig. 1 is the installation side schematic diagram of cantilever frame of the present invention;
图2为本发明悬挑架安装立体图。Fig. 2 is an installation perspective view of the suspension frame of the present invention.
附图标记说明:Explanation of reference signs:
10、结构梁,20、结构柱,1、三角桁架,11、分布梁,12、平台板,13、附着连接件,2、护栏,3、悬挑结构支撑架。10. Structural beams, 20. Structural columns, 1. Triangular trusses, 11. Distribution beams, 12. Platform slabs, 13. Attached connectors, 2. Guardrails, 3. Cantilevered structural support frames.
具体实施方式Detailed ways
以下结合附图1和2对本发明作进一步详细说明。Below in conjunction with accompanying drawing 1 and 2 the present invention is described in further detail.
实施例1:Example 1:
本发明实施例公开一种超高建筑悬挑施工方法,包括以下施工方法:The embodiment of the present invention discloses a cantilevered construction method for super high buildings, including the following construction methods:
步骤一:通过BIM技术和施工现场实地测量,根据测量结果设计悬挑架各受力杆件型号,并进行仿真预拼装;Step 1: Through BIM technology and on-site measurement at the construction site, design the model of each stressed member of the cantilever frame according to the measurement results, and carry out simulation pre-assembly;
步骤二:按照设计图纸及各构件编号在施工现场安装悬挑架,将悬挑架的主体三角桁架1吊装至顶部一侧对齐结构梁10顶面,将附着连接件13与结构对接安装;Step 2: Install the cantilever frame on the construction site according to the design drawings and the serial numbers of each component, hoist the main
步骤三:根据建筑悬挑高度,在悬挑架上安装施工平台和护栏2,并根据悬挑结构支撑架体方案,搭设模板支撑体系,进行悬挑混凝土结构施工;Step 3: Install the construction platform and
步骤四:建筑悬挑结构施工完成且混凝土结构强度达到拆除要求后,拆除悬挑架并吊装至下一层施工位置;Step 4: After the construction of the building cantilever structure is completed and the strength of the concrete structure meets the demolition requirements, the cantilever frame is removed and hoisted to the construction position of the next floor;
步骤五:所述吊装完成后清理施工作业面,填补安装孔洞。Step 5: After the hoisting is completed, the construction work surface is cleaned, and the installation holes are filled.
实施例2:Example 2:
在实施例1的基础上增加:Increase on the basis of embodiment 1:
步骤一所述悬挑架包括附墙式和附梁式两种类型悬挑支撑操作平台,所述悬挑架为直角三角形桁架。The cantilever frame in
步骤一所述仿真预拼装包括碰撞仿真和受力有限元分析。The simulation pre-assembly in
步骤二所述预埋连接结构为竖直内嵌螺杆,安装三角桁架1与结构柱20连接时,通过平台挂座和销轴将悬挑架与结构柱20连接固定。The pre-embedded connection structure described in
步骤二所述悬挑架通过单独型钢加工制作,各型钢构件之间通过销栓连接,并在现场进行拼装。The cantilever frame described in
步骤三所述施工平台安装步骤包括:The construction platform installation steps described in step three include:
在悬挑架上利用螺栓安装固定分布梁11,所述分布梁11与悬挑架底部支撑架相互垂直;Utilize bolts to install and fix the
在分布梁11上利用螺栓安装固定平台板12,所述平台板12为分块拼接结构,所述平台板12安装方向与分布梁11相互垂直。Bolts are used to install and fix the
步骤三所述施工平台安装完成后在施工平台上安装悬挑结构支撑架3,所述悬挑结构支撑架3上捆扎安全绳。After the installation of the construction platform described in
步骤四所述吊装悬挑架时,通过塔吊和卷扬机共同完成吊装,所述卷扬机设置在待安装楼层。When hoisting the suspension frame described in step 4, the hoisting is completed jointly by the tower crane and the hoist, and the hoist is set on the floor to be installed.
实施例3:Example 3:
本发明实施例公开一种超高建筑悬挑施工用悬挑架,包括三角桁架1、护栏2和悬挑结构支撑架3,所述三角桁架1的附着连接件13通过螺栓安装固定在结构梁10的水平面上或结构柱20立面上,所述三角桁架1远离建筑侧设置有护栏2,所述三角桁架1上安装有悬挑结构支撑架3,所述三角桁架1通过工字钢拼接成三角结构,所述三角桁架1与悬挑结构支撑架3之间设置有平台板12,所述平台板12通过分布梁11安装固定在三角桁架1上。The embodiment of the present invention discloses a cantilever frame for cantilevered construction of a super high building, including a
所述三角桁架1内设置有斜撑杆,所述三角桁架1仅顶部与结构梁10或结构柱20连接固定。Diagonal braces are arranged inside the
实施例3的实施方式为:The implementation mode of
安装时,先安装固定在结构梁10上的三角桁架1,然后再安装固定在结构柱20上的三角桁架1,然后将分布梁11和平台板12安装在三角桁架1上,在分布梁11和平台板12上安装护栏2和悬挑结构支撑架3。During installation, first install the
以上均为本发明的较佳实施例,并非依此限制本发明的保护范围,故:凡依本发明的结构、形状、原理所做的等效变化,均应涵盖于本发明的保护范围之内。The above are all preferred embodiments of the present invention, and are not intended to limit the protection scope of the present invention, so: all equivalent changes made according to the structure, shape and principle of the present invention should be covered by the protection scope of the present invention Inside.
Claims (10)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211549424.4A CN115787996A (en) | 2022-12-05 | 2022-12-05 | Overhung construction method and overhung frame for super-high building |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN202211549424.4A CN115787996A (en) | 2022-12-05 | 2022-12-05 | Overhung construction method and overhung frame for super-high building |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN115787996A true CN115787996A (en) | 2023-03-14 |
Family
ID=85445666
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN202211549424.4A Pending CN115787996A (en) | 2022-12-05 | 2022-12-05 | Overhung construction method and overhung frame for super-high building |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN115787996A (en) |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116220383A (en) * | 2023-03-15 | 2023-06-06 | 中建八局装饰工程有限公司 | Pipeline construction method for truss structure building |
| CN116607740A (en) * | 2023-05-26 | 2023-08-18 | 中国建筑第四工程局有限公司 | Construction method and device combining high-altitude protection operation platform with flower stand construction |
| CN116749354A (en) * | 2023-06-25 | 2023-09-15 | 中建八局第二建设有限公司 | A construction method for wire saw guided cutting of out-of-plane concrete components |
Citations (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US20050071936A1 (en) * | 2003-10-07 | 2005-04-07 | Jackson George W. | Bridge overhang bracket |
| CN103821334A (en) * | 2014-02-27 | 2014-05-28 | 中天建设集团有限公司 | Overhung scaffold with detachable triangular supports |
| RU167685U1 (en) * | 2016-04-12 | 2017-01-10 | Иван Владимирович Серебренников | Cornice scaffolding |
| CN106337555A (en) * | 2016-09-26 | 2017-01-18 | 山东金城建设有限公司 | Method for constructing triangular steel support for cantilever structure of outer wall of building |
| CN109441127A (en) * | 2018-12-05 | 2019-03-08 | 中铁二局第三工程有限公司 | A kind of virtual emulation in-site installation construction method across overhanging steel structure greatly |
| CN110027987A (en) * | 2019-04-30 | 2019-07-19 | 中国十七冶集团有限公司 | A kind of arc cantilever steel girder construction method for hanging |
| CN110388000A (en) * | 2019-07-31 | 2019-10-29 | 杭州悦为科技有限公司 | The cast-in-place overhanging beam construction method of multilayer fashioned iron-drag-line dimensional support super-span |
| CN112252698A (en) * | 2020-10-14 | 2021-01-22 | 中国建筑第四工程局有限公司 | A super high-rise large cantilever steel truss construction platform |
| CN214062435U (en) * | 2020-11-26 | 2021-08-27 | 北京城建北方集团有限公司 | Support system for high-altitude ultra-long cantilever structure |
| CN217028088U (en) * | 2022-03-29 | 2022-07-22 | 中建一局集团第三建筑有限公司 | Cantilever tripod template support |
-
2022
- 2022-12-05 CN CN202211549424.4A patent/CN115787996A/en active Pending
Patent Citations (10)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| US20050071936A1 (en) * | 2003-10-07 | 2005-04-07 | Jackson George W. | Bridge overhang bracket |
| CN103821334A (en) * | 2014-02-27 | 2014-05-28 | 中天建设集团有限公司 | Overhung scaffold with detachable triangular supports |
| RU167685U1 (en) * | 2016-04-12 | 2017-01-10 | Иван Владимирович Серебренников | Cornice scaffolding |
| CN106337555A (en) * | 2016-09-26 | 2017-01-18 | 山东金城建设有限公司 | Method for constructing triangular steel support for cantilever structure of outer wall of building |
| CN109441127A (en) * | 2018-12-05 | 2019-03-08 | 中铁二局第三工程有限公司 | A kind of virtual emulation in-site installation construction method across overhanging steel structure greatly |
| CN110027987A (en) * | 2019-04-30 | 2019-07-19 | 中国十七冶集团有限公司 | A kind of arc cantilever steel girder construction method for hanging |
| CN110388000A (en) * | 2019-07-31 | 2019-10-29 | 杭州悦为科技有限公司 | The cast-in-place overhanging beam construction method of multilayer fashioned iron-drag-line dimensional support super-span |
| CN112252698A (en) * | 2020-10-14 | 2021-01-22 | 中国建筑第四工程局有限公司 | A super high-rise large cantilever steel truss construction platform |
| CN214062435U (en) * | 2020-11-26 | 2021-08-27 | 北京城建北方集团有限公司 | Support system for high-altitude ultra-long cantilever structure |
| CN217028088U (en) * | 2022-03-29 | 2022-07-22 | 中建一局集团第三建筑有限公司 | Cantilever tripod template support |
Cited By (3)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN116220383A (en) * | 2023-03-15 | 2023-06-06 | 中建八局装饰工程有限公司 | Pipeline construction method for truss structure building |
| CN116607740A (en) * | 2023-05-26 | 2023-08-18 | 中国建筑第四工程局有限公司 | Construction method and device combining high-altitude protection operation platform with flower stand construction |
| CN116749354A (en) * | 2023-06-25 | 2023-09-15 | 中建八局第二建设有限公司 | A construction method for wire saw guided cutting of out-of-plane concrete components |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN112854745A (en) | Construction process of assembled building aluminum alloy template | |
| CN113401815B (en) | High-altitude conversion system of core tube tower crane of super high-rise building and construction method thereof | |
| CN205558304U (en) | Hoist and mount system of large -scale steel gallery truss | |
| CN111980165A (en) | Large-span net rack external-expanding splicing integral jacking construction method | |
| CN105442839A (en) | Erecting method of cantilever structure formwork bent | |
| CN209780193U (en) | Suspension type scaffold | |
| CN115288449B (en) | Middle support installation construction method for large-span net rack | |
| CN205558306U (en) | Big profiled steel structure vestibule hoist and mount hoisting frame | |
| CN117661865A (en) | Prefabricated building construction integrated platform and its operating methods | |
| CN115749255A (en) | Core tube creeping formwork and horizontal structure aluminum formwork combination system and construction method thereof | |
| CN110318344B (en) | Novel steel box girder No. 0 block support and No. 0 block erection construction method | |
| CN116005960A (en) | Cantilever structure piecewise hoisting and air embedding combined construction method | |
| CN118958482A (en) | A method for positioning a large-span rigid entrance porch and arch columns | |
| CN213836318U (en) | Bridge floor wet joint hangs mould structure | |
| CN111764623B (en) | Hanging construction platform module and construction method of high altitude large cantilever steel roof frame | |
| CN100365237C (en) | A self-elevating deformable and detachable overall lifting steel platform system and construction method | |
| CN106121040A (en) | Lattice column welding device and welding method | |
| CN109653517B (en) | Multidirectional unloading system and construction method for assembling steel corridor by using same | |
| CN115538678A (en) | Construction method for large-angle overhanging landscape platform side small platform | |
| CN119083577B (en) | Truss layer of super high-rise reinforced concrete structure and construction method | |
| CN112267692B (en) | A kind of prefabricated building component hoisting comprehensive equipment and its construction method | |
| CN109989590B (en) | Auxiliary fixing device for mounting roof overlong steel beam and hoisting method of steel beam | |
| CN117418623B (en) | A cantilevered floor end suspension structure and its construction method | |
| CN116122579B (en) | Hoisting method for bidirectional bending dome bracket | |
| CN218714838U (en) | Self-lifting heavy-load construction platform |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20230314 |