CN110014521A - Bar planting assistor and its construction method at the top of secondary structure constructional column - Google Patents

Bar planting assistor and its construction method at the top of secondary structure constructional column Download PDF

Info

Publication number
CN110014521A
CN110014521A CN201910395312.XA CN201910395312A CN110014521A CN 110014521 A CN110014521 A CN 110014521A CN 201910395312 A CN201910395312 A CN 201910395312A CN 110014521 A CN110014521 A CN 110014521A
Authority
CN
China
Prior art keywords
extension bar
bar
electric drill
handrail
operating stick
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910395312.XA
Other languages
Chinese (zh)
Inventor
王奇
布图格其
范士佳
王欣
李德子
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China 22MCC Group Corp Ltd
Original Assignee
China 22MCC Group Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China 22MCC Group Corp Ltd filed Critical China 22MCC Group Corp Ltd
Priority to CN201910395312.XA priority Critical patent/CN110014521A/en
Publication of CN110014521A publication Critical patent/CN110014521A/en
Pending legal-status Critical Current

Links

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28DWORKING STONE OR STONE-LIKE MATERIALS
    • B28D1/00Working stone or stone-like materials, e.g. brick, concrete or glass, not provided for elsewhere; Machines, devices, tools therefor
    • B28D1/14Working stone or stone-like materials, e.g. brick, concrete or glass, not provided for elsewhere; Machines, devices, tools therefor by boring or drilling
    • BPERFORMING OPERATIONS; TRANSPORTING
    • B28WORKING CEMENT, CLAY, OR STONE
    • B28DWORKING STONE OR STONE-LIKE MATERIALS
    • B28D7/00Accessories specially adapted for use with machines or devices of the preceding groups

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • Steps, Ramps, And Handrails (AREA)

Abstract

The present invention provides a kind of secondary structure constructional column top bar planting assistor, and including vertical front end extension bar and handrail, front end extension bar lower part is connected by connecting rod with operating stick with handrail top;Connecting rod and operating stick are arranged in parallel, and front end extension bar, handrail, connecting rod and operating stick are connected in parallelogram frame body by bolt pin;It is equipped with the U-shaped folder for fixing electric drill at the top of the extension bar of front end and is used for support electric drill baffle;The present invention also provides the construction methods of bar planting assistor at the top of above-mentioned secondary structure constructional column, and front end extension bar, handrail, connecting rod, operating stick are bolted;Electric drill is fixed at the top of the extension bar of front end by U-shaped folder, electric drill baffle support is in electric drill bottom;Shake operation bar increases front end extension bar, until assistant structure is simple on electric drill top to bar planting point, easy for installation, bar planting construction, effective protection safety of workers is can be completed in work on the ground.

Description

Bar planting assistor and its construction method at the top of secondary structure constructional column
Technical field
The invention belongs to wall top portion structure construction technology field is filled in architectural engineering, and in particular to secondary structure constructional column Top bar planting assistor and its construction method.
Background technique
In present structure type, frame structure is more and more, after the completion of concrete structure construction, the secondary structure that is related to Filled wall builds more and more.Building wall relates to more constructional column, report frame column binding, needs being related to before binding Bar planting is learned, chemically-planted steel bar construction needs the first aperture on ground or top plate.
Due to higher away from ground at the top of constructional column, worker wants the construction on top plate and needs setting operation platform knot below Structure, more at present is using traveling centering.But traveling centering lease expenses is higher, and uses scaffold aperture Two worker's coordinative constructions (people operates on scaffold, and a people is in ground moving scaffold) are needed when operation, worker is upper and lower Scaffold is inconvenient, and working efficiency is low.Especially aperture construction is carried out using traveling centering facing side or the high higher position of layer When, foot hand does not have enough protection to worker, and risk possibly even endangers worker's life security.
Summary of the invention
The technical problem to be solved by the present invention is to bar planting mounting hole is carried out at the top of secondary structure constructional column using scaffold Punching, working efficiency is low, time-consuming and laborious, and has the problem of biggish security risk.
The present invention provides a kind of secondary structure constructional column top plant that can be used on the ground to solve above-mentioned technical problem Muscle assistor, and using the construction method of the assistor, concrete scheme is as follows:
A kind of secondary structure constructional column top bar planting assistor also connects including vertical front end extension bar and handrail Extension bar and operating stick;Front end extension bar lower part is connected by connecting rod with operating stick with handrail top;Connecting rod one end is with before Extension bar is held to pass through bolt pin joint by bolt pin joint, the other end and handrail top;Operating stick one end passes through bolt and front end Extension bar bottom end pin joint, operating stick centre pass through bolt and handrail pin joint;Connecting rod and operating stick are arranged in parallel;The front end It is equipped with the U-shaped folder for fixing electric drill at the top of extension bar and is used for support electric drill baffle;It is stretched in the middle part of the extension bar of front end equipped with length Shrinking structure;Handrail bottom is equipped with pedestal.
The operation pole length 800mm to 1500mm.
Bolt is 20*60 bolt, and bolt two is equipped with gasket.
This structure replaces movable Scaffold to participate in bar planting construction at the top of constructional column, simple and light, instead of worker's arm Electric drill is lifted to constructional column ceiling height and is exerted oneself to electric drill.Height adjustment range is big, adapts to the high space of a variety of layers.
The construction method of bar planting assistor at the top of above-mentioned secondary structure constructional column: front end extension bar, handrail, connecting rod, Operating stick is bolted, and is configured to the parallelogram frame body of deformation;Electric drill is fixed on front end by U-shaped folder to lengthen At the top of bar, electric drill baffle support is in electric drill bottom;Front end extension bar and handrail is vertical, and pedestal is put it on the ground, and front end adds Stock and pedestal adjust highly according to constructional column top position;Shake operation bar, make front end extension bar increase, until electric drill top to plant On muscle point.
One can be operated the method, and assistor freely adjusts upright bar length, and work efficiency is high for height-regulating, and operator station exists It on ground, does not need to ascend a height, compares safety facing the construction of side position yet.
Detailed description of the invention
Fig. 1 this assistant structure figure;
Fig. 2 this assistor usage state diagram;
This assistor of Fig. 3 receipts disturb state diagram.
In figure: front end extension bar 1, telescopic structure 11, handrail 2, connecting rod 3, operating stick 4, pedestal 5, U-shaped folder 6, Electric drill baffle 7, electric drill 8.
Specific embodiment
As shown in Figure 1, bar planting assistor at the top of secondary structure constructional column provided by the invention, lengthens including vertical front end Bar 1 and handrail 2, there are also connecting rod 3 and operating stick 4,1 lower part of front end extension bar and 2 top of handrail pass through 3 He of connecting rod Operating stick 4 connects;By bolt pin joint, the other end passes through bolt with 2 top of handrail for 3 one end of connecting rod and front end extension bar 1 Pin joint;4 one end of operating stick passes through bolt and 2 pin joint of handrail by bolt and 1 bottom end pin joint of front end extension bar, centre;Connection Bar 3 and operating stick 4 are arranged in parallel;The U-shaped folder 6 and electric drill baffle 7 for fixing electric drill are equipped at the top of the front end extension bar 1; Telescopic structure 11 is equipped in the middle part of front end extension bar 1;2 bottom of handrail is equipped with pedestal 5.
Flitch production can be used in this assistor front end extension bar 1, handrail 2, connecting rod 3, operating stick 4, and front end lengthens Length-adjustable structure is designed in the middle part of bar 1.Flitch uses very universal, materials convenience at the construction field (site).
Operating stick 4 suggests that length is 800mm-1500mm, and the longer lever the more laborsaving.
Four kinds of structural poles form parallel four sides row structure by bolt, and pin joint point connecting portion bolt uses 20*60 bolt, Guarantee consolidating when the quadrilateral structure deformation of assistor.Assistor deformation is controlled by shake operation bar, and amplitude of deformation is very big, The minimum state temporarily collapsed when not used in assistor is shown referring specifically to Fig. 2 and Fig. 3, Fig. 3, but simultaneously non-leading end in Fig. 2 The maximum state of extension bar height.
Bolt two sides Upper gasket prevents from wearing, can also brush used oil here.
Assistor top is using the fixed drilling machine of U-shaped folder.
In conjunction with Fig. 2, using bar planting assistor progress construction method at the top of above-mentioned secondary structure constructional column: front end extension bar 1, Handrail 2, connecting rod 3, operating stick 4 are bolted, and constitute deformable parallelogram frame body;Electric drill 8 is passed through into U Type folder 6 is fixed on 1 top of front end extension bar, and 7 support of electric drill baffle is in 8 bottom of electric drill;Front end extension bar 1 and handrail 2 are erected Directly, pedestal 5 is put it on the ground, and front end extension bar 1 and pedestal 5 adjust highly according to constructional column top position;Shake operation bar 4, Increase front end extension bar 1, until on the top to bar planting point of electric drill 8.
The effect of movable Scaffold when the present invention replaces existing bar planting to construct, extends worker's arm by way of the arm of force Firmly, bar planting can be completed in worker station on the ground, avoids and is ascended a height the danger that can generate of construction by scaffold.

Claims (4)

1. bar planting assistor at the top of a kind of secondary structure constructional column, it is characterized in that: including vertical front end extension bar and handrail, There are also connecting rods and operating stick;Front end extension bar lower part is connected by connecting rod with operating stick with handrail top;Connecting rod one End passes through bolt pin joint by bolt pin joint, the other end and handrail top with front end extension bar;Operating stick one end passes through bolt With front end extension bar bottom end pin joint, operating stick centre passes through bolt and handrail pin joint;Connecting rod and operating stick are arranged in parallel;Institute It states and is equipped at the top of the extension bar of front end for fixing the U-shaped folder of electric drill and for the electric drill baffle of support electric drill;In the extension bar of front end Portion is equipped with telescopic structure;Handrail bottom is equipped with pedestal.
2. bar planting assistor at the top of secondary structure constructional column as described in claim 1, it is characterized in that: the operation pole length 800mm to 1500mm.
3. bar planting assistor at the top of secondary structure constructional column as described in claim 1, it is characterized in that: bolt is 20*60 bolt, spiral shell Bolt two sides are equipped with gasket.
4. the construction method of secondary structure constructional column top bar planting assistor as described in any one of claim 1-3: front end adds Stock, handrail, connecting rod, operating stick are bolted, and are configured to the parallelogram frame body of deformation;By electric drill U Type folder is fixed at the top of the extension bar of front end, and electric drill baffle support is in electric drill bottom;Vertical, the pedestal by front end extension bar and handrail It puts it on the ground, front end extension bar and pedestal adjust highly according to constructional column top position;Shake operation bar makes front end extension bar It increases, until on electric drill top to bar planting point.
CN201910395312.XA 2019-05-13 2019-05-13 Bar planting assistor and its construction method at the top of secondary structure constructional column Pending CN110014521A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910395312.XA CN110014521A (en) 2019-05-13 2019-05-13 Bar planting assistor and its construction method at the top of secondary structure constructional column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910395312.XA CN110014521A (en) 2019-05-13 2019-05-13 Bar planting assistor and its construction method at the top of secondary structure constructional column

Publications (1)

Publication Number Publication Date
CN110014521A true CN110014521A (en) 2019-07-16

Family

ID=67193590

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910395312.XA Pending CN110014521A (en) 2019-05-13 2019-05-13 Bar planting assistor and its construction method at the top of secondary structure constructional column

Country Status (1)

Country Link
CN (1) CN110014521A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110541575A (en) * 2019-09-09 2019-12-06 五冶集团上海有限公司 Movable wall skin shoveling machine

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204430348U (en) * 2014-12-19 2015-07-01 中国建筑第八工程局有限公司 A kind of bar planting boring lever parallelogram mechanical arm
CN205189423U (en) * 2015-10-13 2016-04-27 中国建筑第二工程局有限公司 Bar planting auxiliary device
CN105645749A (en) * 2014-12-01 2016-06-08 肖特股份有限公司 Method and device of carving thin glass and carved thin glass
CN106695356A (en) * 2017-01-25 2017-05-24 湖南省第五工程有限公司 Top plate drilling device and application method thereof
CN206769800U (en) * 2017-05-24 2017-12-19 中建四局第五建筑工程有限公司 A kind of assembly type drilling equipment
CN206854702U (en) * 2017-05-31 2018-01-09 北京城建六建设集团有限公司 A kind of construction drilling device for bonded rebar
CN107999829A (en) * 2017-10-23 2018-05-08 中国十七冶集团有限公司 Bar planting drilling aid at the top of a kind of building secondary structure constructional column
CN210500860U (en) * 2019-05-13 2020-05-12 中国二十二冶集团有限公司 Secondary structure constructional column top bar planting assistor

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105645749A (en) * 2014-12-01 2016-06-08 肖特股份有限公司 Method and device of carving thin glass and carved thin glass
CN204430348U (en) * 2014-12-19 2015-07-01 中国建筑第八工程局有限公司 A kind of bar planting boring lever parallelogram mechanical arm
CN205189423U (en) * 2015-10-13 2016-04-27 中国建筑第二工程局有限公司 Bar planting auxiliary device
CN106695356A (en) * 2017-01-25 2017-05-24 湖南省第五工程有限公司 Top plate drilling device and application method thereof
CN206769800U (en) * 2017-05-24 2017-12-19 中建四局第五建筑工程有限公司 A kind of assembly type drilling equipment
CN206854702U (en) * 2017-05-31 2018-01-09 北京城建六建设集团有限公司 A kind of construction drilling device for bonded rebar
CN107999829A (en) * 2017-10-23 2018-05-08 中国十七冶集团有限公司 Bar planting drilling aid at the top of a kind of building secondary structure constructional column
CN210500860U (en) * 2019-05-13 2020-05-12 中国二十二冶集团有限公司 Secondary structure constructional column top bar planting assistor

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110541575A (en) * 2019-09-09 2019-12-06 五冶集团上海有限公司 Movable wall skin shoveling machine

Similar Documents

Publication Publication Date Title
CN102383588B (en) Lifting platform for protecting safety of high-level construction
CN201158933Y (en) High-rise maintaining scaffold device with extruding structure
CN107999829A (en) Bar planting drilling aid at the top of a kind of building secondary structure constructional column
CN107882317B (en) A kind of nacelle device for external wall high altitude operation
CN209244217U (en) A kind of height-adjustable building construction scaffold
CN110014521A (en) Bar planting assistor and its construction method at the top of secondary structure constructional column
CN213626572U (en) Tool type external cantilever operation platform
CN219241819U (en) Punching device for rectangular anti-slide piles
CN108331335A (en) A kind of pre-splicing separation type hydraulic of steel and wood composite is from climbing support
CN210500860U (en) Secondary structure constructional column top bar planting assistor
CN214942600U (en) Laborsaving advancing device suitable for installation of large-scale round pin axle of steel construction engineering
CN212802413U (en) Combined multifunctional scaffold for building construction
CN212406019U (en) Adjustable regularization safety operation platform construction equipment
CN212406038U (en) Lower hanging construction platform module of high-altitude large-cantilever steel roof truss
CN210459915U (en) Combined operation platform
CN209040527U (en) A kind of scaffold cradle structure
CN211114732U (en) Portable movable reinforcement operation platform
CN209874434U (en) Simple and easy scaffold frame of encorbelmenting of building high latitude
JPH11166315A (en) Structure dismantling device
CN219653539U (en) Support frame is used in construction of multi-functional bridge of convenient regulation
CN220909052U (en) High-strength steel structure supporting frame
CN214605199U (en) Auxiliary device for punching high beam plate
CN220549926U (en) Auxiliary hoisting installation device for railway T-beam top beam moving jack
CN216380480U (en) Integral movable operation frame
CN211622697U (en) Anti-falling device for building construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination