CN110004886A - Asphaltic concrete core wall basement construction method and its structure - Google Patents

Asphaltic concrete core wall basement construction method and its structure Download PDF

Info

Publication number
CN110004886A
CN110004886A CN201910400694.0A CN201910400694A CN110004886A CN 110004886 A CN110004886 A CN 110004886A CN 201910400694 A CN201910400694 A CN 201910400694A CN 110004886 A CN110004886 A CN 110004886A
Authority
CN
China
Prior art keywords
concrete
concrete block
block
construction
asphaltic
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910400694.0A
Other languages
Chinese (zh)
Inventor
胡娟
刘昊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Zhongnan Engineering Corp Ltd
Original Assignee
PowerChina Zhongnan Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Zhongnan Engineering Corp Ltd filed Critical PowerChina Zhongnan Engineering Corp Ltd
Priority to CN201910400694.0A priority Critical patent/CN110004886A/en
Publication of CN110004886A publication Critical patent/CN110004886A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B3/00Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
    • E02B3/16Sealings or joints
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02BHYDRAULIC ENGINEERING
    • E02B7/00Barrages or weirs; Layout, construction, methods of, or devices for, making same
    • E02B7/02Fixed barrages
    • E02B7/04Dams across valleys
    • E02B7/08Wall dams

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Ocean & Marine Engineering (AREA)
  • Revetment (AREA)

Abstract

A kind of asphaltic concrete core wall basement construction method and structure, comprising: which pedestal concrete block is planned to multiple first concrete blocks and multiple second concrete blocks by the length direction along pedestal, one second concrete block is embedded between adjacent first concrete block, and first the section configuration of concrete block be trapezoid, the section configuration of the second concrete block is inverted trapezoidal;The pouring construction of all first concrete blocks is carried out along base length direction, and is reserved the second concrete block between adjacent first concrete block and poured sky;After all first concrete block constructions, interval at least 28 days, the first concrete block contact surface dabbing at interim seam of constructing will be located at, remove loose matter, and after rinsing well, cement mortar is smeared, then is embedded BW water expandable waterstop, the pouring construction for finally carrying out the second concrete block makes the first and second concrete block form an entirety.Core-wall base construction of the present invention is complete continuous entirety, and anti-seepage effect is more preferable, and is easy to construct.

Description

Asphaltic concrete core wall basement construction method and its structure
Technical field
The present invention relates to the asphaltic concrete core wall in hydraulic and hydroelectric engineering, especially a kind of asphaltic concrete core wall pedestal Construction method and its structure.
Background technique
In hydraulic and hydroelectric engineering, asphalt concrete core dam is a kind of common water retaining structure.Concrete pedestal can Using the lid weight as grouting, the structure of antiseepage can also be used as, be a part indispensable in asphaltic concrete core wall.
Concrete pedestal is applied as mass concrete when constructing to prevent the generation of thermal cracking that can be divided into several pieces Work does parting processing, then clogs sealing between these point of good concret block, prevent the leakage of water between seam, such Way makes to form permanent seam between concret block, thus the position that parting sealing is arranged is often weak link, is easy by water Body destroys, and carries out filling sealing in permanent seam, and working procedure is complicated, and water-stagnating effect is unstable, is more easily damaged.
Summary of the invention
The technical problem to be solved by the present invention is to overcome the shortage of prior art, provide one kind and be easy to construct, and formed Whole continuous whole asphaltic concrete core wall basement construction method and its structure.
In order to solve the above technical problems, the present invention provides a kind of asphaltic concrete core wall basement construction methods comprising The following steps:
1) pedestal concrete block is planned to multiple first concrete blocks and multiple second concrete blocks along the length direction of pedestal, It is embedded one second concrete block between adjacent first concrete block, and the section configuration of the first concrete block is trapezoid, second The section configuration of concrete block is inverted trapezoidal;
2) pouring construction of all first concrete blocks is carried out along base length direction, and is stayed between adjacent first concrete block The second concrete block pours sky out;
3) it after all first concrete block constructions, is spaced at least 28 days, the first concrete at interim seam of constructing will be located at Block contact surface dabbing removes loose matter, and after rinsing well, smears cement mortar, then be embedded BW water expandable waterstop, most laggard The pouring construction of the second concrete block of row makes the first and second concrete block form an entirety.
Further, the length of first concrete block is determined according to construction speed and construction intensity, generally 20 ~ 25m, the length of second concrete block are 1 ~ 1.5m.
Further, the lower base angle of first concrete block is 60 ° ~ 75 °.
Further, the position temporarily stitched of constructing should be set on the base by smaller and convenient for construction the position of shearing.
In order to solve the above technical problems, the present invention also provides a kind of asphaltic concrete core wall base constructions comprising more It is a to be arranged along base length direction and pour integral the first concrete block and the second concrete block, adjacent first concrete block Between be embedded one second concrete block, and the section configuration of the first concrete block is trapezoid, the section shape of the second concrete block Shape is inverted trapezoidal, the construction between the first concrete block and the second concrete block temporarily stitch in be embedded BW water expandable waterstop.
Compared with the prior art, the advantages of the present invention are as follows:
1, the present invention is between the first and second concrete block by being arranged the interim seam of construction, and by the contact surface of the first concrete block Dabbing removes loose matter, and after rinsing well, smears cement mortar, then be embedded BW water expandable waterstop, finally just carry out second The pouring construction of concrete block makes the first and second concrete block form one complete continuous whole, and then makes anti-seepage effect more It is good.
2, construction technology of the present invention is simple, is easy to construct.
Detailed description of the invention
Fig. 1 is sectional view of the asphaltic concrete core wall base construction of the present invention along base axis direction.
Fig. 2 is enlarged drawing at the A of Fig. 1.
In figure: 1-core-wall;2-pedestals;The first concrete block of 3--;The second concrete block of 4--;5-contact surfaces.
Specific embodiment
Below in conjunction with specific preferred embodiment, the invention will be further described, but not thereby limiting the invention Protection scope.
For ease of description, the relative positional relationship of each component, such as: the description of upper and lower, left and right is according to explanation Restriction effect is not played to the structure of this patent come what is be described in the Butut direction of book attached drawing.
Embodiment 1:
As shown in Figure 1 and Figure 2, one embodiment of asphaltic concrete core wall basement construction method of the present invention includes the following steps:
1) pedestal concrete block is planned to multiple first concrete blocks 3 and multiple second concrete along the length direction of pedestal 2 Block 4, is embedded one second concrete block 4 between adjacent first concrete block 3, and the section configuration of the first concrete block 3 is positive ladder Shape, the section configuration of the second concrete block 4 are inverted trapezoidal, the position that the construction of 3 two sides of the first concrete block is temporarily stitched be located at by Shear smaller and convenient for construction position;
2) pouring construction of all first concrete blocks 3 is carried out along the length direction of pedestal 2, and in adjacent first concrete block 3 Between reserve the second concrete block casting space;
3) it after all first concrete block, 3 pouring constructions, is spaced at least 28 days, be located at interim seam of constructing first is mixed Solidifying 5 dabbing of soil block contact surface removes loose matter, and after rinsing well, smears cement mortar, then in the first concrete block contact surface 5 It is embedded BW water expandable waterstop, finally carries out the pouring construction of the second concrete block 4, makes the formation of the first and second concrete block 3,4 One entirety.
Wherein, the length of the first concrete block 3 is determined according to construction speed and construction intensity, generally uses 20 ~ 25m, Lower base angle θ=60 ° ~ 75 ° of first concrete block 3;Length L=1 ~ 1.5m of second concrete block 4.
The above is only the preferred embodiment of the application, not does any type of limitation to the application, although this Shen Please disclosed as above with preferred embodiment, however not to limit the application, any person skilled in the art is not taking off In the range of technical scheme, a little variation or modification are made using the technology contents of the disclosure above and is equal to Case study on implementation is imitated, is belonged in technical proposal scope.

Claims (8)

1. a kind of asphaltic concrete core wall basement construction method, it is characterised in that include the following steps:
1) pedestal concrete block multiple first concrete blocks (3) and multiple second are planned to along the length direction of pedestal (2) to mix It coagulates soil block (4), is embedded one second concrete block between adjacent first concrete block, and the section configuration of the first concrete block is positive Trapezoidal, the section configuration of the second concrete block is inverted trapezoidal;
2) pouring construction of all first concrete blocks is carried out along base length direction, and is stayed between adjacent first concrete block The second concrete block pours sky out;
3) it after all first concrete block constructions, is spaced at least 28 days, the first concrete at interim seam of constructing will be located at Block contact surface (5) dabbing removes loose matter, and after rinsing well, smears cement mortar, then be embedded BW water expandable waterstop, most The pouring construction for carrying out the second concrete block afterwards makes the first and second concrete block form an entirety.
2. asphaltic concrete core wall basement construction method according to claim 1, which is characterized in that first concrete The length of block is 20 ~ 25m, and the length of second concrete block is 1 ~ 1.5m.
3. asphaltic concrete core wall basement construction method according to claim 1, which is characterized in that first concrete The lower base angle of block is 60 ° ~ 75 °.
4. asphaltic concrete core wall basement construction method according to claim 1, which is characterized in that the interim seam of construction Position should set on the base by shearing smaller and convenient for construction position.
5. the bituminous concrete that asphaltic concrete core wall basement construction method described in a kind of any one of claim 1-4 is formed Core-wall base construction, it is characterised in that including it is multiple arrange and pour along base length direction integral the first concrete block and Second concrete block is embedded one second concrete block, and the section configuration of the first concrete block between adjacent first concrete block For trapezoid, the section configuration of the second concrete block is inverted trapezoidal, the construction between the first concrete block and the second concrete block BW water expandable waterstop is embedded in interim seam.
6. asphaltic concrete core wall base construction according to claim 5, which is characterized in that first concrete block Length is 20 ~ 25m, and the length of second concrete block is 1 ~ 1.5m.
7. asphaltic concrete core wall base construction according to claim 5, which is characterized in that first concrete block Lower base angle is 60 ° ~ 75 °.
8. asphaltic concrete core wall base construction according to claim 5, which is characterized in that the position temporarily stitched of constructing Setting should set on the base by smaller and convenient for construction the position of shearing.
CN201910400694.0A 2019-05-15 2019-05-15 Asphaltic concrete core wall basement construction method and its structure Pending CN110004886A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910400694.0A CN110004886A (en) 2019-05-15 2019-05-15 Asphaltic concrete core wall basement construction method and its structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910400694.0A CN110004886A (en) 2019-05-15 2019-05-15 Asphaltic concrete core wall basement construction method and its structure

Publications (1)

Publication Number Publication Date
CN110004886A true CN110004886A (en) 2019-07-12

Family

ID=67176994

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910400694.0A Pending CN110004886A (en) 2019-05-15 2019-05-15 Asphaltic concrete core wall basement construction method and its structure

Country Status (1)

Country Link
CN (1) CN110004886A (en)

Citations (28)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1285556A (en) * 1968-07-17 1972-08-16 Grace W R & Co Method of sealing concrete joints
US3758650A (en) * 1969-01-22 1973-09-11 J Hurst Nal waterstop for use in forming joints in concrete method of sealing shuttering against a deformable section of an exter
US4793162A (en) * 1986-08-07 1988-12-27 Spt, Inc. Method for repairing failed waterstops and products relating to same
CN2214958Y (en) * 1995-01-19 1995-12-13 陈宏森 Main sliding block for hydraulic gate
CN1213029A (en) * 1998-10-15 1999-04-07 国家电力公司华东勘测设计研究院科学研究所 Anti-leakage water-tight structure used for water conservancy and water power engineering
CN101603298A (en) * 2009-07-02 2009-12-16 中国水电顾问集团华东勘测设计研究院 A kind of dam joint structure and job practices thereof
CN101886435A (en) * 2010-07-09 2010-11-17 中国二十二冶集团有限公司 Water-swelling rubber water bar fixing method
CN101906768A (en) * 2010-08-19 2010-12-08 中国水电建设集团十五工程局有限公司 Panel construction method of concrete faced rock-fill dam
CN202509446U (en) * 2012-03-29 2012-10-31 中国十九冶集团有限公司 Tailings dam for river intercepting type tailings pond
CN102839629A (en) * 2012-08-17 2012-12-26 北京科技大学 Method and structure for disturbed riverbed seepage-proof governing
CN203373704U (en) * 2013-07-18 2014-01-01 宁欣 Flood prevention water baffle
CN203383193U (en) * 2013-03-22 2014-01-08 中国水电顾问集团贵阳勘测设计研究院 Core-wall rockfill dam structure without cofferdams
CN103643656A (en) * 2013-11-22 2014-03-19 河海大学 High rock-fill dam membrane anti-seepage body on deep coverage layer and construction method of high rock-fill dam membrane anti-seepage body
CN103758086A (en) * 2014-01-22 2014-04-30 中机国际工程设计研究院有限责任公司 Weir plate assembly capable of adjusting liquid level
CN104480903A (en) * 2014-12-12 2015-04-01 中国电建集团贵阳勘测设计研究院有限公司 Panel joint structure for concrete panel rockfill dam and construction method of panel joint structure
CN204435318U (en) * 2014-11-13 2015-07-01 北京中水科海利工程技术有限公司 Be applied to the slab joint top layer application type water-stopping structure of Concrete Face Rockfill Dam
CN104846791A (en) * 2015-05-27 2015-08-19 中国电建集团华东勘测设计研究院有限公司 Construction method of concrete connecting slabs of broken-line face rockfill dam
CN205617317U (en) * 2016-01-05 2016-10-05 中国电建集团华东勘测设计研究院有限公司 Asphalt concrete core and concrete foundation's connection structure
CN106049372A (en) * 2016-07-28 2016-10-26 中水东北勘测设计研究有限责任公司 Asphalt concrete core wall first-stage and second-stage construction seam slot-shaped connection structure and construction method
CN206110094U (en) * 2016-10-27 2017-04-19 中国葛洲坝集团第一工程有限公司 Permanent keyway of rockfill dam panel seam
CN106638487A (en) * 2017-01-19 2017-05-10 中国电力建设股份有限公司 Combined water retaining dam and construction method of combined water retaining dam
CN107143046A (en) * 2017-06-09 2017-09-08 王军 A kind of water expandable waterstop, glue combination constructing method thereof
CN207314284U (en) * 2017-09-11 2018-05-04 中国电建集团北京勘测设计研究院有限公司 Leakage preventing structure in a kind of dam of narrow steep river valley rockfill dam with asphalt concrete core
CN207582419U (en) * 2017-11-08 2018-07-06 中国水利水电科学研究院 Channel expansive soil slope protective slope structure and channel expansive soil slope
CN108301384A (en) * 2018-04-11 2018-07-20 中国电建集团成都勘测设计研究院有限公司 Asphaltic concrete core wall and dam foundation concrete watertight wall joint structure
CN207672529U (en) * 2017-12-14 2018-07-31 中国电建集团成都勘测设计研究院有限公司 A kind of bracing means of concrete dam
CN108930292A (en) * 2017-05-27 2018-12-04 中铁第四勘察设计院集团有限公司 The method that a kind of pair of new-old concrete interface carries out water-proofing treatment
CN208219568U (en) * 2018-04-20 2018-12-11 中国电建集团贵阳勘测设计研究院有限公司 A kind of surface watertight seal structure for concrete face rockfill dam

Patent Citations (28)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
GB1285556A (en) * 1968-07-17 1972-08-16 Grace W R & Co Method of sealing concrete joints
US3758650A (en) * 1969-01-22 1973-09-11 J Hurst Nal waterstop for use in forming joints in concrete method of sealing shuttering against a deformable section of an exter
US4793162A (en) * 1986-08-07 1988-12-27 Spt, Inc. Method for repairing failed waterstops and products relating to same
CN2214958Y (en) * 1995-01-19 1995-12-13 陈宏森 Main sliding block for hydraulic gate
CN1213029A (en) * 1998-10-15 1999-04-07 国家电力公司华东勘测设计研究院科学研究所 Anti-leakage water-tight structure used for water conservancy and water power engineering
CN101603298A (en) * 2009-07-02 2009-12-16 中国水电顾问集团华东勘测设计研究院 A kind of dam joint structure and job practices thereof
CN101886435A (en) * 2010-07-09 2010-11-17 中国二十二冶集团有限公司 Water-swelling rubber water bar fixing method
CN101906768A (en) * 2010-08-19 2010-12-08 中国水电建设集团十五工程局有限公司 Panel construction method of concrete faced rock-fill dam
CN202509446U (en) * 2012-03-29 2012-10-31 中国十九冶集团有限公司 Tailings dam for river intercepting type tailings pond
CN102839629A (en) * 2012-08-17 2012-12-26 北京科技大学 Method and structure for disturbed riverbed seepage-proof governing
CN203383193U (en) * 2013-03-22 2014-01-08 中国水电顾问集团贵阳勘测设计研究院 Core-wall rockfill dam structure without cofferdams
CN203373704U (en) * 2013-07-18 2014-01-01 宁欣 Flood prevention water baffle
CN103643656A (en) * 2013-11-22 2014-03-19 河海大学 High rock-fill dam membrane anti-seepage body on deep coverage layer and construction method of high rock-fill dam membrane anti-seepage body
CN103758086A (en) * 2014-01-22 2014-04-30 中机国际工程设计研究院有限责任公司 Weir plate assembly capable of adjusting liquid level
CN204435318U (en) * 2014-11-13 2015-07-01 北京中水科海利工程技术有限公司 Be applied to the slab joint top layer application type water-stopping structure of Concrete Face Rockfill Dam
CN104480903A (en) * 2014-12-12 2015-04-01 中国电建集团贵阳勘测设计研究院有限公司 Panel joint structure for concrete panel rockfill dam and construction method of panel joint structure
CN104846791A (en) * 2015-05-27 2015-08-19 中国电建集团华东勘测设计研究院有限公司 Construction method of concrete connecting slabs of broken-line face rockfill dam
CN205617317U (en) * 2016-01-05 2016-10-05 中国电建集团华东勘测设计研究院有限公司 Asphalt concrete core and concrete foundation's connection structure
CN106049372A (en) * 2016-07-28 2016-10-26 中水东北勘测设计研究有限责任公司 Asphalt concrete core wall first-stage and second-stage construction seam slot-shaped connection structure and construction method
CN206110094U (en) * 2016-10-27 2017-04-19 中国葛洲坝集团第一工程有限公司 Permanent keyway of rockfill dam panel seam
CN106638487A (en) * 2017-01-19 2017-05-10 中国电力建设股份有限公司 Combined water retaining dam and construction method of combined water retaining dam
CN108930292A (en) * 2017-05-27 2018-12-04 中铁第四勘察设计院集团有限公司 The method that a kind of pair of new-old concrete interface carries out water-proofing treatment
CN107143046A (en) * 2017-06-09 2017-09-08 王军 A kind of water expandable waterstop, glue combination constructing method thereof
CN207314284U (en) * 2017-09-11 2018-05-04 中国电建集团北京勘测设计研究院有限公司 Leakage preventing structure in a kind of dam of narrow steep river valley rockfill dam with asphalt concrete core
CN207582419U (en) * 2017-11-08 2018-07-06 中国水利水电科学研究院 Channel expansive soil slope protective slope structure and channel expansive soil slope
CN207672529U (en) * 2017-12-14 2018-07-31 中国电建集团成都勘测设计研究院有限公司 A kind of bracing means of concrete dam
CN108301384A (en) * 2018-04-11 2018-07-20 中国电建集团成都勘测设计研究院有限公司 Asphaltic concrete core wall and dam foundation concrete watertight wall joint structure
CN208219568U (en) * 2018-04-20 2018-12-11 中国电建集团贵阳勘测设计研究院有限公司 A kind of surface watertight seal structure for concrete face rockfill dam

Non-Patent Citations (5)

* Cited by examiner, † Cited by third party
Title
沈春林等: "建筑防水材料", 30 June 2000, 化学工业出版社, pages: 454 - 455 *
胡安静;蒋亮;姚田跃;虞舜;: "甲岩水电站高趾墙混凝土面板堆石坝主要施工技术", 云南水力发电, no. 2 *
袁光裕 等: "《高等学校教材 水利工程施工》", vol. 2, 30 April 2018, 化学工业出版社, pages: 135 - 136 *
贺佳欣;: "碾压式沥青混凝土心墙坝设计及其安全评价探讨", 水利技术监督, no. 03, pages 14 - 15 *
马峰;: "沥青混凝土心墙坝工程设计", 甘肃水利水电技术, no. 04 *

Similar Documents

Publication Publication Date Title
CN207597441U (en) A kind of basement side wall horizontal construction joint water proof structure
CN201326185Y (en) Connection joint structure of subway station bottom plates on sealing wall
CN107476351B (en) The waterproof method of the assembled prefabricated side wall assembling construction seam in station
CN104652371B (en) The glue of crossing set up based on old dam coagulates rock-fill dams and construction method thereof
CN206408655U (en) The top plate sidewall structure of covered back-digging construction
CN104652495B (en) Internal support of foundation pit column and base plate node waterproof construction technology
CN110004991A (en) Underground structure anti-floating system and construction method based on raised type tangs plate
CN106884436A (en) A kind of construction method of the waterproof connecting structure of foundation ditch uplift pile and structure base slab
CN205669211U (en) A kind of prefabricated Gravity Retaining Wall
CN110004886A (en) Asphaltic concrete core wall basement construction method and its structure
CN208293344U (en) Kerbstone, gutter and the molding pavement structure of top course one-time-concreting
CN216041282U (en) Cast-in-place concrete slope cushion plate for bearing platform
CN207812509U (en) Bottom plate post-poured strip waterproof structure
CN210049204U (en) Asphalt concrete core wall base structure
CN216342124U (en) Disposal structure of tunnel side lower part karst cave
CN108193706A (en) A kind of downward construction concrete pouring procedure of part contrary sequence method vertical structure
CN208996022U (en) A kind of diaphram wall containing precast construction
CN209353327U (en) The quick pile extension device of rotary digging stake in small space
CN107100208A (en) The anti-floating waterproof construction and construction method of a kind of underground structure
CN208701724U (en) A kind of GCL complex vertical mud antiseepage barrier
CN207597184U (en) A kind of road of the quick assembling of the layer of face containing assembled
CN106436749B (en) A kind of method of underwater splicing U-type groove construction subway station
CN208604640U (en) A kind of quick construction structure of post-pouring belt of outer wall
CN105220696A (en) Rotating-milling formula deep-layer stirring construction method of enclosure structure
CN106120655B (en) The fast repairing method of asphalt concrete core of embankment dams depths leak

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination