CN110004886A - Asphaltic concrete core wall basement construction method and its structure - Google Patents
Asphaltic concrete core wall basement construction method and its structure Download PDFInfo
- Publication number
- CN110004886A CN110004886A CN201910400694.0A CN201910400694A CN110004886A CN 110004886 A CN110004886 A CN 110004886A CN 201910400694 A CN201910400694 A CN 201910400694A CN 110004886 A CN110004886 A CN 110004886A
- Authority
- CN
- China
- Prior art keywords
- concrete
- concrete block
- block
- construction
- asphaltic
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 239000004567 concrete Substances 0.000 title claims abstract description 113
- 238000010276 construction Methods 0.000 title claims abstract description 39
- NJPPVKZQTLUDBO-UHFFFAOYSA-N novaluron Chemical compound C1=C(Cl)C(OC(F)(F)C(OC(F)(F)F)F)=CC=C1NC(=O)NC(=O)C1=C(F)C=CC=C1F NJPPVKZQTLUDBO-UHFFFAOYSA-N 0.000 claims abstract description 12
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 claims abstract description 10
- 238000009411 base construction Methods 0.000 claims abstract description 7
- 239000011083 cement mortar Substances 0.000 claims abstract description 5
- 238000010008 shearing Methods 0.000 claims description 3
- 239000002689 soil Substances 0.000 claims description 2
- 238000007789 sealing Methods 0.000 description 3
- 238000005516 engineering process Methods 0.000 description 2
- 238000000034 method Methods 0.000 description 2
- 239000011384 asphalt concrete Substances 0.000 description 1
- 230000015572 biosynthetic process Effects 0.000 description 1
- 238000005266 casting Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 238000004227 thermal cracking Methods 0.000 description 1
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B3/00—Engineering works in connection with control or use of streams, rivers, coasts, or other marine sites; Sealings or joints for engineering works in general
- E02B3/16—Sealings or joints
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02B—HYDRAULIC ENGINEERING
- E02B7/00—Barrages or weirs; Layout, construction, methods of, or devices for, making same
- E02B7/02—Fixed barrages
- E02B7/04—Dams across valleys
- E02B7/08—Wall dams
Landscapes
- Engineering & Computer Science (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Mechanical Engineering (AREA)
- Civil Engineering (AREA)
- Environmental & Geological Engineering (AREA)
- Ocean & Marine Engineering (AREA)
- Revetment (AREA)
Abstract
A kind of asphaltic concrete core wall basement construction method and structure, comprising: which pedestal concrete block is planned to multiple first concrete blocks and multiple second concrete blocks by the length direction along pedestal, one second concrete block is embedded between adjacent first concrete block, and first the section configuration of concrete block be trapezoid, the section configuration of the second concrete block is inverted trapezoidal;The pouring construction of all first concrete blocks is carried out along base length direction, and is reserved the second concrete block between adjacent first concrete block and poured sky;After all first concrete block constructions, interval at least 28 days, the first concrete block contact surface dabbing at interim seam of constructing will be located at, remove loose matter, and after rinsing well, cement mortar is smeared, then is embedded BW water expandable waterstop, the pouring construction for finally carrying out the second concrete block makes the first and second concrete block form an entirety.Core-wall base construction of the present invention is complete continuous entirety, and anti-seepage effect is more preferable, and is easy to construct.
Description
Technical field
The present invention relates to the asphaltic concrete core wall in hydraulic and hydroelectric engineering, especially a kind of asphaltic concrete core wall pedestal
Construction method and its structure.
Background technique
In hydraulic and hydroelectric engineering, asphalt concrete core dam is a kind of common water retaining structure.Concrete pedestal can
Using the lid weight as grouting, the structure of antiseepage can also be used as, be a part indispensable in asphaltic concrete core wall.
Concrete pedestal is applied as mass concrete when constructing to prevent the generation of thermal cracking that can be divided into several pieces
Work does parting processing, then clogs sealing between these point of good concret block, prevent the leakage of water between seam, such
Way makes to form permanent seam between concret block, thus the position that parting sealing is arranged is often weak link, is easy by water
Body destroys, and carries out filling sealing in permanent seam, and working procedure is complicated, and water-stagnating effect is unstable, is more easily damaged.
Summary of the invention
The technical problem to be solved by the present invention is to overcome the shortage of prior art, provide one kind and be easy to construct, and formed
Whole continuous whole asphaltic concrete core wall basement construction method and its structure.
In order to solve the above technical problems, the present invention provides a kind of asphaltic concrete core wall basement construction methods comprising
The following steps:
1) pedestal concrete block is planned to multiple first concrete blocks and multiple second concrete blocks along the length direction of pedestal,
It is embedded one second concrete block between adjacent first concrete block, and the section configuration of the first concrete block is trapezoid, second
The section configuration of concrete block is inverted trapezoidal;
2) pouring construction of all first concrete blocks is carried out along base length direction, and is stayed between adjacent first concrete block
The second concrete block pours sky out;
3) it after all first concrete block constructions, is spaced at least 28 days, the first concrete at interim seam of constructing will be located at
Block contact surface dabbing removes loose matter, and after rinsing well, smears cement mortar, then be embedded BW water expandable waterstop, most laggard
The pouring construction of the second concrete block of row makes the first and second concrete block form an entirety.
Further, the length of first concrete block is determined according to construction speed and construction intensity, generally 20 ~
25m, the length of second concrete block are 1 ~ 1.5m.
Further, the lower base angle of first concrete block is 60 ° ~ 75 °.
Further, the position temporarily stitched of constructing should be set on the base by smaller and convenient for construction the position of shearing.
In order to solve the above technical problems, the present invention also provides a kind of asphaltic concrete core wall base constructions comprising more
It is a to be arranged along base length direction and pour integral the first concrete block and the second concrete block, adjacent first concrete block
Between be embedded one second concrete block, and the section configuration of the first concrete block is trapezoid, the section shape of the second concrete block
Shape is inverted trapezoidal, the construction between the first concrete block and the second concrete block temporarily stitch in be embedded BW water expandable waterstop.
Compared with the prior art, the advantages of the present invention are as follows:
1, the present invention is between the first and second concrete block by being arranged the interim seam of construction, and by the contact surface of the first concrete block
Dabbing removes loose matter, and after rinsing well, smears cement mortar, then be embedded BW water expandable waterstop, finally just carry out second
The pouring construction of concrete block makes the first and second concrete block form one complete continuous whole, and then makes anti-seepage effect more
It is good.
2, construction technology of the present invention is simple, is easy to construct.
Detailed description of the invention
Fig. 1 is sectional view of the asphaltic concrete core wall base construction of the present invention along base axis direction.
Fig. 2 is enlarged drawing at the A of Fig. 1.
In figure: 1-core-wall;2-pedestals;The first concrete block of 3--;The second concrete block of 4--;5-contact surfaces.
Specific embodiment
Below in conjunction with specific preferred embodiment, the invention will be further described, but not thereby limiting the invention
Protection scope.
For ease of description, the relative positional relationship of each component, such as: the description of upper and lower, left and right is according to explanation
Restriction effect is not played to the structure of this patent come what is be described in the Butut direction of book attached drawing.
Embodiment 1:
As shown in Figure 1 and Figure 2, one embodiment of asphaltic concrete core wall basement construction method of the present invention includes the following steps:
1) pedestal concrete block is planned to multiple first concrete blocks 3 and multiple second concrete along the length direction of pedestal 2
Block 4, is embedded one second concrete block 4 between adjacent first concrete block 3, and the section configuration of the first concrete block 3 is positive ladder
Shape, the section configuration of the second concrete block 4 are inverted trapezoidal, the position that the construction of 3 two sides of the first concrete block is temporarily stitched be located at by
Shear smaller and convenient for construction position;
2) pouring construction of all first concrete blocks 3 is carried out along the length direction of pedestal 2, and in adjacent first concrete block 3
Between reserve the second concrete block casting space;
3) it after all first concrete block, 3 pouring constructions, is spaced at least 28 days, be located at interim seam of constructing first is mixed
Solidifying 5 dabbing of soil block contact surface removes loose matter, and after rinsing well, smears cement mortar, then in the first concrete block contact surface 5
It is embedded BW water expandable waterstop, finally carries out the pouring construction of the second concrete block 4, makes the formation of the first and second concrete block 3,4
One entirety.
Wherein, the length of the first concrete block 3 is determined according to construction speed and construction intensity, generally uses 20 ~ 25m,
Lower base angle θ=60 ° ~ 75 ° of first concrete block 3;Length L=1 ~ 1.5m of second concrete block 4.
The above is only the preferred embodiment of the application, not does any type of limitation to the application, although this Shen
Please disclosed as above with preferred embodiment, however not to limit the application, any person skilled in the art is not taking off
In the range of technical scheme, a little variation or modification are made using the technology contents of the disclosure above and is equal to
Case study on implementation is imitated, is belonged in technical proposal scope.
Claims (8)
1. a kind of asphaltic concrete core wall basement construction method, it is characterised in that include the following steps:
1) pedestal concrete block multiple first concrete blocks (3) and multiple second are planned to along the length direction of pedestal (2) to mix
It coagulates soil block (4), is embedded one second concrete block between adjacent first concrete block, and the section configuration of the first concrete block is positive
Trapezoidal, the section configuration of the second concrete block is inverted trapezoidal;
2) pouring construction of all first concrete blocks is carried out along base length direction, and is stayed between adjacent first concrete block
The second concrete block pours sky out;
3) it after all first concrete block constructions, is spaced at least 28 days, the first concrete at interim seam of constructing will be located at
Block contact surface (5) dabbing removes loose matter, and after rinsing well, smears cement mortar, then be embedded BW water expandable waterstop, most
The pouring construction for carrying out the second concrete block afterwards makes the first and second concrete block form an entirety.
2. asphaltic concrete core wall basement construction method according to claim 1, which is characterized in that first concrete
The length of block is 20 ~ 25m, and the length of second concrete block is 1 ~ 1.5m.
3. asphaltic concrete core wall basement construction method according to claim 1, which is characterized in that first concrete
The lower base angle of block is 60 ° ~ 75 °.
4. asphaltic concrete core wall basement construction method according to claim 1, which is characterized in that the interim seam of construction
Position should set on the base by shearing smaller and convenient for construction position.
5. the bituminous concrete that asphaltic concrete core wall basement construction method described in a kind of any one of claim 1-4 is formed
Core-wall base construction, it is characterised in that including it is multiple arrange and pour along base length direction integral the first concrete block and
Second concrete block is embedded one second concrete block, and the section configuration of the first concrete block between adjacent first concrete block
For trapezoid, the section configuration of the second concrete block is inverted trapezoidal, the construction between the first concrete block and the second concrete block
BW water expandable waterstop is embedded in interim seam.
6. asphaltic concrete core wall base construction according to claim 5, which is characterized in that first concrete block
Length is 20 ~ 25m, and the length of second concrete block is 1 ~ 1.5m.
7. asphaltic concrete core wall base construction according to claim 5, which is characterized in that first concrete block
Lower base angle is 60 ° ~ 75 °.
8. asphaltic concrete core wall base construction according to claim 5, which is characterized in that the position temporarily stitched of constructing
Setting should set on the base by smaller and convenient for construction the position of shearing.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910400694.0A CN110004886A (en) | 2019-05-15 | 2019-05-15 | Asphaltic concrete core wall basement construction method and its structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910400694.0A CN110004886A (en) | 2019-05-15 | 2019-05-15 | Asphaltic concrete core wall basement construction method and its structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110004886A true CN110004886A (en) | 2019-07-12 |
Family
ID=67176994
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910400694.0A Pending CN110004886A (en) | 2019-05-15 | 2019-05-15 | Asphaltic concrete core wall basement construction method and its structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110004886A (en) |
Citations (28)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB1285556A (en) * | 1968-07-17 | 1972-08-16 | Grace W R & Co | Method of sealing concrete joints |
US3758650A (en) * | 1969-01-22 | 1973-09-11 | J Hurst | Nal waterstop for use in forming joints in concrete method of sealing shuttering against a deformable section of an exter |
US4793162A (en) * | 1986-08-07 | 1988-12-27 | Spt, Inc. | Method for repairing failed waterstops and products relating to same |
CN2214958Y (en) * | 1995-01-19 | 1995-12-13 | 陈宏森 | Main sliding block for hydraulic gate |
CN1213029A (en) * | 1998-10-15 | 1999-04-07 | 国家电力公司华东勘测设计研究院科学研究所 | Anti-leakage water-tight structure used for water conservancy and water power engineering |
CN101603298A (en) * | 2009-07-02 | 2009-12-16 | 中国水电顾问集团华东勘测设计研究院 | A kind of dam joint structure and job practices thereof |
CN101886435A (en) * | 2010-07-09 | 2010-11-17 | 中国二十二冶集团有限公司 | Water-swelling rubber water bar fixing method |
CN101906768A (en) * | 2010-08-19 | 2010-12-08 | 中国水电建设集团十五工程局有限公司 | Panel construction method of concrete faced rock-fill dam |
CN202509446U (en) * | 2012-03-29 | 2012-10-31 | 中国十九冶集团有限公司 | Tailings dam for river intercepting type tailings pond |
CN102839629A (en) * | 2012-08-17 | 2012-12-26 | 北京科技大学 | Method and structure for disturbed riverbed seepage-proof governing |
CN203373704U (en) * | 2013-07-18 | 2014-01-01 | 宁欣 | Flood prevention water baffle |
CN203383193U (en) * | 2013-03-22 | 2014-01-08 | 中国水电顾问集团贵阳勘测设计研究院 | Core-wall rockfill dam structure without cofferdams |
CN103643656A (en) * | 2013-11-22 | 2014-03-19 | 河海大学 | High rock-fill dam membrane anti-seepage body on deep coverage layer and construction method of high rock-fill dam membrane anti-seepage body |
CN103758086A (en) * | 2014-01-22 | 2014-04-30 | 中机国际工程设计研究院有限责任公司 | Weir plate assembly capable of adjusting liquid level |
CN104480903A (en) * | 2014-12-12 | 2015-04-01 | 中国电建集团贵阳勘测设计研究院有限公司 | Panel joint structure for concrete panel rockfill dam and construction method of panel joint structure |
CN204435318U (en) * | 2014-11-13 | 2015-07-01 | 北京中水科海利工程技术有限公司 | Be applied to the slab joint top layer application type water-stopping structure of Concrete Face Rockfill Dam |
CN104846791A (en) * | 2015-05-27 | 2015-08-19 | 中国电建集团华东勘测设计研究院有限公司 | Construction method of concrete connecting slabs of broken-line face rockfill dam |
CN205617317U (en) * | 2016-01-05 | 2016-10-05 | 中国电建集团华东勘测设计研究院有限公司 | Asphalt concrete core and concrete foundation's connection structure |
CN106049372A (en) * | 2016-07-28 | 2016-10-26 | 中水东北勘测设计研究有限责任公司 | Asphalt concrete core wall first-stage and second-stage construction seam slot-shaped connection structure and construction method |
CN206110094U (en) * | 2016-10-27 | 2017-04-19 | 中国葛洲坝集团第一工程有限公司 | Permanent keyway of rockfill dam panel seam |
CN106638487A (en) * | 2017-01-19 | 2017-05-10 | 中国电力建设股份有限公司 | Combined water retaining dam and construction method of combined water retaining dam |
CN107143046A (en) * | 2017-06-09 | 2017-09-08 | 王军 | A kind of water expandable waterstop, glue combination constructing method thereof |
CN207314284U (en) * | 2017-09-11 | 2018-05-04 | 中国电建集团北京勘测设计研究院有限公司 | Leakage preventing structure in a kind of dam of narrow steep river valley rockfill dam with asphalt concrete core |
CN207582419U (en) * | 2017-11-08 | 2018-07-06 | 中国水利水电科学研究院 | Channel expansive soil slope protective slope structure and channel expansive soil slope |
CN108301384A (en) * | 2018-04-11 | 2018-07-20 | 中国电建集团成都勘测设计研究院有限公司 | Asphaltic concrete core wall and dam foundation concrete watertight wall joint structure |
CN207672529U (en) * | 2017-12-14 | 2018-07-31 | 中国电建集团成都勘测设计研究院有限公司 | A kind of bracing means of concrete dam |
CN108930292A (en) * | 2017-05-27 | 2018-12-04 | 中铁第四勘察设计院集团有限公司 | The method that a kind of pair of new-old concrete interface carries out water-proofing treatment |
CN208219568U (en) * | 2018-04-20 | 2018-12-11 | 中国电建集团贵阳勘测设计研究院有限公司 | A kind of surface watertight seal structure for concrete face rockfill dam |
-
2019
- 2019-05-15 CN CN201910400694.0A patent/CN110004886A/en active Pending
Patent Citations (28)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
GB1285556A (en) * | 1968-07-17 | 1972-08-16 | Grace W R & Co | Method of sealing concrete joints |
US3758650A (en) * | 1969-01-22 | 1973-09-11 | J Hurst | Nal waterstop for use in forming joints in concrete method of sealing shuttering against a deformable section of an exter |
US4793162A (en) * | 1986-08-07 | 1988-12-27 | Spt, Inc. | Method for repairing failed waterstops and products relating to same |
CN2214958Y (en) * | 1995-01-19 | 1995-12-13 | 陈宏森 | Main sliding block for hydraulic gate |
CN1213029A (en) * | 1998-10-15 | 1999-04-07 | 国家电力公司华东勘测设计研究院科学研究所 | Anti-leakage water-tight structure used for water conservancy and water power engineering |
CN101603298A (en) * | 2009-07-02 | 2009-12-16 | 中国水电顾问集团华东勘测设计研究院 | A kind of dam joint structure and job practices thereof |
CN101886435A (en) * | 2010-07-09 | 2010-11-17 | 中国二十二冶集团有限公司 | Water-swelling rubber water bar fixing method |
CN101906768A (en) * | 2010-08-19 | 2010-12-08 | 中国水电建设集团十五工程局有限公司 | Panel construction method of concrete faced rock-fill dam |
CN202509446U (en) * | 2012-03-29 | 2012-10-31 | 中国十九冶集团有限公司 | Tailings dam for river intercepting type tailings pond |
CN102839629A (en) * | 2012-08-17 | 2012-12-26 | 北京科技大学 | Method and structure for disturbed riverbed seepage-proof governing |
CN203383193U (en) * | 2013-03-22 | 2014-01-08 | 中国水电顾问集团贵阳勘测设计研究院 | Core-wall rockfill dam structure without cofferdams |
CN203373704U (en) * | 2013-07-18 | 2014-01-01 | 宁欣 | Flood prevention water baffle |
CN103643656A (en) * | 2013-11-22 | 2014-03-19 | 河海大学 | High rock-fill dam membrane anti-seepage body on deep coverage layer and construction method of high rock-fill dam membrane anti-seepage body |
CN103758086A (en) * | 2014-01-22 | 2014-04-30 | 中机国际工程设计研究院有限责任公司 | Weir plate assembly capable of adjusting liquid level |
CN204435318U (en) * | 2014-11-13 | 2015-07-01 | 北京中水科海利工程技术有限公司 | Be applied to the slab joint top layer application type water-stopping structure of Concrete Face Rockfill Dam |
CN104480903A (en) * | 2014-12-12 | 2015-04-01 | 中国电建集团贵阳勘测设计研究院有限公司 | Panel joint structure for concrete panel rockfill dam and construction method of panel joint structure |
CN104846791A (en) * | 2015-05-27 | 2015-08-19 | 中国电建集团华东勘测设计研究院有限公司 | Construction method of concrete connecting slabs of broken-line face rockfill dam |
CN205617317U (en) * | 2016-01-05 | 2016-10-05 | 中国电建集团华东勘测设计研究院有限公司 | Asphalt concrete core and concrete foundation's connection structure |
CN106049372A (en) * | 2016-07-28 | 2016-10-26 | 中水东北勘测设计研究有限责任公司 | Asphalt concrete core wall first-stage and second-stage construction seam slot-shaped connection structure and construction method |
CN206110094U (en) * | 2016-10-27 | 2017-04-19 | 中国葛洲坝集团第一工程有限公司 | Permanent keyway of rockfill dam panel seam |
CN106638487A (en) * | 2017-01-19 | 2017-05-10 | 中国电力建设股份有限公司 | Combined water retaining dam and construction method of combined water retaining dam |
CN108930292A (en) * | 2017-05-27 | 2018-12-04 | 中铁第四勘察设计院集团有限公司 | The method that a kind of pair of new-old concrete interface carries out water-proofing treatment |
CN107143046A (en) * | 2017-06-09 | 2017-09-08 | 王军 | A kind of water expandable waterstop, glue combination constructing method thereof |
CN207314284U (en) * | 2017-09-11 | 2018-05-04 | 中国电建集团北京勘测设计研究院有限公司 | Leakage preventing structure in a kind of dam of narrow steep river valley rockfill dam with asphalt concrete core |
CN207582419U (en) * | 2017-11-08 | 2018-07-06 | 中国水利水电科学研究院 | Channel expansive soil slope protective slope structure and channel expansive soil slope |
CN207672529U (en) * | 2017-12-14 | 2018-07-31 | 中国电建集团成都勘测设计研究院有限公司 | A kind of bracing means of concrete dam |
CN108301384A (en) * | 2018-04-11 | 2018-07-20 | 中国电建集团成都勘测设计研究院有限公司 | Asphaltic concrete core wall and dam foundation concrete watertight wall joint structure |
CN208219568U (en) * | 2018-04-20 | 2018-12-11 | 中国电建集团贵阳勘测设计研究院有限公司 | A kind of surface watertight seal structure for concrete face rockfill dam |
Non-Patent Citations (5)
Title |
---|
沈春林等: "建筑防水材料", 30 June 2000, 化学工业出版社, pages: 454 - 455 * |
胡安静;蒋亮;姚田跃;虞舜;: "甲岩水电站高趾墙混凝土面板堆石坝主要施工技术", 云南水力发电, no. 2 * |
袁光裕 等: "《高等学校教材 水利工程施工》", vol. 2, 30 April 2018, 化学工业出版社, pages: 135 - 136 * |
贺佳欣;: "碾压式沥青混凝土心墙坝设计及其安全评价探讨", 水利技术监督, no. 03, pages 14 - 15 * |
马峰;: "沥青混凝土心墙坝工程设计", 甘肃水利水电技术, no. 04 * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN207597441U (en) | A kind of basement side wall horizontal construction joint water proof structure | |
CN201326185Y (en) | Connection joint structure of subway station bottom plates on sealing wall | |
CN107476351B (en) | The waterproof method of the assembled prefabricated side wall assembling construction seam in station | |
CN104652371B (en) | The glue of crossing set up based on old dam coagulates rock-fill dams and construction method thereof | |
CN206408655U (en) | The top plate sidewall structure of covered back-digging construction | |
CN104652495B (en) | Internal support of foundation pit column and base plate node waterproof construction technology | |
CN110004991A (en) | Underground structure anti-floating system and construction method based on raised type tangs plate | |
CN106884436A (en) | A kind of construction method of the waterproof connecting structure of foundation ditch uplift pile and structure base slab | |
CN205669211U (en) | A kind of prefabricated Gravity Retaining Wall | |
CN110004886A (en) | Asphaltic concrete core wall basement construction method and its structure | |
CN208293344U (en) | Kerbstone, gutter and the molding pavement structure of top course one-time-concreting | |
CN216041282U (en) | Cast-in-place concrete slope cushion plate for bearing platform | |
CN207812509U (en) | Bottom plate post-poured strip waterproof structure | |
CN210049204U (en) | Asphalt concrete core wall base structure | |
CN216342124U (en) | Disposal structure of tunnel side lower part karst cave | |
CN108193706A (en) | A kind of downward construction concrete pouring procedure of part contrary sequence method vertical structure | |
CN208996022U (en) | A kind of diaphram wall containing precast construction | |
CN209353327U (en) | The quick pile extension device of rotary digging stake in small space | |
CN107100208A (en) | The anti-floating waterproof construction and construction method of a kind of underground structure | |
CN208701724U (en) | A kind of GCL complex vertical mud antiseepage barrier | |
CN207597184U (en) | A kind of road of the quick assembling of the layer of face containing assembled | |
CN106436749B (en) | A kind of method of underwater splicing U-type groove construction subway station | |
CN208604640U (en) | A kind of quick construction structure of post-pouring belt of outer wall | |
CN105220696A (en) | Rotating-milling formula deep-layer stirring construction method of enclosure structure | |
CN106120655B (en) | The fast repairing method of asphalt concrete core of embankment dams depths leak |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |