CN106884436A - A kind of construction method of the waterproof connecting structure of foundation ditch uplift pile and structure base slab - Google Patents
A kind of construction method of the waterproof connecting structure of foundation ditch uplift pile and structure base slab Download PDFInfo
- Publication number
- CN106884436A CN106884436A CN201710060574.1A CN201710060574A CN106884436A CN 106884436 A CN106884436 A CN 106884436A CN 201710060574 A CN201710060574 A CN 201710060574A CN 106884436 A CN106884436 A CN 106884436A
- Authority
- CN
- China
- Prior art keywords
- construction
- pile
- base slab
- waterproof
- structure base
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D27/00—Foundations as substructures
- E02D27/10—Deep foundations
- E02D27/12—Pile foundations
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D29/00—Independent underground or underwater structures; Retaining walls
- E02D29/16—Arrangement or construction of joints in foundation structures
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D31/00—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
- E02D31/02—Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against ground humidity or ground water
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2300/00—Materials
- E02D2300/0004—Synthetics
- E02D2300/0018—Cement used as binder
- E02D2300/002—Concrete
Abstract
The present invention relates to a kind of foundation ditch uplift pile and the construction method of the waterproof connecting structure of structure base slab, it includes following construction procedure:(1) soil body construction at pile crown;(2) cushion construction;(3) pile crown amputation;(4) Slab Waterproof Construction;(5) assembling reinforcement;(6) concreting.The present invention abolishes to base plate at D/4 pile crown, is poured using rounding stage body when structure base slab is with pile crown concreting.Rounding stage body is poured can protect baseplate reinforcing bar not to be etched, and prevent from being seeped water due to the improper caused base plate of pile head waterproofing, with convenience for construction and economic rationality.
Description
【Technical field】
The present invention relates to a kind of construction method of foundation ditch, and in particular to a kind of foundation ditch uplift pile connects with the waterproof of structure base slab
The construction method of binding structure, belongs to base pit engineering technical field.
【Background technology】
At present, engineering construction occur base plate infiltration situation it is a lot, its influence factor is a lot, wherein the water-proofing treatment of pile crown
It is also particularly important one.The side that traditional pile crown waterproof construction is combined using waterproof roll, water-repellent paint, encapsulant
Formula carries out water-proofing treatment, not only wastes time and energy, and it cannot be guaranteed that waterproof effect.
Pile head waterproofing will solve three difficult points:1. it is not while pour, in pile crown periphery, stake top with base plate because of pile crown
With the concrete construction joint of concrete floor connecting part.2. blinding concrete shrinks the gap produced and between pile crown.3. pile crown
There is the gap of differential settlement generation because of the not equal reason of the packing of following soil in surrounding bed course.
Therefore, in order to solve the above technical problems, it is necessory to provide a kind of foundation ditch uplift pile of innovation with structure base slab
The construction method of waterproof connecting structure, to overcome the defect of the prior art.
【The content of the invention】
It is an object of the invention to provide a kind of foundation ditch uplift pile and the construction method of the waterproof connecting structure of structure base slab,
It need not carry out above-mentioned traditional pile crown waterproof construction in practice of construction to pile crown, with convenience for construction and economical rationality
Property.
To achieve the above object, the technical scheme taken of the present invention is:A kind of foundation ditch uplift pile and the waterproof of structure base slab
The construction method of attachment structure, including following construction procedure:
(1) soil body construction at pile crown:The soil body at pile crown is tiltedly dug out into an inverted round stage along the stake whole body with 45 ° of inclination angle
Body;
(2) cushion construction:When carrying out structure base slab with the construction of underlayer, same construction thickness is d's around pile crown
Bed course, bed course is constructed around pile body with 45 degree of inclination angles at pile crown;
(3) pile crown amputation:Pile crown is amputated to structure base slab lower surface absolute altitude at D/4, and waterproof construction and cleaning
Basic unit, basic unit's debris, dust, lime-ash are cleaned up, basic unit's acceptance(check);
(4) Slab Waterproof Construction:The construction of waterproof slab is carried out before concreting, waterproof material thickness is h;
(5) assembling reinforcement:Binding structure baseplate reinforcing bar, by the Reinforcement at resistance to plucking pile head and structure base slab master
Muscle is connected in a welding manner;
(6) concreting:To locate around structure base slab and pile crown rest pour jointly to be formed one it is unified mixed
Solidifying soil is overall, and the concrete poured below structure base slab lower surface absolute altitude is highly exactly D.
Foundation ditch uplift pile of the invention is further with the construction method of the waterproof connecting structure of structure base slab:Step 1)
In, a diameter of D of uplift pile is set, cushion thickness is d, and waterproof material thickness is h, digs deep degree and is
It is exactly tiltedly to dig to below structure base slab lower surface absolute altitudePlace, is taken as integer during construction, the face tiltedly dug out is i.e.
It is the side of rounding stage body.
Foundation ditch uplift pile of the invention is also with the construction method of the waterproof connecting structure of structure base slab:Step 3) in, stake
Waterproof at head is constructed around pile body with 45 ° of inclination angles.
Compared with prior art, the present invention has the advantages that:Foundation ditch uplift pile of the invention and structure base slab
The construction method of waterproof connecting structure is amputated to base plate lower surface pile crown by many amputation part pile crowns, and concrete is poured
Poured using rounding stage body at pile crown when building, same casting concrete at pile crown, such construction joint has been left in distance structure bottom
Plate lower surfaceThe bottom pile body at place, it is to avoid construction joint is stayed in into stake top is connected with concrete floor
Position, effectively prevent structure base slab reinforcing bar and be corroded.
Meanwhile, pile concrete is poured and poured using rounding stage body, and rounding stage body bottom construction inclination angle is 45 ° of bed courses, i.e.,
Mat layer concrete shrinks, and the concrete for pouring more can effectively prevent the intrusion of water, but also can effectively reduce uneven
Settle the gap for producing.
【Brief description of the drawings】
Fig. 1 is the structural representation of uplift pile of the invention.
In figure:1. structural flooring;2. waterproof material;3. bed course;4. pile body steel bar stress;5 pile bodies;6. baseplate reinforcing bar.
【Specific embodiment】
Refer to shown in Figure of description 1, the present invention is a kind of foundation ditch uplift pile and the waterproof connecting structure of structure base slab
Construction method, including following construction procedure:
(1) soil body construction at pile crown:The setting a diameter of D of uplift pile, cushion thickness is d, and waterproof material thickness is h, by stake
The soil body at head tiltedly digs out a rounding stage body along the stake whole body with 45 ° of inclination angle, digs depth and isAlso
It is tiltedly to dig to below structure base slab lower surface absolute altitudePlace, is taken as integer during construction, the face tiltedly dug out is
The side of rounding stage body.Reverse frustoconic is poured can protect baseplate reinforcing bar not to be etched, and prevent from being led because pile head waterproofing is improper
The base plate infiltration of cause.
(2) cushion construction:When carrying out structure base slab with the construction of underlayer, same construction thickness is d's around pile crown
Bed course, bed course is constructed around pile body with 45 degree of inclination angles at pile crown.
(3) pile crown amputation:Pile crown is amputated to structure base slab lower surface absolute altitude at D/4, and waterproof construction and cleaning
Basic unit, basic unit's debris, dust, lime-ash are cleaned up, basic unit's acceptance(check);Wherein, waterproof construction need not be carried out at pile crown
The complicated operational procedures such as sealing rod, waterstop and fluid sealant construction, need to only use with the same waterproof of other parts under base plate
Material and operational procedure, unlike, the construction of waterproofing work is carried out along pile body with 45 ° of inclination angles at pile crown.
(4) Slab Waterproof Construction:The construction of waterproof slab is carried out before concreting, waterproof material thickness is h;
(5) assembling reinforcement:Binding structure baseplate reinforcing bar, by the Reinforcement at resistance to plucking pile head and structure base slab master
Muscle is connected in a welding manner;
(6) concreting:To locate around structure base slab and pile crown rest pour jointly to be formed one it is unified mixed
Solidifying soil is overall, and the concrete poured below structure base slab lower surface absolute altitude is highly exactly D.
The present invention certain below uplift pile base plate lower surface absolute altitude by pile crown by will amputate a part pile crown more
Distance, while the concrete poured at pile crown, pile crown surrounding concrete and structure base slab are poured jointly more, is ensureing resistance to plucking
Under the early stage of the uplift effect of stake resistance to plucking, the concrete for pouring more is wrapped in pile crown and can improve uplift pile and structure base slab junction
Water resistance.
Specific embodiment above is only the preferred embodiment of this creation, is not used to limit this creation, all in this wound
Any modification, equivalent substitution and improvements for being done etc. within the spirit and principle of work, should be included in this creation protection domain it
It is interior.
Claims (3)
1. the construction method of the waterproof connecting structure of a kind of foundation ditch uplift pile and structure base slab, it is characterised in that:Including applying as follows
Work step is rapid:
(1) soil body construction at pile crown:The soil body at pile crown is tiltedly dug out into a rounding stage body along the stake whole body with 45 ° of inclination angle;
(2) cushion construction:When carrying out structure base slab with the construction of underlayer, same construction thickness is the bed course of d around pile crown,
Bed course is constructed around pile body with 45 degree of inclination angles at pile crown;
(3) pile crown amputation:Pile crown is amputated to structure base slab lower surface absolute altitude at D/4, and waterproof construction and cleaning basic unit,
By basic unit's debris, dust, lime-ash, clean up, basic unit's acceptance(check);
(4) Slab Waterproof Construction:The construction of bottom waterproof is carried out before concreting, waterproof material thickness is h;
(5) assembling reinforcement:Binding structure baseplate reinforcing bar, by the Reinforcement at resistance to plucking pile head and structure base slab cage bar with
The mode of welding is connected;
(6) concreting:Pour to form a unified concrete jointly by rest is located around structure base slab and pile crown
Overall, the concrete poured below structure base slab lower surface absolute altitude is highly exactly D.
2. the construction method of the waterproof connecting structure of foundation ditch uplift pile as claimed in claim 1 and structure base slab, its feature exists
In:Step 2) in, a diameter of D of uplift pile is set, cushion thickness is d, and waterproof material thickness is h, digs deep degree and isNamely tiltedly dig to below structure base slab lower surface absolute altitudePlace, takes during construction
It is integer, the side of the face tiltedly dug out as rounding stage body.
3. the construction method of the waterproof connecting structure of foundation ditch uplift pile as claimed in claim 1 and structure base slab, its feature exists
In:Step 3) in, the waterproof at pile crown is constructed around pile body with 45 ° of inclination angles.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710060574.1A CN106884436B (en) | 2017-01-25 | 2017-01-25 | A kind of construction method of the waterproof connecting structure of foundation pit uplift pile and structure base slab |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201710060574.1A CN106884436B (en) | 2017-01-25 | 2017-01-25 | A kind of construction method of the waterproof connecting structure of foundation pit uplift pile and structure base slab |
Publications (2)
Publication Number | Publication Date |
---|---|
CN106884436A true CN106884436A (en) | 2017-06-23 |
CN106884436B CN106884436B (en) | 2019-08-27 |
Family
ID=59176090
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201710060574.1A Active CN106884436B (en) | 2017-01-25 | 2017-01-25 | A kind of construction method of the waterproof connecting structure of foundation pit uplift pile and structure base slab |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN106884436B (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108517898A (en) * | 2018-03-26 | 2018-09-11 | 中交路桥北方工程有限公司 | The construction method of uplift pile and bottom plate seam crossing waterproof construction |
CN108560611A (en) * | 2018-01-19 | 2018-09-21 | 江苏沪武建设集团有限公司 | A kind of basement tilts the float anchor structure after resetting leveling and construction method |
CN112575820A (en) * | 2020-12-16 | 2021-03-30 | 中建三局第一建设工程有限责任公司 | Construction structure and method for waterproof joints of steel pipe column and bottom plate of coastal deep foundation pit |
CN113931213A (en) * | 2021-10-19 | 2022-01-14 | 济南市规划设计研究院 | Pile foundation flexible connection node only used for uplift resistance and construction method |
Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004308330A (en) * | 2003-04-09 | 2004-11-04 | Nippon Steel Corp | High floor type steel structure foundation beam structure |
CN102493472A (en) * | 2011-12-13 | 2012-06-13 | 中交第二公路工程局有限公司 | Deepwater soft soil foundation reverse construction method low pile cap composite foundation construction process for bridge |
CN203256816U (en) * | 2013-04-08 | 2013-10-30 | 中国建筑第七工程局有限公司 | Pile foundation bottom plate pile head waterproof structure |
CN103953054A (en) * | 2014-04-01 | 2014-07-30 | 中铁大桥局集团第一工程有限公司 | Dry-sealed concrete pile foundation for protecting pile head reinforcement and construction method thereof |
-
2017
- 2017-01-25 CN CN201710060574.1A patent/CN106884436B/en active Active
Patent Citations (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JP2004308330A (en) * | 2003-04-09 | 2004-11-04 | Nippon Steel Corp | High floor type steel structure foundation beam structure |
CN102493472A (en) * | 2011-12-13 | 2012-06-13 | 中交第二公路工程局有限公司 | Deepwater soft soil foundation reverse construction method low pile cap composite foundation construction process for bridge |
CN203256816U (en) * | 2013-04-08 | 2013-10-30 | 中国建筑第七工程局有限公司 | Pile foundation bottom plate pile head waterproof structure |
CN103953054A (en) * | 2014-04-01 | 2014-07-30 | 中铁大桥局集团第一工程有限公司 | Dry-sealed concrete pile foundation for protecting pile head reinforcement and construction method thereof |
Non-Patent Citations (1)
Title |
---|
关文俊: "论灌注桩桩头与地下室底板连接部位的防水处理", 《科技情报开发与经济》 * |
Cited By (7)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN108560611A (en) * | 2018-01-19 | 2018-09-21 | 江苏沪武建设集团有限公司 | A kind of basement tilts the float anchor structure after resetting leveling and construction method |
CN108560611B (en) * | 2018-01-19 | 2020-07-14 | 江苏沪武建设集团有限公司 | Anchoring structure for basement after inclined floating, resetting and leveling and construction method |
CN108517898A (en) * | 2018-03-26 | 2018-09-11 | 中交路桥北方工程有限公司 | The construction method of uplift pile and bottom plate seam crossing waterproof construction |
CN108517898B (en) * | 2018-03-26 | 2019-09-13 | 中交路桥北方工程有限公司 | The construction method of uplift pile and bottom plate seam crossing waterproof construction |
CN112575820A (en) * | 2020-12-16 | 2021-03-30 | 中建三局第一建设工程有限责任公司 | Construction structure and method for waterproof joints of steel pipe column and bottom plate of coastal deep foundation pit |
CN113931213A (en) * | 2021-10-19 | 2022-01-14 | 济南市规划设计研究院 | Pile foundation flexible connection node only used for uplift resistance and construction method |
CN113931213B (en) * | 2021-10-19 | 2022-12-27 | 济南市规划设计研究院 | Pile foundation flexible connection node only used for uplift resistance and construction method |
Also Published As
Publication number | Publication date |
---|---|
CN106884436B (en) | 2019-08-27 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206768880U (en) | A kind of waterproof construction for seashore pipe gallery | |
CN104153400B (en) | A kind of construction method of soft foundation pouring pile head waterproof | |
CN106884436A (en) | A kind of construction method of the waterproof connecting structure of foundation ditch uplift pile and structure base slab | |
CN107059946A (en) | A kind of basement drain plate and its construction | |
CN110004991B (en) | Underground structure anti-floating system based on convex wing foot plate and construction method | |
CN207775948U (en) | Pulling-Resistant Anchor Rod root waterproofing node structure | |
CN104264700A (en) | Seepage prevention construction method for light-weight precipitation well point post-cast strip of underground construction | |
CN104652495B (en) | Internal support of foundation pit column and base plate node waterproof construction technology | |
CN108547260A (en) | A kind of full library basin Anti-seeping technology structure of karst area and construction method | |
CN108517898A (en) | The construction method of uplift pile and bottom plate seam crossing waterproof construction | |
CN106193644B (en) | Basement reconstruction structure with raft foundation building | |
CN105178364B (en) | Underground building light precipitation well point post-cast strip anti-seepage construction method | |
CN103572786A (en) | Pile head joint waterproof processing device and construction method thereof | |
CN203229927U (en) | Treatment structure for dam body upstream face superficial layer temperature crack | |
CN204174629U (en) | A kind of light-duty precipitation well point ater-casting, underground building multi-way prevention plugging structure | |
CN205874851U (en) | Ballastless track roadbed structure is made up with stake raft with section to flexible stake | |
CN108867709A (en) | A kind of waterproofing for basement method | |
CN210712891U (en) | Underground engineering deep well precipitation wellhead plugging structure | |
CN204370463U (en) | Ultra-soft cob brick loose tool assists suspended deck structure | |
CN103498476B (en) | Major-diameter hole-forming pile pier foundation and net foundation slab reverse building construction method | |
CN209760313U (en) | Underground totally-enclosed pile head waterproof structure | |
CN208455573U (en) | A kind of full library basin Anti-seeping technology structure of karst area | |
CN207092154U (en) | A kind of basement drain plate | |
CN106758682B (en) | A kind of ecology wooden footway structure and its technique | |
CN106869412B (en) | A kind of device for preventing pitched roof waterproof roll and its upper structural layer from falling off |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |