CN103498476B - Major-diameter hole-forming pile pier foundation and net foundation slab reverse building construction method - Google Patents

Major-diameter hole-forming pile pier foundation and net foundation slab reverse building construction method Download PDF

Info

Publication number
CN103498476B
CN103498476B CN201310476802.5A CN201310476802A CN103498476B CN 103498476 B CN103498476 B CN 103498476B CN 201310476802 A CN201310476802 A CN 201310476802A CN 103498476 B CN103498476 B CN 103498476B
Authority
CN
China
Prior art keywords
pier
concrete
foundation
hole
construction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN201310476802.5A
Other languages
Chinese (zh)
Other versions
CN103498476A (en
Inventor
成军
周炳高
江海燕
季豪
周波
邵小锋
黄坤坤
葛佳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
HAOJIA HENGYE CONSTRUCTION DEVELOPMENT Co Ltd
JIANGSU TONGZHOU FORTH CONSTRUCTION GROUP CO Ltd
Nantong University
Original Assignee
Haojia Hengye Construction Development Co ltd
JIANGSU TONGZHOU FOURTH CONSTRUCTION GROUP CO Ltd
Nantong University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Haojia Hengye Construction Development Co ltd, JIANGSU TONGZHOU FOURTH CONSTRUCTION GROUP CO Ltd, Nantong University filed Critical Haojia Hengye Construction Development Co ltd
Priority to CN201310476802.5A priority Critical patent/CN103498476B/en
Publication of CN103498476A publication Critical patent/CN103498476A/en
Application granted granted Critical
Publication of CN103498476B publication Critical patent/CN103498476B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Bridges Or Land Bridges (AREA)
  • Foundations (AREA)

Abstract

The invention discloses a major-diameter hole-forming pile pier foundation and net foundation slab reverse building construction method. The method comprises the steps of earth excavating, foundation slab pouring, pier position cave reserving, waterstop installing, pier foundation constructing, pier foundation waterproof treatment and the like. By means of the method, construction is convenient, and the construction effect is good. The stability of pile legs is guaranteed through the self-weight of a net foundation slab, and the stability of a foundation pit support is guaranteed through a support inner brace. The processing technique is advanced, and the method is safe, reliable, obvious in economic benefit and social benefit and worth popularizing and applying.

Description

Major diameter drilling pile pier foundation and netted sole plate reversed construction method
Technical field
The present invention relates to a kind of major diameter drilling pile pier foundation and netted sole plate reversed construction method.
Background technology
In deep foundation pit of tall buildings work progress at some with major diameter drilling pile pier foundation; often can run into the design alteration that basement structure level is added or embedded depth of foundation is deepened; if the change of this type occurs in foundation pit supporting system constructed after; can be because of the further intensification of design elevation at the bottom of major diameter pier foundation; and causing supporting depth requirements also to be deepened thereupon, original support system cannot meet supporting requirement.If rethink construction supporting system, certainly will cause larger economic loss and construction delay to engineering, even take some strengthening measures also to have larger difficulty on former supporting basis, and may not necessarily ensure long-term supporting effect, how the appropriate problem of handling this pattern foundation pit supporting structure in particular cases well has just become a difficult problem in engineering construction.
Summary of the invention
The object of the present invention is to provide a kind of easy construction, the major diameter drilling pile pier foundation that construction effect is good and netted sole plate reversed construction method.
Technical solution of the present invention is:
A kind of major diameter drilling pile pier foundation and netted sole plate reversed construction method, is characterized in that: comprise the following steps:
(1) soil excavation
(1) soil excavation requires machinery to be once excavated to the above 20mm of back-plane design absolute altitude place, manually repair and dig to design elevation, after completing, check of foundation subsoil carries out immediately building of bed course, waterproof roll and netted underplate concrete, shorten as far as possible drying in the air the groove time of foundation ditch, discharge and reduce because of dry in the air resistance to shear of soil that groove overlong time causes of foundation ditch preventing, or rainwater soaks the impact that the special circumstances such as foundation ditch cause support system, thereby ensure the stability of support system;
(2) carry out the drainage works that falls of foundation ditch when soil excavation, foundation ditch base arranges gutter and sump, to prevent that rainwater from soaking foundation ditch and causing the destruction to support system;
(2) build sole plate
(1) must be ferreted out+1.0m absolute altitude control line on wall, post reinforcing bar, and draw upper red triangle with red paint and make marks, scene has level gauge, to sump absolute altitude priority control, so that levelling is at any time grasped absolute altitude dynamic;
(2), in the time building sole plate concrete in mass, take balance pouring at reserved opening, from bottom to top, vibration compacting;
(3) concrete surface makes real after rubbing and pressure with wood float, then uses plasterer's trowel press polish, ensures surperficial compactness and fineness, slows down concrete surface dehydrating speed, prevents surface checking; After the press polish of surface, after slightly due-in water, cover layer of plastic film in time at concrete surface, additional two-layer exhausted combustion straw screen or mat quilt, prevents the appearance in crack;
(3) hole, pier position is stayed and is established and waterstop setting
(1) in the time of construction of bottom plates, first on foundation pad, adopt transit setting-out to go out pile pier bit position, then to prop with the framed pile pier position opening mould plate of reserving of customization, exact position the final location of finally checking template are fixing again, accurate to ensure pier position;
(2) before sole plate is built, together with adopting with pier foundation hole seam at base plate steel plate water stopper with together with the double-deck waterproof of rubber swelling sealing rod
(3) after reserved pier position hole place form removable, residual concrete and scum silica frost on cleaning tape edge and reinforcing bar in time, carry out interface waterproof roll protection work, and interface concrete surface is picked and cuts a hole into pitted skin, have an effective adhesive when ensureing the follow-up concreting in pile pier position;
(4) pile pier foundation construction
(1) before pile foundation construction, adopt transit to carry out setting-out by design pier position, ensure that pile pier position is accurate, and guarantee that spot face position and the biased difference of design pier are not more than 5cm;
(2) before construction, establish gutter, collecting well in pier mouth surrounding, prevent that surface water from entering in hole; Dun Kou goes along with sb. to guard him than the high 30cm in ground, prevents that soil, stone, foreign material from rolling in hole and hurting sb.'s feelings; Employing interval, Wa Dun hole borehole method, influences each other while avoiding constructing, keeps the stable of the pier hole wall soil body;
(3) pier hole excavation adopts merogenesis shoveling method, artificial hand-held pneumatic pick or pick successively merogenesis excavation and retaining wall from top to bottom, and every joint cutting depth is 0.5m to 1m; In the time that rock in pier must bursting work, adopt short hole blasting method, borehole depth is no more than 0.4m at hard formation, and incompetent bed is no more than 0.8m; Explosion adopts specialized team, and near borehole, adds strong supporting, prevents shock collapse Dun Bi;
(4) while lifting means being installed, make wire rope center and the pier axially bored line position consistency of well-bucket, rough control central line during as shoveling; On every joint retaining wall, establish cross control point, ceiling hammer does center line, determines pier footpath with horizontal rod;
(5) retaining wall adopts inner bearing type template, external tooth type concrete guard wall, breast wall concrete job mix machine mix, and diesel dumper transport, steel tumbling barrel enters mould, and internal vibration rod is made firm by ramming; In breast wall concrete, mix accelerating admixture, dado template is removed after 24h; Borehole reaches after projected depth, notifies in time the department such as management, design to carry out an acceptance inspection, qualified rear rapid back cover;
(6) reinforcing cage adopts tower crane whole once to lift hand-hole in place, and when lifting, Heave Here is located at and strengthens stirrup position, hangs directly to hold up surely, aims at pier hole and slowly sinks, and avoids colliding Dun Bi, and hoisted in position deviation is not more than 5cm; The topping of cage of reinforcement, by penetrate center drilling on spiral bar, the circular C30 cement mortar bedding block of thick 5cm ensures, mortar piece is by vertically establishing together every 2m, often penetrates 6 layouts along circumference together;
(7) concrete adopts commercial concrete, concrete delivery truck transport, and with the perfusion of deceleration tumbling barrel, tumbling barrel bottom is not more than 2m with pier inner bottom part or concrete surface height; After pore-forming, pour into immediately pier shaft concrete, and the same day disposable completing; The method of taking continuous stratification perfusion, layering to vibrate, every layer of influx height must not exceed 1.5m, and the every layer of thickness that vibrates must not exceed 0.5m; It is real that concrete adopts perfusion limit, internal vibration rod limit to insert, to ensure concrete compactness; Pier top concrete is smeared and is flattened before initial set, and surface will cut to ensure to be connected well with top pier cap if any laitance layer;
(5) pier foundation waterproofing work
After pile pier place cushion construction completes, be subsidy construction waterproof roll, reinforcing bar and steel pipe adopt welding steel waterproof through base plate place, and waterproof roll paving is on waterproof steel plate, and waterproof steel plate root on steel pipe and reinforcing bar is sticked on one deck enhancement Layer.
Easy construction of the present invention, construction effect is good; By netted base plate, deadweight has ensured the stable of footing part, and has doubled as one supporting inner support and ensured the stability of pattern foundation pit supporting structure.Technology advanced person, safe and reliable, economic benefit and social benefit are obvious, are worthy of popularization.
Below in conjunction with embodiment, the invention will be further described.
Detailed description of the invention
A kind of major diameter drilling pile pier foundation and netted sole plate reversed construction method, comprise the following steps:
(1) soil excavation
(1) soil excavation requires machinery to be once excavated to the above 20mm of back-plane design absolute altitude place, manually repair and dig to design elevation, after completing, check of foundation subsoil carries out immediately building of bed course, waterproof roll and netted underplate concrete, shorten as far as possible drying in the air the groove time of foundation ditch, discharge and reduce because of dry in the air resistance to shear of soil that groove overlong time causes of foundation ditch preventing, or rainwater soaks the impact that the special circumstances such as foundation ditch cause support system, thereby ensure the stability of support system;
(2) carry out the drainage works that falls of foundation ditch when soil excavation, foundation ditch base arranges gutter and sump, to prevent that rainwater from soaking foundation ditch and causing the destruction to support system;
(2) build sole plate
(1) must be ferreted out+1.0m absolute altitude control line on wall, post reinforcing bar, and draw upper red triangle with red paint and make marks, scene has level gauge, to sump absolute altitude priority control, so that levelling is at any time grasped absolute altitude dynamic;
(2), in the time building sole plate concrete in mass, take balance pouring at reserved opening, from bottom to top, vibration compacting;
(3) concrete surface makes real after rubbing and pressure with wood float, then uses plasterer's trowel press polish, ensures surperficial compactness and fineness, slows down concrete surface dehydrating speed, prevents surface checking; After the press polish of surface, after slightly due-in water, cover layer of plastic film in time at concrete surface, additional two-layer exhausted combustion straw screen or mat quilt, prevents the appearance in crack;
(3) hole, pier position is stayed and is established and waterstop setting
(1) in the time of construction of bottom plates, first on foundation pad, adopt transit setting-out to go out pile pier bit position, then to prop with the framed pile pier position opening mould plate of reserving of customization, exact position the final location of finally checking template are fixing again, accurate to ensure pier position;
(2) before sole plate is built, together with adopting with pier foundation hole seam at base plate steel plate water stopper with together with the double-deck waterproof of rubber swelling sealing rod
(3) after reserved pier position hole place form removable, residual concrete and scum silica frost on cleaning tape edge and reinforcing bar in time, carry out interface waterproof roll protection work, and interface concrete surface is picked and cuts a hole into pitted skin, have an effective adhesive when ensureing the follow-up concreting in pile pier position;
(4) pile pier foundation construction
(1) before pile foundation construction, adopt transit to carry out setting-out by design pier position, ensure that pile pier position is accurate, and guarantee that spot face position and the biased difference of design pier are not more than 5cm;
(2) before construction, establish gutter, collecting well in pier mouth surrounding, prevent that surface water from entering in hole; Dun Kou goes along with sb. to guard him than the high 30cm in ground, prevents that soil, stone, foreign material from rolling in hole and hurting sb.'s feelings; Employing interval, Wa Dun hole borehole method, influences each other while avoiding constructing, keeps the stable of the pier hole wall soil body;
(3) pier hole excavation adopts merogenesis shoveling method, artificial hand-held pneumatic pick or pick successively merogenesis excavation and retaining wall from top to bottom, and every joint cutting depth is 0.5m to 1m; In the time that rock in pier must bursting work, adopt short hole blasting method, borehole depth is no more than 0.4m at hard formation, and incompetent bed is no more than 0.8m; Explosion adopts specialized team, and near borehole, adds strong supporting, prevents shock collapse Dun Bi;
(4) while lifting means being installed, make wire rope center and the pier axially bored line position consistency of well-bucket, rough control central line during as shoveling; On every joint retaining wall, establish cross control point, ceiling hammer does center line, determines pier footpath with horizontal rod;
(5) retaining wall adopts inner bearing type template, external tooth type concrete guard wall, breast wall concrete job mix machine mix, and diesel dumper transport, steel tumbling barrel enters mould, and internal vibration rod is made firm by ramming; In breast wall concrete, mix accelerating admixture, dado template is removed after 24h; Borehole reaches after projected depth, notifies in time the department such as management, design to carry out an acceptance inspection, qualified rear rapid back cover;
(6) reinforcing cage adopts tower crane whole once to lift hand-hole in place, and when lifting, Heave Here is located at and strengthens stirrup position, hangs directly to hold up surely, aims at pier hole and slowly sinks, and avoids colliding Dun Bi, and hoisted in position deviation is not more than 5cm; The topping of cage of reinforcement, by penetrate center drilling on spiral bar, the circular C30 cement mortar bedding block of thick 5cm ensures, mortar piece is by vertically establishing together every 2m, often penetrates 6 layouts along circumference together;
(7) concrete adopts commercial concrete, concrete delivery truck transport, and with the perfusion of deceleration tumbling barrel, tumbling barrel bottom is not more than 2m with pier inner bottom part or concrete surface height; After pore-forming, pour into immediately pier shaft concrete, and the same day disposable completing; The method of taking continuous stratification perfusion, layering to vibrate, every layer of influx height must not exceed 1.5m, and the every layer of thickness that vibrates must not exceed 0.5m; It is real that concrete adopts perfusion limit, internal vibration rod limit to insert, to ensure concrete compactness; Pier top concrete is smeared and is flattened before initial set, and surface will cut to ensure to be connected well with top pier cap if any laitance layer;
(5) pier foundation waterproofing work
After pile pier place cushion construction completes, be subsidy construction waterproof roll, reinforcing bar and steel pipe adopt welding steel waterproof through base plate place, and waterproof roll paving is on waterproof steel plate, and waterproof steel plate root on steel pipe and reinforcing bar is sticked on one deck enhancement Layer.

Claims (1)

1. major diameter drilling pile pier foundation and a netted sole plate reversed construction method, is characterized in that: comprise the following steps:
(1) soil excavation
(1) soil excavation requires machinery to be once excavated to the above 20mm of back-plane design absolute altitude place, manually repaiies and digs to design elevation, carries out immediately building of bed course, waterproof roll and netted underplate concrete after check of foundation subsoil completes;
(2) carry out the drainage works that falls of foundation ditch when soil excavation, foundation ditch base arranges gutter and sump, to prevent that rainwater from soaking foundation ditch and causing the destruction to support system;
(2) build sole plate
(1) must be ferreted out+1.0m absolute altitude control line on wall, post reinforcing bar, and draw upper red triangle with red paint and make marks, scene has level gauge, to sump absolute altitude priority control, so that levelling is at any time grasped absolute altitude dynamic;
(2), in the time building sole plate concrete in mass, take balance pouring at reserved opening, from bottom to top, vibration compacting;
(3) concrete surface makes real after rubbing and pressure with wood float, then uses plasterer's trowel press polish, ensures surperficial compactness and fineness, slows down concrete surface dehydrating speed, prevents surface checking; After the press polish of surface, after slightly due-in water, cover layer of plastic film in time at concrete surface, additional two-layer exhausted combustion straw screen or mat quilt, prevents the appearance in crack;
(3) hole, pier position is stayed and is established and waterstop setting
(1) in the time of construction of bottom plates, first on foundation pad, adopt transit setting-out to go out pile pier bit position, then to prop with the framed pile pier position opening mould plate of reserving of customization, exact position the final location of finally checking template are fixing again, accurate to ensure pier position;
(2) before sole plate is built, together with adopting with pier foundation hole seam at base plate steel plate water stopper with together with the double-deck waterproof of rubber swelling sealing rod;
(3) after reserved pier position hole place form removable, residual concrete and scum silica frost on cleaning tape edge and reinforcing bar in time, carry out interface waterproof roll protection work, and interface concrete surface is picked and cuts a hole into pitted skin, have an effective adhesive when ensureing the follow-up concreting in pile pier position;
(4) pile pier foundation construction
(1) before pile foundation construction, adopt transit to carry out setting-out by design pier position, ensure that pile pier position is accurate, and guarantee that spot face position and the biased difference of design pier are not more than 5cm;
(2) before construction, establish gutter, collecting well in pier mouth surrounding, prevent that surface water from entering in hole; Dun Kou goes along with sb. to guard him than the high 30cm in ground, prevents that soil, stone, foreign material from rolling in hole and hurting sb.'s feelings; Employing interval, Wa Dun hole borehole method, influences each other while avoiding constructing, keeps the stable of the pier hole wall soil body;
(3) pier hole excavation adopts merogenesis shoveling method, artificial hand-held pneumatic pick or pick successively merogenesis excavation and retaining wall from top to bottom, and every joint cutting depth is 0.5m to 1m; In the time that rock in pier must bursting work, adopt short hole blasting method, borehole depth is no more than 0.4m at hard formation, and incompetent bed is no more than 0.8m; Explosion adopts specialized team, and near borehole, adds strong supporting, prevents shock collapse Dun Bi;
(4) while lifting means being installed, make wire rope center and the pier axially bored line position consistency of well-bucket, rough control central line during as shoveling; On every joint retaining wall, establish cross control point, ceiling hammer does center line, determines pier footpath with horizontal rod;
(5) retaining wall adopts inner bearing type template, external tooth type concrete guard wall, breast wall concrete job mix machine mix, and diesel dumper transport, steel tumbling barrel enters mould, and internal vibration rod is made firm by ramming; In breast wall concrete, mix accelerating admixture, dado template is removed after 24h; Borehole reaches after projected depth, notifies in time the department such as management, design to carry out an acceptance inspection, qualified rear rapid back cover;
(6) reinforcing cage adopts tower crane whole once to lift hand-hole in place, and when lifting, Heave Here is located at and strengthens stirrup position, hangs directly to hold up surely, aims at pier hole and slowly sinks, and avoids colliding Dun Bi, and hoisted in position deviation is not more than 5cm; The topping of cage of reinforcement, by penetrate center drilling on spiral bar, the circular C30 cement mortar bedding block of thick 5cm ensures, mortar piece is by vertically establishing together every 2m, often penetrates 6 layouts along circumference together;
(7) concrete adopts commercial concrete, concrete delivery truck transport, and with the perfusion of deceleration tumbling barrel, tumbling barrel bottom is not more than 2m with pier inner bottom part or concrete surface height; After pore-forming, pour into immediately pier shaft concrete, and the same day disposable completing; The method of taking continuous stratification perfusion, layering to vibrate, every layer of influx height must not exceed 1.5m, and the every layer of thickness that vibrates must not exceed 0.5m; It is real that concrete adopts perfusion limit, internal vibration rod limit to insert, to ensure concrete compactness; Pier top concrete is smeared and is flattened before initial set, and surface will cut to ensure to be connected well with top pier cap if any laitance layer;
(5) pier foundation waterproofing work
After pile pier place cushion construction completes, be subsidy construction waterproof roll, reinforcing bar and steel pipe adopt welding steel waterproof through base plate place, and waterproof roll paving is on waterproof steel plate, and waterproof steel plate root on steel pipe and reinforcing bar is sticked on one deck enhancement Layer.
CN201310476802.5A 2013-10-14 2013-10-14 Major-diameter hole-forming pile pier foundation and net foundation slab reverse building construction method Expired - Fee Related CN103498476B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201310476802.5A CN103498476B (en) 2013-10-14 2013-10-14 Major-diameter hole-forming pile pier foundation and net foundation slab reverse building construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201310476802.5A CN103498476B (en) 2013-10-14 2013-10-14 Major-diameter hole-forming pile pier foundation and net foundation slab reverse building construction method

Publications (2)

Publication Number Publication Date
CN103498476A CN103498476A (en) 2014-01-08
CN103498476B true CN103498476B (en) 2014-09-10

Family

ID=49863726

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201310476802.5A Expired - Fee Related CN103498476B (en) 2013-10-14 2013-10-14 Major-diameter hole-forming pile pier foundation and net foundation slab reverse building construction method

Country Status (1)

Country Link
CN (1) CN103498476B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN103967015B (en) * 2014-05-21 2016-04-27 刘绍国 A kind of water seal for deep foundation pit excavation method and structure thereof
CN115559299A (en) * 2022-11-23 2023-01-03 中交第一航务工程局有限公司 Pre-hole forming method for foundation concrete cushion pile foundation

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100775767B1 (en) * 2006-08-14 2007-11-12 깨뱉시스템주식회사 Top-down method using the vertical steel bar for the src column
CN101538867A (en) * 2009-02-25 2009-09-23 叶长青 Long-short pile composite foundation top-down construction method
CN201901876U (en) * 2010-12-23 2011-07-20 东南大学 Steel sheet pile inversely-constructed foundation ditch supporting structure
CN102425184A (en) * 2011-12-13 2012-04-25 中交第二公路工程局有限公司 Cap preserved hole construction method for deep-water soft soil foundation reverse low pile cap composite foundation

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR100775767B1 (en) * 2006-08-14 2007-11-12 깨뱉시스템주식회사 Top-down method using the vertical steel bar for the src column
CN101538867A (en) * 2009-02-25 2009-09-23 叶长青 Long-short pile composite foundation top-down construction method
CN201901876U (en) * 2010-12-23 2011-07-20 东南大学 Steel sheet pile inversely-constructed foundation ditch supporting structure
CN102425184A (en) * 2011-12-13 2012-04-25 中交第二公路工程局有限公司 Cap preserved hole construction method for deep-water soft soil foundation reverse low pile cap composite foundation

Also Published As

Publication number Publication date
CN103498476A (en) 2014-01-08

Similar Documents

Publication Publication Date Title
CN102444142B (en) Pile group column replacement expanded basement and construction method of same
CN111733837B (en) Rock slope filling and sealing protection system and construction method
CN104532957B (en) Existing building sets up basement reversed construction method
CN101446088A (en) Construction method for pole and tower foundation in Gobi Desert gravelly soil area
CN106760620A (en) A kind of utilization open caisson increases the construction method for building the underground space under existing building
CN105369826A (en) Basement bearing platform side mold construction method
CN107675704A (en) A kind of artificial digging pile assembled retaining wall and its construction technology
CN107326928A (en) A kind of part is related to the construction method in the deeper subsurface garage of basement
CN108301440A (en) With waterproof, the underground pipe gallery construction method of drain function
CN107100164A (en) A kind of long auger guncreting pile construction method
CN102071698A (en) Construction method of beddings of foundation downward overturn beam and pile cap
CN109706952A (en) Large-scale well-sinking construction method
CN104652495B (en) Internal support of foundation pit column and base plate node waterproof construction technology
CN105862897B (en) Sandy Silt ground shallow foundation original groove pouring construction engineering method
CN107964977A (en) The composite foundation and its construction method of a kind of karst landform
CN103498476B (en) Major-diameter hole-forming pile pier foundation and net foundation slab reverse building construction method
CN106884436A (en) A kind of construction method of the waterproof connecting structure of foundation ditch uplift pile and structure base slab
CN105332386B (en) Structure construction method for tower crane foundation serving as basement bottom plate
CN103469828A (en) Construction method of hydrophobic structure of post-cast strip of bottom plate of basement
CN107299640A (en) A kind of variable cross-section well shaft type ground continuous wall base and its construction method
CN108661087A (en) The waterproof construction and construction method of tower crane in a kind of basement bottom board
CN209293068U (en) A kind of open trench tunnel falsework system
Grigor'ev et al. Reasons for Deformation and Failure of the Structural Units of an Apartment Building on a Slopeside Site.
CN207331699U (en) Pit-in-pit reinforced concrete retaining wall composite supporting structure
CN101205722B (en) Integral rapid construction method for earthwork, ground mould and pile of manhole pile multi-pile cap

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
ASS Succession or assignment of patent right

Owner name: HAOJIA HENGYE CONSTRUCTION DEVELOPMENT CO., LTD. J

Effective date: 20140730

Owner name: NANTONG UNIVERSITY

Free format text: FORMER OWNER: CHENG JUN

Effective date: 20140730

C41 Transfer of patent application or patent right or utility model
C53 Correction of patent of invention or patent application
CB03 Change of inventor or designer information

Inventor after: Cheng Jun

Inventor after: Zhou Binggao

Inventor after: Jiang Haiyan

Inventor after: Ji Hao

Inventor after: Zhou Bo

Inventor after: Shao Xiaofeng

Inventor after: Huang Kunkun

Inventor after: Ge Jia

Inventor before: Cheng Jun

COR Change of bibliographic data

Free format text: CORRECT: INVENTOR; FROM: CHENG JUN TO: CHENG JUN ZHOU BINGGAO JIANG HAIYAN JI HAO ZHOU BO SHAO XIAOFENG HUANG KUNKUN GE JIA

Free format text: CORRECT: ADDRESS; FROM: 226300 NANTONG, JIANGSU PROVINCE TO: 226019 NANTONG, JIANGSU PROVINCE

TA01 Transfer of patent application right

Effective date of registration: 20140730

Address after: 226019 Jiangsu city of Nantong province sik Road No. 9

Applicant after: Nantong University

Applicant after: HAOJIA HENGYE CONSTRUCTION DEVELOPMENT CO., LTD.

Applicant after: Jiangsu Tongzhou Forth Construction Group Co., Ltd.

Address before: Tongzhou District Xingyuan road Jiangsu city of Nantong province sunshine mansion 226300 Building No. 63 room 2208

Applicant before: Cheng Jun

C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20140910

Termination date: 20161014

CF01 Termination of patent right due to non-payment of annual fee