CN101205722B - Integral rapid construction method for earthwork, ground mould and pile of manhole pile multi-pile cap - Google Patents

Integral rapid construction method for earthwork, ground mould and pile of manhole pile multi-pile cap Download PDF

Info

Publication number
CN101205722B
CN101205722B CN200610157672A CN200610157672A CN101205722B CN 101205722 B CN101205722 B CN 101205722B CN 200610157672 A CN200610157672 A CN 200610157672A CN 200610157672 A CN200610157672 A CN 200610157672A CN 101205722 B CN101205722 B CN 101205722B
Authority
CN
China
Prior art keywords
stake
construction
pile
cushion cap
earthwork
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Expired - Fee Related
Application number
CN200610157672A
Other languages
Chinese (zh)
Other versions
CN101205722A (en
Inventor
郑鸿彰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN200610157672A priority Critical patent/CN101205722B/en
Publication of CN101205722A publication Critical patent/CN101205722A/en
Application granted granted Critical
Publication of CN101205722B publication Critical patent/CN101205722B/en
Expired - Fee Related legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Abstract

The invention relates to an integrated quick construction method of an earthwork, an earth formwork and a pile for a multi-pile cap of a man-hole pile. After a foundation pit is dug, the pile cap earthwork is dug to near a preset pile cap soil-layer height mark according to the shape and the position of the preset pile cap to form a pile cap pit, then the construction of the man-hole pile and the construction of the pile cap earth formwork are made. By that the earthwork in the pile cap is directly dug during the construction of the earthwork in the foundation pit, the construction of the pile cap earth formwork can be made during or around the construction of the pile, thereby being capable of shortening the time limit of the construction. The preset pile cap soil-layer height mark accessory is directly dug during the construction of the earthwork, thereby avoiding the longer hollow pile concrete protection wall existing in the prior art, reducing the waste of the resource, and reducing the pollution to the natural environment.

Description

The earthwork of the many pile framings of manhole stake, topotype and the integrated rapid constructing method of stake
Technical field
The present invention relates to the job practices of the earthwork of many pile caps, topotype and the stake integrated construction of hand excavated pile in a kind of construction work, to accelerate construction progress.
Background technology
In construction work, common design has many pile caps according to the cushion cap stressing conditions.Many pile caps described in the present invention are meant the same load cushion cap that needs many (containing two) hand excavated pile together support, below abbreviate many pile caps as cushion cap.As shown in Figure 1, 2, 3, traditional job practices generally includes following construction sequence when this cushion cap of construction:
1, in foundation ditch 111, digs out the pile driving construction operating surface 101 that satisfies predetermined manhole pile driving construction, on absolute altitude, often do not distinguish the inside and outside stake of cushion cap this moment;
2, subregion or whole unwrapping wire, test the construction of carrying out stake behind the position of line justification stake, comprise and dig in the manhole stake cubic metre of earth, reinforcing bar 109 in pile wall 104 constructions, colligation stake, build a core concrete 103, stake core concrete curing, generally do not distinguish the stake or the stake of many pile caps of single pile cushion cap this moment, do not distinguish the inside and outside stake of cushion cap yet, may construct simultaneously;
3, after pile driving construction was finished, detection, data, the stake of carrying out stake checked and accepted etc., and so far pile driving construction team can withdraw from, structure construction team admission digging structure base plate, grade beam and the cushion cap earthwork, and excavate empty stake concrete dado 105;
4, carry out the construction of cushion cap topotype etc. again, comprise 113 constructions of side stock mould, the side stock mould may also be plastered with cement mortar, also comprises with concrete or with the cement mortar foot mat of constructing;
5 and carry out the construction of concrete bed course 107, grade beam, structure base plate and cushion cap concrete 112 etc.
Existing construction method has many negative effects to the construction in many pile framings:
Operation planar 102 height when the operating surface 101 during 1, because of pile driving construction is constructed than cushion cap foot mat, stake core concrete 103 is lower, thereby can form long empty concrete dado 105, cause the wasting of resources, and the empty concrete dado of excavating, chiseling out pollutes the environment also.
2, when carrying out the construction of concrete bed course, grade beam, cushion cap topotype etc., under the dark again little situation of foundation ditch, because in the cushion cap cubic metre of earth, the topotype engineering quantity is relatively large and can not be corrupted to the finished products of having finished such as stake, thereby make and get off or excavate all inconveniences of construction passage.
3, after pile driving construction is finished, before the cushion cap earthwork construction, wait pile driving construction team and structure construction team join good after, during pile driving construction the water around the manhole stake of precipitation might again go up, be unfavorable for the construction of the cushion cap earthwork, topotype etc.
Summary of the invention
The technical problem to be solved in the present invention is, at the defective of the above-mentioned existence of prior art, provides the earthwork, topotype and the incorporate rapid constructing method of stake of the many pile caps of manhole stake, to shorten construction period, to reduce the wasting of resources.
The technical solution adopted for the present invention to solve the technical problems is: the earthwork, topotype and the incorporate rapid constructing method of stake of the many pile caps of a kind of manhole stake are set, it is characterized in that, comprise following construction sequence:
S1, earthwork construction is carried out S2 near the default absolute altitude in cushion cap top in foundation ditch;
The cushion cap earthwork is excavated near the default absolute altitude of cushion cap soil layer in the shape and the position of S2, the default cushion cap of basis,
S3 and S4 are carried out in formation cushion cap hole;
S3, determine manhole stake stake position in the cushion cap, carry out the manhole pile driving construction;
S4, construction cushion cap soil put in place, carry out the construction of cushion cap topotype.
In the earthwork, topotype and the integrated rapid constructing method of stake of the many pile framings of manhole stake of the present invention, after carrying out S1, dig the side gully on default cushion cap side.
In the earthwork, topotype and the incorporate rapid constructing method of stake of the many pile caps of manhole stake of the present invention, described S3 may further comprise the steps:
S3.1a, after carrying out S2, determine manhole stake stake position in the cushion cap, according in the stake of default manhole stake size construction manhole cubic metre of earth, and satisfy the up big and down small or diameter of epimerite retaining wall and save the construction requirement of retaining wall greater than next;
S3.1b, the good reinforcing bar of colligation, a pile wall mould waters the pile wall concrete, finishes the pile wall construction, wherein adopts anastrophe or increasing epimerite pile wall diameter to construct when construction epimerite pile wall.
In the earthwork, topotype and the incorporate rapid constructing method of stake of the many pile caps of manhole stake of the present invention, described S3 may further comprise the steps:
S3.2a, after carrying out S2, determine manhole stake stake position in the cushion cap, according to the earthwork in the stake of default manhole stake size construction manhole;
S3.2b, finish the construction before the maintenance;
S3.2c, be bundled in the lateral wall at pile wall top with the soft thing that do not seep water, the storage chamber that forms upper end open at stake core concrete top carries out the maintenance of stake.
In the earthwork, topotype and the incorporate rapid constructing method of stake of the many pile caps of manhole stake of the present invention, described S3 may further comprise the steps:
S3.3a, after carrying out S2, determine manhole stake stake position in the cushion cap, according to the earthwork in the stake of default manhole stake size construction manhole;
S3.3b, finish the construction of a core concrete before building, water a core concrete to default absolute altitude following near;
S3.3c, ride over the inside wall at pile wall top, form the cavity of upper end open building a core concrete top, continue to build a core concrete to default absolute altitude building a core concrete top with the soft thing that do not seep water,
The soft thing that do not seep water is pressed between the inside wall and stake core concrete that is clipped in the pile wall top, and the storage chamber that forms upper end open at stake core concrete top carries out the maintenance of stake.
In the earthwork, topotype and the integrated rapid constructing method of stake of the many pile framings of manhole stake of the present invention, after carrying out S2, in described cushion cap hole, set up to carry out the operating platform of pile driving construction, carry out again S3.
Implement the earthwork, topotype and the integrated rapid constructing method of stake of the many pile framings of manhole stake of the present invention, has following beneficial effect: by when earthwork construction digs out foundation ditch, shape and position thereof according to the many pile framings of manhole stake in the foundation structure, directly excavate near the cushion cap soil layer absolute altitude that the earthwork is extremely preset in the cushion cap, formation cushion cap hole, so that earthmoving machinery construction one-time-reach-place, the inconvenience that has brought when having avoided after pile driving construction is complete, also needing in the prior art again to carry out the earthmoving machinery construction; Can no longer establish and excavate the required construction passage of earthwork construction; Do not need in earthwork construction to worry that mechanical execution can destroy the finished products such as completed manhole stake, thereby can accelerate the earthwork construction process; When pile driving construction, also can carry out the construction of cushion cap topotype, avoid in the stake of rainy region manhole that precipitation gos up to the negative effect of cushion cap topotype construction, thereby shorten the relevant construction period.In addition, because earthwork construction directly digs near the default cushion cap soil layer absolute altitude, thereby avoided the long empty stake concrete dado that exists in the prior art, reduced the waste of resource, and reduced the pollution to natural environment.
Description of drawings
The invention will be further described below in conjunction with drawings and Examples, in the accompanying drawing:
Fig. 1 is the construction process figure of the many pile framings of manhole stake in the prior art;
Fig. 2 is the schematic diagram that carries out the manhole stake in the prior art;
Fig. 3 is the schematic diagram of the many pile caps of manhole stake in the prior art;
Fig. 4 is the flow chart of the earthwork, topotype and the incorporate rapid constructing method preferred embodiment of stake of the many pile caps of manhole stake of the present invention;
Fig. 5 is the schematic diagram of the earthwork, topotype and the stake of the many pile framings of manhole stake of the present invention;
Fig. 6 is the soft thing that do not seep water of the present invention forms storage chamber at pile wall lateral wall place a flow chart;
Fig. 7 is the soft thing that do not seep water of the present invention forms storage chamber at pile wall lateral wall place a schematic diagram;
Fig. 8 is the soft thing that do not seep water of the present invention forms storage chamber at pile wall inside wall place a flow chart;
Fig. 9 is the soft thing that do not seep water of the present invention forms storage chamber at pile wall inside wall place a schematic diagram.
The specific embodiment
As shown in Figure 1, 2, 3, before carrying out the many pile cap constructions of manhole stake, in foundation ditch 111, carry out earthwork construction earlier in the prior art, construct out and satisfy the pile driving construction operating surface 101 of predetermined manhole pile driving construction, as shown in Figure 2, often not distinguishing stake this moment is stake or cushion cap stud in the cushion cap.Rezone or whole unwrapping wire, test the construction of carrying out stake behind the position of line justification stake, comprise and digging in the manhole stake cubic metre of earth, carry out pile wall 104 constructions, colligation stake core reinforcing bar is built a core concrete 103 and is carried out a maintenance of core concrete.After treating that the inside and outside pile driving construction of cushion cap is all finished, pile driving construction team withdraws from, the admission of structure construction team.As shown in Figure 3, dig earlier cushion cap etc. cubic metre of earth and construction this moment except empty stake concrete dado 105, carry out again the construction of cushion cap topotype, and carry out the reinforced concretes constructions such as structure base slab 107, cushion cap, finish whole construction.
The many pile framings of manhole stake of the present invention the earthwork, topotype and the stake integrated rapid constructing method preferred embodiment in, shown in Fig. 4,5, may further comprise the steps: S1 presets near the absolute altitude 201, such as the step 210 among Fig. 4 on earthwork construction to cushion cap top in foundation ditch; S2 is according to shape and the position of default cushion cap, excavate the cushion cap earthwork near the default absolute altitude of cushion cap soil layer, form cushion cap hole 221, such as the step 220 among Fig. 4, this cushion cap was cheated for 221 ends and is tried one's best construction near this suspended deck structure concrete bed course 203, and satisfied the construction requirement of manhole stake 204, cushion cap topotype 205; S3 determines 204 positions of manhole stake and carries out pile driving construction, such as the step 230 among Fig. 4; S4 construction bearing platform soil puts in place, carries out 205 constructions of cushion cap topotype, such as the step 240 among Fig. 4.Wherein, according to the different different arrangement and method for construction of determining stake, topotype, earthwork, draining of rain, water and cushion cap topotype 205 etc., thereby safety, fast finish the earthwork, with the integrated construction of topotype.
According to various actual conditions in the foundation ditch, the Specific construction schemes under different situations such as the below earthwork of the many pile framings of specific descriptions manhole stake of the present invention, topotype and the integrated rapid constructing method king-pile of stake, topotype, the earthwork, draining:
Orient earlier near the absolute altitude of the base plate earthwork construction default cushion cap according to designing requirement, carry out earthwork construction according to this absolute altitude, form foundation ditch 219.According to various actual conditions in the foundation ditch 219, as whether rainy season, the underground water depth, what, cushion cap position, size, the depth, the constructure scheme of stake in tight, rational, the feasible cushion cap earthwork of numerous factor establishments, cap mold, the cushion caps such as the stake core concrete depth.
When the cushion cap earthwork construction, rain in the sky, underground water are very big to its construction infection.Saturating the adverse effect analysis of rainwater, select safety, rationally effective arrangement and method for construction.The construction of the cushion cap earthwork can be according to on-the-spot and Construction Plan unified construction, but also subregion or single cushion cap are constructed.If rainwater is few, or when having no adverse effect, when cushion cap top earthwork construction after the condition that satisfies the construction bottom cushion cap earthwork, according to construction plan, the outer shoveling of Accurate Determining cap mold plan-position.Select suitable shoveling to put the gradient, appropriate to the occasion the digging under the cushion cap foot mat of cutting the earth according to pile construction needs in the depth of cushion cap, soil property quality, the cushion cap.
Owing to mainly be that stake is stressed in the cushion cap, thereby cubic metre of earth can suitably the backbreaking of at the bottom of the cushion cap topotype and cushion cap side, be fit to come operation with machinery.Do not backbreak or owe to dig be not can not, just workman's the spirit of bearing hardships may be worse and worse, and is more by manually being unfavorable for rapid construction.After cutting the earth, machinery determines whether earlier to rebuild with manually going according to cushion cap topotype and pile construction plan and shaping situation.If construction bearing platform stake behind the first construction bearing platform mould, then rationally use is artificial, and finishing cushion cap side soil, subsoil can utilize machinery that unnecessary soil is dug and transport to the predetermined position of constructing.If the stake in the construction cushion cap is earlier cut the earth minimum normal, the safe construction that guarantees stake just, standard can be higher better certain.And in the prior art, by the time pile driving construction is when carrying out the excavation of the cushion cap earthwork again after finishing, mechanical work is not too convenient, and this preferred embodiment adopts the mechanical work more can the reduction of erection time by contrast, to reach the purpose of rapid construction.
Will take into full account problem rainproof, draining if rain digs on the cushion cap more, if the underground water height, water percolating capacity is big, also to solve earlier fall, drainage problem.If disorderly dig by force, especially more deeply, bigger cushion cap, to add soil property more bad, many unthinkable not good things all might take place.So top rain is many, rain is big, want significant care careful to native construction of cushion cap when the high water percolating capacity of following water level is big.
Because rainwater is bigger than other position impact to the relevant construction in the cushion cap, when doing the anti-draining of bearing platform construction, must comprehensively consider.Take full advantage of the inside and outside facility system of foundation ditch mutually support, cooperate, with prevent in rational cost, the careful solution cushion cap, fall, the problem of draining, guarantee in the cushion cap cubic metre of earth and other easy construction, safety, fast, specifically can be with reference to following description:
To rainwater, at first should dam outside foundation ditch, prevent from entering in the hole as far as possible.To cushion cap, in construction foundation pit more than the stake operating surface cubic metre of earth the time, can dig temporarily in the part cushion cap and to be temporarily falling of constructing of pit earthwork, gully.But in case near construction (or local construction) stake operation or when in the foundation ditch, if will be conscientiously according to soil property situation in the cushion cap when continuing in the construction bearing platform soil, the problems such as the depth whether continue to establish within it with fall temporarily, gully.Because rainwater has uncertainty, do not rain then fall temporarily, gully generally can be anhydrous, when guaranteed, can dig earlier in the cushion cap cubic metre of earth to put in place.But it is a plurality of that perhaps cushion cap has, and do not have also reality not necessarily of rain when digging in the cushion cap soil at every turn.So dig should prevent to rain the negative effect of soil in the cushion cap, get lodged in possible rainwater outside the cushion cap and do not have negative effect place as far as possible as far as possible to soil construction in the cushion cap.Even want with low advantage in the cushion cap, wait otherwise this cushion cap in wouldn't construct, or construction to possess safe be used as fall, in the condition of gully.
Relatively good anti-, the row of rainwater, and underground water is just very complicated.If there is foundation ditch water-stop curtain interception water effect better, water level is easy to fall, and difficulty is little.If effect is not so good, that also can be pretty troublesome.This trouble not only affects integrated relevant construction in the cushion cap, also affects the later on construction of suspended deck structure, and the scheme of safe and feasible must be arranged for this reason.The method of precipitation is diversified, to the manhole stake and Yan Youduo self precipitation method of stake.The cushion cap king-pile is many, digs to reduce that its water level can be selected in only not too tight in the pile driving construction duration or be a selection by other lower.The general pile driving construction duration is more anxious, and multiple other method is preferably arranged.Such as: if the cushion cap area occupied is big, the precipitation of can in cushion cap, digging pit earlier, but secondary not in place or three times are once fallen.So not only fallen water in the cushion cap, but also dug cushion cap soil, but will note the negative effect to cushion cap limit mould soil stabilization, then should not do like this (scope that especially may produce stream mud, quicksand) bigger than normal.
In many to rainwater, big, groundwater table height, the many ground of infiltration, to cushion cap fall, before draining not only will consider construction, also to consider construction after.If cushion cap bottom application worker's catch pit can ensure from now on suspended deck structure construction and quality safety then solution at the bottom of cushion cap.If water is many, big, or repair for being preferably in the cushion cap limit for the purpose of bearing platform construction safety, the architecture quality that special use is fallen, catch pit 206, step 215 as shown in Figure 4.Cushion cap is little, shallow can be a little close to the cushion cap; Deeply can far, catchmenting in the cushion cap be pumped out in hole or pipe laying introducing gully greatly.If this class catch pit is outlying or on the cushion cap limit from cushion cap, can dig out ditch during the earthwork of construction cushion cap, well location comes, and is convenient to the back and uses manpower less, also calculate and cubic metre of earth once survive! Construction cushion cap limit special use is fallen, catch pit 206 digs out ditch, will note not influencing the construction of subsequent handling when well location comes, and fully take into account the negative effect of rainwater, can delay by normal construction if condition such as rainwater is too big too much is bad.If dig out ditch, well location, this position can not be located at has negative effect place to structure: as rain etc. should consider earlier to dig out ditch, well is constructed.Fall, the pipe trench of gully 206 to hang down some guarantee cushion caps at the bottom of water can normally discharge.This pipe trench can also can use suitable tubing with brick, and assurance water can normally be discharged and be got final product.Special use is fallen, gully 206 is generally used brick masonry, neglect greatly well depth shallow, need displacement and decide.Special use is fallen, gully 206 construction should be before the construction of cushion cap side form or in the construction, like this before the pile driving construction special use of just constructing after good fall, perhaps gully 206 can be that pile driving construction falls, draining.
After finishing the interior earthwork construction of cushion cap, put, confirmed 204 positions of manhole stake, carry out pile construction in the cushion cap by the corresponding requirements of pile driving construction again, cap mold is afterwards only constructed otherwise affecting pile construction safety all can construct with pile driving construction while or front and back at any time with construction.Because the earthwork has been dug to default cushion cap bottom in this moment cushion cap, save empty stake construction partly long in the prior art, save resource and reduced impact to construction environment.
But this moment, the safety problem of manhole pile driving construction was relatively protruded, safety does not have the what is said or talked about of guarantee, and what is all meaningless, mainly contain which potential safety hazard after changing so, how to solve? the one, the impact of raining or seeping water, can be collected in water in the cushion cap hole and drain in the low hole, also can establish at pile lining and bury vent 218, specially arrange this type of rainwater, to get rid of rainy or to seep water to the impact of manhole pile driving construction.The 2nd, the next door has foreign matter to roll in the stake to hurt sb.'s feelings easily, can strengthen increasing stake mouthful protection, prevents that the foreign matter next door from rolling into.The 3rd, propose the negative effect of native machine: a kind of situation be stake less, cushion cap is shallow, carry native machine normally proposes the soil operation in a high position; thereby but can depress like this cushion cap limit soil or press construction safety in the quick-fried cushion cap brick side form impact stake; but Adopts measure has: add the pressure that cushion cap limit soil or brick side form are dissolved in the lumps of wood, plank or support etc. under the native machine carrying, or the mould or strengthen the early strong intensity of its mortar etc. of early laying bricks.Its another kind of situation is that cushion cap is dark, stake is many, carries native machine and can't directly carry soil for the stake that has, and can place in cushion cap this moment for carrying native machine, carries out secondary or repeatedly hang upside down muck haulage; Also can carry the satisfied construction of native machine needs by special longwell.No matter the cushion cap depth, stake what, relatively the safe course is erection construction operating platform in cushion cap, height is almost high with the operating surface on cushion cap top.This operating platform is solid and reliable, satisfies, the safe construction of related personnel, equipment during convenient construction.The method of setting up this operating platform has multiple choices.As processing, set up special operating platform; Also can utilize existence conditions, realize the safe construction operating platform such as erecting scaffold, boarding, make the pressure of carrying native machine by scaffold or at the bottom of importing cushion cap into, or keep clear of the cushion cap limit, thereby dissolve the pressure of cushion cap limit soil or brick side form.
For the rainwater of cushion cap hole top margin, can cheat the article such as the sclerosis of top margin construction cushion coat or laying waterproof cloth at cushion cap and come rainwater-proof or the downslide of anti-limit thing to flow in the stake.
The stake top construction of stake in the cushion cap can be constructed with reference to old law, and also can put in place in safety, the guaranteed condition of quality is constructed into the cushion cap stake that meets design, code requirement to the stake top next time.Because complexity, the quality of workers of pile driving construction are uneven, there is polytropy in stake core concrete laitance, guarantee that it is inconvenient that an every pile head of core concrete laitance is all handled well.In order to increase the safety stock of pile crown; can be when construction stake epimerite retaining wall 211; take inverted job practices; promptly at construction retaining wall mould or when processing special-purpose retaining wall mould; make big mouthful 212 last; osculum 213 is down, even possible some deficiency of stake core concrete top quality so also can have not big harm to superstructure.This joint of constructing will be put earlier line during retaining wall well and confirms, digs to repair a limit soil and will put in place, will become when retaining wall reinforcement fabrication, colligation to meet the demands thereupon, props up afterwards the retaining wall mould rear construction retaining wall concrete that meets the demands, and finishes the construction of this joint retaining wall.Be also noted that in addition this joint retaining wall since big mouthful 212 upper, osculum 213 can produce the connectivity problem that saves up and down retaining wall lower, thus the perpendicular muscle of retaining wall to control well with lower joint retaining wall rationally, safety is connected; To make its bottom concrete not affect the construction of next joint retaining wall concrete when building an epimerite pile wall concrete.For head it off can strengthen epimerite pile wall 211 diameters or base diameter; Perhaps when next the joint pile wall that is connected with the epimerite retaining wall carries out the concrete construction, water thinner; Perhaps should save pile wall and epimerite stake bottom retaining wall together carries out concrete and builds.
There is not empty retaining wall in the method for above-mentioned pile driving construction, and maintenance is carried out in an inconvenient retaining after the construction of a stake core concrete like this, this moment can pile crown place can suction thing, frequent water seasoning; Also can realize the water storing conservation on stake concrete top at easy water-storing device of stake concrete top construction, this simple and easy water storing conservation device can place in the pile wall or outward, seep water less or not, but one or many uses, have certain retaining satisfy function then can, shown in Fig. 6,7,8,9.This water-storing device can arrange with the soft thing 214 that do not seep water, and this soft thing 214 can be with disposable, cheaply when pile wall 208 interior the setting, such as plastics Bao Mo etc.; This soft thing 214 can adopt when pile wall 208 outer the setting and can repeatedly use, the rational material of cost, such as waterproof cloth, paulin etc.When this soft thing 214 places in the pile wall 208, place the concrete that waters behind the pile wall inner edge quilt to press soft thing 214 bottoms watering a core top concrete 216 before, top can be satisfied the water storing conservation requirement and then can.When requirement places pile wall 208 outer, place tied the pressing less or not in pile wall outside to seep water watering stake core concrete 209 rear lowers, top can be satisfied the water storing conservation requirement and then can.Because soft thing is difficult for supporting oneself, can borrow stake core reinforced frame upright.
Specifically be provided with shown in Fig. 7,9, described storage chamber can be provided with in the following manner: with the soft thing 214 that do not seep water, be bundled in the lateral wall at pile wall 208 tops as oilcloth etc., form the storage chamber 217 of upper end open at stake core concrete 209 tops, the pile construction method of this moment is as shown in Figure 6: S3.2a determines manhole stake stake position in the cushion cap, dig top in the manhole stake according to the default manhole stake size and the degree of depth, as the step 234 among Fig. 6; S3.2b finishes the construction before the default stake core concrete curing, comprises reinforcing bar in construction stake retaining wall, the colligation stake, builds a core concrete etc., as step 235 among Fig. 6; S3.2c uses the soft thing that do not seep water to be bundled in the lateral wall at pile wall top, and the storage chamber that forms upper end open at stake core concrete top carries out the maintenance of stake, as step 236 among Fig. 6.The lower end of the soft thing that do not seep water can also be attached to the inside wall at pile wall 208 tops, carry out a core concrete 209 constructions again, the soft thing that do not seep water is ridden between the inside wall and stake core concrete 209 at pile wall 208 tops, thereby form the storage chamber of upper end open at stake core concrete 209 tops, as Fig. 8, shown in 9, thereby there is water just can guarantee the normal maintenance of a core concrete 209 in the storage chamber as long as guarantee, avoided continually stake core concrete 209 being watered, the pile driving construction flow process as shown in Figure 8 at this moment: S3.3a determines manhole stake stake position in the cushion cap, dig the earthwork in the manhole stake according to the default manhole stake size and the degree of depth, as the step 237 among Fig. 8; S3.3b finishes the construction of a default stake core concrete before building, and comprises reinforcing bar in construction stake retaining wall, the colligation stake, builds a core concrete etc., water again concrete in the pile wall to default absolute altitude following near, as the step 238 among Fig. 8; S3.3c is attached to the inside wall at pile wall top with the soft thing that do not seep water, building a cavity of core concrete top formation upper end open, continuation is built a core concrete to default absolute altitude building a core concrete top, the soft thing that do not seep water is pressed between the inside wall and stake core concrete that is clipped in the pile wall top, the storage chamber that forms upper end open at stake core concrete top carries out the maintenance of stake, as the step 239 among Fig. 8.
After pile driving construction is finished or when pile driving construction carries out or front and back, carry out the construction of cushion cap topotype, as long as this cushion cap topotype construction does not have influence on the interior pile construction of cushion cap safely, thereby avoided only having in the prior art the by the time complete rear construction that just can carry out the cushion cap earthwork and cushion cap topotype of pile driving construction, shortened the construction period.What will be clear that recognizes; an ingredient that has excavated the cushion cap earthwork and cooperated pile driving construction is just protected in the construction of cap mold in the earthwork of the many pile caps of manhole stake of the present invention, topotype and the stake integrated construction; for the duration also not on crucial or leading operation; so only otherwise influence the cushion cap earthwork and pile driving construction, early or all can late.In order to finish early the cushion cap earthwork, stake, the integrated construction of topotype can intert enforcement as early as possible, thereby provide operating surface for structure construction etc. as early as possible.
To sum up summary: in the earthwork, topotype and the incorporate rapid constructing method of stake of the many pile caps of manhole stake of the present invention, by accurate unwrapping wire, control, safety are dug the cushion cap earthwork and are put in place, satisfy the pile driving construction condition and carry out pile driving construction, according to the construction of field condition, situation decision cap mold.And according to season situation, condition such as rainwater, underground water and field engineering geology do preventive action.In guaranteeing cushion cap, construct safe the time, can set up the safe construction operating platform as the case may be, wait the problem such as safe, convenient of construction as solve stake in the cushion cap with the scaffold power transmission.In safety, satisfy and finish fast the cushion cap earthwork, topotype and the integrated construction of stake under the prerequisite of relevant criterion, requirement.

Claims (6)

1. the earthwork of the many pile caps of manhole stake, topotype and the incorporate rapid constructing method of stake is characterized in that, comprise following construction sequence:
S1, earthwork construction is carried out S2 near the default absolute altitude in cushion cap top in foundation ditch;
The cushion cap earthwork is excavated near the default absolute altitude of cushion cap soil layer in shape and the position of S2, the default cushion cap of basis, forms the cushion cap hole, execution S3 and S4;
S3, determine manhole stake stake position in the cushion cap, carry out the manhole pile driving construction;
S4, construction cushion cap soil put in place, carry out the construction of cushion cap topotype.
2. according to the earthwork, topotype and the integrated rapid constructing method of stake of the many pile framings of the described manhole stake of claim 1, it is characterized in that, after carrying out S1, dig the side gully on default cushion cap side.
3. according to the earthwork, topotype and the incorporate rapid constructing method of stake of the many pile caps of the described manhole stake of claim 1, it is characterized in that described S3 may further comprise the steps:
S3.1a, after carrying out S2, determine manhole stake stake position in the cushion cap, according in the stake of default manhole stake size construction manhole cubic metre of earth, and satisfy the up big and down small or diameter of epimerite pile wall and save the construction requirement of retaining wall greater than next;
S3.1b, the good reinforcing bar of colligation, a pile wall mould waters the pile wall concrete, finishes the pile wall construction, wherein adopts anastrophe or increasing epimerite pile wall diameter to construct when construction epimerite pile wall.
4. according to the earthwork, topotype and the incorporate rapid constructing method of stake of the many pile caps of the described manhole stake of claim 1, it is characterized in that described S3 may further comprise the steps:
S3.2a, after carrying out S2, determine manhole stake stake position in the cushion cap, according to the earthwork in the stake of default manhole stake size construction manhole;
S3.2b, finish the construction before the maintenance;
S3.2c, be bundled in the lateral wall at pile wall top with the soft thing that do not seep water, the storage chamber that forms upper end open at stake core concrete top carries out the maintenance of stake.
5. according to the earthwork, topotype and the incorporate rapid constructing method of stake of the many pile caps of the described manhole stake of claim 1, it is characterized in that described S3 may further comprise the steps:
S3.3a, after carrying out S2, determine manhole stake stake position in the cushion cap, according to the earthwork in the stake of default manhole stake size construction manhole;
S3.3b, finish the construction of a core concrete before building, water a core concrete to default absolute altitude following near;
S3.3c, ride over the inside wall at pile wall top with the soft thing that do not seep water, building a cavity of core concrete top formation upper end open, continuation is built a core concrete to default absolute altitude building a core concrete top, the soft thing that do not seep water is pressed between the inside wall and stake core concrete that is clipped in the pile wall top, and the storage chamber that forms upper end open at stake core concrete top carries out the maintenance of stake.
6. according to the earthwork, topotype and the incorporate rapid constructing method of stake of the many pile caps of the described manhole stake of claim 1, it is characterized in that, after carrying out S2, in described cushion cap hole, set up the operating platform that is used for carrying out pile driving construction, carry out S3 again.
CN200610157672A 2006-12-18 2006-12-18 Integral rapid construction method for earthwork, ground mould and pile of manhole pile multi-pile cap Expired - Fee Related CN101205722B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN200610157672A CN101205722B (en) 2006-12-18 2006-12-18 Integral rapid construction method for earthwork, ground mould and pile of manhole pile multi-pile cap

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN200610157672A CN101205722B (en) 2006-12-18 2006-12-18 Integral rapid construction method for earthwork, ground mould and pile of manhole pile multi-pile cap

Publications (2)

Publication Number Publication Date
CN101205722A CN101205722A (en) 2008-06-25
CN101205722B true CN101205722B (en) 2010-05-19

Family

ID=39566184

Family Applications (1)

Application Number Title Priority Date Filing Date
CN200610157672A Expired - Fee Related CN101205722B (en) 2006-12-18 2006-12-18 Integral rapid construction method for earthwork, ground mould and pile of manhole pile multi-pile cap

Country Status (1)

Country Link
CN (1) CN101205722B (en)

Families Citing this family (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN101787701B (en) * 2010-03-16 2013-07-31 标力建设集团有限公司 Construction method for supporting pine pile in elevator shaft foundation pit
CN102995644B (en) * 2011-09-13 2016-03-30 中国二十冶集团有限公司 What Whirlwind tank connect rock section goes along with sb. to guard him enclosed construction
CN104074199B (en) * 2014-06-17 2017-02-08 杭州华能工程安全科技股份有限公司 Underwater bearing platform construction method
CN106087991B (en) * 2016-06-17 2018-07-31 中国建筑第八工程局有限公司 Stake top absolute altitude is in natural ground dug pile construction method below

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1807771A (en) * 2006-01-27 2006-07-26 郑鸿彰 Foundation pit earthwork and support integrated construction method
CN1807766A (en) * 2006-01-26 2006-07-26 郑鸿彰 Pile head and bearing stand integrated construction method
CN1807774A (en) * 2006-01-26 2006-07-26 郑鸿彰 Foundation and pile foundation integrated construction method

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1807766A (en) * 2006-01-26 2006-07-26 郑鸿彰 Pile head and bearing stand integrated construction method
CN1807774A (en) * 2006-01-26 2006-07-26 郑鸿彰 Foundation and pile foundation integrated construction method
CN1807771A (en) * 2006-01-27 2006-07-26 郑鸿彰 Foundation pit earthwork and support integrated construction method

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
JP昭57-193626A 1982.11.29
JP特开2003-278160A 2003.10.02
JP特开平5-9928A 1993.01.19

Also Published As

Publication number Publication date
CN101205722A (en) 2008-06-25

Similar Documents

Publication Publication Date Title
CN102444142B (en) Pile group column replacement expanded basement and construction method of same
CN110984999B (en) Tunnel shaft construction method
CN110778328B (en) Loess tunnel entrance section construction method for passing through landslide body
CN107938683A (en) One kind tilts pile pit supporting construction and its construction method
CN110438999A (en) A kind of deep basal pit slope excavation construction method of rich groundwater
CN109797769A (en) A kind of Collapsible Loess District underground pipe gallery foundation structure and its construction method
CN107675704A (en) A kind of artificial digging pile assembled retaining wall and its construction technology
CN110042842A (en) A kind of open cut construction method of deep foundation ditch for wearing river
CN101205722B (en) Integral rapid construction method for earthwork, ground mould and pile of manhole pile multi-pile cap
CN109706952A (en) Large-scale well-sinking construction method
CN109403350A (en) Foundation pit supporting construction and foundation pit supporting method
CN112695763A (en) Deep sludge stratum foundation pit excavation method
CN103334450B (en) Construction method of pile precast slab retaining wall with drainage ditch
CN107700497A (en) A kind of building basement pattern foundation pit supporting structure and earth excavation construction method
CN110397050A (en) A kind of light-duty draining barricade of novel beam anchor formula and its construction method
CN100443673C (en) Method of construction
CN113431097A (en) Protection structure of shallow foundation building next to deep foundation pit engineering and construction method
CN204919566U (en) Soft soil area tower crane foundation construction supporting construction
CN110725323A (en) Foundation pit supporting structure and construction method
KR20020022446A (en) Repairing method of earth-fill dam
CN110080234A (en) A method of it is excavated in the secondary central island of deep foundation pit of soft soil foundation
CN212026135U (en) Slope protection structure of waterfront footpath
CN211815253U (en) Cutting slope toe beam plate type reinforced structure
KR101525942B1 (en) Method for slope reinforcement construction using the ground improvement product
CN209482313U (en) Foundation pit supporting construction

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
C14 Grant of patent or utility model
GR01 Patent grant
CF01 Termination of patent right due to non-payment of annual fee
CF01 Termination of patent right due to non-payment of annual fee

Granted publication date: 20100519

Termination date: 20211218