CN107700497A - A kind of building basement pattern foundation pit supporting structure and earth excavation construction method - Google Patents

A kind of building basement pattern foundation pit supporting structure and earth excavation construction method Download PDF

Info

Publication number
CN107700497A
CN107700497A CN201710915861.6A CN201710915861A CN107700497A CN 107700497 A CN107700497 A CN 107700497A CN 201710915861 A CN201710915861 A CN 201710915861A CN 107700497 A CN107700497 A CN 107700497A
Authority
CN
China
Prior art keywords
water
construction
foundation pit
foundation ditch
basement
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201710915861.6A
Other languages
Chinese (zh)
Inventor
欧阳子雄
陈文伟
何兆强
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Panyu District Guangzhou Fifth Construction Engineering Co
Original Assignee
Panyu District Guangzhou Fifth Construction Engineering Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Panyu District Guangzhou Fifth Construction Engineering Co filed Critical Panyu District Guangzhou Fifth Construction Engineering Co
Priority to CN201710915861.6A priority Critical patent/CN107700497A/en
Publication of CN107700497A publication Critical patent/CN107700497A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/40Miscellaneous comprising stabilising elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The present invention relates to a kind of building basement pattern foundation pit supporting structure and earth excavation construction method, comprise the following steps:S1:Place is levelling, and sideline, construction axis, mixing pile stake position are put in side;S2:Mixing pile construction;S3:Prestressing pipe pile construction;S4:Foundation ditch top row water system;S5:Excavate the earthwork;S6:Bottom of foundation ditch drainage system is set.Sealing or draining device, such as water-stop curtain, sump are provided with because building is provided in below underground water, therefore in foundation ditch the week side of boss;Allow the obstruction of surface water, dash coagulation soil matrix mainly is set on side slope top, top of the slope is slightly higher, allows surface water to be discharged in the gutter beyond foundation ditch, while cure process is done on top of the slope ground, prevents surface water and rainwater from penetrating into side slope retaining wall;Temporary drain and sump then are set by design requirement along foundation ditch surrounding in foundation ditch, drain the water of foundation ditch in time;Avoid the structural strength of surface water or influence on groundwater foundation ditch.

Description

A kind of building basement pattern foundation pit supporting structure and earth excavation construction method
Technical field
The present invention relates to a kind of construction techniques, more particularly to a kind of building basement pattern foundation pit supporting structure is applied with earth excavation Work method.
Background technology
With the popularization of the Larger Engineering Projects with basement, pattern foundation pit supporting structure is with earth excavation special construction plan in band Have in the Larger Engineering Projects of basement and play an important role.
If certain engineering project B1 is 6628 square metres, 11 layers are shared on the ground, area is 46720 square metres, extrusion Using PHC-AB500 type hammer blow tubular piles;Deep Foundation Pit soil layer from top to bottom sequentially includes:Artificial earth fill (thickness 2.8-3.4m), Muck soil (thickness 2.2-5.5m);The underground water in place is pore ground water, mainly by Atmospheric precipitation and water-bearing layer side seepage Supply, groundwater level is higher, and nearer apart from earth's surface, if building structure may result in into foundation ditch above underground water It is unstable;If by building structure below underground water, underground water it is long-term wash away under, still can influence the structure of building Intensity.
Here, we provide and a kind of alleviate shadow of the underground water to building foundation pit by the way of cement mixing pile is kept out Ring.
The content of the invention
It is an object of the invention to provide one kind to build underground pile base construction method.
The present invention above-mentioned technical purpose technical scheme is that:A kind of building basement foundation ditch branch Shield and earth excavation construction method, comprise the following steps:
S1:Place is levelling, and sideline, construction axis, mixing pile stake position are put in side;
S2:Mixing pile construction;
S3:Prestressing pipe pile construction;
S4:Foundation ditch top row water system
S5:Excavate the earthwork;
S6:Bottom of foundation ditch drainage system is set.
As preferred, the S2 comprises the following steps:
S21:Fixed, core stake position;
S22:Telephone-moving aligns;
S23:Prepare cement mortar;
S24:Whitewashing stirring is sunk;
S25:Whitewashing stirring lifting;
S26:Repeat whitewashing stirring and sink down into an end;
S27:Repeat whitewashing stirring lifting;
S28:Stop starching;
S29:Stirring-head is lifted to earth's surface;
S30:Stake processed terminates, and moves to next position.
As preferred, the cement mortar prepared in the S23 include the Portland cement that strength grade is 32.5R and Water, ratio of mud 0.45-0.5.
As preferred, the S5 comprises the following steps:
S51:The earthwork is successively excavated to basement bottom board bottom, deep 4m;
S52:Excavate cushion cap position, deep 1.5m;
S53:Excavate elevator position, deep 2m;
S54:Basement bottom board absolute altitude is backfilled to after completing elevator, cushion cap and central pile bearing platform construction;
S55:Basement edge cushion cap local excavation, deep 1m;
S56:Basement bottom board absolute altitude is backfilled to after completing bearing platform construction;
S57:Basement bottom board is constructed;
S58:Foundation pit construction terminates.
As preferred, the S4 comprises the following steps:
S41:Build intercepting ditch in hole top periphery;
S42:Foundation ditch top periphery sets water-stop curtain;
Wherein, timely pump drainage hole internal water accumulation, base are answered after hole top periphery build intercepting ditch, every layer of earth excavation before excavation of foundation pit Hole is overall when being excavated to basement bottom board, and sump is set by spacing 35-40m, and the pump drainage that will catchment is discharged into after precipitation to intercepting ditch Municipal sewer.
Preferably, before S1 construction, wide 0.9-1.0m is cleared up according to design, deep 1-2m construction guide groove, Exclude the underground obstacle in the boundary of works area that the enclosure of construction guide groove is formed.
Formed preferably, water-stop curtain is set up by cement mixing method, the long 500-650mm of stake diameter, the lap of splice is 130-150mm, a length of 8-10m of stake.
Preferably, being provided with clasp between adjacent cement mixing method, the clasp is included from soil cement Mixing pile side wall stretches out the arc hasp to be formed and the rubber water-proof bar that is arranged on arc hasp.
In summary, the invention has the advantages that:
(1) because building is provided in below underground water, therefore foundation ditch the week side of boss is provided with sealing or draining device, such as Water-stop curtain, sump etc.;Allow the obstruction of surface water, dash coagulation soil matrix mainly is set on side slope top, top of the slope is slightly higher, allows ground Table water is discharged in the gutter beyond foundation ditch, while cure process is done on top of the slope ground, prevents surface water and rainwater from penetrating into side slope In retaining wall;Temporary drain and sump then are set by design requirement along foundation ditch surrounding in foundation ditch, drain the water of foundation ditch in time;Keep away Exempt from the structural strength of surface water or influence on groundwater foundation ditch.
(2) water-stop curtain is spliced by some mixing piles, and cement is used as adhesive backers, within the specific limits, is added Cement in concrete is more, concrete all the more consolidation and porosity is smaller, and aperture is also smaller, and slump is low, therefore by this The mixing pile permeability rate that kind of concrete pours into is low and Stability Analysis of Structures.
(3) it is mixed into cement therein and uses the portland cement that strength grade is 32.5R, this portland cement Self structure intensity is higher, and the moisture being added thereto is less, and in the process of setting of cement, the moisture evaporation in cement is in cement Surface forms small hole;Fewer moisture is added middle to a certain degree, the hole of formation is smaller.
(4) clasp set between adjacent mixing pile is advantageous to the fixation between two mixing piles, mixing pile side wall On be provided with the hasp of arc, two neighboring mixing pile rely between hasp clamping, situations such as avoiding misplacing;And in arc Rubber water-proof bar is provided with the face that the hasp of shape mutually abuts, rubber water-proof strip adoption is hydroscopic high-molecular resin, this kind of Material water-swellable, the gap between mixing pile can be blocked by being disposed between adjacent mixing pile, be further functioned as anti- The effect of water;Secondly underground water has certain impulsive force to mixing pile, after washing away for a long time, may result in mixing pile inclination etc. The appearance of situation, but after mixing pile water-swellable, make closely to abut between mixing pile, it is had underground water stronger Resistance.
Brief description of the drawings
Fig. 1 is integral construction flow chart in embodiment;
Fig. 2 is S2 steps construction process figure in embodiment;
Fig. 3 is S4 steps construction process figure in embodiment;
Fig. 4 is clasp structural representation in embodiment;
Fig. 5 is S5 steps construction process figure in embodiment.
In figure, 11, arc hasp;12nd, rubber water-proof bar.
Embodiment
The present invention is described in further detail below in conjunction with accompanying drawing.
This specific embodiment is only explanation of the invention, and it is not limitation of the present invention, people in the art Member can make the modification of no creative contribution to the present embodiment as needed after this specification is read, but as long as at this All protected in the right of invention by Patent Law.
Embodiment:
A kind of building basement pattern foundation pit supporting structure and earth excavation construction method, as shown in figure 1, mainly including following 6 main steps Suddenly:
S1:Place is levelling, and sideline, construction axis, mixing pile stake position are put in side;
S2:Mixing pile construction;
S3:Prestressing pipe pile construction;
S4:Foundation ditch top row water system;
S5:Excavate the earthwork;
S6:Bottom of foundation ditch drainage system is set.
Before practice of construction, original situation of the road around foundation ditch before excavation, pipeline need to be investigated, be recorded; And draining, sealing and the dewatering measure of foundation ditch are carried out, in Excavation Process, foundation ditch sealing problem is kept a close eye on, is avoided out The appearance of the problems such as existing leak, infiltration and piping.
Foundation ditch sideline is determined according to design, carries out Deep Mixing Piles Construction at first;It is first along Deep Mixing Piles Construction face Clear out wide one 1m, deep 1-2m construction guide groove, the construction guide groove in the present embodiment is 1m, is construction model between guide groove of constructing Enclose, using the underground obstacle in the technologies such as infrared acquisition discharge boundary of works area, including building extrusion, stone etc., then carry out Mixing pile construction;After the completion of mixing pile, the construction in tube pile construction and gutter is proceeded by, then begins to excavation of foundation pit, until Excavation of foundation pit is completed.
As shown in Fig. 2 S2:The step of mixing pile construction, mainly includes:
S21:Fixed, core stake position;
S22:Telephone-moving aligns;
S23:Prepare cement mortar;
S24:Whitewashing stirring is sunk;
S25:Whitewashing stirring lifting;
S26:Repeat whitewashing stirring and sink down into an end;
S27:Repeat whitewashing stirring lifting;
S28:Stop starching;
S29:Stirring-head is lifted to earth's surface;
S30:Stake processed terminates, and moves to next position.
Prepare cement mortar:
Clean container is taken, adds Portland cement thereto, the strength grade of the cement is 32.5R, then is added thereto A certain amount of clear water, make mixed water in products.The ratio of mud is 0.45-0.5, and the ratio of mud in the present embodiment is 0.45;Water Mud incorporation is 80 kilograms of cement of every meter of mixing pile.
Construction machinery uses deep-layer stirring pile foundation, and drill bit uses the cross bits of φ 168 of address brill;It is well prepared in advance to stir Stake, then the setting-out on the mixing pile to be intubated are mixed, stake machine is in place afterwards, leveling, starts to punch after centering, using cement mortar conduct Pore-forming mud, squeeze into a projected depth.Finally using the hoist engine being arranged on mixing pile machine the steel tube suspendings of φ 114 processed After rising, pipe is received in into well and on the holes of φ 168 full of cement mortar, completes intubation task;Table 1 is main technique in construction Parameter.
Table 1:
Project Parameter Remarks
Subsidence velocity (m/min) 1.0~1.3 IIth, III gear
Lift speed (m/min) 0.5~0.8 Ith, II gear
Mixing speed (r/min) 30~50 Ith, II gear
Whitewashing number (secondary) 4
Stir number (secondary) 4
Grout outlet is pumped (MPa) 0.4~0.6
Cement mixed weight Every meter of stake mixes 80 kilograms
In prestressing pipe pile construction, pile tube is the concrete-pile for ensureing fabric structure intensity, is made using piling machine It is plugged in foundation ditch.
As shown in Fig. 2 S4:The step of foundation ditch top row water system, mainly includes:
S41:Build intercepting ditch in hole top periphery;
S42:Foundation ditch top periphery sets water-stop curtain.
Before excavation of foundation pit, gutter is set at top by design drawing requirement and smears pea gravel concreten shield top, prevents ground Oozed under table water and rainwater etc. washes away to excavation slope, and sedimentation basin is set;Build and cut on hole top periphery before excavation of foundation pit Ditch, after every layer of earth excavation, timely pump drainage hole internal water accumulation is answered, when foundation ditch is integrally excavated to basement bottom board, by spacing 35- 40m sets sump, and the water of sump is extracted into the gutter on hole top with suction pump, is discharged into after sedimentation basin precipitates to downcomer Road.
Gutter and sump are arranged in beyond proposed building base side clear distance 0.4m, and draining furrow rim leaves Slope Pin is no less than 0.3m.
Because foundation ditch excavation is relatively deep larger, and drawing is mostly layer of sand, is middle water penetration, water penetration is stronger, using deep water Water-stop curtain of the soil mixing pile as foundation ditch, according to soil layer property and neighbouring construction experience, using double cement mixing method, Stake footpath is 650mm, and the stake lap of splice is 150mm, and stake is long should to squeeze into the poor silty sand ground of water penetration, and 11m is most suitable.
As shown in figure 4, being provided with clasp between cement mixing method, clasp includes being arranged on Soil-cement Arc hasp 11 in stake side wall, arc hasp 11 is provided with some on cement mixing method, is provided only with the present embodiment Two, rubber water-proof bar 12 is provided with arc hasp, rubber water-proof bar 12 is made of hydroscopic high-molecular resin.When adjacent two When individual cement mixing method is set up, arc hasp 11 cooperates, and the rubber water-proof bar 12 being arranged on arc hasp mutually supports Connect, and abutting even closer after water-swellable is together, to play a part of sealing.
As shown in Fig. 2 S5:The step of excavating the earthwork mainly includes:
S51:The earthwork is successively excavated to basement bottom board bottom, deep 4m;
S52:Excavate cushion cap position, deep 1.5m;
S53:Excavate elevator position, deep 2m;
S54:Basement bottom board absolute altitude is backfilled to after completing elevator, cushion cap and central pile bearing platform construction;
S55:Basement edge cushion cap local excavation, deep 1m;
S56:Basement bottom board absolute altitude is backfilled to after completing bearing platform construction;
S57:Basement bottom board is constructed;
S58:Foundation pit construction terminates.
Stake age to be mixed, which reaches 28 days, to be started to excavate;First layer first is dug with 700 type hook machines, by 1:1 slope, first layer Cutting depth is 2m, then digs the second layer earthwork with long-armed hook machine, by 1:1 slope, excavation arrive bottom cushion bottom.30 types of cushion cap position Small hook machine is excavated, and long-armed hook machine is given in the earthwork.Earth excavation direction promotes from south to north, until excavation of foundation pit terminates.
Be unearthed ramp and the driving chute that is unearthed are reinforced with deep-mixed pile.
Earth excavation wants strict implement stage excavation, avoids sediment failure, and the position for having stake will set mark, indicate stake Position and the absolute altitude of stake, close to supporting construction and engineering pile position, it is impossible to take mechanical shoveling, should be changed to manually cut the earth.Sternly Prohibit hook machine collision engineering pile.
Elevator cushion cap base pit stand construction:After earth excavation is to bottom cushion bottom absolute altitude, held in elevator Two row's mixing piles are made a call to as supporting in platform periphery, then excavate the elevator cushion cap earthwork with small hook machine.
Dug with large-scale hook machine to predetermined absolute altitude above 30cm, the remaining earthwork is used the small-sized hook machine of hand fit instead and cut the earth;Cubic metre of earth Before excavation, ensure that mixing pile has reached intensity 70%.
It should not be collided during shoveling or injury of primary engineering pile, supporting construction, pumping equipment;Large-scale hook machine is cut the earth close to supporting Structure and engineering pile position, it is changed to the small-sized hook machine of hand fit and cuts the earth;Once occurring tilting and ftractureing, to stop excavating at once.
Water level outside supporting construction, surrounding buildings or structures, foundation ditch is observed and monitored in pit earthwork construction, is avoided There is water level beyond abnormal conditions such as warning values.
Earth excavation first selects one section exemplarily, after excavation to can ensure that deep pit monitor carries out full-face tunneling again.
In work progress, comprehensive detection should be carried out to foundation ditch, such as level of ground water, supporting construction deviational survey, top horizontal Displacement, the surface subsidence of foundation ditch surrounding, periphery town road and underground utilities etc.;So as to understand the displacement of foundation ditch, sedimentation etc. in time Situation of change, avoid the occurrence of the anomalies such as foundation ditch displacement is excessive, settling amount is excessive or pace of change is too fast.

Claims (8)

1. a kind of building basement pattern foundation pit supporting structure and earth excavation construction method, it is characterised in that comprise the following steps:
S1:Place is levelling, and sideline, construction axis, mixing pile stake position are put in side;
S2:Mixing pile construction;
S3:Prestressing pipe pile construction;
S4:Foundation ditch top row water system
S5:Excavate the earthwork;
S6:Bottom of foundation ditch drainage system is set.
2. a kind of building basement pattern foundation pit supporting structure according to claim 1 and earth excavation construction method, it is characterised in that: The S2 comprises the following steps:
S21:Fixed, core stake position;
S22:Telephone-moving aligns;
S23:Prepare cement mortar;
S24:Whitewashing stirring is sunk;
S25:Whitewashing stirring lifting;
S26:Repeat whitewashing stirring and sink down into an end;
S27:Repeat whitewashing stirring lifting;
S28:Stop starching;
S29:Stirring-head is lifted to earth's surface;
S30:Stake processed terminates, and moves to next position.
3. a kind of building basement pattern foundation pit supporting structure according to claim 2 and earth excavation construction method, it is characterised in that: The cement mortar prepared in the S23 includes the Portland cement and water that strength grade is 32.5R, ratio of mud 0.45- 0.5。
4. a kind of building basement pattern foundation pit supporting structure according to claim 1 and earth excavation construction method, it is characterised in that: The S5 comprises the following steps:
S51:The earthwork is successively excavated to basement bottom board bottom, deep 4m;
S52:Excavate cushion cap position, deep 1.5m;
S53:Excavate elevator position, deep 2m;
S54:Basement bottom board absolute altitude is backfilled to after completing elevator, cushion cap and central pile bearing platform construction;
S55:Basement edge cushion cap local excavation, deep 1m;
S56:Basement bottom board absolute altitude is backfilled to after completing bearing platform construction;
S57:Basement bottom board is constructed;
S58:Foundation pit construction terminates.
5. a kind of building basement pattern foundation pit supporting structure according to claim 1 and earth excavation construction method, it is characterised in that: The S4 comprises the following steps:
S41:Build intercepting ditch in hole top periphery;
S42:Foundation ditch top periphery sets water-stop curtain;
Wherein, timely pump drainage hole internal water accumulation, base are answered after hole top periphery build intercepting ditch, every layer of earth excavation before excavation of foundation pit Hole is overall when being excavated to basement bottom board, and sump is set by spacing 35-40m, and the pump drainage that will catchment is discharged into after precipitation to intercepting ditch Municipal sewer.
6. a kind of building basement pattern foundation pit supporting structure according to claim 1 and earth excavation construction method, it is characterised in that: Before the S1 constructions, wide 0.9-1.0m is cleared up according to design, deep 1-2m construction guide groove, excludes construction guide groove enclosure shape Into boundary of works area in underground obstacle.
7. a kind of building basement pattern foundation pit supporting structure according to claim 5 and earth excavation construction method, it is characterised in that: Water-stop curtain is set up by cement mixing method and formed, stake diameter long 500-650mm, lap of splice 130-150mm, a length of 8- of stake 10m。
8. a kind of building basement pattern foundation pit supporting structure according to claim 6 and earth excavation construction method, it is characterised in that: Clasp is provided between adjacent cement mixing method, the clasp includes stretching out from cement mixing method side wall The arc hasp of formation and the rubber water-proof bar being arranged on arc hasp.
CN201710915861.6A 2017-09-29 2017-09-29 A kind of building basement pattern foundation pit supporting structure and earth excavation construction method Pending CN107700497A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201710915861.6A CN107700497A (en) 2017-09-29 2017-09-29 A kind of building basement pattern foundation pit supporting structure and earth excavation construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201710915861.6A CN107700497A (en) 2017-09-29 2017-09-29 A kind of building basement pattern foundation pit supporting structure and earth excavation construction method

Publications (1)

Publication Number Publication Date
CN107700497A true CN107700497A (en) 2018-02-16

Family

ID=61183985

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201710915861.6A Pending CN107700497A (en) 2017-09-29 2017-09-29 A kind of building basement pattern foundation pit supporting structure and earth excavation construction method

Country Status (1)

Country Link
CN (1) CN107700497A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109056765A (en) * 2018-07-20 2018-12-21 广东建邦兴业集团有限公司 A kind of foundation ditch construction method of anti-collapse flood bubble
CN110295606A (en) * 2019-07-05 2019-10-01 广州穗岩土木科技股份有限公司 A kind of foundation pit interlocking pile water stop construction method
CN113529730A (en) * 2021-07-28 2021-10-22 中建八局天津建设工程有限公司 Construction method of foundation pit
CN113863076A (en) * 2021-09-27 2021-12-31 中国一冶集团有限公司 Construction method of sunken road under sandbar bridge

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105089061A (en) * 2015-08-11 2015-11-25 泰兴市第一建筑安装工程有限公司 Ultra-deep foundation pit supporting method
CN205224013U (en) * 2015-12-21 2016-05-11 郭永 But recovery type steel diaphragm wall

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN105089061A (en) * 2015-08-11 2015-11-25 泰兴市第一建筑安装工程有限公司 Ultra-deep foundation pit supporting method
CN205224013U (en) * 2015-12-21 2016-05-11 郭永 But recovery type steel diaphragm wall

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
中国电力企业联合会电力工程造价与定额管理总站等: "《电网工程建筑》", 31 March 2012, 中国电力出版社 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN109056765A (en) * 2018-07-20 2018-12-21 广东建邦兴业集团有限公司 A kind of foundation ditch construction method of anti-collapse flood bubble
CN110295606A (en) * 2019-07-05 2019-10-01 广州穗岩土木科技股份有限公司 A kind of foundation pit interlocking pile water stop construction method
CN113529730A (en) * 2021-07-28 2021-10-22 中建八局天津建设工程有限公司 Construction method of foundation pit
CN113863076A (en) * 2021-09-27 2021-12-31 中国一冶集团有限公司 Construction method of sunken road under sandbar bridge
CN113863076B (en) * 2021-09-27 2023-10-24 中国一冶集团有限公司 Sinking road construction method under sand bridge

Similar Documents

Publication Publication Date Title
CN102454167B (en) The construction method of especially big & deep open caisson
CN103343544B (en) Construction method for large-scale open caisson
CN103993603B (en) A kind of anchor pole churning back cover deep foundation ditch reversed construction method without dewatering operation
CN102418347B (en) Drainage construction method for blind drain and sump wells in deep foundation pit
CN108797598A (en) The construction technology of pre-loaded support struts in a kind of deep basal pit
CN103741714A (en) Full-cover excavation top-down construction method for underground engineering
CN105951711A (en) Enclosing construction method of underground continuous wall of seashore power station
CN107700497A (en) A kind of building basement pattern foundation pit supporting structure and earth excavation construction method
CN105804089A (en) Locally-deepened supporting and protecting system used after original deep foundation pit is constructed and construction method of system
CN112252336A (en) Construction method for backfilling foundation trench of premixed fluidized solidified soil
CN110042842A (en) A kind of open cut construction method of deep foundation ditch for wearing river
CN113235601A (en) Deep foundation pit construction risk control structure and method for collapsible loess adjacent building
CN110219359A (en) A kind of Submersed type inspection well and its construction method
CN111395322A (en) Construction method for rotary digging cast-in-place pile under karst landform
CN104153371A (en) Grouting-to-stop-water construction method of underwater rubble bed
CN112160324A (en) Construction method for deep foundation pit support
CN108571000A (en) The construction method of underground water cutting when wearing existing railway under a kind of road of location along the river
CN103572764A (en) Ultra-deep manual hole digging pile dado water stop structure and construction method thereof
CN114411756A (en) Construction method and construction device for water-rich sand layer subway station open excavation foundation pit without precipitation
CN112392049A (en) Excavation construction method for deep foundation pit in weak stratum
CN209066468U (en) A kind of base pit dewatering device
CN114575355A (en) Soil protection and descent construction method
CN113026757A (en) Rapid excavation and support construction method for complex stratum pipe-jacking comprehensive well
CN111042171A (en) Open caisson construction method suitable for silt soft soil foundation and high underground water level
CN108625404B (en) Basement waterproof leaking stoppage method based on grouting and internal and external dredging combination

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20180216