CN105089061A - Ultra-deep foundation pit supporting method - Google Patents
Ultra-deep foundation pit supporting method Download PDFInfo
- Publication number
- CN105089061A CN105089061A CN201510487933.2A CN201510487933A CN105089061A CN 105089061 A CN105089061 A CN 105089061A CN 201510487933 A CN201510487933 A CN 201510487933A CN 105089061 A CN105089061 A CN 105089061A
- Authority
- CN
- China
- Prior art keywords
- foundation pit
- reinforced concrete
- piles
- bored
- purlins
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Granted
Links
Landscapes
- Foundations (AREA)
- Piles And Underground Anchors (AREA)
- Revetment (AREA)
Abstract
本发明涉及一种超深基坑支护方法:包括单排三轴深搅桩止水帷幕、钻孔灌注桩和钢立柱,单排三轴深搅桩止水帷幕低于自然地面沿基坑四周围护设置,多个钻孔灌注桩依次间隔设置于单排三轴深搅桩止水帷幕内侧的基坑内,多个钢立柱设置于钻孔灌注桩内侧的基坑内,多个钻孔灌注桩顶部依次经钢筋砼冠梁拉接,多个钻孔灌注桩的非各个地下楼层楼板高度位置内侧设置沿基坑四周的钢筋砼围檩,钢筋砼围檩内围经多个支撑于钢立柱上钢筋砼围檩梁拉接,钢筋砼围檩梁与钢筋砼围檩之间经多组钢筋砼内支撑呈网格状拉接,多个钻孔灌注桩的底部向内设置填实素砼,填实素砼内围的基坑上铺设底板,底板上设置一道以上的带换撑的后浇带。
The invention relates to an ultra-deep foundation pit support method: comprising a single-row three-axis deep-stirring pile water-stop curtain, bored piles and steel columns, the single-row three-axis deep-stirring pile water-stop curtain is lower than the natural ground along the foundation pit Surrounding protection settings, multiple bored cast-in-place piles are arranged at intervals in the foundation pit inside the water-stop curtain of a single row of three-axis deep stirring piles, multiple steel columns are set in the foundation pit inside the bored piles, and multiple bored cast-in-place piles are placed in the foundation pit The tops of the piles are successively connected by reinforced concrete crown beams, and the inner sides of the non-subterranean floors of the multiple bored piles are provided with reinforced concrete purlins along the periphery of the foundation pit, and the inner perimeter of the reinforced concrete purlins is supported by multiple steel columns. The upper reinforced concrete purlin girder is pulled and connected, and the reinforced concrete purlin girder and the reinforced concrete purlin are connected in a grid pattern through multiple sets of reinforced concrete inner supports, and the bottoms of multiple bored piles are set inward to fill plain concrete , laying a bottom plate on the foundation pit filled with plain concrete, and setting more than one post-casting belt with replacement braces on the bottom plate.
Description
技术领域 technical field
本发明涉及一种基坑支护方法,具体说是一种超深基坑支护方法。 The invention relates to a foundation pit support method, in particular to an ultra-deep foundation pit support method.
背景技术 Background technique
基坑属于临时性工程,其作用是提供一个空间,使基础的砌筑作业得以按照设计所指定的位置进行。为保证地下结构施工及基坑周边环境的安全,通常需要对基坑侧壁及周边环境通常采用支挡、加固的基坑支护措施。 The foundation pit is a temporary project, and its function is to provide a space so that the foundation masonry can be carried out according to the position specified by the design. In order to ensure the safety of the underground structure construction and the surrounding environment of the foundation pit, it is usually necessary to adopt support and reinforcement foundation pit support measures for the side walls of the foundation pit and the surrounding environment.
随着经济建设的发展,超高层建筑及城市综合体建筑等大体量的工程也越来越多地出现,这些大体量工程不仅地上部分的面积和高度较大,地下部分的面积和深度一般也都比较大,而这些大体量工程一般都会地处城市的繁华地段,平面规划用地非常紧张,周边环境也会比较复杂,由此对地下工程的施工会造成很大的影响,其基坑深度远超10米,属于超深基坑,基坑较为复杂,其开挖和支护直接影响到工程施工。传统的深基坑支护大都为5米的基坑,配套的深基坑开挖和支护技术无法满足深基坑的需求。 With the development of economic construction, there are more and more large-scale projects such as super high-rise buildings and urban complex buildings. These large-scale projects not only have a large area and height of the above-ground part, but also generally have a larger area and depth of the underground part. They are all relatively large, and these large-scale projects are generally located in the bustling areas of the city, the plan planning land is very tight, and the surrounding environment will be relatively complicated, which will have a great impact on the construction of underground projects. The depth of the foundation pit is far More than 10 meters, it is an ultra-deep foundation pit, and the foundation pit is relatively complicated, and its excavation and support directly affect the construction of the project. Most of the traditional deep foundation pit supports are 5-meter foundation pits, and the matching deep foundation pit excavation and support technologies cannot meet the needs of deep foundation pits.
发明内容 Contents of the invention
针对现有技术中的深基坑支护无法满足超深基坑需求的问题,本发明提供了一种结构简单、牢固,施工便捷,支护性能高,便于基坑安全开挖的超深基坑支护方法。 Aiming at the problem that the deep foundation pit support in the prior art cannot meet the needs of ultra-deep foundation pits, the present invention provides an ultra-deep foundation with simple and firm structure, convenient construction, high support performance, and convenient excavation of foundation pits safely. pit support method.
本发明采用的技术方案是:一种超深基坑支护系统,包括单排三轴深搅桩止水帷幕、钻孔灌注桩和钢立柱,单排三轴深搅桩止水帷幕低于自然地面沿基坑四周围护设置,多个钻孔灌注桩依次间隔设置于单排三轴深搅桩止水帷幕内侧的基坑内,多个钢立柱设置于钻孔灌注桩内侧的基坑内,多个钻孔灌注桩顶部依次经钢筋砼冠梁拉接,多个钻孔灌注桩的非各个地下楼层楼板高度位置内侧设置沿基坑四周的钢筋砼围檩,钢筋砼围檩内围经多个支撑于钢立柱上钢筋砼围檩梁拉接,钢筋砼围檩梁与钢筋砼围檩之间经多组钢筋砼内支撑呈网格状拉接,多个钻孔灌注桩的底部向内设置填实素砼,填实素砼内围的基坑上铺设底板,底板上设置一道以上的带换撑的后浇带。 The technical solution adopted in the present invention is: an ultra-deep foundation pit support system, including a single-row three-axis deep-stirring pile water-stop curtain, bored piles and steel columns, and the single-row three-axis deep-stirring pile water-stop curtain is lower than The natural ground is set along the surrounding protection of the foundation pit. Multiple bored cast-in-place piles are arranged at intervals in the foundation pit inside the single-row three-axis deep-stirring pile water-stop curtain, and multiple steel columns are arranged in the foundation pit inside the bored piles. The tops of multiple bored cast-in-place piles are sequentially connected by reinforced concrete crown beams, and the inner sides of the multiple bored cast-in-place piles are set at the height of the floor of each underground floor along the surroundings of the foundation pit. The reinforced concrete purlin beams supported on the steel column are pulled and connected, and the reinforced concrete purlin beams and the reinforced concrete purlins are connected in a grid pattern through multiple groups of reinforced concrete inner supports, and the bottoms of the multiple bored piles are inward. Set up filled plain concrete, lay a bottom plate on the foundation pit inside the filled plain concrete, and set more than one post-casting belt with replacement braces on the bottom plate.
进一步地,底板与基坑间设置垫层。 Further, a cushion layer is provided between the bottom plate and the foundation pit.
进一步地,单排三轴深搅桩止水帷幕顶端上经钢管伸入单排三轴深搅桩止水帷幕内拉接压顶板。 Further, the top of the water-stop curtain of the single-row three-axis deep-stirring piles is extended into the water-stop curtain of the single-row three-axis deep-stirring piles through the steel pipe to connect and press the top plate.
进一步地,钻孔灌注桩内的桩长为沿基坑内外方向一长二短交替设置。 Further, the lengths of the piles in the bored piles are arranged alternately, one long and two short along the inner and outer directions of the foundation pit.
进一步地,多个钻孔灌注桩的各个地下楼层楼板高度位置内侧均布设置多个嵌装在钻孔灌注桩上的换撑块,换撑块水平对应各个地下楼层楼板厚度且垂直支撑基坑内地下楼层外墙。 Further, a plurality of bored cast-in-place piles are uniformly arranged on the inner side of each underground floor height position, and a plurality of support blocks embedded in the bored piles are arranged. The support blocks horizontally correspond to the thickness of each underground floor floor and vertically support the foundation pit. The exterior walls of the basement floor.
进一步地,换撑块至少完全嵌装一个钻孔灌注桩。 Further, at least one bored cast-in-situ pile is completely embedded in the support block.
进一步地,钢立柱为角钢格构柱,钢立柱下部为混凝土立柱桩。 Further, the steel column is an angle steel lattice column, and the lower part of the steel column is a concrete column pile.
进一步地,基坑单排三轴深搅桩止水帷幕外侧的自然地面上设置沿基坑四周的截水沟,基坑钻孔灌注桩内侧设置的多个降水井。 Further, on the natural ground outside the water-stop curtain of the single row of three-axis deep-stirring piles in the foundation pit, intercepting ditches along the periphery of the foundation pit are arranged, and a plurality of dewatering wells are arranged inside the bored piles of the foundation pit.
再进一步地,单排三轴深搅桩止水帷幕外侧设有对应施工冷缝的三轴素桩,三轴素桩与以施工冷缝中心对称的三轴深搅桩搭接,搭接厚度不小于三轴深搅桩直径的1/5。 Furthermore, the single row of three-axis deep-stirring piles is equipped with three-axis plain piles corresponding to the construction cold joints on the outside of the water-stop curtain. Not less than 1/5 of the diameter of the triaxial deep stirring pile.
超深基坑支护方法步骤: Ultra-deep foundation pit support method steps:
(1)按基坑设计四围放线,跳槽式双孔全套复搅式施工单排三轴深搅桩止水帷幕; (1) According to the design of the foundation pit, set out the lines around the foundation pit, and use a double-hole full set of double-stirring construction for the single-row three-axis deep-stirring pile water-stop curtain;
(2)单排三轴深搅桩止水帷幕内围间隔施工多个沿基坑四围均匀间隔排布的钻孔灌注桩,钻孔灌注桩设计强度为水下混凝土C35,钻孔灌注桩内的桩长为沿基坑内外方向一长二短交替设置; (2) A single row of three-axis deep-stirring piles shall be constructed at intervals inside the water-stop curtain to construct multiple bored piles evenly spaced around the foundation pit. The design strength of the bored piles is underwater concrete C35. The pile lengths are alternately set along the inside and outside direction of the foundation pit, one long and two short;
(3)基坑内钻多个立柱孔,立柱孔内设钢立柱,钢立柱基坑下混凝土浇筑立柱桩; (3) Multiple column holes are drilled in the foundation pit, steel columns are installed in the column holes, and column piles are poured with concrete under the foundation pit of the steel columns;
(4)开挖基坑内第一层土方,钻孔灌注桩内围施工多个降水井,降水井预降水;钻孔灌注桩顶部施工钢筋砼冠梁拉接;第一层土方开挖后的基坑面上施工钢筋砼围檩,钢筋砼围檩连接钻孔灌注桩,钢筋砼围檩内施工支撑在钢立柱上的钢筋砼围檩梁,钢筋砼围檩和钢筋砼围檩梁之间施工网格状钢筋砼内支撑拉接为一体,支撑养护; (4) Excavate the first layer of earthwork in the foundation pit, construct multiple dewatering wells inside the bored piles, and pre-dewater in the dewatering wells; construct reinforced concrete crown beam tensioning on the top of the bored piles; Construction of reinforced concrete purlins on the surface of the foundation pit, reinforced concrete purlins connected with bored piles, construction of reinforced concrete purlins supported on steel columns inside the reinforced concrete purlins, between reinforced concrete purlins and reinforced concrete purlins The inner support of the construction grid-shaped reinforced concrete is pulled and connected as a whole, and the support is maintained;
(5)开挖基坑内第二层土方,第二层土方开挖后的基坑面上施工钢筋砼围檩,钢筋砼围檩连接钻孔灌注桩,钢筋砼围檩内施工支撑在钢立柱上的钢筋砼围檩梁,钢筋砼围檩和钢筋砼围檩梁之间施工网格状钢筋砼内支撑拉接为一体,支撑养护;同时降水井降水维持; (5) Excavate the second layer of earthwork in the foundation pit, construct reinforced concrete purlins on the surface of the foundation pit after the excavation of the second layer of earthwork, the reinforced concrete purlins are connected to the bored piles, and the construction inside the reinforced concrete purlins is supported on steel columns The reinforced concrete girders on the top, the grid-shaped reinforced concrete internal support between the reinforced concrete girders and the reinforced concrete girders are integrated to support maintenance; at the same time, the dewatering wells are dewatered to maintain;
(6)按步骤(5)完成后续多层土方开挖,以及每层土方开挖后的基坑面上施工支撑结构,直至基坑最底层,基坑最底层施工垫层和角落素砼填实,垫层上施工底板,底板防水; (6) Complete the subsequent multi-layer earthwork excavation according to step (5), and construct the supporting structure on the foundation pit surface after each layer of earthwork excavation, until the bottom layer of the foundation pit, the bottom layer of the foundation pit shall be constructed with cushion and corner plain concrete filling Solid, the bottom plate is constructed on the cushion, and the bottom plate is waterproof;
(7)施工基坑地下室外墙;由下至上拆除每层土方开挖后的基坑面上施工支撑结构,拆除中间隔施工地下室每个楼层楼板,并在楼层楼板高度位置的外墙与钻孔灌注桩之间施工换撑块,换撑块嵌装在钻孔灌注桩上; (7) Construction of the outer wall of the basement of the foundation pit; remove the construction support structure on the surface of the foundation pit after the excavation of each layer of earthwork from bottom to top, remove the floor slabs of each floor of the construction basement at the middle interval, and remove the outer walls at the height of the floor slabs and the drill The supporting blocks are constructed between the bored piles, and the supporting blocks are embedded on the bored piles;
(8)外墙防水、回填;基坑地下室结构封顶。 (8) Waterproofing and backfilling of the exterior wall; capping of the basement structure of the foundation pit.
采用上述技术方案后,本发明的有益效果是:三轴深搅桩跳槽式双孔全套复搅式施工,能确保施工质量,保证止水帷幕的连续性和接头部位的施工质量,配合外围的截水沟起止水作用;施工时止水帷幕出现冷缝时,对应三轴深搅桩外围采取在冷缝外侧补搅、搭接素桩,确保三轴深搅桩的结构强度和安全;钻孔灌注桩采用一长二短的桩长设置,有效兼顾工程投资成本和承载能力,提高使用安全性能;采用截水沟明降水和降水井深井降水的集合,确保土体的施工安全;基坑按开挖层数由上至下施工,先挖土,再施工钢筋砼围檩、钢筋砼围檩梁和网格状钢筋砼内支撑,配合钻孔灌注桩和钢立柱的支撑,逐层开挖和支护设计,提高开挖基坑的安全性;支护施工至基坑最底层,素砼填实底板与钻孔灌注桩转角角落,进一步提高底板与钻孔灌注桩连接结构稳定;施工基坑地下室外墙使,采用换撑块支撑每层楼层楼板和钻孔灌注桩,确保外墙的垂直、稳定施工。 After adopting the above-mentioned technical scheme, the beneficial effect of the present invention is: three-axis deep-stirring pile hopping type double-hole full-set re-stirring construction, which can ensure the construction quality, ensure the continuity of the water-stop curtain and the construction quality of the joint parts, and cooperate with the peripheral The intercepting ditch plays the role of water stop; when there are cold joints in the water stop curtain during construction, supplementary stirring and lapping of plain piles on the outside of the corresponding three-axis deep-stirring piles shall be adopted to ensure the structural strength and safety of the three-axis deep-stirring piles; One long and two short pile lengths are used for the bored piles, which effectively balances the project investment cost and bearing capacity, and improves the safety performance of the use; the collection of open precipitation in the intercepting ditch and deep well precipitation in the precipitation well is used to ensure the construction safety of the soil; the foundation pit According to the number of excavation layers, the construction is carried out from top to bottom. First excavate the soil, and then construct reinforced concrete purlins, reinforced concrete purlin beams and grid-shaped reinforced concrete inner supports. With the support of bored piles and steel columns, the excavation is carried out layer by layer. Excavation and support design to improve the safety of the excavated foundation pit; support construction to the bottom of the foundation pit, fill the corners of the bottom plate and bored piles with plain concrete, and further improve the stability of the connection structure between the bottom plate and bored piles; construction For the exterior walls of the basement of the foundation pit, support blocks are used to support the floor slabs and bored piles of each floor to ensure the vertical and stable construction of the exterior walls.
附图说明 Description of drawings
图1为本发明系统的俯视图; Fig. 1 is the top view of system of the present invention ;
图2为本发明系统的截面图。 Figure 2 is a cross-sectional view of the system of the present invention .
图中:基坑1,截水沟2,三轴深搅桩止水帷幕3,钻孔灌注桩4,钢立柱5,钢筋砼冠梁6,钢筋砼围檩7,钢筋砼围檩梁8,钢筋砼内支撑9,底板10,垫层11,素砼填实12,降水井13,外墙14,换撑块15,压顶板16,地下楼层楼板17。 In the figure: foundation pit 1, cut-off ditch 2, three-axis deep-stirred pile water-stop curtain 3, bored pile 4, steel column 5, reinforced concrete crown beam 6, reinforced concrete purlin 7, reinforced concrete purlin beam 8 , reinforced concrete inner support 9, bottom plate 10, cushion layer 11, plain concrete filling 12, dewatering well 13, outer wall 14, support block 15, top plate 16, and floor slab 17 of the underground floor.
具体实施方式 Detailed ways
以下结合附图和实施例对本发明作进一步说明。 The present invention will be further described below in conjunction with drawings and embodiments.
图1、2所示:一种超深基坑支护系统包括单排三轴深搅桩止水帷幕3、钻孔灌注桩4和钢立柱5,单排三轴深搅桩止水帷幕3低于自然地面沿基坑1四周围护设置,单排三轴深搅桩止水帷幕3顶端上经钢管伸入单排三轴深搅桩止水帷幕内拉接压顶板16,多个钻孔灌注桩4依次间隔设置于单排三轴深搅桩止水帷幕3内侧的基坑1内,钻孔灌注桩4内的桩长为沿基坑内外方向一长二短交替设置,多个钢立柱5设置于钻孔灌注桩4内侧的基坑1内,钢立柱为角钢格构柱,钢立柱下部为混凝土立柱桩,单排三轴深搅桩止水帷幕3外侧的自然地面上设置沿基坑1四周的截水沟2和沿基坑1四周均匀间隔设置的多个降水井13。多个钻孔灌注桩4顶部依次经钢筋砼冠梁6拉接,多个钻孔灌注桩4的非各个地下楼层楼板高度位置内侧设置沿基坑1四周的钢筋砼围檩7,钢筋砼围檩7内围经多个支撑于钢立柱5上钢筋砼围檩梁8拉接,钢筋砼围檩梁8与钢筋砼围檩7之间经多组钢筋砼内支撑9呈网格状拉接,多个钻孔灌注桩4的底部向内设置填实素砼12,填实素砼12内围的基坑上铺设垫层11和底板10,底板上设置一道以上的带换撑的后浇带。 As shown in Figures 1 and 2, an ultra-deep foundation pit support system includes a single-row three-axis deep-stirred pile water-stop curtain 3, a bored pile 4 and a steel column 5, and a single-row three-axis deep-stirred pile water-stop curtain 3 It is lower than the natural ground and is set along the surrounding protection of the foundation pit 1. The top of the single-row three-axis deep-stirring pile water-stop curtain 3 extends through the steel pipe into the single-row three-axis deep-stirring pile water-stop curtain to pull and press the top plate 16. The bored cast-in-place piles 4 are sequentially arranged at intervals in the foundation pit 1 inside the water-stop curtain 3 of the single-row three-axis deep-stirring piles. The steel column 5 is set in the foundation pit 1 inside the bored pile 4. The steel column is an angle steel lattice column, and the lower part of the steel column is a concrete column pile. The intercepting ditches 2 along the periphery of the foundation pit 1 and a plurality of dewatering wells 13 arranged at regular intervals along the periphery of the foundation pit 1 . The tops of multiple bored cast-in-place piles 4 are successively connected by reinforced concrete crown beams 6, and the inner sides of the multiple bored cast-in-place piles 4 are provided with reinforced concrete purlins 7 along the periphery of the foundation pit 1, and reinforced concrete surrounds The inner circumference of the purlin 7 is connected to the reinforced concrete purlin beam 8 on the steel column 5 through multiple supports, and the reinforced concrete surrounding purlin beam 8 and the reinforced concrete purlin 7 are connected in a grid pattern through multiple sets of reinforced concrete inner supports 9 , the bottom of a plurality of bored piles 4 is provided with filled plain concrete 12 inwardly, and a cushion layer 11 and a bottom plate 10 are laid on the foundation pit inside the filled plain concrete 12, and more than one post-cast concrete with replacement braces is arranged on the bottom plate. bring.
多个钻孔灌注桩4的各个地下楼层楼板17高度位置内侧均布设置多个嵌装在钻孔灌注桩4上的换撑块15,换撑块水平对应各个地下楼层楼板厚度且垂直支撑基坑内地下楼层外墙,换撑块至少完全嵌装一个钻孔灌注桩。 A plurality of support blocks 15 embedded in the bored piles 4 are evenly distributed on the inner side of each underground floor slab 17 of the plurality of bored piles 4, and the support blocks are horizontally corresponding to the thickness of each underground floor slab and vertically support For the outer wall of the underground floor in the pit, at least one bored cast-in-situ pile is completely embedded in the replacement support block.
本发明超深基坑支护方法步骤: The steps of the ultra-deep foundation pit supporting method of the present invention:
(1)按基坑设计四围放线,跳槽式双孔全套复搅式施工单排三轴深搅桩止水帷幕,单排三轴深搅桩止水帷幕外侧的自然地面上施工截水沟2; (1) According to the design of the foundation pit, set out the lines around the foundation pit, and construct a single-row three-axis deep-stirring pile water-stop curtain with a full set of double-hole double-stirring construction, and construct a water-cutting ditch on the natural ground outside the single-row three-axis deep-stirring pile water-stop curtain 2;
(2)单排三轴深搅桩止水帷幕内围间隔施工多个沿基坑四围均匀间隔排布的钻孔灌注桩,钻孔灌注桩设计强度为水下混凝土C35,钻孔灌注桩内的桩长为沿基坑内外方向一长二短交替设置; (2) A single row of three-axis deep-stirring piles shall be constructed at intervals inside the water-stop curtain to construct multiple bored piles evenly spaced around the foundation pit. The design strength of the bored piles is underwater concrete C35. The pile lengths are alternately set along the inside and outside direction of the foundation pit, one long and two short;
(3)基坑内钻多个立柱孔,立柱孔内设钢立柱,钢立柱基坑下混凝土浇筑立柱桩; (3) Multiple column holes are drilled in the foundation pit, steel columns are installed in the column holes, and column piles are poured with concrete under the foundation pit of the steel columns;
(4)开挖基坑内第一层土方,钻孔灌注桩内围施工多个降水井13,降水井预降水;钻孔灌注桩顶部施工钢筋砼冠梁拉接;第一层土方开挖后的基坑面上施工钢筋砼围檩,钢筋砼围檩连接钻孔灌注桩,钢筋砼围檩内施工支撑在钢立柱上的钢筋砼围檩梁,钢筋砼围檩和钢筋砼围檩梁之间施工网格状钢筋砼内支撑拉接为一体,支撑养护; (4) Excavate the first layer of earthwork in the foundation pit, construct a plurality of dewatering wells 13 inside the bored piles, and pre-dewater in the dewatering wells; The reinforced concrete purlins are constructed on the surface of the foundation pit, the reinforced concrete purlins are connected to the bored piles, the reinforced concrete purlins are supported on the steel columns inside the reinforced concrete purlins, and the reinforced concrete purlins and the reinforced concrete purlin beams are constructed. The inter-construction grid-shaped reinforced concrete internal support is pulled and connected as a whole, and the support is maintained;
(5)开挖基坑内第二层土方,第二层土方开挖后的基坑面上施工钢筋砼围檩,钢筋砼围檩连接钻孔灌注桩,钢筋砼围檩内施工支撑在钢立柱上的钢筋砼围檩梁,钢筋砼围檩和钢筋砼围檩梁之间施工网格状钢筋砼内支撑拉接为一体,支撑养护;同时降水井降水维持; (5) Excavate the second layer of earthwork in the foundation pit, construct reinforced concrete purlins on the surface of the foundation pit after the excavation of the second layer of earthwork, the reinforced concrete purlins are connected to the bored piles, and the construction inside the reinforced concrete purlins is supported on steel columns The reinforced concrete girders on the top, the grid-shaped reinforced concrete internal support between the reinforced concrete girders and the reinforced concrete girders are integrated to support maintenance; at the same time, the dewatering wells are dewatered to maintain;
(6)按步骤(5)完成后续多层土方开挖,以及每层土方开挖后的基坑面上施工支撑结构,直至基坑最底层,基坑最底层施工垫层和角落素砼填实,垫层上施工底板,底板防水; (6) Complete the subsequent multi-layer earthwork excavation according to step (5), and construct the supporting structure on the foundation pit surface after each layer of earthwork excavation, until the bottom layer of the foundation pit, the bottom layer of the foundation pit shall be constructed with cushion and corner plain concrete filling Solid, the bottom plate is constructed on the cushion, and the bottom plate is waterproof;
(7)施工基坑地下室外墙;由下至上拆除每层土方开挖后的基坑面上施工支撑结构,拆除中间隔施工地下室每个楼层楼板,并在楼层楼板高度位置的外墙与钻孔灌注桩之间施工换撑块,换撑块嵌装在钻孔灌注桩上; (7) Construction of the outer wall of the basement of the foundation pit; remove the construction support structure on the surface of the foundation pit after the excavation of each layer of earthwork from bottom to top, remove the floor slabs of each floor of the construction basement at the middle interval, and remove the outer walls at the height of the floor slabs and the drill The supporting blocks are constructed between the bored piles, and the supporting blocks are embedded on the bored piles;
外墙防水、回填;基坑地下室结构封顶。 Waterproofing and backfilling of the exterior wall; capping of the basement structure of the foundation pit.
Claims (1)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510487933.2A CN105089061B (en) | 2015-08-11 | 2015-08-11 | Ultra-deep foundation pit supporting method |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201510487933.2A CN105089061B (en) | 2015-08-11 | 2015-08-11 | Ultra-deep foundation pit supporting method |
Publications (2)
| Publication Number | Publication Date |
|---|---|
| CN105089061A true CN105089061A (en) | 2015-11-25 |
| CN105089061B CN105089061B (en) | 2017-01-18 |
Family
ID=54570320
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201510487933.2A Withdrawn - After Issue CN105089061B (en) | 2015-08-11 | 2015-08-11 | Ultra-deep foundation pit supporting method |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN105089061B (en) |
Cited By (19)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106351343A (en) * | 2016-11-10 | 2017-01-25 | 成都市第八建筑工程公司 | Basement outer wall waterproof protection structure capable of realizing synchronous crossing construction and construction method thereof |
| CN106400985A (en) * | 2016-11-10 | 2017-02-15 | 成都市第八建筑工程公司 | Basement outer wall waterproof protection structure and construction method |
| CN107246017A (en) * | 2017-08-07 | 2017-10-13 | 深圳市勘察研究院有限公司 | A kind of steel-concrete structure assembled underground engineering support system and construction technology |
| CN107313454A (en) * | 2017-08-31 | 2017-11-03 | 南京叭叭智能科技有限公司 | A kind of construction method of underground garage |
| CN107700497A (en) * | 2017-09-29 | 2018-02-16 | 广州市番禺区第五建筑工程公司 | A kind of building basement pattern foundation pit supporting structure and earth excavation construction method |
| CN107938706A (en) * | 2017-11-14 | 2018-04-20 | 宁波市交通规划设计研究院有限公司 | Shallow tunnel foundation pit enclosure section arched roof formula combines open-cut tunnel structure and construction method |
| CN108442406A (en) * | 2018-03-29 | 2018-08-24 | 中冶成都勘察研究总院有限公司 | A kind of semi-inverse method internal support of foundation pit structure and its construction method |
| CN109371982A (en) * | 2018-12-07 | 2019-02-22 | 武汉丰达地质工程有限公司 | A kind of construction method of basement bottom board support replacement |
| CN109577337A (en) * | 2017-09-29 | 2019-04-05 | 中国石油天然气股份有限公司 | Construction Method of Deep Foundation Pit of Drainage Pipeline |
| CN109706939A (en) * | 2019-01-14 | 2019-05-03 | 杭州江润科技有限公司 | Deep basal pit prestressing combination bracing members and construction method |
| CN111576435A (en) * | 2020-04-17 | 2020-08-25 | 中建五局第三建设有限公司 | Construction method and structure of column control slip surface of inter-pile soil steel structure |
| CN112359844A (en) * | 2020-11-23 | 2021-02-12 | 中国电建集团江西省电力建设有限公司 | Foundation pit supporting structure and construction method thereof |
| CN114482016A (en) * | 2022-03-11 | 2022-05-13 | 中国十九冶集团有限公司 | Threaded steel pipe pile and deep foundation pit construction method |
| CN114703859A (en) * | 2021-12-20 | 2022-07-05 | 浙江交工集团股份有限公司 | Deep soft soil pool foundation pit support system for complex land storage yard and construction method thereof |
| CN115125962A (en) * | 2021-10-30 | 2022-09-30 | 上海宝冶集团有限公司 | Construction method of river-crossing foundation pit support |
| CN115710913A (en) * | 2022-11-18 | 2023-02-24 | 中国十七冶集团有限公司 | Foundation pit supporting method for water-rich weak geology |
| CN116356844A (en) * | 2023-04-21 | 2023-06-30 | 中建科工集团武汉有限公司 | The support construction method and foundation pit structure for the first-grade foundation pit in high water level sandy soil |
| CN117248538A (en) * | 2023-11-06 | 2023-12-19 | 中交一公局集团有限公司 | Construction method of secondary utilization subway station bite pile foundation pit supporting structure system |
| CN120844602A (en) * | 2025-09-23 | 2025-10-28 | 山西四建集团有限公司 | A deep foundation pit support system that is extremely close to subway structures and existing buildings |
Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP5180022B2 (en) * | 2008-10-03 | 2013-04-10 | 株式会社竹中土木 | Constraining method for mountain retaining wall head |
| CN203403422U (en) * | 2013-06-06 | 2014-01-22 | 广西建工集团第五建筑工程有限责任公司 | Long-span reinforced concrete inner support structure of rectangular deep foundation pit |
| CN204343301U (en) * | 2014-12-13 | 2015-05-20 | 中铁二十局集团第三工程有限公司 | A kind of Metro station excavation excavation supporting structure |
| CN104775440A (en) * | 2015-04-21 | 2015-07-15 | 五洋建设集团股份有限公司 | Mineshaft-type underground garage deep foundation pit supporting structure |
-
2015
- 2015-08-11 CN CN201510487933.2A patent/CN105089061B/en not_active Withdrawn - After Issue
Patent Citations (4)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP5180022B2 (en) * | 2008-10-03 | 2013-04-10 | 株式会社竹中土木 | Constraining method for mountain retaining wall head |
| CN203403422U (en) * | 2013-06-06 | 2014-01-22 | 广西建工集团第五建筑工程有限责任公司 | Long-span reinforced concrete inner support structure of rectangular deep foundation pit |
| CN204343301U (en) * | 2014-12-13 | 2015-05-20 | 中铁二十局集团第三工程有限公司 | A kind of Metro station excavation excavation supporting structure |
| CN104775440A (en) * | 2015-04-21 | 2015-07-15 | 五洋建设集团股份有限公司 | Mineshaft-type underground garage deep foundation pit supporting structure |
Cited By (22)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN106400985A (en) * | 2016-11-10 | 2017-02-15 | 成都市第八建筑工程公司 | Basement outer wall waterproof protection structure and construction method |
| CN106400985B (en) * | 2016-11-10 | 2020-01-31 | 成都市第八建筑工程公司 | basement exterior wall waterproof protection structure and construction method |
| CN106351343A (en) * | 2016-11-10 | 2017-01-25 | 成都市第八建筑工程公司 | Basement outer wall waterproof protection structure capable of realizing synchronous crossing construction and construction method thereof |
| CN107246017A (en) * | 2017-08-07 | 2017-10-13 | 深圳市勘察研究院有限公司 | A kind of steel-concrete structure assembled underground engineering support system and construction technology |
| CN107313454A (en) * | 2017-08-31 | 2017-11-03 | 南京叭叭智能科技有限公司 | A kind of construction method of underground garage |
| CN109577337A (en) * | 2017-09-29 | 2019-04-05 | 中国石油天然气股份有限公司 | Construction Method of Deep Foundation Pit of Drainage Pipeline |
| CN107700497A (en) * | 2017-09-29 | 2018-02-16 | 广州市番禺区第五建筑工程公司 | A kind of building basement pattern foundation pit supporting structure and earth excavation construction method |
| CN107938706B (en) * | 2017-11-14 | 2019-10-18 | 宁波市交通规划设计研究院有限公司 | Shallow tunnel foundation pit enclosure section arched roof formula combines open-cut tunnel structure and construction method |
| CN107938706A (en) * | 2017-11-14 | 2018-04-20 | 宁波市交通规划设计研究院有限公司 | Shallow tunnel foundation pit enclosure section arched roof formula combines open-cut tunnel structure and construction method |
| CN108442406A (en) * | 2018-03-29 | 2018-08-24 | 中冶成都勘察研究总院有限公司 | A kind of semi-inverse method internal support of foundation pit structure and its construction method |
| CN109371982A (en) * | 2018-12-07 | 2019-02-22 | 武汉丰达地质工程有限公司 | A kind of construction method of basement bottom board support replacement |
| CN109706939A (en) * | 2019-01-14 | 2019-05-03 | 杭州江润科技有限公司 | Deep basal pit prestressing combination bracing members and construction method |
| CN109706939B (en) * | 2019-01-14 | 2020-09-15 | 杭州江润科技有限公司 | Deep foundation pit prestress combined steel support and construction method |
| CN111576435A (en) * | 2020-04-17 | 2020-08-25 | 中建五局第三建设有限公司 | Construction method and structure of column control slip surface of inter-pile soil steel structure |
| CN112359844A (en) * | 2020-11-23 | 2021-02-12 | 中国电建集团江西省电力建设有限公司 | Foundation pit supporting structure and construction method thereof |
| CN115125962A (en) * | 2021-10-30 | 2022-09-30 | 上海宝冶集团有限公司 | Construction method of river-crossing foundation pit support |
| CN114703859A (en) * | 2021-12-20 | 2022-07-05 | 浙江交工集团股份有限公司 | Deep soft soil pool foundation pit support system for complex land storage yard and construction method thereof |
| CN114482016A (en) * | 2022-03-11 | 2022-05-13 | 中国十九冶集团有限公司 | Threaded steel pipe pile and deep foundation pit construction method |
| CN115710913A (en) * | 2022-11-18 | 2023-02-24 | 中国十七冶集团有限公司 | Foundation pit supporting method for water-rich weak geology |
| CN116356844A (en) * | 2023-04-21 | 2023-06-30 | 中建科工集团武汉有限公司 | The support construction method and foundation pit structure for the first-grade foundation pit in high water level sandy soil |
| CN117248538A (en) * | 2023-11-06 | 2023-12-19 | 中交一公局集团有限公司 | Construction method of secondary utilization subway station bite pile foundation pit supporting structure system |
| CN120844602A (en) * | 2025-09-23 | 2025-10-28 | 山西四建集团有限公司 | A deep foundation pit support system that is extremely close to subway structures and existing buildings |
Also Published As
| Publication number | Publication date |
|---|---|
| CN105089061B (en) | 2017-01-18 |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN105089061B (en) | Ultra-deep foundation pit supporting method | |
| CN205742213U (en) | Foundation pit supporting construction | |
| CN109026064B (en) | Construction method for large-span multi-arch tunnel with semi-bright and semi-dark | |
| CN104264688B (en) | Manually digging hole non-uniform pile support construction process | |
| CN205776249U (en) | A kind of combined inner supporting structure | |
| CN105569064B (en) | A kind of setting formula construction of Open Caisson Foundation method suitable for deep water drift net | |
| JP7624570B1 (en) | Underground excavation for interchange subway station - Cut and cover semi-reverse construction method | |
| CN101418569B (en) | Optimized composite arch wall with combination of prefabricated arch, support and main structure | |
| CN108278115A (en) | A kind of three step Rapid Construction of Tunnels method of big arch springing and structure based on pre-timbering with tubular prop | |
| CN103741725B (en) | A kind of immersed tube tunnel final joint and bank is dry makes construction method | |
| CN105155549A (en) | Partition support system for large-area deep foundation pit under forward and backward working condition, and construction method thereof | |
| CN111911168B (en) | Construction Method and Permanent Support System of Shallow Buried Long-Span Tunnel | |
| CN104894926B (en) | Retaining structure and its construction method on the high embankment of existing railway | |
| CN103195085A (en) | Downward story-adding basement and construction method thereof | |
| CN101418577B (en) | Construction Method of Covering and Excavating Underground Space Pavement in Soft Soil Area | |
| CN111236241B (en) | Reinforcement and excavation method of subway foundation pit in soft and water-rich stratum based on half-cover excavation method | |
| CN204898684U (en) | Super dark excavation supporting system | |
| CN107489106B (en) | A kind of construction method of rock river bed water cap | |
| CN214832726U (en) | A kind of support structure of pipe jacking working well in deep soft soil area | |
| CN104631469A (en) | Astylar reinforced concrete supporting framework for deep and big foundation pit and building method thereof | |
| CN204753262U (en) | A fender structure on high embankment of existing railway | |
| CN105040708A (en) | Support system for ultra-deep foundation pit | |
| CN204326080U (en) | A kind of next-door neighbour's existing building pit maintenance soil structure | |
| CN204311456U (en) | Foundation ditch strengthening structure | |
| CN108571010B (en) | Method for integrating open cut method engineering prefabricated main structure and supporting structure |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| C06 | Publication | ||
| PB01 | Publication | ||
| C10 | Entry into substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| C14 | Grant of patent or utility model | ||
| GR01 | Patent grant | ||
| CB03 | Change of inventor or designer information |
Inventor after: Li Hongbing Inventor after: Feng Guitai Inventor after: Liu Guohua Inventor after: Li Haibo Inventor after: Ji Chun Inventor after: Chen Junyi Inventor after: Xiao Yarong Inventor after: Zhou Jian Inventor before: Chen Junyi Inventor before: Xiao Yarong Inventor before: Zhou Jian |
|
| CB03 | Change of inventor or designer information | ||
| CP03 | Change of name, title or address | ||
| CP03 | Change of name, title or address |
Address after: No. 87, Jinchuan Road, Taixing City, Taizhou, Jiangsu Patentee after: TAIXING FIRST CONSTRUCTION GROUP CO.,LTD. Address before: 225400 Daqing East Road, Taixing City, Taizhou, Jiangsu Province, No. 21 Patentee before: TAIXING FIRST CONSTRUCTION INSTALLATION Co.,Ltd. |
|
| AV01 | Patent right actively abandoned | ||
| AV01 | Patent right actively abandoned | ||
| AV01 | Patent right actively abandoned |
Granted publication date: 20170118 Effective date of abandoning: 20251030 |
|
| AV01 | Patent right actively abandoned |
Granted publication date: 20170118 Effective date of abandoning: 20251030 |