CN109944630A - A kind of low-permeable thin seam working surface gas pumping method - Google Patents

A kind of low-permeable thin seam working surface gas pumping method Download PDF

Info

Publication number
CN109944630A
CN109944630A CN201910404271.6A CN201910404271A CN109944630A CN 109944630 A CN109944630 A CN 109944630A CN 201910404271 A CN201910404271 A CN 201910404271A CN 109944630 A CN109944630 A CN 109944630A
Authority
CN
China
Prior art keywords
gas
evaluation unit
drilling
working face
lane
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910404271.6A
Other languages
Chinese (zh)
Other versions
CN109944630B (en
Inventor
王浩
李红斌
谭毅
白二虎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Henan University of Technology
Original Assignee
Henan University of Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Henan University of Technology filed Critical Henan University of Technology
Priority to CN201910404271.6A priority Critical patent/CN109944630B/en
Publication of CN109944630A publication Critical patent/CN109944630A/en
Application granted granted Critical
Publication of CN109944630B publication Critical patent/CN109944630B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Excavating Of Shafts Or Tunnels (AREA)
  • Drilling And Exploitation, And Mining Machines And Methods (AREA)
  • Examining Or Testing Airtightness (AREA)

Abstract

Low-permeable thin seam working surface gas pumping method proposed by the present invention, back production lane evaluation unit is closed on by the way that working face to be divided into, close on evaluation unit in the middle part of the lane Qie Yan evaluation unit and working face, and different suitable coal bed gas extraction drilling method for arranging is taken for different evaluation unit, finally concordant mash gas pumping drilling is connect with methane gas extraction pipeline, coal-bed gas in each evaluation unit in extraction working face under the action of negative pressure, and drilling is investigated to each evaluation unit construction gas, examine gas pumping effect, the mentioned method of the present invention preferably resolves working face due to balk, poor air permeability, mash gas pumping drilling caused by length is big is easy to be biased to top plate or bottom plate and then leads to gas drainage problem not up to standard, improve coal bed gas extraction compliance rate in the middle part of the effective rate of utilization and working face of mash gas pumping drilling, ensure Working face safety coal extraction.

Description

A kind of low-permeable thin seam working surface gas pumping method
Technical field
The present invention relates to coal mining technology fields, specially a kind of low-permeable thin seam working surface gas drainage side Method.
Background technique
Coal and gas prominent is one of the disaster that Safety of Coal Mine Production faces, with coal in China mining rate and depth The risk of the increase of degree, coal and gas prominent disaster is increasingly severe, causes significant negative impact to coal industry image.
South China coal resources are based on girdle, and gas bearing capacity is high, gas permeability of coal seam is poor, and working face extraction is up to standard Required time is long, and extraction difficulty is big, is on the other hand work on the one hand the reason is that working face open-off cut Vitrea eye domain is short with respect to the extraction time Middle face region concordant mash gas pumping drilling construction quality is difficult to ensure.
It is directed to the face gas extraction of low-permeable stoping low coal seam in the past, by two sides back production usually before working face extraction To working face coal body construction concordant hole pumping and mining gas in the lane Ji Qieyan of tunnel, but the method is difficult to ensure gas in the middle part of working face Extracting result, especially for low-permeable thin seam working surface, due to gas in coal seam flow difficulties, gas drainage is more Difficulty, working face central region biggish for length, concordant mash gas pumping drilling, which there is also, is biased to top plate or floor strata The phenomenon that, it further reduced concordant mash gas pumping drilling extracting result, and then working face central region coal-bed gas is caused to be taken out It is poor to adopt effect, often causes gas exceeding limit in working face during working face extraction, coal and gas prominent is even induced when serious Disaster.
Therefore, the big working face coal-bed gas of low for gas permeability, balk, length takes out problem, needs to design more needle Coal-bed gas pressure is reduced to reduce coal seam gas-bearing capacity to property, gas pumping effect more preferably pumping method, weakens coal seam Coal and gas prominent risk improves working face extraction safety.
Summary of the invention
To achieve the above object, the invention provides the following technical scheme: a kind of low-permeable thin seam working surface gas is taken out Mining method, it includes following steps:
Step 1: region is divided;The two sides up and down of working face are back production lane, and the right side of working face is the lane Qie Yan, by work Face, which is divided into, to be closed on back production lane evaluation unit, closes on the lane Qie Yan evaluation unit and working face middle part evaluation unit, to not Same region separately carries out gas drainage evaluation;
Step 2: construction concordant mash gas pumping drilling one;First, for back production lane evaluation unit construction concordant gas is closed on Extraction borehole one is constructed concordant mash gas pumping drilling one perpendicular to the lane side in back production lane into working face;Second, being cut for closing on Eye lane evaluation unit construct concordant mash gas pumping drilling one, perpendicular to the lane Qie Yan lane side construct into working face concordant gas pumping Borehole one;
Step 3: construction gas drainage tunnel;For evaluation unit construction gas drainage tunnel in the middle part of working face, working While the tunnelling in the back production lane of face two sides, tunneled from the tunnel in back production lane to the inside of working face using rectangle light section Mode tunnel to form gas drainage tunnel, the axis in the gas drainage tunnel is vertical with the axis in the tunnel in back production lane, institute It states gas drainage tunnel to tunnel along seat earth, meet head on to be located in the middle part of working face in the middle part of the long side of evaluation unit;
Step 4: construction concordant mash gas pumping drilling two;The construction concordant gas on the end face of meeting head in gas drainage tunnel Extraction borehole two, the concordant mash gas pumping drilling two are arranged in " sector ", along drilling in coal;
Step 5: piping connection;By above-mentioned concordant mash gas pumping drilling one and concordant mash gas pumping drilling two and gas Extraction piping connection, under the action of negative pressure coal-bed gas in each evaluation unit in extraction working face, negative pressure in methane gas extraction pipeline Not less than 13KPa, methane gas extraction pipeline is through gas drainage tunnel, the tunnel in back production lane, mining roadway and ground gas extraction system System connection;
Step 6: construction gas investigates drilling;Gas of constructing in each evaluation unit of working face investigates drilling, to Whether up to standard investigate gas pressure and gas remainder quantity in each evaluation unit.
Further, in step 1, the width of the working face is L, is closed in the middle part of back production lane evaluation unit and working face The length of evaluation unit is 150~200m, and wide is L/3, and the length for closing on the lane Qie Yan evaluation unit is L, width 100m.
Further, in step 2, the sealing of hole for closing on the concordant mash gas pumping drilling one in the evaluation unit of back production lane Length is 10~15m, and aperture is located in the middle part of coal seam, and single arrangement, pitch of holes is 5~10m, is closed in the evaluation unit of back production lane Concordant mash gas pumping drilling one a length of L/3, a diameter of 90~135mm;Close on the concordant watt in the evaluation unit of the lane Qie Yan The sealed borehole length 10m of this extraction borehole one, aperture are located in the middle part of coal seam, and single arrangement, pitch of holes is 3~5m, close on and cut eye A length of 100m of concordant mash gas pumping drilling one in the evaluation unit of lane, a diameter of 90~135mm.
Further, in step 3, the gas drainage tunnel is arranged in " taking a step " formula, and the gas drainage tunnel is broken Face is rectangle, and the width of the rectangle is 3.5m, and a height of 2m, gas drainage tunnel length is L/3.
Further, in step 4, the concordant mash gas pumping drilling two is arranged in " sector ", and along drilling in coal, Its sealed borehole length is 10~15m, and aperture uses " three presbyopia " arrangement, and array pitch is 0.5m~1m between tapping point, whole hole Point linear distance is 5~10m, and the length of the concordant mash gas pumping drilling two, which is subject to, covers evaluation unit, the concordant watt The diameter of this extraction borehole two is 90~135mm.
Further, in step 6, the gas investigates the parallel drilling in coal that drills, and the gas investigates the sealing of hole of drilling Length is 10~15m, and position of opening is located in the middle part of the aperture line of adjacent two concordants mash gas pumping drilling one, or is located at phase In the middle part of the aperture line of adjacent two concordant mash gas pumping drillings two, the borehole bottom location that the gas investigates drilling is located at adjacent two concordant It is described in the middle part of the whole hole line of mash gas pumping drilling one or in the middle part of the whole hole line of adjacent two concordants mash gas pumping drilling two Gas investigates 90~135mm of diameter of drilling.
Further, in step 6, it is less than 0.74MPa when investigating gas pressure, and gas remainder quantity is less than 8m3/t When, show that extraction is up to standard, in evaluation unit otherwise coal seam can show that extraction is not up to standard, coal seam in evaluation unit with safe working It can not exploit, the extraction time need to be extended until extraction is up to standard.
Compared with prior art, the beneficial effects of the present invention are:
Low-permeable thin seam working surface gas pumping method proposed by the present invention, is closed on back by the way that working face to be divided into It adopts lane evaluation unit, close on the lane Qie Yan evaluation unit and working face middle part evaluation unit, and taken for different evaluation unit Concordant mash gas pumping drilling, finally connect by different suitable coal bed gas extraction drilling method for arranging with methane gas extraction pipeline, Coal-bed gas in each evaluation unit in extraction working face under suction function, and drilling is investigated to each evaluation unit construction gas, Gas pumping effect is examined, especially for evaluation unit setting construction gas drainage tunnel in the middle part of working face and construction concordant gas Extraction borehole two, further ensures the gas pumping effect in the middle part of working face in evaluation unit, and the mentioned method of the present invention is preferable The working face mash gas pumping drilling as caused by balk, poor air permeability, length are big that solves be easy to be biased to top plate or bottom plate And then lead to gas drainage problem not up to standard, improve coal-bed gas in the middle part of the effective rate of utilization and working face of mash gas pumping drilling Extraction compliance rate, it is ensured that working face safety coal extraction.
Detailed description of the invention
Fig. 1 is that low-permeable thin seam working surface gas drainage evaluation unit divides plan view;
Fig. 2 is mash gas pumping drilling plane of arrangement figure in coal face evaluation unit;
Fig. 3 is mash gas pumping drilling plane of arrangement figure in gas drainage lane;
Fig. 4 is that end view in section (A-A section in Fig. 3) is met head in gas drainage lane;
In figure: 1, working face;2, back production lane;3, concordant mash gas pumping drilling one;4, the lane Qie Yan;5, gas drainage tunnel; 6, concordant mash gas pumping drilling two;7, gas investigates drilling.
Specific embodiment
Following will be combined with the drawings in the embodiments of the present invention, and technical solution in the embodiment of the present invention carries out clear, complete Site preparation description, it is clear that described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.It is based on Embodiment in the present invention, it is obtained by those of ordinary skill in the art without making creative efforts every other Embodiment shall fall within the protection scope of the present invention.
Fig. 1-4 is please referred to, the present invention provides a kind of technical solution: a kind of low-permeable thin seam working surface gas drainage side Method, which is characterized in that it includes following steps:
Step 1: region is divided;Such as Fig. 1, the two sides up and down of working face 1 are back production lane 2, and the right side of working face 1 is to cut eye Lane 4, working face 1 is divided into close on back production lane evaluation unit (C, D, F, G, I, J), close on the lane Qie Yan evaluation unit (A) and Evaluation unit (B, E, H) in the middle part of working face, separately to carry out gas drainage evaluation to different regions;
Step 2: construction concordant mash gas pumping drilling 1;First, for back production lane evaluation unit construction concordant watt is closed on This extraction borehole 1 is constructed concordant mash gas pumping drilling 1 perpendicular to the lane side in back production lane 2 into working face 1;Second, being directed to The lane Qie Yan evaluation unit construction concordant mash gas pumping drilling 1 is closed on, is constructed perpendicular to the lane side in the lane Qie Yan 4 into working face 1 Concordant mash gas pumping drilling 1;
Step 3: construction gas drainage tunnel 5;For evaluation unit construction gas drainage tunnel 5 in the middle part of working face, in work It is small disconnected using rectangle from the tunnel in back production lane 2 to the inside of working face 1 while making the tunnelling in the back production lane 2 of 1 two sides of face The mode of face driving tunnels to form gas drainage tunnel 5, the axis in the tunnel of the axis and back production lane 2 in the gas drainage tunnel 5 Line is vertical, and the gas drainage tunnel 5 is tunneled along seat earth, meets head on to be located in the middle part of working face in the long side of evaluation unit Portion;
Step 4: construction concordant mash gas pumping drilling 26;The construction concordant watt on the end face of meeting head in gas drainage tunnel 5 This extraction borehole 26, the concordant mash gas pumping drilling 26 are arranged in " sector ", along drilling in coal;
Step 5: piping connection;By above-mentioned concordant mash gas pumping drilling 1 and concordant mash gas pumping drilling 26 with watt This extraction piping connection, under the action of negative pressure coal-bed gas in each evaluation unit in extraction working face 1 are born in methane gas extraction pipeline Pressure is not less than 13KPa, and methane gas extraction pipeline is taken out through gas drainage tunnel 5, the tunnel in back production lane 2, mining roadway and ground gas Extraction system connection;
Step 6: construction gas investigates drilling 7;Gas of constructing in each evaluation unit of working face 1 investigates drilling 7, It is whether up to standard to investigate gas pressure and gas remainder quantity in each evaluation unit.
Specifically, the width of the working face 1 is L in step 1, closes in the middle part of back production lane evaluation unit and working face and comment The length of valence unit is 200m, and wide is L/3, and the length for closing on the lane Qie Yan evaluation unit is L, width 100m.
Specifically, the sealing of hole for closing on the concordant mash gas pumping drilling 1 in the evaluation unit of back production lane is long in step 2 Degree is 15m, and aperture is located in the middle part of coal seam, and single arrangement, pitch of holes 10m closes on the concordant watt in the evaluation unit of back production lane A length of L/3 of this extraction borehole 1, a diameter of 135mm;Close on the concordant mash gas pumping drilling one in the evaluation unit of the lane Qie Yan 3 sealed borehole length 10m, aperture are located in the middle part of coal seam, and single arrangement, pitch of holes 5m closes in the evaluation unit of the lane Qie Yan A length of 100m of concordant mash gas pumping drilling 1, a diameter of 135mm.
Specifically, the gas drainage tunnel 5 is arranged in " taking a step " formula in step 3, the gas drainage tunnel 5 is broken Face is rectangle, and the width of the rectangle is 3.5m, a height of 2m, and 5 length of gas drainage tunnel is L/3, two neighboring gas drainage The axis in tunnel 5 is at a distance of 400m.
Specifically, such as Fig. 2 and 3, the concordant mash gas pumping drilling 26 is arranged in " sector ", and along coal in step 4 Layer drilling, sealed borehole length 15m, such as Fig. 4, aperture is using three presbyopia of mouth " arrangement, array pitch is between tapping point 0.5m, whole hole point linear distance is 10m, and the length of the concordant mash gas pumping drilling 26, which is subject to, covers evaluation unit, institute The diameter for stating concordant mash gas pumping drilling 26 is 135mm.
Specifically, the gas investigates 7 parallel drilling in coal of drilling in step 6, the gas investigates the sealing of hole of drilling 7 Length is 10~15m, and position of opening is located in the middle part of the aperture line of adjacent two concordants mash gas pumping drilling 1, or is located at In the middle part of the aperture line of adjacent two concordants mash gas pumping drilling 26, the borehole bottom location that the gas investigates drilling 7 is located at adjacent two In the middle part of the whole hole line of concordant mash gas pumping drilling 1 or in the whole hole line of adjacent two concordants mash gas pumping drilling 26 Portion, the gas investigate 90~135mm of diameter of drilling 7.
Specifically, being less than 0.74MPa when investigating gas pressure, and gas remainder quantity is less than 8m3When/t, show that extraction reaches It marks, in evaluation unit otherwise coal seam can show that extraction is not up to standard with safe working, and coal seam can not exploit in evaluation unit, need to prolong The long extraction time is until extraction is up to standard.
Low-permeable thin seam working surface gas pumping method proposed by the present invention, is closed on back by the way that working face to be divided into It adopts lane evaluation unit, close on the lane Qie Yan evaluation unit and working face middle part evaluation unit, and taken for different evaluation unit Concordant mash gas pumping drilling, finally connect by different suitable coal bed gas extraction drilling method for arranging with methane gas extraction pipeline, Coal-bed gas in each evaluation unit in extraction working face under suction function, and drilling is investigated to each evaluation unit construction gas, Gas pumping effect is examined, especially for evaluation unit setting construction gas drainage tunnel in the middle part of working face and construction concordant gas Extraction borehole two, further ensures the gas pumping effect in the middle part of working face in evaluation unit, and the mentioned method of the present invention is preferable The working face mash gas pumping drilling as caused by balk, poor air permeability, length are big that solves be easy to be biased to top plate or bottom plate And then lead to gas drainage problem not up to standard, improve coal-bed gas in the middle part of the effective rate of utilization and working face of mash gas pumping drilling Extraction compliance rate, it is ensured that working face safety coal extraction.
It although an embodiment of the present invention has been shown and described, for the ordinary skill in the art, can be with A variety of variations, modification, replacement can be carried out to these embodiments without departing from the principles and spirit of the present invention by understanding And modification, the scope of the present invention is defined by the appended.

Claims (7)

1. a kind of low-permeable thin seam working surface gas pumping method, which is characterized in that it includes following steps:
Step 1: region is divided;The two sides up and down of working face (1) are back production lane (2), and the right side of working face (1) is the lane Qie Yan (4), working face (1) is divided into and closes on back production lane evaluation unit, closes on the lane Qie Yan evaluation unit and the evaluation of working face middle part Unit, separately to carry out gas drainage evaluation to different regions;
Step 2: construction concordant mash gas pumping drilling one (3);First, for back production lane (2) evaluation unit construction concordant watt is closed on This extraction borehole one (3) constructs concordant mash gas pumping drilling one (3) into working face (1) perpendicular to the lane side of back production lane (2); Second, for the lane Qie Yan (4) evaluation unit construction concordant mash gas pumping drilling one (3) is closed on, perpendicular to the lane side of the lane Qie Yan (4) Concordant mash gas pumping drilling one (3) are constructed into working face (1);
Step 3: construction gas drainage tunnel (5);For evaluation unit construction gas drainage tunnel (5) in the middle part of working face, in work While making the tunnelling in the back production lane (2) of face (1) two sides, used from the tunnel of back production lane (2) to the inside of working face (1) The mode of rectangle light section driving tunnels to be formed gas drainage tunnel (5), the axis of the gas drainage tunnel (5) and back production lane (2) axis in tunnel is vertical, and the gas drainage tunnel (5) is tunneled along seat earth, meets head on to be located in the middle part of working face and comment In the middle part of the long side of valence unit;
Step 4: construction concordant mash gas pumping drilling two (6);The construction concordant watt on the end face of meeting head on of gas drainage tunnel (5) This extraction borehole two (6), the concordant mash gas pumping drilling two (6) are arranged in " sector ", along drilling in coal;
Step 5: piping connection;By above-mentioned concordant mash gas pumping drilling one (3) and concordant mash gas pumping drilling two (6) with watt This extraction piping connection, coal-bed gas in each evaluation unit in extraction working face (1) under the action of negative pressure, in methane gas extraction pipeline Negative pressure is not less than 13KPa, tunnel, mining roadway and ground of the methane gas extraction pipeline through gas drainage tunnel (5), back production lane (2) Gas drainage system connection;
Step 6: construction gas investigates drilling (7);Construction gas investigates drilling in each evaluation unit of working face (1) (7), whether up to standard to investigate gas pressure and gas remainder quantity in each evaluation unit.
2. a kind of low-permeable thin seam working surface gas pumping method according to claim 1, which is characterized in that step In one, the width of the working face (1) is L, and the length for closing on evaluation unit in the middle part of back production lane evaluation unit and working face is 150 ~200m, wide is L/3, and the length for closing on the lane Qie Yan evaluation unit is L, width 100m.
3. a kind of low-permeable thin seam working surface gas pumping method according to claim 1, which is characterized in that step In two, the sealed borehole length for closing on the concordant mash gas pumping drilling one (3) in back production lane (2) evaluation unit is 10~15m, Aperture is located in the middle part of coal seam, single arrangement, and pitch of holes is 5~10m, and the concordant gas drainage closed in the evaluation unit of back production lane is bored A length of L/3 in hole one (3), a diameter of 90~135mm;Close on the concordant mash gas pumping drilling one in the evaluation unit of the lane Qie Yan (3) sealed borehole length 10m, aperture are located in the middle part of coal seam, and single arrangement, pitch of holes is 3~5m, close on the lane Qie Yan evaluation unit In concordant mash gas pumping drilling one (3) a length of 100m, a diameter of 90~135mm.
4. a kind of low-permeable thin seam working surface gas pumping method according to claim 1, which is characterized in that step In three, the gas drainage tunnel (5) is arranged in " taking a step " formula, and the section of the gas drainage tunnel (5) is rectangle, the rectangle Width be 3.5m, a height of 2m, gas drainage tunnel (5) length be L/3.
5. a kind of low-permeable thin seam working surface gas pumping method according to claim 1, which is characterized in that step In four, the concordant mash gas pumping drilling two (6) is arranged in " sector ", and along drilling in coal, sealed borehole length is 10~ 15m, aperture use " three presbyopia " arrangement, and array pitch is 0.5m~1m between tapping point, and whole hole point linear distance is 5~ 10m, the length of the concordant mash gas pumping drilling two (6), which is subject to, covers evaluation unit, the concordant mash gas pumping drilling two (6) diameter is 90~135mm.
6. a kind of low-permeable thin seam working surface gas pumping method according to claim 1, which is characterized in that step In six, the gas investigates the parallel drilling in coal of drilling (7), and the sealed borehole length that the gas investigates drilling (7) is 10~15m, Its position of opening is located in the middle part of the aperture line of adjacent two concordants mash gas pumping drilling one (3), or is located at adjacent two concordant watt In the middle part of the aperture line of this extraction borehole two (6), the borehole bottom location that the gas investigates drilling (7) is located at adjacent two concordants gas In the middle part of the whole hole line of extraction borehole one (3) or in the middle part of the whole hole line of adjacent two concordants mash gas pumping drilling two (6), institute State 90~135mm of diameter that gas investigates drilling (7).
7. a kind of low-permeable thin seam working surface gas pumping method according to claim 1, which is characterized in that described In step 6, it is less than 0.74MPa when investigating gas pressure, and gas remainder quantity is less than 8m3When/t, shows that extraction is up to standard, comment In valence unit otherwise coal seam can show that extraction is not up to standard with safe working, and coal seam can not exploit in evaluation unit, need to extend extraction Time is until extraction is up to standard.
CN201910404271.6A 2019-05-15 2019-05-15 Low-permeability thin coal seam working face gas extraction method Active CN109944630B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910404271.6A CN109944630B (en) 2019-05-15 2019-05-15 Low-permeability thin coal seam working face gas extraction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910404271.6A CN109944630B (en) 2019-05-15 2019-05-15 Low-permeability thin coal seam working face gas extraction method

Publications (2)

Publication Number Publication Date
CN109944630A true CN109944630A (en) 2019-06-28
CN109944630B CN109944630B (en) 2020-08-25

Family

ID=67017317

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910404271.6A Active CN109944630B (en) 2019-05-15 2019-05-15 Low-permeability thin coal seam working face gas extraction method

Country Status (1)

Country Link
CN (1) CN109944630B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110685732A (en) * 2019-09-29 2020-01-14 华北科技学院 Coal seam drilling gas extraction method based on extraction pipeline valve control
CN110836114A (en) * 2019-11-21 2020-02-25 中煤科工集团重庆研究院有限公司 Method for treating coal mine rock burst and gas composite disaster

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4544208A (en) * 1984-07-23 1985-10-01 Concoco Inc. Degasification of coal
CN103670496A (en) * 2013-12-12 2014-03-26 中国矿业大学 Gob-side entry retaining and sectional coal seam gas pre-extracting method for single low-permeability outburst coal seam
CN103775127A (en) * 2013-12-31 2014-05-07 中国矿业大学 Method for comprehensively treating gas in low-air-permeability high-gas-content coal seam group
CN104018874A (en) * 2014-06-13 2014-09-03 中煤科工集团重庆研究院有限公司 Method for pre-pumping working face gas by bedding drilling
CN105927269A (en) * 2016-06-28 2016-09-07 杨国和 Gas control method of outburst coal seam
CN108590741A (en) * 2018-05-02 2018-09-28 辽宁工程技术大学 A kind of super high seam mash gas pumping drilling method for arranging

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4544208A (en) * 1984-07-23 1985-10-01 Concoco Inc. Degasification of coal
CN103670496A (en) * 2013-12-12 2014-03-26 中国矿业大学 Gob-side entry retaining and sectional coal seam gas pre-extracting method for single low-permeability outburst coal seam
CN103775127A (en) * 2013-12-31 2014-05-07 中国矿业大学 Method for comprehensively treating gas in low-air-permeability high-gas-content coal seam group
CN104018874A (en) * 2014-06-13 2014-09-03 中煤科工集团重庆研究院有限公司 Method for pre-pumping working face gas by bedding drilling
CN105927269A (en) * 2016-06-28 2016-09-07 杨国和 Gas control method of outburst coal seam
CN108590741A (en) * 2018-05-02 2018-09-28 辽宁工程技术大学 A kind of super high seam mash gas pumping drilling method for arranging

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
何国益: "《矿井瓦斯治理实用技术》", 30 November 2017, 煤炭工业出版社 *
刘益文等: "《南方煤矿瓦斯抽采与利用实用技术》", 31 October 2009, 中国矿业大学出版社 *
崔崇斌: "马兰矿工作面瓦斯综合防治措施研究", 《能源与环保》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110685732A (en) * 2019-09-29 2020-01-14 华北科技学院 Coal seam drilling gas extraction method based on extraction pipeline valve control
CN110836114A (en) * 2019-11-21 2020-02-25 中煤科工集团重庆研究院有限公司 Method for treating coal mine rock burst and gas composite disaster

Also Published As

Publication number Publication date
CN109944630B (en) 2020-08-25

Similar Documents

Publication Publication Date Title
CN101915083B (en) Method for extracting coalbed gases from coal mines by upper and lower combination
CN102619552B (en) Directional hydraulic pressing penetration, permeability increase and outburst elimination method of guide groove
CN103670496B (en) Single low permeability outburst coal seam gob side entry retaining with take out section coal-bed gas method in advance
CN101575983B (en) Directional fracturing permeability improvement outburst elimination method in coal mine and device thereof.
CN102587959B (en) Method for draining coal seam gas
CN100526606C (en) Method for extracting protruded coal-bed downward bedding long-borehole step-by-step covering area gas
CN105909254B (en) Projecting coal bed bottom plate, which is faced upward, wears the advanced area cover coal roadway tunneling method of layer directional hole
CN104131831A (en) Coal-bed gas well vertical three-dimensional united extraction method
CN108301866B (en) Mining of closed distance coal seam group adjacent layer gas pressure relief directional drilling stops pumping method
CN104314610A (en) Outburst eliminating method for coal roadway stripe region
CN107120137B (en) A kind of coal roadway tunneling is along seat earth Deephole pre-splitting blasting pumping method
CN103510958B (en) A kind of gentle dip super-high seam rock cross-cut coal uncovering
CN103147734A (en) Method for multi-section hydraulic fracture along coal layer of underground coal mine
CN103899348A (en) Method for fast extracting gas on coalface
WO2020006870A1 (en) Gas extraction hole drilling and hole sealing method for building anti-seepage barrier based on grooving-backfilling method
CN104018874A (en) Method for pre-pumping working face gas by bedding drilling
CN102678166B (en) Method for increasing gas extraction rate by permeability increasing of single thick coal seam
CN109944630A (en) A kind of low-permeable thin seam working surface gas pumping method
CN102587958A (en) Method for mining coal seam gas
CN108316964A (en) A kind of low air permeability coal seam pressure relief gas pumping mining method
CN104819008B (en) A kind of efficient pumping method of coal-bed gas
CN109098711A (en) It is a kind of to block the heavily stressed method in ore body top using pressure relief groove
CN106014345B (en) A kind of lower part caving method exploits the pumping method for the compound old dead zone coal bed gas to be formed
CN107956467A (en) A kind of high seam pre-draining borehole parameter optimization and the method for extracting result assessment
CN105351000A (en) Goaf roof high-position directional borehole gas extraction technology

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant