CN109914800B - 一种民用建筑联排线管精确预安装结构和施工方法 - Google Patents
一种民用建筑联排线管精确预安装结构和施工方法 Download PDFInfo
- Publication number
- CN109914800B CN109914800B CN201910197042.1A CN201910197042A CN109914800B CN 109914800 B CN109914800 B CN 109914800B CN 201910197042 A CN201910197042 A CN 201910197042A CN 109914800 B CN109914800 B CN 109914800B
- Authority
- CN
- China
- Prior art keywords
- steel
- fixed
- main structure
- steel bars
- sleeve
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Landscapes
- Mutual Connection Of Rods And Tubes (AREA)
- Forms Removed On Construction Sites Or Auxiliary Members Thereof (AREA)
- Joining Of Building Structures In Genera (AREA)
- Reinforcement Elements For Buildings (AREA)
Abstract
本发明公开了一种民用建筑联排线管精确预安装结构和施工方法,包括固定支架、主体结构钢筋;固定支架包括角钢、套筒和固定钢筋,套筒固定在角钢上,角钢的两侧设置固定钢筋;联排线管插入套筒中;主体结构钢筋包括主体结构定位钢筋和主体结构竖向钢筋,主体结构定位钢筋水平固定,主体结构竖向钢筋与固定的主体结构定位钢筋连接;固定钢筋与主体结构竖向钢筋用铁丝绑扎牢固,绑扎铁丝采用八字扣绑扎。本发明用工具式支架固定定位,定位精确,预埋固定强度好,用工合理,准确、高效的进行联排线管预埋固定。
Description
技术领域
本发明涉及一种民用建筑联排线管精确预安装结构和施工方法。
背景技术
相比较以往主体结构砼浇筑施工时联排线管预埋固定的施工方法,采用工具式民用建筑联排线管精确预埋施工方法,在主体结构砼浇筑之前对联排线管进行预埋固定,用工具式钢支架固定定位,定位精确,预埋固定强度好,用工合理,准确、高效的进行联排线管预埋固定。
发明内容
本发明的目的在于克服现有技术的不足,提供一种民用建筑联排线管精确预安装结构和施工方法。
本发明的目的是通过以下技术方案来实现的:
一种微调式民用建筑联排线管精确预安装结构,包括固定支架、主体结构钢筋;
固定支架包括角钢、套筒和固定钢筋,套筒固定在角钢上,角钢的两侧设置固定钢筋;
联排线管插入套筒中;
主体结构钢筋包括主体结构定位钢筋和主体结构竖向钢筋,主体结构定位钢筋水平固定,主体结构竖向钢筋与固定的主体结构定位钢筋连接;
固定钢筋与主体结构竖向钢筋用铁丝绑扎牢固,绑扎铁丝采用八字扣绑扎。
作为优选方式,所述的套筒为钢套筒。
作为优选方式,固定钢筋的长度不超过建筑剪力墙厚度。
作为优选方式,联排线管为联排PVC线管。
作为优选方式,将要预埋的联排线管顶部修整平齐。
作为优选方式,主体结构竖向钢筋与固定的主体结构定位钢筋通过钢丝绑扎在一起。
作为优选方式,套管的数量与将要预埋的联排线管数量一致,根据联排线管预埋间距在角钢边肢上铣孔成为孔洞,孔洞直径大于联排线管直径,孔洞上口焊接一截钢套管。
作为优选方式,钢套管顶部焊接一截薄钢板封顶。
作为优选方式,角钢的两侧焊接固定钢筋。
一种微调式民用建筑联排线管精确施工方法:
步骤一:截取一段角钢,根据联排线管预埋间距,在角钢边肢上铣孔,孔洞直径大于线管直径,孔洞上口焊接一截同孔洞直径的钢套管,钢套管顶部焊接一截薄钢板封顶,角钢两侧各焊接一根短钢筋;
步骤二:将要预埋的联排线管顶部修整平齐,将各线管插入套筒中,检查每个联排线管的位置准确;
步骤三:在角钢的两端水平安装固定钢筋,而角钢的下方水平安装主体结构定位钢筋,固定钢筋的水平方向与主体结构定位钢筋的水平方向相交,固定钢筋与主体结构定位钢筋之间安装主体结构竖向钢筋,主体结构竖向钢筋与固定钢筋之间用铁丝绑扎牢固,而主体结构竖向钢筋与主体结构定位钢筋之间同样用铁丝绑扎牢固,绑扎铁丝采用八字扣绑扎;
步骤四:砼浇筑完成后,将固定支架的绑扎铁丝拆除,固定支架整体移除。
本发明的有益效果是:本发明用工具式支架固定定位,定位精确,预埋固定强度好,用工合理,准确、高效的进行联排线管预埋固定。
附图说明
图1为管线固定支架制作示意图;
图2为联排线管支架安装示意图;
图3为联排线管支架固定示意图;
图中,1-角钢,2-钢套管,3-封顶钢板,4-固定钢筋,5-联排PVC线管,6-主体结构定位钢筋,7-主体结构竖向钢筋。
具体实施方式
下面结合附图进一步详细描述本发明的技术方案,但本发明的保护范围不局限于以下所述。
如图1-图3所示,一种微调式民用建筑联排线管精确预安装结构,包括固定支架、主体结构钢筋;
固定支架包括角钢1、套筒和固定钢筋4,套筒固定在角钢1上,角钢1的两侧设置固定钢筋4;
联排线管插入套筒中;
主体结构钢筋包括主体结构定位钢筋6和主体结构竖向钢筋7,主体结构定位钢筋6水平固定,主体结构竖向钢筋7与固定的主体结构定位钢筋6连接;
固定钢筋4与主体结构竖向钢筋7(或主体结构定位横筋)通过铁丝绑扎在一起,绑扎铁丝采用八字扣绑扎。
在一个优选实施例中,所述的套筒为钢套筒。
在一个优选实施例中,固定钢筋4的长度不超过建筑剪力墙厚度(或设计的剪力墙厚度)。
在一个优选实施例中,联排线管为联排PVC线管5。
在一个优选实施例中,将要预埋的联排线管顶部修整平齐。
在一个优选实施例中,主体结构竖向钢筋7与固定的主体结构定位钢筋6通过钢丝绑扎在一起或者焊接在一起。
在一个优选实施例中,套管的数量与将要预埋的联排线管数量一致,根据联排线管预埋间距在角钢1边肢上铣孔成为孔洞,孔洞直径大于联排线管直径(大1mm-5mm),孔洞上口焊接一截同孔洞直径一致的钢套管2。
在一个优选实施例中,钢套管2顶部焊接一截薄钢板封顶。
在一个优选实施例中,角钢1的两侧焊接固定钢筋4。
一种微调式民用建筑联排线管精确施工方法:
步骤一:截取一段角钢1,根据联排线管预埋间距,在角钢1边肢上铣孔,孔洞直径大于线管直径,孔洞上口焊接一截同孔洞直径的钢套管2,钢套管2顶部焊接一截薄钢板封顶,角钢1两侧各焊接一根短钢筋,短钢筋长度同剪力墙厚度;
步骤二:将要预埋的联排线管顶部修整平齐,将各线管插入套筒中,线管固定支架从上向下套于预埋线管顶部,检查每个联排线管的位置准确,联排各线管插入支架各钢套管2内;
步骤三:在角钢1的两端水平安装固定钢筋4,而角钢1的下方水平安装主体结构定位钢筋6,固定钢筋4的水平方向与主体结构定位钢筋6的水平方向相交,固定钢筋4与主体结构定位钢筋6之间安装主体结构竖向钢筋7,主体结构竖向钢筋7与固定钢筋4之间用铁丝绑扎牢固,而主体结构竖向钢筋7与主体结构定位钢筋6之间同样用铁丝绑扎牢固,绑扎铁丝采用八字扣绑扎;
步骤四:砼浇筑完成后,将固定支架的绑扎铁丝拆除,固定支架整体移除,在其他楼层、楼栋重复使用。
实施例具备以下优势:
1、根据建筑联排线管间距、数量和施工进度,提前进行支架的整体制作,可进行模块化或工厂化制作,提高施工效率。
2、采用钢套管2角钢1固定,强度高,固定效果稳固,安装位置准确。
3、支架轻便、安装、拆卸灵活方便,重复利用率高,降低辅材用量。
5、联排线管整体固定,操作简易,提高工效,降低人工费用。
6、用工具式联排线管体预埋精确预埋施工方法施工,提高工序穿插,施工效率高、减少辅材用料、节约人工、缩短工期、施工过程可调整、提高施工质量,产生了很大的经济效益,同时也有较大的社会效益和较高的推广应用价值。
以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,应当指出的是,凡在本发明的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本发明的保护范围之内。
Claims (10)
1.一种微调式民用建筑联排线管精确预安装结构,其特征在于:包括固定支架、主体结构钢筋;
固定支架包括角钢、套筒和固定钢筋,套筒固定在角钢上,角钢的两侧设置固定钢筋;
联排线管插入套筒中;
主体结构钢筋包括主体结构定位钢筋和主体结构竖向钢筋,主体结构定位钢筋水平固定,主体结构竖向钢筋与固定的主体结构定位钢筋连接;
固定钢筋与主体结构竖向钢筋用铁丝绑扎牢固,绑扎铁丝采用八字扣绑扎。
2.根据权利要求1所述的一种微调式民用建筑联排线管精确预安装结构,其特征在于:所述的套筒为钢套筒。
3.根据权利要求1所述的一种微调式民用建筑联排线管精确预安装结构,其特征在于:固定钢筋的长度不超过建筑剪力墙厚度。
4.根据权利要求1所述的一种微调式民用建筑联排线管精确预安装结构,其特征在于:联排线管为联排PVC线管。
5.根据权利要求1所述的一种微调式民用建筑联排线管精确预安装结构,其特征在于:将要预埋的联排线管顶部修整平齐。
6.根据权利要求1所述的一种微调式民用建筑联排线管精确预安装结构,其特征在于:主体结构竖向钢筋与固定的主体结构定位钢筋通过钢丝绑扎在一起。
7.根据权利要求1所述的一种微调式民用建筑联排线管精确预安装结构,其特征在于:套管的数量与将要预埋的联排线管数量一致,根据联排线管预埋间距在角钢边肢上铣孔成为孔洞,孔洞直径大于联排线管直径,孔洞上口焊接一截钢套管。
8.根据权利要求7所述的一种微调式民用建筑联排线管精确预安装结构,其特征在于:钢套管顶部焊接一截薄钢板封顶。
9.根据权利要求1所述的一种微调式民用建筑联排线管精确预安装结构,其特征在于:角钢的两侧焊接固定钢筋。
10.一种微调式民用建筑联排线管精确施工方法,其特征在于:
步骤一:截取一段角钢,根据联排线管预埋间距,在角钢边肢上铣孔,孔洞直径大于线管直径,孔洞上口焊接一截同孔洞直径的钢套管,钢套管顶部焊接一截薄钢板封顶,角钢两侧各焊接一根短钢筋;
步骤二:将要预埋的联排线管顶部修整平齐,将各线管插入套筒中,检查每个联排线管的位置准确;
步骤三:在角钢的两端水平安装固定钢筋,而角钢的下方水平安装主体结构定位钢筋,固定钢筋的水平方向与主体结构定位钢筋的水平方向相交,固定钢筋与主体结构定位钢筋之间安装主体结构竖向钢筋,主体结构竖向钢筋与固定钢筋之间用铁丝绑扎牢固,而主体结构竖向钢筋与主体结构定位钢筋之间同样用铁丝绑扎牢固,绑扎铁丝采用八字扣绑扎;
步骤四:砼浇筑完成后,将固定支架的绑扎铁丝拆除,固定支架整体移除。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910197042.1A CN109914800B (zh) | 2019-03-15 | 2019-03-15 | 一种民用建筑联排线管精确预安装结构和施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910197042.1A CN109914800B (zh) | 2019-03-15 | 2019-03-15 | 一种民用建筑联排线管精确预安装结构和施工方法 |
Publications (2)
Publication Number | Publication Date |
---|---|
CN109914800A CN109914800A (zh) | 2019-06-21 |
CN109914800B true CN109914800B (zh) | 2021-02-26 |
Family
ID=66965088
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910197042.1A Active CN109914800B (zh) | 2019-03-15 | 2019-03-15 | 一种民用建筑联排线管精确预安装结构和施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109914800B (zh) |
Families Citing this family (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111969510A (zh) * | 2020-07-27 | 2020-11-20 | 中冶天工集团有限公司 | 一种电线套管预埋固定装置及其固定方法 |
Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0923553A (ja) * | 1995-07-07 | 1997-01-21 | Fujita Corp | 昇降装置における電源ケーブルの巻出装置と巻出方法 |
JP2005213909A (ja) * | 2004-01-30 | 2005-08-11 | Kameda Denki:Kk | 支持材 |
CN103321436A (zh) * | 2013-07-10 | 2013-09-25 | 成都市第八建筑工程公司 | 建筑砖砌体上线盒预安装施工方法及其预安装支架 |
CN204456862U (zh) * | 2015-02-16 | 2015-07-08 | 北京建工四建工程建设有限公司 | 一种现浇楼板中预埋线管的固定保护件 |
CN105762728A (zh) * | 2016-03-08 | 2016-07-13 | 中国五冶集团有限公司 | 一种预埋强弱电箱及电气配管的方法 |
CN107178210A (zh) * | 2017-07-11 | 2017-09-19 | 中国五冶集团有限公司 | 民建墙体多线盒精确预埋施工方法 |
CN206682430U (zh) * | 2017-04-27 | 2017-11-28 | 中建城市建设发展有限公司 | 一种墙内复杂线管排布固定装置及其墙体结构 |
CN108468431A (zh) * | 2018-05-22 | 2018-08-31 | 中国五冶集团有限公司 | 一种微调式民用建筑电箱精确预安装施工方法和结构 |
CN108539687A (zh) * | 2018-05-22 | 2018-09-14 | 中国五冶集团有限公司 | 一种微调式民用建筑联排线盒精确预安装结构和施工方法 |
-
2019
- 2019-03-15 CN CN201910197042.1A patent/CN109914800B/zh active Active
Patent Citations (9)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH0923553A (ja) * | 1995-07-07 | 1997-01-21 | Fujita Corp | 昇降装置における電源ケーブルの巻出装置と巻出方法 |
JP2005213909A (ja) * | 2004-01-30 | 2005-08-11 | Kameda Denki:Kk | 支持材 |
CN103321436A (zh) * | 2013-07-10 | 2013-09-25 | 成都市第八建筑工程公司 | 建筑砖砌体上线盒预安装施工方法及其预安装支架 |
CN204456862U (zh) * | 2015-02-16 | 2015-07-08 | 北京建工四建工程建设有限公司 | 一种现浇楼板中预埋线管的固定保护件 |
CN105762728A (zh) * | 2016-03-08 | 2016-07-13 | 中国五冶集团有限公司 | 一种预埋强弱电箱及电气配管的方法 |
CN206682430U (zh) * | 2017-04-27 | 2017-11-28 | 中建城市建设发展有限公司 | 一种墙内复杂线管排布固定装置及其墙体结构 |
CN107178210A (zh) * | 2017-07-11 | 2017-09-19 | 中国五冶集团有限公司 | 民建墙体多线盒精确预埋施工方法 |
CN108468431A (zh) * | 2018-05-22 | 2018-08-31 | 中国五冶集团有限公司 | 一种微调式民用建筑电箱精确预安装施工方法和结构 |
CN108539687A (zh) * | 2018-05-22 | 2018-09-14 | 中国五冶集团有限公司 | 一种微调式民用建筑联排线盒精确预安装结构和施工方法 |
Non-Patent Citations (1)
Title |
---|
中小企业管理与科技(下旬刊);周锐;《砌体中机电管线(盒)一次性预埋施工技术研究与开发》;20180125;152-153 * |
Also Published As
Publication number | Publication date |
---|---|
CN109914800A (zh) | 2019-06-21 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN116079890B (zh) | 竖向预制构件竖向钢筋定位装置及竖向预制构件加工方法 | |
CN109914800B (zh) | 一种民用建筑联排线管精确预安装结构和施工方法 | |
CN112302209B (zh) | 钢与混凝土剪力墙混合结构及其制作方法 | |
CN210918232U (zh) | 一种穿梁钢套管安装定位装置 | |
CN107313587A (zh) | 建筑防水结构的模板固定系统和防水结构的施工方法 | |
CN110777656A (zh) | 一种基于bim技术的连续梁0号块施工质量控制方法 | |
JP3673108B2 (ja) | 中空スラブのボイド部材設置方法 | |
CN206815542U (zh) | 一种便捷式牛腿预埋螺栓固定结构 | |
CN111438800A (zh) | 一种高速道路上栅栏板的预制模板体系及其施工方法 | |
CN112096096B (zh) | 预埋钢板的定位装置及其施工方法 | |
CN216239744U (zh) | 一种高层建筑管道井套管预埋定位工具 | |
CN105643791B (zh) | 预制墙体灌浆套筒条状密排外露钢筋精确定位模具 | |
CN210563413U (zh) | 一种用于现浇水平楼板的压槽装置 | |
CN111878636B (zh) | 安装出墙防水套管用的定位架及其施工方法 | |
CN217480794U (zh) | 一种综合管廊腋角导墙模板固定装置 | |
CN111576638A (zh) | 一种墙板预埋件成套施工方法 | |
CN210420851U (zh) | 桥梁支座垫石锚栓孔定位装置 | |
CN211058344U (zh) | 一种简易、快速、高效穿梁钢套管预埋结构 | |
CN111502260A (zh) | 一种厨卫间防水导墙与板整体浇筑定型化模具施工方法 | |
CN209760295U (zh) | 一种地下管廊电力支架预埋t型螺栓固定结构 | |
CN215671080U (zh) | 一种剪力墙暗埋线盒定位装置 | |
CN112482322A (zh) | 一种分缝闸墩施工成套装置以及施工工艺 | |
CN220621135U (zh) | 一种穿梁套管精准定位装置及其安装结构 | |
CN113802773B (zh) | 一种大直径缓粘结预应力筋在大跨度构件的施工方法 | |
CN204326495U (zh) | 一种悬挑外脚手架型钢梁的工具式锚固端的构造 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
GR01 | Patent grant | ||
GR01 | Patent grant |