CN109882240A - A kind of outdoor end side pressure coal filling mining system - Google Patents

A kind of outdoor end side pressure coal filling mining system Download PDF

Info

Publication number
CN109882240A
CN109882240A CN201910246912.XA CN201910246912A CN109882240A CN 109882240 A CN109882240 A CN 109882240A CN 201910246912 A CN201910246912 A CN 201910246912A CN 109882240 A CN109882240 A CN 109882240A
Authority
CN
China
Prior art keywords
filling
tunnel
coal
pipeline
piping
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910246912.XA
Other languages
Chinese (zh)
Other versions
CN109882240B (en
Inventor
周楠
张吉雄
孟国豪
李猛
张卫清
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China University of Mining and Technology CUMT
Original Assignee
China University of Mining and Technology CUMT
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China University of Mining and Technology CUMT filed Critical China University of Mining and Technology CUMT
Priority to CN201910246912.XA priority Critical patent/CN109882240B/en
Publication of CN109882240A publication Critical patent/CN109882240A/en
Priority to PCT/CN2019/109879 priority patent/WO2020199546A1/en
Priority to AU2019439785A priority patent/AU2019439785B2/en
Priority to RU2020136147A priority patent/RU2756537C1/en
Application granted granted Critical
Publication of CN109882240B publication Critical patent/CN109882240B/en
Priority to ZA2020/06726A priority patent/ZA202006726B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings
    • EFIXED CONSTRUCTIONS
    • E21EARTH DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F15/00Methods or devices for placing filling-up materials in underground workings
    • E21F15/06Filling-up mechanically

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Pipe Accessories (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

The invention discloses a kind of outdoor end side pressure coal filling mining system, including the automatic coal cutting of driving, automatic stringing, closing entrance to a lane, pipeline automatic filling, full lane monitor automatically.It when development machine tunnels coal cutting, stretches out mechanical arm dragging filling piping and advances, pipeline is automatically arranged at tunnel side bottom end, after back production, separates with development machine recession mechanical arm with filling piping, pipeline just stays in original place, that is, realizes automatic stringing;The setting monitoring pipeline on the corresponding square position of stowboard issues signal by monitoring pipeline after cemented filling material is full of tunnel, and filling pump stops pumping slurry to filling piping, to complete tunnel filling, that is, realizes that full lane monitors automatically.The technique combines consolidated fill coal winning technology and end side driving coal winning technology, comes out outdoor end side mining pressed coal using unmanned filling operation face, realizes that automation stringing, full lane monitor automatically.

Description

A kind of outdoor end side pressure coal filling mining system
Technical field
The invention belongs to filling in mine production practice fields, and in particular to a kind of outdoor end side pressure coal filling mining system.
Background technique
China part open coal mine is because mining rate is big, and mining time is long, the coal resources easily exploited in Opent-pit limit It is produced and finishes substantially.But pit side slope covers a large amount of coal resources, will cause coal resources if abandoning not adopting Serious waste, is unfavorable for the sustainable development of coal mine, while making country by great resources loss;And the coal left it is long when Between with oxygen contact weathering, be also easy to produce spontaneous fire, periphery natural environment and village caused to seriously threaten safely.
The main method of general recycling side slope pressure coal is to carry out end to help exploitation, but, intensity inadequate feelings imperfect in top plate Side exploitation in end is carried out under condition be easy to cause roof large area inbreak to endanger personnel safety to damage machine;At end, side is opened It needs to stay during adopting and sets a large amount of coal column for safeguarding mining safety, coal column, which stays, sets and will affect coal mining rate, is also easy to produce Spontaneous fire disaster;And side exploitation in end will lead to subsidence again, management of slope is difficult.
Summary of the invention
Goal of the invention: the present invention provides a kind of outdoor end side pressure coal filling mining systems, to overcome existing mining method Deficiency, can either realize the recycling of a large amount of coal resources, and subsidence can be reduced, it is ensured that Stope safty is steady with side slope It is fixed.
The technical solution adopted by the present invention are as follows:
A kind of outdoor end side pressure coal filling mining system of the present invention, has a consisting of: development machine in the case where step is helped at end from Dynamic digging laneway coal cutting, the outlet end of the hinged mechanical arm connection filling piping of the development machine, drags it and is laid in tunnel; Filling pump outside the arrival end connection of the filling piping;The filling pumps the entrance P of external two-position three way magnetic valve, described Two outlets A, B of two-position three way magnetic valve are separately connected filling piping and external wastewater disposal basin in tunnel;It is corresponding in tunnel Square position on vertical drilling to goaf, bury monitoring pipeline, electrode is respectively set in the monitoring channel interior two sides for being higher by square position, External cord to the two-position three way magnetic valve electromagnet.
Further, the mechanical arm is hingedly made of L-shaped hinged arm and clamped arm at top, described clamped The vertical section and horizontal segment of arm are affixed;The hinged arm matching is placed on the inside of clamped arm, is hingedly made of telescopic segment and horizontal segment, Horizontal segment is equipped with several pinned holes;
Reinforced Hoop is installed in the front end of the filling piping, and the Reinforced Hoop is welded with overhanging platform, which is provided with it is described The pinned hole of Corresponding matching on hinged arm horizontal segment.
The telescopic segment of the hinged arm is made of the large and small pipe socket of two sections.
The monitoring pipeline is made of pvc pipe, suitable for reading to be higher by square position 200mm, two sides and the same water of square position earth's surface in pipeline Two electrodes are symmetrically laid at flat position, electrode is mutually not turned on.
Further, a kind of outdoor end side pressure coal filling mining system of the present invention, comprising the following steps:
(1) tunnel automatic coal cutting: development machine tunnels coal cutting automatically, and coal transports tunnel by rubber conveyer;
(2) automatic stringing: development machine stretches out mechanical arm and drags filling piping, constantly promotes with development machine, and filling piping is certainly It is dynamic to be arranged in tunnel side bottom end, when development machine is pushed into stop adopting line, stop coal cutting, equipment withdraws from filling lane, and filling piping is stayed In tunnel;
(3) it closes entrance to a lane: setting up filling bag in roadway entry, utilize filling bag filling expansion, enclosing tunnel entrance;
(4) pipeline automatic filling: filling pump is opened, progress pipeline water-filling, mortar pushes away water, cemented filling material pushes away mortar, pump Send cemented filling material each filling procedure;
(5) full lane monitors automatically: after cemented filling material is full of tunnel, cemented filling material, connection are full of in monitoring pipeline Two lateral electrodes issue signal to two-position three way magnetic valve by monitoring pipeline, and control filling pump, which stops pumping to filling piping, expects Slurry realizes that full lane monitors automatically, completes tunnel filling.
Further, the automatic stringing technique are as follows:
Before development machine enters tunnel, the hinged arm and Reinforced Hoop of mechanical arm are assembled with pin, when development machine advances, Mechanical arm is linked together with Reinforced Hoop, dragging filling piping advance forward, to back production after, clamped arm is dropped back with development machine, Its pin supported gradually falls off, and final hinged arm is separated with Reinforced Hoop, and filling piping just stays in original place.
Further, the full lane monitors technique automatically are as follows:
When tunnel is unfilled full, monitors in pipeline without cemented filling material, be not turned between two electrodes, two-position three way Solenoid valve is in normal position state, i.e. filling pump is connect with filling piping, carries out tunnel filling;After tunnel is full of, the monitoring pipe Be full of cemented filling material in road, be connected between two electrodes, two-position three way magnetic valve is in obtain electrical excitation state, i.e., filling pump with Wastewater disposal basin connection, interior cemented filling material are passed through wastewater disposal basin, and tunnel filling terminates.
The utility model has the advantages that a kind of outdoor end side pressure coal filling mining system provided by the invention has compared with prior art Following advantage:
(1) it present invention incorporates the consolidated fill coal winning technology and end side driving coal winning technology for well industrial and mineral, solves Opencut end is helped to cover the recycling problem of coal resources, improves resource recovery.
(2) present invention realizes coal mining, filling automation, and working face is unmanned, can effectively improve working surface production effect Rate and production security reduce production cost and labor intensity of workers.
(3) scale of the present invention has handled the solid waste such as spoil and casting, meets the requirement of Green Mine development;Subtract Lack end side exploitation bring subsidence, meets the requirement for keeping slope stability.
Detailed description of the invention
Fig. 1 is the outdoor end side mining pressed coal process schematic representation of the present invention;
Fig. 2 is the outdoor end side pressure coal filling process schematic diagram of the present invention;
Fig. 3 is the clamped arm schematic diagram of the present invention;
Fig. 4 is the hinged arm schematic diagram of the present invention;
Fig. 5 is Reinforced Hoop schematic diagram of the present invention;
Fig. 6 is present invention monitoring pipeline schematic diagram;
Fig. 7 is mechanical arm dragging pipeline schematic diagram of the present invention;
Fig. 8 is that mechanical arm of the present invention is detached from pipeline schematic diagram;
Fig. 9 is the full lane Automatic monitoring principle schematic diagram of the present invention;
In figure: 1, development machine, 2, end side step, 3, tunnel, 4, end side pressure coal, 5, filling piping, 6, filling bag, 7, filling Pump, 8, monitoring pipeline, 9, wastewater disposal basin, 10, Reinforced Hoop, 11, overhanging platform, 12, mechanical arm, 121, hinged arm, 122, clamped arm, 13, pin, 141, electrode a, 142, electrode b, 15, slurry bucket, 16, two-position three way magnetic valve, 17, electromagnet.
Specific embodiment
The present invention provides a kind of outdoor end side pressure coal filling mining technique, can either realize the recycling of a large amount of coal resources, Subsidence can be reduced again, it is ensured that Stope safty and stability of slope.
The present invention will be further explained with reference to the accompanying drawing.
A kind of outdoor end side pressure coal filling mining system of the present invention, as shown in Figure 1, 2, have consisting of: development machine 1 exists Automatic digging laneway 3 under end side step 2, exploitation end side pressure coal 4, coal by 1 raking pawl of development machine is packed into middle part scraper-trough conveyer, and to go to adhesive tape defeated It sending on machine, and tunnel 3 is transported by rubber conveyer, the hinged mechanical arm of the development machine 1 connects the outlet end of filling piping, with Development machine 1 constantly promotes, and drags it and is laid in tunnel 3;Filling pump 7 outside the arrival end connection of the filling piping 5;Institute The entrance P of filling 7 external two-position three way magnetic valves 16 of pump is stated, two outlets A, B of the two-position three way magnetic valve 16 connect respectively Connect the filling piping 5 in tunnel and external wastewater disposal basin 9;Vertical drilling buries prison to goaf on the corresponding square position in tunnel 3 Electrode, external cord to the two-position three way magnetic valve is respectively set in test tube road 8, the 8 inside two sides of monitoring pipeline for being higher by square position 16 electromagnet 17.
Further, the mechanical arm 12 is hingedly made of L-shaped hinged arm 121 and clamped arm 122 at top, The vertical section and horizontal segment of the clamped arm 122 are affixed, as shown in Figure 3;The matching of hinged arm 121 is placed in clamped arm 122 Side is hingedly made of telescopic segment and horizontal segment, and horizontal segment is equipped with several pinned holes, as shown in Figure 4;
The telescopic segment of the hinged arm is made of the large and small pipe socket of two sections.
Reinforced Hoop 10 is installed in the front end of the filling piping 5, as shown in figure 5, the Reinforced Hoop 10 is welded with overhanging platform 11, it which is provided with the pinned hole with Corresponding matching on hinged 121 horizontal segment of arm;
The monitoring pipeline 8 is made of pvc pipe, suitable for reading to be higher by square position 200mm, two sides and the same water of square position earth's surface in pipeline Two electrodes are symmetrically laid at flat position, electrode is mutually not turned on, as shown in Figure 6.
Further, a kind of outdoor end side pressure coal filling mining system of the present invention, comprising the following steps:
(1) tunnel automatic coal cutting: driving coal cutting, coal transport tunnel 3 by rubber conveyer to development machine 1 automatically;
(2) automatic stringing: development machine 1 stretches out mechanical arm 12 and drags filling piping 5, constantly promotes with development machine, filling pipe Road 5 is automatically arranged at 3 side bottom end of tunnel, when development machine 1 is pushed into stop adopting line, stop coal cutting, voluntarily retreated using unit and Development machine 1 and rubber conveyer are withdrawn from into tunnel 3 in a manner of drawing outside loading machine auxiliary force, filling piping 5 stays in tunnel;
(3) it closes entrance to a lane: setting up filling bag 6 in roadway entry, utilize filling bag filling expansion, enclosing tunnel entrance;
(4) pipeline automatic filling: filling pump 7 is opened, progress pipeline water-filling, mortar pushes away water, cemented filling material pushes away mortar, pump Send cemented filling material each filling procedure;
(5) full lane monitors automatically: after cemented filling material is full of tunnel, cemented filling material, connection are full of in monitoring pipeline Two lateral electrodes issue signal to two-position three way magnetic valve 16 by monitoring pipeline, and control filling pump 7 stops pumping to filling piping 5 Feeding slurry realizes that full lane monitors automatically, completes tunnel filling.
Further, the automatic stringing technique are as follows:
Before development machine 1 enters tunnel 3, the hinged arm 121 of mechanical arm 12 and the pin 13 of Reinforced Hoop 10 are assembled, dug When advancing into machine 1, mechanical arm 12 is linked together with Reinforced Hoop 10, and dragging filling piping 5 is advanced forward, as shown in Figure 7;To back production After, clamped arm 122 is dropped back with development machine 1, and the pin 13 of support gradually falls off, final hinged arm 121 and Reinforced Hoop 10 Separation, filling piping 5 just stay in original place, as shown in Figure 8.
Further, the full lane monitors technique automatically are as follows:
When tunnel is unfilled full, monitors in pipeline 8 without cemented filling material, be not turned between two electrodes, two three Three-way electromagnetic valve 16 is in normal position state, i.e., filling pump 7 is connect with filling piping 5, carries out tunnel filling;It is described after tunnel is full of It monitoring and is full of cemented filling material in pipeline 8, be connected between two electrodes, two-position three way magnetic valve 16 is in obtain electrical excitation state, I.e. filling pump 7 is connect with wastewater disposal basin 9, and interior cemented filling material is passed through wastewater disposal basin 9, and tunnel filling terminates, as shown in Figure 9.

Claims (7)

1. a kind of outdoor end side pressure coal filling mining system, which is characterized in that development machine (1) is helped to dig automatically under step (2) at end Into tunnel (3) coal cutting, the outlet end of hinged mechanical arm (12) connection filling piping (5) of the development machine (1) drags its laying In tunnel (3);Filling outside the arrival end connection of the filling piping (5) pumps (7);
Two of the entrance P of the filling pump (7) external two-position three way magnetic valve (16), the two-position three way magnetic valve (16) go out Mouth A, B are separately connected filling piping (5) and external wastewater disposal basin (9) in tunnel;
Vertical drilling buries monitoring pipeline (8), is higher by the monitoring pipeline of square position to goaf on tunnel (3) corresponding square position (8) electrode, the electromagnet (17) of external cord to the two-position three way magnetic valve (16) is respectively set in internal two sides.
2. a kind of outdoor end side pressure coal filling mining system according to claim 1, which is characterized in that the mechanical arm (12) be hingedly made of L-shaped hinged arm (121) and clamped arm (122) at top, the clamped arm (122) it is vertical Section and horizontal segment are affixed;Hinged arm (121) matching is placed on the inside of clamped arm (122), by hinged group of telescopic segment and horizontal segment At horizontal segment is equipped with several pinned holes;
Reinforced Hoop (10) are installed in the front end of the filling piping (5), and the Reinforced Hoop (10) is welded with overhanging platform (11), thereon Equipped with the pinned hole with Corresponding matching on hinged arm (121) horizontal segment.
3. a kind of outdoor end side pressure coal filling mining system according to claim 2, which is characterized in that the hinged arm (121) telescopic segment is made of the large and small pipe socket of two sections.
4. a kind of outdoor end side pressure coal filling mining system according to claim 1, which is characterized in that the monitoring pipeline (8) it is made of pvc pipe, it is suitable for reading to be higher by square position 200mm, it is symmetrically laid at two sides and the position of square position earth's surface same level in pipeline Two electrodes, electrode are mutually not turned on.
5. a kind of production practice of outdoor end side pressure coal filling mining system according to claim 1 to 4, feature It is, comprising the following steps:
(1) tunnel automatic coal cutting: development machine (1) tunnels coal cutting automatically, and coal transports tunnel (3) by rubber conveyer;
(2) automatic stringing: development machine (1) stretches out mechanical arm (12) dragging filling piping (5), constantly promotes with development machine, fills Pipeline (5) is automatically arranged at tunnel (3) side bottom end, when development machine (1) is pushed into stop adopting line, stops coal cutting, equipment, which is withdrawn from, fills Lane is filled out, filling piping (5) stays in tunnel;
(3) it closes entrance to a lane: setting up filling bag (6) in roadway entry, utilize filling bag filling expansion, enclosing tunnel entrance;
(4) pipeline automatic filling: filling pump (7) is opened, progress pipeline water-filling, mortar pushes away water, cemented filling material pushes away mortar, pumping Each filling procedure of cemented filling material;
(5) full lane monitors automatically: after cemented filling material is full of tunnel, being full of cemented filling material in monitoring pipeline, is connected to two sides Electrode issues signal to two-position three way magnetic valve (16) by monitoring pipeline, and control filling pump (7) stops to filling piping (5) Slurry is pumped, realizes that full lane monitors automatically, completes tunnel filling.
6. a kind of production practice of outdoor end side pressure coal filling mining system according to claim 5, which is characterized in that from Dynamic stringing technique are as follows:
Before development machine (1) enters tunnel (3), the hinged arm (121) of mechanical arm (12) and Reinforced Hoop (10) are used into pin (13) group It loads, when development machine (1) advances, mechanical arm (12) is linked together with Reinforced Hoop (10), drags filling piping (5) Xiang Qianhang Into, to back production after, clamped arm (122) is dropped back with development machine (1), and the pin (13) of support gradually falls off, final hinged Arm (121) is separated with Reinforced Hoop (10), and filling piping (5) just stays in original place.
7. a kind of production practice of outdoor end side pressure coal filling mining system according to claim 5, which is characterized in that full Lane monitors technique automatically are as follows:
When tunnel is unfilled full, without cemented filling material in monitoring pipeline (8), it is not turned between two electrodes, two-position three way Solenoid valve (16) is in normal position state, i.e., filling pump (7) is connect with filling piping (5), carries out tunnel filling;
After tunnel is full of, it is full of cemented filling material in the monitoring pipeline (8), is connected between two electrodes, two-position three way electricity Magnet valve (16) is in obtain electrical excitation state, i.e., filling pump (7) is connect with wastewater disposal basin (9), and interior cemented filling material is passed through waste water Pond (9), tunnel filling terminates.
CN201910246912.XA 2019-03-29 2019-03-29 Open-air end slope coal-pressing filling mining system Active CN109882240B (en)

Priority Applications (5)

Application Number Priority Date Filing Date Title
CN201910246912.XA CN109882240B (en) 2019-03-29 2019-03-29 Open-air end slope coal-pressing filling mining system
PCT/CN2019/109879 WO2020199546A1 (en) 2019-03-29 2019-10-08 Pressed coal filling mining system and process for end slope of open pit
AU2019439785A AU2019439785B2 (en) 2019-03-29 2019-10-08 Pressed coal filling mining system and process for end slope of open pit
RU2020136147A RU2756537C1 (en) 2019-03-29 2019-10-08 System for development of cemented coal and process of open mining on a longitudinal slope
ZA2020/06726A ZA202006726B (en) 2019-03-29 2020-10-28 Pressed coal filling mining system and process for end slope of open pit

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910246912.XA CN109882240B (en) 2019-03-29 2019-03-29 Open-air end slope coal-pressing filling mining system

Publications (2)

Publication Number Publication Date
CN109882240A true CN109882240A (en) 2019-06-14
CN109882240B CN109882240B (en) 2020-04-14

Family

ID=66935120

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910246912.XA Active CN109882240B (en) 2019-03-29 2019-03-29 Open-air end slope coal-pressing filling mining system

Country Status (5)

Country Link
CN (1) CN109882240B (en)
AU (1) AU2019439785B2 (en)
RU (1) RU2756537C1 (en)
WO (1) WO2020199546A1 (en)
ZA (1) ZA202006726B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110284883A (en) * 2019-07-08 2019-09-27 中国矿业大学 Recovery method is filled by a kind of row of adopting, open coal mine end side
CN111075505A (en) * 2019-12-17 2020-04-28 天地科技股份有限公司 Coal mine fully-mechanized coal mining face segmented filling mining method
CN111236943A (en) * 2020-02-27 2020-06-05 中煤能源研究院有限责任公司 Mining method for advancing, cutting and retreating filling of open-air end slope
CN111364998A (en) * 2020-03-12 2020-07-03 中煤能源研究院有限责任公司 Single-side edge filling and tunneling mining method for open-pit mine end slope coal pressing
CN111396055A (en) * 2020-03-24 2020-07-10 中煤科工集团沈阳设计研究院有限公司 Method for arranging side coal pressing mining chamber of strip mine
WO2020199546A1 (en) * 2019-03-29 2020-10-08 中国矿业大学 Pressed coal filling mining system and process for end slope of open pit
CN112855162A (en) * 2021-01-29 2021-05-28 辽宁工程技术大学 Mining method for upper coal seam of composite coal seam strip mine near extraction end slope
CN112963618A (en) * 2021-05-19 2021-06-15 中煤科工能源科技发展有限公司 Method and device for long-distance laying and continuous filling of filling pipeline of side coal mining cave

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4323280A (en) * 1976-11-30 1982-04-06 Coalex, Inc. Remote controlled high wall coal mining system
CN102444420A (en) * 2011-12-31 2012-05-09 山东科技大学 Dragging tube type filling method of thin coal bed fractured roof
CN103758568A (en) * 2014-02-14 2014-04-30 中国矿业大学 Opencast coal mine end slope filling mining method
CN103821515A (en) * 2014-02-20 2014-05-28 山西晋煤集团技术研究院有限责任公司 Double-unit face filling and mining technology
CN104074521A (en) * 2014-06-20 2014-10-01 中国矿业大学 End slope coal bed remote control excavating mining method
CN106327731A (en) * 2016-10-19 2017-01-11 中铁隧道集团第五建筑有限公司 Anti-void monitor for tunnel lining concrete vault
CN207676227U (en) * 2017-12-28 2018-07-31 甘肃大漠紫光生物科技有限公司 A kind of cistern water auto-regulation system
CN108825299A (en) * 2018-05-30 2018-11-16 贵州锦丰矿业有限公司 A kind of movable type filling pipeline device and construction method

Family Cites Families (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2055218C1 (en) * 1992-08-10 1996-02-27 Научно-исследовательский, проектный и конструкторский институт горного дела и металлургии цветных металлов Method for different strength backfills of underground drifts and device for implementation the same
DE4443130A1 (en) * 1994-12-03 1996-06-13 Hoelter Heinz Monitoring biological activity of packing and filling materials for disposal in mines
RU2099524C1 (en) * 1996-05-17 1997-12-20 Акционерное общество Угольная компания "Прокопьевскуголь" Combined method of mining of formation of steeply dipping coal seams
CN102121397B (en) * 2010-12-27 2012-12-26 淄博矿业集团有限责任公司 Paste filling pipeline system for coal mine
RU2521234C1 (en) * 2013-01-29 2014-06-27 Федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Национальный минерально-сырьевой университет "Горный" Creation of filling massif at development of deposit under permafrost conditions
RU2522495C1 (en) * 2013-02-19 2014-07-20 Федеральное государственное бюджетное образовательное учреждение высшего профессионального образования "Национальный минерально-сырьевой университет "Горный" Complete stowage of bottom layer breakage cuts at declining excavation of minerals
CN103939102B (en) * 2014-04-14 2016-09-28 中国矿业大学 A kind of solid filling reclaims opencut side eventually and presses down the coal-mining method of coal
CN107313804B (en) * 2017-06-29 2019-05-17 中国矿业大学 A kind of open coal mine end side pressure coal filling fully mechanized mining recovery method
CN109667618A (en) * 2019-02-25 2019-04-23 闫红世 A kind of grouting vehicle backfilling coal cutting roadway
CN109882240B (en) * 2019-03-29 2020-04-14 中国矿业大学 Open-air end slope coal-pressing filling mining system

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4323280A (en) * 1976-11-30 1982-04-06 Coalex, Inc. Remote controlled high wall coal mining system
CN102444420A (en) * 2011-12-31 2012-05-09 山东科技大学 Dragging tube type filling method of thin coal bed fractured roof
CN103758568A (en) * 2014-02-14 2014-04-30 中国矿业大学 Opencast coal mine end slope filling mining method
CN103821515A (en) * 2014-02-20 2014-05-28 山西晋煤集团技术研究院有限责任公司 Double-unit face filling and mining technology
CN104074521A (en) * 2014-06-20 2014-10-01 中国矿业大学 End slope coal bed remote control excavating mining method
CN106327731A (en) * 2016-10-19 2017-01-11 中铁隧道集团第五建筑有限公司 Anti-void monitor for tunnel lining concrete vault
CN207676227U (en) * 2017-12-28 2018-07-31 甘肃大漠紫光生物科技有限公司 A kind of cistern water auto-regulation system
CN108825299A (en) * 2018-05-30 2018-11-16 贵州锦丰矿业有限公司 A kind of movable type filling pipeline device and construction method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
袁伟昊等: "《充填采煤方法与技术》", 30 April 2012, 煤炭工业出版社 *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2020199546A1 (en) * 2019-03-29 2020-10-08 中国矿业大学 Pressed coal filling mining system and process for end slope of open pit
CN110284883A (en) * 2019-07-08 2019-09-27 中国矿业大学 Recovery method is filled by a kind of row of adopting, open coal mine end side
CN111075505A (en) * 2019-12-17 2020-04-28 天地科技股份有限公司 Coal mine fully-mechanized coal mining face segmented filling mining method
CN111075505B (en) * 2019-12-17 2021-03-16 天地科技股份有限公司 Coal mine fully-mechanized coal mining face segmented filling mining method
CN111236943A (en) * 2020-02-27 2020-06-05 中煤能源研究院有限责任公司 Mining method for advancing, cutting and retreating filling of open-air end slope
CN111236943B (en) * 2020-02-27 2021-06-08 中煤能源研究院有限责任公司 Mining method for advancing, cutting and retreating filling of open-air end slope
CN111364998A (en) * 2020-03-12 2020-07-03 中煤能源研究院有限责任公司 Single-side edge filling and tunneling mining method for open-pit mine end slope coal pressing
CN111364998B (en) * 2020-03-12 2021-05-25 中煤能源研究院有限责任公司 Single-side edge filling and tunneling mining method for open-pit mine end slope coal pressing
CN111396055A (en) * 2020-03-24 2020-07-10 中煤科工集团沈阳设计研究院有限公司 Method for arranging side coal pressing mining chamber of strip mine
CN112855162A (en) * 2021-01-29 2021-05-28 辽宁工程技术大学 Mining method for upper coal seam of composite coal seam strip mine near extraction end slope
CN112855162B (en) * 2021-01-29 2023-03-21 辽宁工程技术大学 Mining method for upper coal seam of composite coal seam strip mine near extraction end slope
CN112963618A (en) * 2021-05-19 2021-06-15 中煤科工能源科技发展有限公司 Method and device for long-distance laying and continuous filling of filling pipeline of side coal mining cave

Also Published As

Publication number Publication date
ZA202006726B (en) 2021-09-29
AU2019439785A1 (en) 2020-11-19
AU2019439785B2 (en) 2021-09-16
RU2756537C1 (en) 2021-10-01
WO2020199546A1 (en) 2020-10-08
CN109882240B (en) 2020-04-14

Similar Documents

Publication Publication Date Title
CN109882240A (en) A kind of outdoor end side pressure coal filling mining system
CN110656937B (en) Fluidized coal gas simultaneous mining system and method
US9689258B2 (en) Water-preserved-mining roof-contacted filling method for controlling fissure of overlying strata and surface subsidence
CN103485747B (en) A kind of automatic compensation borehole sealing device and method
CN109826665B (en) Gangue and high-water-content material mixed filling method
CN111335944B (en) Coal face gangue slurry pipeline collaborative filling method
CN113803104B (en) Method for integrally arranging upper mining area buried pipe and downward drilling and extracting full-period gas
EP2602426A1 (en) Liquid guiding and collection process with secondary channels for in situ leaching
CN103195477B (en) Gravity drainage system for underground roadway high-pressure water inrush
CN110067597A (en) A kind of mine angle of depression negative pressure visits the method for putting old dead zone ponding
CN103291313A (en) Arch crown pressure supporting system of excavation of earth pressure shield and construction method thereof
CN106907177A (en) A kind of girdle gob side entry retaining roadside packing method for protecting support
CN104088637B (en) A kind of residual coal second mining of upper group shallow embedding method under coal seam group condition
CN108590716A (en) A kind of tunnel crosses rich water tomography tree root type and dredges water blockoff integral construction method
CN112879079B (en) Full life cycle utilization method for bottom drainage roadway of outburst coal seam
CN105298494B (en) Solid and adhesive bond combination filling coal-mining method
CN103742098A (en) Device and method for sealing hole by using returned slag of layer-through drill hole of low drainage roadway of coal mine
CN209340000U (en) A kind of mineral building Dewatering of fills structure
CN106638894A (en) Underground sludge discharging device and method
CN109695455A (en) Method of reseptance in a kind of earth pressure balanced shield, EPBS pure water
CN102748031A (en) Water pressure control method for use in TBM (Tunnel Boring Machine) method construction of heavy-gradient high-burial-depth water-rich stratum inclined shaft
CN105604605B (en) The complicated anti-broke-out diseases device of flood mine underground mine
CN112554941A (en) Room and pillar type mining and remaining coal pillar collaborative solid waste filling system and method
CN111322093A (en) Deep soft rock roadway anchoring-U-shaped steel support-after-frame filling cooperative control method
CN204738818U (en) Inside lining reinforced structure is established to electrified operation cover of cable tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant