CN109838098A - Distributing platform system for the construction of Super High tube structure - Google Patents

Distributing platform system for the construction of Super High tube structure Download PDF

Info

Publication number
CN109838098A
CN109838098A CN201910035947.9A CN201910035947A CN109838098A CN 109838098 A CN109838098 A CN 109838098A CN 201910035947 A CN201910035947 A CN 201910035947A CN 109838098 A CN109838098 A CN 109838098A
Authority
CN
China
Prior art keywords
construction
super high
distributing platform
dumping
pulley
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910035947.9A
Other languages
Chinese (zh)
Other versions
CN109838098B (en
Inventor
朱毅敏
徐磊
张星波
陆庆华
陶云海
丁惟峰
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 1 Group Co Ltd
Original Assignee
Shanghai Construction No 1 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 1 Group Co Ltd filed Critical Shanghai Construction No 1 Group Co Ltd
Priority to CN201910035947.9A priority Critical patent/CN109838098B/en
Publication of CN109838098A publication Critical patent/CN109838098A/en
Application granted granted Critical
Publication of CN109838098B publication Critical patent/CN109838098B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Landscapes

  • Types And Forms Of Lifts (AREA)
  • Refuge Islands, Traffic Blockers, Or Guard Fence (AREA)

Abstract

The present invention provides a kind of distributing platform systems for the construction of Super High tube structure, and anti-tilt device of the invention includes anti-dumping pulley, anti-dumping guide rail and crown wall pulley, for preventing accentric support Split assembled distributing platform system from toppling risk.Vertical anti-dumping guide rail can be set close to the horizontal structure side of super high-rise building Core Walls Structure in interior tub, and anti-dumping pulley is arranged in horizontal structure edge in super high-rise building Core Walls Structure elevator according to requirement of engineering, be stuck in anti-dumping pulley on anti-dumping guide rail.In addition, if close to the vertically arranged arterial highway crown wall pulley in the wall body structure side in split type interior tub, the anti-dumping pulley cooperation crown wall idler wheel symmetrically and evenly arranged provides the two-way effective lateral restraint of distributing platform system, guarantees the safe construction of distributing platform system.

Description

Distributing platform system for the construction of Super High tube structure
Technical field
The present invention relates to a kind of distributing platform systems for the construction of Super High tube structure.
Background technique
The height of super high-rise building Core Walls Structure is generally at 5 meters or more.Super high-rise building Core Walls Structure concrete distributing is usually adopted Distributing mode is combined with hard tube hose or using the whole material distributing machine cloth to climb in hydraulic steel platform, stability is poor.Hard tube is soft Pipe combination cloth form is simple and crude, need to put into considerable amount of labour;The disadvantage of steel platform material distributing machine be it is whole climb it is hydraulic Steel platform involves great expense, and construction cost is big, needs at the top of concrete pumping to Core Walls Structure through the level above steel platform top beam Pipe accesses material distributing machine, makes troubles to construction personnel's walking in steel platform.
Summary of the invention
The purpose of the present invention is to provide a kind of distributing platform systems for the construction of Super High tube structure, are able to solve The problem of existing distributing platform stability difference.
To solve the above problems, the present invention provides a kind of distributing platform system for the construction of Super High tube structure, packet It includes:
It is set to the wall body structure of the two sides of the super high-rise building Core Walls Structure of construction;
It is set to the lifting rail at the top of the wall body structure;
The distributing platform being set on the lifting rail;
The material distributing machine being set on the distributing platform;
Split type interior tub, each split type inner cylinder set up the super high-rise building Core Walls Structure and wall knot for being placed in the construction Between structure, the top of each split type interior tub is connect with the distributing platform, and the lower part of each split type interior tub is prolonged Extend to the super high-rise building core tube region of construction;
The crown wall pulley being disposed in proximity in the split type interior tub in each of described wall body structure side, the crown wall pulley are used When the distributing platform climbs along the lifting rail, the split type interior tub for driving the distributing platform to be connected is described in Wall body structure climbs together;
The anti-dumping guide rail being disposed in proximity in the split type interior tub in each of super high-rise building Core Walls Structure side;
The anti-dumping pulley being set on the edge of the horizontal structure of the super high-rise building Core Walls Structure of construction, and be stuck in point In anti-dumping guide rail in body formula in tub, when the anti-dumping pulley climbs for the distributing platform along the lifting rail, band The split type interior tub that the distributing platform is connected is moved to climb together along the anti-dumping guide rail.
Further, in above system, further includes:
The steel construction bracket being disposed in proximity in the split type interior tub in each of described wall body structure side, the steel construction ox Leg is set to the lower section of the crown wall pulley;
It is set to reserving hole on the wall body structure, the split type interior tub is climbed to after predeterminated position, the steel Structure bracket is set up in the reserving hole.
Further, in above system, the concrete of the reserving hole, which is shelved, is provided with pre-buried angle member on face.
Further, in above system, the anti-dumping guide rail is I-steel.
It further, further include two embedded steel tubes being embedded in the horizontal structure in above system, wherein The anti-dumping pulley is reliably connected simultaneously with two embedded steel tubes, and two embedded steel tubes are abscissused face interval along horizontal structure Distribution.
It further, further include vertical pump line and horizontal pump line in above system, wherein
The vertical pump line arranges that the vertical pump line passes through the one 90 degree of bend pipe and the cloth along the wall body structure One end of horizontal pump line below the top beam of platform connects;
The other end of the horizontal pump line is connect with one end of the 2nd 90 degree of bend pipe, the other end of the 2nd 90 degree of bend pipe It is connect after being passed through upwards between the top beam lattice of distributing platform gear with the material distributing machine.
Compared with prior art, anti-tilt device of the invention includes anti-dumping pulley, anti-dumping guide rail and crown wall pulley, for preventing Only accentric support Split assembled distributing platform system is toppled risk.It can be in super high-rise building Core Walls Structure elevator according to work Journey needs, and vertical anti-dumping guide rail is arranged close to the horizontal structure side of super high-rise building Core Walls Structure in interior tub, and anti-dumping is sliding Wheel is arranged in horizontal structure edge, is stuck in anti-dumping pulley on anti-dumping guide rail.In addition, close to institute in split type interior tub If stating the vertically arranged arterial highway crown wall pulley in wall body structure side, the anti-dumping pulley cooperation crown wall idler wheel symmetrically and evenly arranged is provided The two-way effective lateral restraint of distributing platform system guarantees the safe construction of distributing platform system.
Detailed description of the invention
Fig. 1 is the structure chart of the distributing platform system for the construction of Super High tube structure of one embodiment of the invention;
Fig. 2 is the amplification assumption diagram of the steel construction bracket in Fig. 1;
Fig. 3 is the amplification assumption diagram of the crown wall pulley in Fig. 1;
Fig. 4 is the amplification assumption diagram of the anti-dumping pulley in Fig. 1;
Fig. 5 is the cross section structure figure of the anti-dumping pulley of one embodiment of the invention;
Fig. 6 is the vertical pump line of one embodiment of the invention and the structure chart of horizontal pump line;
Fig. 7 is the amplification assumption diagram in the telescopic plug-type channel in Fig. 1;
Fig. 8 is the construction profile in the telescopic plug-type channel of one embodiment of the invention;
Fig. 9 is the amplification assumption diagram in the telescopic plug-type channel of one embodiment of the invention.
Specific embodiment
In order to make the foregoing objectives, features and advantages of the present invention clearer and more comprehensible, with reference to the accompanying drawing and specific real Applying mode, the present invention is described in further detail.
As shown in Fig. 1~8, the present invention provides a kind of distributing platform system for the construction of Super High tube structure, comprising:
It is set to the wall body structure 4 of the two sides of the super high-rise building Core Walls Structure of construction;
As shown in Figure 1, the super high-rise building Core Walls Structure of the construction may include complete layer 1, conservation layer 2 and construction layer 3;
It is set to the lifting rail 5 at the top of the wall body structure 4;
The distributing platform 6 being set on the lifting rail 5;
The material distributing machine 7 being set on the distributing platform 6;
Split type interior tub 8, each split type interior tub 8 are set to the super high-rise building Core Walls Structure and wall of the construction Between structure 4, the top of each split type interior tub 8 is connect with the distributing platform 6, each split type interior tub 8 Lower part extends to the super high-rise building core tube region of construction;
The crown wall pulley 9 being disposed in proximity in the split type interior tub 8 in each of described 4 side of wall body structure, the crown wall are sliding When wheel 9 climbs for the distributing platform along the lifting rail, the split type interior tub that drives the distributing platform to be connected It climbs together along the wall body structure;
The anti-dumping guide rail 10 being disposed in proximity in the split type interior tub 8 in each of super high-rise building Core Walls Structure side;
The anti-dumping pulley 12 being set on the edge of the horizontal structure 11 of the super high-rise building Core Walls Structure of construction, anti-dumping Pulley 12 is stuck in the anti-dumping guide rail 10 in split type interior tub 8, and the anti-dumping pulley 12 is for the distributing platform 6 along described When lifting rail 5 climbs, the split type interior tub 8 for driving the distributing platform 6 to be connected is climbed together along the anti-dumping guide rail 10 It rises;
It is set to the telescopic plug-type channel on the distributing platform 6.
Here, anti-tilt device of the invention includes anti-dumping pulley, anti-dumping guide rail and crown wall pulley, for preventing accentric support Split assembled distributing platform system is toppled risk.Can in super high-rise building Core Walls Structure elevator according to requirement of engineering, Vertical anti-dumping guide rail is arranged close to the horizontal structure side of super high-rise building Core Walls Structure in interior tub, and anti-dumping pulley is arranged in water Flat structure edge is stuck in anti-dumping pulley on anti-dumping guide rail.In addition, close to the wall body structure in split type interior tub If the vertically arranged arterial highway crown wall pulley in side, the anti-dumping pulley cooperation crown wall idler wheel symmetrically and evenly arranged provides distributing platform system The two-way effective lateral restraint of system guarantees the safe construction of distributing platform system.
Anti-dumping idler wheel is fixed on to the horizontal structure outer edge of super high-rise building Core Walls Structure, and is stuck in split type interior tub Anti-dumping guide rail in, cooperate in crown wall pulley in tub, form two-way effective lateral restraint, guarantee that distributing platform works normally With the safety and stability of climb mode.
Distributing platform system uses the novel vertical multiple tracks anti-tilt device of horizontal bidirectional, the advantage of doing so is that using several The lateral rigidity of layer horizontal structure, preventing independent tall and big interior tub from lateral displacement occurs causes to topple, and guarantees two-way stable, just Normal work of climbing.It can be realized two-way effective anti-dumping of accentric support Split assembled distributing platform system.
In the composition of distributing platform system of the invention, if there are horizontal structure in super high-rise building Core Walls Structure, system can It is made of split type interior tub, lifting rail, anti-tilt device, distributing platform and material distributing machine;If in super high-rise building Core Walls Structure not There are horizontal structure, then the maximum difference of plateform system, which can be its split type interior tub and is connected by combination bottom beam, forms entirety Unit.
As shown in Fig. 2, also being wrapped in one embodiment of distributing platform system for the construction of Super High tube structure of the invention It includes:
The steel construction bracket 13 being disposed in proximity in the split type interior tub 8 in each of described 4 side of wall body structure, the steel knot Structure bracket 13 is set to the lower section of the crown wall pulley 9;
It is set to reserving hole 14 on the wall body structure, the split type interior tub is climbed to after predeterminated position, described Steel construction bracket 13 is set up in the reserving hole 14.
Here, steel construction bracket is arranged by the lower section of crown wall pulley, may be implemented the split type interior tub climb to Split type interior tub reliably shelves and fixes after predeterminated position.
In addition, accentric support of the present invention in split type interior tub, bottom beam after being climbed every time due to distributing platform system It stops absolute altitude not to be consistent with flooring absolute altitude, be arranged if being arranged to shelve supporting point and will increase additional construction on horizontal structure Expense, fee of material, labour cost are applied, therefore the bottom of distributing platform system support bracket is provided entirely in interior tub close to vertical wall The side of body is held on wall body structure in reserving hole, and distributing platform load is transferred directly to Core Walls Structure shear wall, such nothing It need to be installed on horizontal structure and additionally temporarily shelve structure, substantially reduce the construction cost of distributing platform system.In Super High core Horizontal section concrete pumping under platform is realized in heart tube construction, is offered convenience to the walking of construction personnel on platform, is improved safety Property.
As shown in Fig. 2, in one embodiment of distributing platform system for the construction of Super High tube structure of the invention, it is described The concrete of reserving hole 14, which is shelved, is provided with pre-buried angle member 15 on face.
Here, the concrete of reserving hole, which is shelved, increases pre-buried angle member on face, local bearing capacity is improved, concrete is prevented Generation office crushes bad.
In one embodiment of distributing platform system for the construction of Super High tube structure of the invention, the anti-dumping guide rail is I-steel, to guarantee the reliability of guide rail.
As shown in Figures 4 and 5, in one embodiment of distributing platform system for the construction of Super High tube structure of the invention, It further include two embedded steel tubes 16 being embedded in the horizontal structure, wherein the anti-dumping pulley 12 and two embedded steel tubes 16 are reliably connected simultaneously, and two embedded steel tubes 16 are spaced apart along 11 normal section of horizontal structure, this anti-dumping pulley Fixed form can provide anti-dumping guide rail stronger more reliable two-way horizontal constraint, guarantee stability.
As shown in fig. 6, also being wrapped in one embodiment of distributing platform system for the construction of Super High tube structure of the invention Include vertical pump line 20 and horizontal pump line 21, wherein
The vertical pump line 20 arranges along the wall body structure, the vertical pump line 20 by the one 90 degree of bend pipe with it is described One end of horizontal pump line 21 below the top beam of distributing platform connects;
The other end of the horizontal pump line 21 is connect with one end of the 2nd 90 degree of bend pipe, the 2nd 90 degree of bend pipe it is another End is connect after passing through upwards between the top beam lattice of distributing platform 6 gear with the material distributing machine 7.
Here, being minimized to make concrete horizontal pump line on traditional construction platform avoid construction personnel's track route Horizontal pump line is completed conversion by interference below distributing platform.Horizontal pump line can be fixed under the top beam of distributing platform system It on the edge of a wing, is converted by right-angle elbow pipe, pump line is passed through between the lattice of top beam gear, accesses cloth motor spindle.
The punching pump line arrangement of material distributing machine of the invention are as follows: the vertical pump line along the wall body structure passes through first 90 degree of bend pipes are connect with the horizontal pump line below the top beam of the distributing platform, and horizontal pump line is fixed on the top of the distributing platform It on lower flange of girder edge, then is converted by the 2nd 90 degree of bend pipe between the top beam lattice of distributing platform gear and is passed through upwards, be directly accessed cloth Material machine.
Horizontal pump line is fixed under platform the walking disorder that can further remove on platform, improves working security, The lateral rigidity for efficiently using permanent horizontal structure keeps system platform steady operation and can climb, and reduces distributing platform Construction cost integrates operation side, the management difficulty at the scene of reducing.This pump line arrangement is avoided applying on distributing platform The track route of worker person realizes the noiseless independent operating of pumping construction and cloth construction, fully ensures that construction production safety.
As shown in figs. 7-9, in one embodiment of distributing platform system for the construction of Super High tube structure of the invention, The plug-type channel includes:
For the channel flase floor 17 of people's walking;
The sliding rail 18 being connect with the channel flase floor;
It is set to the mobile idler pulley 19 of 18 lower part of sliding rail, the mobile idler pulley 19 is stuck in the steel of distributing platform 6 Liang Zhong, and the mobile idler pulley is limited by the section steel beam in split type interior tub and distributing platform 6, the section steel beam is described in The spacing L in sliding rail direction is the movable distance of the mobile idler pulley 19.
The present invention is provided with and the plug-type channel between other Core Walls Structures, distributing platform and adjacent core cylinder inner cylinder mould bases Traffic between system can be connected by plug-type channel, and the channel flase floor in the plug-type channel is reliably connected in push-and-pull Guide rail, sliding rail is slided by being stuck in the mobile idler pulley of the girder steel of distributing platform, and mobile idler pulley passes through split type interior tub With on distributing platform section steel beam limit, spacing of the section steel beam along the sliding rail direction be plug-type channel can Distance of stretch out and draw back, plug-type channel greatly improve construction personnel distributing platform system and other inner cylinder formwork systems of Core Walls Structure it Between walking it is convenient, guarantee construction safety.
Each embodiment in this specification is described in a progressive manner, the highlights of each of the examples are with other The difference of embodiment, the same or similar parts in each embodiment may refer to each other.
Obviously, those skilled in the art can carry out various modification and variations without departing from spirit of the invention to invention And range.If in this way, these modifications and changes of the present invention belong to the claims in the present invention and its equivalent technologies range it Interior, then the invention is also intended to include including these modification and variations.

Claims (6)

1. a kind of distributing platform system for the construction of Super High tube structure characterized by comprising
It is set to the wall body structure of the two sides of the super high-rise building Core Walls Structure of construction;
It is set to the lifting rail at the top of the wall body structure;
The distributing platform being set on the lifting rail;
The material distributing machine being set on the distributing platform;
Split type interior tub, each split type inner cylinder set up the super high-rise building Core Walls Structure for being placed in the construction and wall body structure it Between, the top of each split type interior tub is connect with the distributing platform, and the lower part of each split type interior tub extends to The super high-rise building core tube region of construction;
The crown wall pulley being disposed in proximity in the split type interior tub in each of described wall body structure side, the crown wall pulley are used for institute When stating distributing platform and climbing along the lifting rail, the split type interior tub for driving the distributing platform to be connected is along the wall Structure is climbed together;
The anti-dumping guide rail being disposed in proximity in the split type interior tub in each of super high-rise building Core Walls Structure side;
The anti-dumping pulley being set on the edge of the horizontal structure of the super high-rise building Core Walls Structure of construction, and be stuck in split type In anti-dumping guide rail in interior tub, when the anti-dumping pulley climbs for the distributing platform along the lifting rail, institute is driven The split type interior tub that distributing platform is connected is stated to climb together along the anti-dumping guide rail.
2. the distributing platform system for the construction of Super High tube structure as described in claim 1, which is characterized in that also wrap It includes:
The steel construction bracket being disposed in proximity in the split type interior tub in each of described wall body structure side, the steel construction bracket are set It is placed in the lower section of the crown wall pulley;
It is set to reserving hole on the wall body structure, the split type interior tub is climbed to after predeterminated position, the steel construction Bracket is set up in the reserving hole.
3. the distributing platform system for the construction of Super High tube structure as claimed in claim 2, which is characterized in that described pre- The concrete in hole of boxing out is shelved and is provided with pre-buried angle member on face.
4. the distributing platform system for the construction of Super High tube structure as described in claim 1, which is characterized in that described anti- The guide rail that inclines is I-steel.
5. the distributing platform system for the construction of Super High tube structure as described in claim 1, which is characterized in that further include Two embedded steel tubes being embedded in the horizontal structure, wherein the anti-dumping pulley is connect with two embedded steel tubes respectively, and two Root embedded steel tube is spaced apart along horizontal structure normal section.
6. the distributing platform system for the construction of Super High tube structure as described in claim 1, which is characterized in that further include Vertical pump line and horizontal pump line, wherein
The vertical pump line arranges that the vertical pump line passes through the one 90 degree of bend pipe and the distributing platform along the wall body structure Top beam below horizontal pump line one end connection;
The other end of the horizontal pump line is connect with one end of the 2nd 90 degree of bend pipe, and the other end of the 2nd 90 degree of bend pipe is from cloth It is connect after being passed through upwards between the top beam lattice gear of material platform with the material distributing machine.
CN201910035947.9A 2019-01-15 2019-01-15 Material distribution platform system for super high-rise barrel structure construction Active CN109838098B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910035947.9A CN109838098B (en) 2019-01-15 2019-01-15 Material distribution platform system for super high-rise barrel structure construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910035947.9A CN109838098B (en) 2019-01-15 2019-01-15 Material distribution platform system for super high-rise barrel structure construction

Publications (2)

Publication Number Publication Date
CN109838098A true CN109838098A (en) 2019-06-04
CN109838098B CN109838098B (en) 2024-02-13

Family

ID=66883841

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910035947.9A Active CN109838098B (en) 2019-01-15 2019-01-15 Material distribution platform system for super high-rise barrel structure construction

Country Status (1)

Country Link
CN (1) CN109838098B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111456439A (en) * 2020-03-24 2020-07-28 中建西部建设西南有限公司 Concrete pouring construction method for large-fall core tube of super high-rise building
CN115217311A (en) * 2022-06-14 2022-10-21 成都建工第三建筑工程有限公司 Super high-rise core tube large-span intelligent climbing safety protection platform

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2013185277A1 (en) * 2012-06-11 2013-12-19 浙江省建工集团有限责任公司 Constructing method for concrete cylinder of construction steel bar of high-rise steel structure
CN203514814U (en) * 2013-10-11 2014-04-02 卓越置业集团有限公司 Overhead building putting-up machine
CN203769280U (en) * 2014-01-17 2014-08-13 上海建工集团股份有限公司 Climbing inclination-prevention device of steel column cylinder frame alternate-support steel platform
CN206233541U (en) * 2016-10-10 2017-06-09 中国建筑第八工程局有限公司 A kind of interior top external climbing mould bases operation platform for construction of super highrise building
CN107035156A (en) * 2017-04-19 2017-08-11 上海建工建集团有限公司 Core Walls Structure horizontal structure self-crawling type protective platform
CN107217831A (en) * 2017-04-28 2017-09-29 中建三局集团有限公司 High-rise building Core Walls Structure horizontal structure construction method
CN210289172U (en) * 2019-01-15 2020-04-10 上海建工一建集团有限公司 Material distribution platform system for construction of super high-rise tubular structure

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2013185277A1 (en) * 2012-06-11 2013-12-19 浙江省建工集团有限责任公司 Constructing method for concrete cylinder of construction steel bar of high-rise steel structure
CN203514814U (en) * 2013-10-11 2014-04-02 卓越置业集团有限公司 Overhead building putting-up machine
CN203769280U (en) * 2014-01-17 2014-08-13 上海建工集团股份有限公司 Climbing inclination-prevention device of steel column cylinder frame alternate-support steel platform
CN206233541U (en) * 2016-10-10 2017-06-09 中国建筑第八工程局有限公司 A kind of interior top external climbing mould bases operation platform for construction of super highrise building
CN107035156A (en) * 2017-04-19 2017-08-11 上海建工建集团有限公司 Core Walls Structure horizontal structure self-crawling type protective platform
CN107217831A (en) * 2017-04-28 2017-09-29 中建三局集团有限公司 High-rise building Core Walls Structure horizontal structure construction method
CN210289172U (en) * 2019-01-15 2020-04-10 上海建工一建集团有限公司 Material distribution platform system for construction of super high-rise tubular structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111456439A (en) * 2020-03-24 2020-07-28 中建西部建设西南有限公司 Concrete pouring construction method for large-fall core tube of super high-rise building
CN115217311A (en) * 2022-06-14 2022-10-21 成都建工第三建筑工程有限公司 Super high-rise core tube large-span intelligent climbing safety protection platform
CN115217311B (en) * 2022-06-14 2024-03-12 成都建工第三建筑工程有限公司 Intelligent climbing safety protection platform with large span for super high-rise core tube

Also Published As

Publication number Publication date
CN109838098B (en) 2024-02-13

Similar Documents

Publication Publication Date Title
CN109750840A (en) The installation method of distributing platform system for the construction of Super High tube structure
CN105016223B (en) Cross beam supporting system used for tower crane
CN104060844B (en) Sliding device and lifting device for truss frame of steel structural transfer floor of the high-rise building and construction method thereof
CN105000482B (en) Tower crane with walking mechanism
CN106437130A (en) Inner roof external climbing type formwork construction platform for super high-rise building construction
KR102109969B1 (en) A work bogie for tunnel work
CN209323962U (en) A kind of hybrid power system steel platform mould bases climbs system
CN104179090B (en) A kind of subway is laid a railway track system
CN201610631U (en) Traction and movable type lifting platform for construction
CN109838098A (en) Distributing platform system for the construction of Super High tube structure
CN103726421A (en) Height and span adjustable track paver for metro construction
CN108033367A (en) A kind of steel column drum rack alternating brace type steel platform and tower crane synchronous hoisting device and its method for improving
CN206233541U (en) A kind of interior top external climbing mould bases operation platform for construction of super highrise building
CN109750842A (en) A kind of installation method of the distributing platform system of tube structure construction
CN206448820U (en) A kind of tunnel construction trolley
CN109750841A (en) A kind of distributing platform system of tube structure construction
CN203684019U (en) Height and span adjustable track laying machine for subway construction
CN204848050U (en) A crossbeam braced system for tower crane
CN213418443U (en) Self-climbing type elevator shaft operation platform
CN105217420A (en) A kind of device for short range transport
CN203961317U (en) Slip list Pin and many truss structures moulding bed
CN209799394U (en) Cloth platform system for barrel structure construction
CN205873594U (en) Special construction elevator of cooling tower section of thick bamboo wall
CN210289172U (en) Material distribution platform system for construction of super high-rise tubular structure
CN204780925U (en) City gate hole type inclined shaft slipform platform truck pulls removal structure

Legal Events

Date Code Title Description