CN109779144A - Utilize the prefabricated lintel of U-shaped building block and its construction method - Google Patents
Utilize the prefabricated lintel of U-shaped building block and its construction method Download PDFInfo
- Publication number
- CN109779144A CN109779144A CN201910148830.1A CN201910148830A CN109779144A CN 109779144 A CN109779144 A CN 109779144A CN 201910148830 A CN201910148830 A CN 201910148830A CN 109779144 A CN109779144 A CN 109779144A
- Authority
- CN
- China
- Prior art keywords
- lintel
- building block
- shaped building
- concrete
- construction method
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Abstract
The invention discloses a kind of lintels and its construction method prefabricated using U-shaped building block.The lintel includes: U-shaped building block of the opening up same column masonry of muti-piece at groove body;It is set up in the intracorporal at least one of slot and crosses beam steel;And it is filled in the intracorporal concrete for wrapping beam steel of slot.The step of construction method include: 1) masonry build before, U-shaped building block is opening up, build at groove body, beam steel was installed in slot, if good protective layer thickness, casting concrete, maintenance molding;2) floor structure face is levelling by absolute altitude, control line is released in wall;3) when building wall to lintel absolute altitude, door and window hole both sides remains for overlapping in advance the position of U-shaped building block;4) prefabricated doors and windows lintel is not necessarily to demoulding, is directly mounted to reserved location.The lintel is easy to make, and simple installation, building process does not need demoulding, does not interfere with masonry construction progress, conducive to shortening the construction period and improving construction quality.
Description
Technical field
The invention belongs to technical field of building construction, and in particular to a kind of lintel prefabricated using U-shaped building block and its
Construction method.
Background technique
When opening up door-window opening on wall, and wall hole be greater than 300mm when, in order to support hole top masonry to be passed
The various loads come, and these loads are transmitted to the wall on the holes such as door and window both sides, crossbeam is often set on door-window opening, the cross
Beam is lintel.The construction method for making lintel, generally use be mounted on after concentration pre-casting lintel door-window opening it
On, or the secondary casting concrete after lintel corresponding position formwork and setting reinforcing bar.The former installs after generally requiring demoulding, after
Person is easy to influence masonry construction, and then influences construction speed and construction quality.
Summary of the invention
The object of the present invention is to provide a kind of lintel and its construction method prefabricated using U-shaped building block, the door and window mistakes
Beam is easy to make, and simple installation, building process does not need demoulding, does not interfere with masonry construction progress, conducive to shortening the construction period and mentioning
High construction quality.
To achieve the above object, the invention adopts the following technical scheme:
On the one hand, the present invention provides a kind of lintel prefabricated using U-shaped building block, which includes:
The opening up same column of muti-piece builds the U-shaped building block at groove body;
It is set up in the intracorporal at least one of slot and crosses beam steel;
And it is filled in the intracorporal concrete for wrapping beam steel of slot.
Wherein:
The groove body should have the length enough as lintel, and length will be adapted to the width in door and window hole.That is, the slot
The length of body should be greater than the door and window hole width of installation place, which is suitable for the case where door and window hole width is less than 1600mm.
The U-shaped building block is preferably dimensioned to be 190mm × 190mm × 190mm.
The gray seam thickness built between the U-shaped building block is 10 ± 2mm.
Quantity, specification and the layout for crossing beam steel, be according to the load of lintel, in conjunction with various countries, industry standard
It is calculated and is selected, this is ordinary skill in the art means, and detailed description is not added herein.
The concrete preferably uses C15 concrete, i.e. the strength grade concrete that is C15.
On the other hand, present invention offer also provides the construction method of the above-mentioned lintel prefabricated using U-shaped building block, this is applied
Work method the following steps are included:
1) before masonry is built, U-shaped building block is opening up, the groove body at lintel size is built, was installed in slot
Beam steel, there are cover to reinforcement, casting concrete, maintenance molding obtains prefabricated doors and windows lintel;
2) before masonry is built, floor structure face is levelling by absolute altitude, control line is released in wall, for controlling lintel
Absolute altitude;
3) when building wall to lintel absolute altitude, door and window hole both sides remains for overlapping in advance the position of U-shaped building block;
4) mortar is coated in above-mentioned reserved location, prefabricated doors and windows lintel is not necessarily to demoulding, is directly mounted to reserved location, hereafter
Continue to build using conventional method.
Wherein:
The concrete preferably uses C15 concrete, pours thickness no more than 40mm for every layer in concreting process.It smashes
The real duration is until making concrete surface laitance, bubble-free, not sinking.Casting process avoids collision reinforcing bar, U-shaped building block,
It was found that having deformation, displacement, should handle in time.Mode of the cast-in-place concrete in the U-shaped building block for having bound reinforcing bar can be used.
The U-shaped building block is completely grouted for side and is built, and must not have vertical straight joint, gray seam thickness 10 with delivery position by hole
±2mm。
The highly preferred of the control line is 1m.The width in the door and window hole should be less than 1600mm.The reserved location
Depth is not less than 240mm, is one of preferred with 240mm.
The beneficial effects of the present invention are:
Lintel of the invention is simple and reasonable, can be prefabricated by using U-shaped building block in a pre-installation, is building when prefabricated
What setting met design leader in block crosses beam steel after-pouring concrete, and lintel is mounted directly to door after prefabricated
At window opening, preparation is simple, and building block can directly be built on upper layer after completing by pouring, and next procedure is completed, without waiting for demoulding.
Compared with prior art, the invention has the following advantages that 1) casting concrete can directly start next procedure after completing, it is not necessarily to
Demoulding;2) secondary structure lintel can be served as in tall and big masonry, can continue next procedure without demoulding.
Detailed description of the invention
Fig. 1 is structural schematic diagram of the present invention using the prefabricated lintel of U-shaped building block.
Figure label are as follows: 1-U-shaped building block;2-cross beam steel;3-concrete.
Specific embodiment
The present invention will be described with reference to the accompanying drawing, and the specific embodiments described herein are only used for describing and explaining
The present invention is not intended to limit the present invention.
As described in Figure 1, the lintel prefabricated using U-shaped building block provided by the invention, primary structure include: that muti-piece is opened
The same column of mouth upward builds the U-shaped building block 1 at groove body, is set up in the intracorporal at least one of slot and crosses beam steel 2, and is filled in slot
The intracorporal concrete 3 for wrapping beam steel 2.
Wherein, groove body should have the length enough as lintel, i.e. the length of groove body should be greater than the door and window of installation place
Hole width, and door and window hole width is less than 1600mm.The size of U-shaped building block 1 is 190mm × 190mm × 190mm.U-shaped building block 1 it
Between gray seam thickness be 10 ± 2mm.Concrete uses C15 concrete.
The present invention will also provide multiple embodiments, be mainly used for specifically describing construction method of the invention, it should be understood that with
Lower embodiment is without of the invention in limiting.
Embodiment 1
Project name: certain mansion project
1.1 project profiles: this engineering is located at Nanning City, engineering overall floorage 118195.01m2, wherein hypogee face
Product 55657.90m2, 1 layer of basement, 47090.04 ㎡ of superstructure area, aerial part has the building 1#~3#, is building ground 23
Layer, 3 layers of annex, building general height 72.3m;Main structure type is frame-shear structure, and in September, 2016 goes into operation.
1.2 construction methods:
Construction method of the invention is applied to need to install at lintel, the specific steps are as follows:
1) before masonry is built, U-shaped building block is opening up, the groove body at lintel size is built, was installed in slot
Beam steel, if good thickness of protection tier, casting concrete, maintenance molding obtains prefabricated doors and windows lintel;
2) before masonry is built, floor structure face is levelling by absolute altitude, control line is released in wall, for controlling lintel
Absolute altitude;
3) when building wall to lintel absolute altitude, door and window hole both sides remains for overlapping in advance the position of U-shaped building block;
4) mortar is coated in above-mentioned reserved location, prefabricated doors and windows lintel is not necessarily to demoulding, is directly mounted to reserved location, hereafter
Continue to build using conventional method;
Wherein, when prefabricated, casting concrete again, concrete are set after the beam steel excessively for meeting design leader in building block
Using C15 concrete, thickness is poured no more than 40mm for every layer in concreting process;The tamping duration is to make concrete table
Face laitance, bubble-free, until not sinking.U-shaped building block is completely grouted for side and is built, and must not be had vertically with delivery position by door-window opening
Straight joint.Control line height is 1m;Door and window hole width is less than 1600mm;Door and window hole reserved location depth is 240mm.
1.3 condition of construction: before submitting application to the present invention, 3# building-owner's body has bound, 1~7 layer of progress masonry construction.
1.4 performance analyses: the engineering construction is constructed using this engineering method, and the integral construction duration shifts to an earlier date 10d completion, through calculating,
About 59418.82 yuan of accumulative save the cost.It is detailed in following table analysis.
Embodiment 2
Project name: certain automobile city project
1.1 project profiles: this engineering is located at tourist resources, and engineering uses frame-shear-wall structure, wherein ground 3
Layer, construction area 23614.42m2。
1.2 construction methods: with embodiment 1.
1.3 condition of construction: before submitting application to the present invention, main body has bound, 1~3 layer of progress masonry construction.
1.4 performance analyses: this engineering integral construction duration shifts to an earlier date 8d completion, the lintel component of engineering about 2000;
Reference implementation example 1, administration fee save 3000 yuan/day, and the fee of material of component can save about 15.5 yuan/, the labour cost of component
9 yuan/are saved, specific statistics is as shown in the table:
Embodiment 3
Project name: certain project first stage of the project A#, B# building engineering
1.1 project profiles: this engineering is located at tourist resources Gangkou District, and 2 layers of underground, 31 layers on the ground, construction area is about
26000 ㎡, the design life of structure are 50 years.
1.2 construction methods: with embodiment 1.
1.3 condition of construction: before submitting application to the present invention, it has been completed.
1.4 performance analyses: the engineering construction is constructed using this engineering method, and the integral construction duration shifts to an earlier date 10d completion, the door of engineering
Window lintel component about 1500;Reference implementation example 1, administration fee save 3000 yuan/day, and the fee of material of component can save about 15.5
Member/, the labour cost of component saves 9 yuan/, and specific statistics is as shown in the table:
Construction method of the invention can obtain significant economic benefit it can be seen from Examples 1 to 3, commercially
Huge success can be obtained.And the construction method successfully solves building process and needs to arrange worker's progress template and support
The problem of dismounting, had not only reduced the probability for security risk occur, but also can be reduced to extraneous influence of noise and a large amount of building wastes
Generation, while there is significant social benefit and environmental benefit.
Claims (10)
1. utilizing the lintel that U-shaped building block is prefabricated characterized by comprising
The opening up same column of muti-piece builds the U-shaped building block at groove body;
It is set up in the intracorporal at least one of slot and crosses beam steel;
And it is filled in the intracorporal concrete for wrapping beam steel of slot.
2. lintel according to claim 1, it is characterised in that:
The groove body has the length enough as lintel.
3. lintel according to claim 1 or 2, it is characterised in that:
The length of the groove body is greater than the door and window hole width of installation place, and door and window hole width is less than 1600mm.
4. lintel according to claim 1, it is characterised in that:
The size of the U-shaped building block is 190mm × 190mm × 190mm.
5. lintel according to claim 1, it is characterised in that:
The gray seam thickness built between the U-shaped building block is 10 ± 2mm.
6. lintel according to claim 1, it is characterised in that:
The concrete selects C15 concrete.
7. utilizing the construction method of the prefabricated lintel of U-shaped building block, which comprises the following steps:
1) before masonry is built, U-shaped building block is opening up, the groove body at lintel size is built, joist steel was installed in slot
Muscle, there are cover to reinforcement, casting concrete, maintenance molding obtains prefabricated doors and windows lintel;
2) before masonry is built, floor structure face is levelling by absolute altitude, control line is released in wall, for controlling lintel mark
It is high;
3) when building wall to lintel absolute altitude, door and window hole both sides remains for overlapping in advance the position of U-shaped building block;
4) mortar is coated in above-mentioned reserved location, prefabricated doors and windows lintel is not necessarily to demoulding, is directly mounted to reserved location, hereafter uses
Conventional method continues to build.
8. construction method according to claim 7, it is characterised in that:
The concrete selects C15 concrete, pours thickness no more than 40mm for every layer in concreting process.
9. construction method according to claim 7, it is characterised in that:
The U-shaped building block is completely grouted for side and is built, and gray seam thickness is 10 ± 2mm.
10. construction method according to claim 7, it is characterised in that:
The size of the U-shaped building block is 190mm × 190mm × 190mm;
The height of the control line is 1m;
The width in the door and window hole is less than 1600mm;
The depth of the reserved location is not less than 240mm.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910148830.1A CN109779144A (en) | 2019-02-28 | 2019-02-28 | Utilize the prefabricated lintel of U-shaped building block and its construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910148830.1A CN109779144A (en) | 2019-02-28 | 2019-02-28 | Utilize the prefabricated lintel of U-shaped building block and its construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109779144A true CN109779144A (en) | 2019-05-21 |
Family
ID=66485853
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910148830.1A Pending CN109779144A (en) | 2019-02-28 | 2019-02-28 | Utilize the prefabricated lintel of U-shaped building block and its construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109779144A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111075101A (en) * | 2019-12-12 | 2020-04-28 | 中国建筑第五工程局有限公司 | BM interlocking building block U-shaped block lintel, ring beam and horizontal tie beam and construction method thereof |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20020148187A1 (en) * | 2001-04-17 | 2002-10-17 | Walters Donald L. | Construction blocks and structures therefrom |
DE10358753A1 (en) * | 2003-12-12 | 2005-07-14 | Xella Kalksandsteinwerke Nordhessen Gmbh & Co.Kg | Lintel consists of lintel blocks which incorporate a groove and have specified standard lengths |
CN102094525A (en) * | 2011-01-07 | 2011-06-15 | 吴方伯 | Method for constructing reinforced concrete lintel |
CN106013509A (en) * | 2016-07-22 | 2016-10-12 | 湖北神州建材有限责任公司 | Dry-method construction method for high-performance autolaved aerated concrete block wall |
US9932737B1 (en) * | 2010-10-15 | 2018-04-03 | Constructive , Llc | Prefabricated masonry lintels |
CN108756016A (en) * | 2018-04-12 | 2018-11-06 | 五冶集团上海有限公司 | A kind of construction method for making secondary structure beam form with U-shaped building block |
CN108978995A (en) * | 2018-09-05 | 2018-12-11 | 上海建工五建集团有限公司 | Autoclave aerated concrete building block crosses girder construction and its construction method |
CN209817272U (en) * | 2019-02-28 | 2019-12-20 | 广西建工集团建筑工程总承包有限公司 | Door and window lintel prefabricated by U-shaped building blocks |
-
2019
- 2019-02-28 CN CN201910148830.1A patent/CN109779144A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20020148187A1 (en) * | 2001-04-17 | 2002-10-17 | Walters Donald L. | Construction blocks and structures therefrom |
DE10358753A1 (en) * | 2003-12-12 | 2005-07-14 | Xella Kalksandsteinwerke Nordhessen Gmbh & Co.Kg | Lintel consists of lintel blocks which incorporate a groove and have specified standard lengths |
US9932737B1 (en) * | 2010-10-15 | 2018-04-03 | Constructive , Llc | Prefabricated masonry lintels |
CN102094525A (en) * | 2011-01-07 | 2011-06-15 | 吴方伯 | Method for constructing reinforced concrete lintel |
CN106013509A (en) * | 2016-07-22 | 2016-10-12 | 湖北神州建材有限责任公司 | Dry-method construction method for high-performance autolaved aerated concrete block wall |
CN108756016A (en) * | 2018-04-12 | 2018-11-06 | 五冶集团上海有限公司 | A kind of construction method for making secondary structure beam form with U-shaped building block |
CN108978995A (en) * | 2018-09-05 | 2018-12-11 | 上海建工五建集团有限公司 | Autoclave aerated concrete building block crosses girder construction and its construction method |
CN209817272U (en) * | 2019-02-28 | 2019-12-20 | 广西建工集团建筑工程总承包有限公司 | Door and window lintel prefabricated by U-shaped building blocks |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111075101A (en) * | 2019-12-12 | 2020-04-28 | 中国建筑第五工程局有限公司 | BM interlocking building block U-shaped block lintel, ring beam and horizontal tie beam and construction method thereof |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106223360B (en) | Using the open cut cast in place and precast construction subway station construction method of stake supporting system | |
CN208702444U (en) | A kind of prefabricated rail top air channel structure of postposition | |
CN109811878A (en) | The shell integrated structure of the cast-in-place coinsiding die of assembled architecture and construction method | |
CN107700361B (en) | A kind of dumb-bell shape grout sleeve and the method for carrying out assembly construction with the grout sleeve | |
CN111335490A (en) | Crack-resistant structure at joint of filler wall and shear wall under full-concrete outer wall window and construction method of crack-resistant structure | |
CN102296816A (en) | Factorial construction method for component of total prefabricated assembly integral type shear wall structure system | |
CN205242706U (en) | Cast -in -place constructional column of infilled wall and wall body synchronous construction structure between high -rise outer eaves window | |
CN107724533A (en) | A kind of Super High Core Walls Structure beam and vertical structure connection method | |
CN105525753A (en) | Method and structure for simultaneously constructing constructional column and main body structure | |
CN110984359A (en) | Low-rise assembled building structure | |
CN109853956A (en) | Residential building construction method | |
CN108798059A (en) | A kind of old masonry seismic reinforcing structure and construction method | |
CN106088493A (en) | A kind of pin key connects mounting structure and the construction thereof of prefabricated bench | |
CN107100083A (en) | A kind of T-shaped high pier Cast-in-place Bent Cap formwork erecting structure and construction method | |
CN111188508A (en) | Supplement plate of existing cantilever floor slab of building structure and construction method thereof | |
CN103061508A (en) | Triangular slip form device and construction method for the same triangular slip form | |
CN107355008A (en) | A kind of prefabricated attachment structure and method of newly-increased steel core concrete column and existing structure | |
CN110552706A (en) | Permanent-temporary combined shield hoisting hole sealing structure and method | |
CN205243063U (en) | Masonry structure is consolidated to prefabricated wallboard | |
CN208534081U (en) | A kind of reconstruction structure of old building constructional column | |
CN205224332U (en) | Prefabricated wall body and prefabricated wallboard | |
CN113697640A (en) | Finished hoistway of integrally assembled elevator added in existing multi-story building and construction method | |
CN109779144A (en) | Utilize the prefabricated lintel of U-shaped building block and its construction method | |
CN206346486U (en) | Precast lining for multilayer floor slab template support frame body | |
CN111441513A (en) | Cast-in-place concrete wall body combining truss reinforcing steel bars and steel plates and construction method |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination |