CN106088493A - A kind of pin key connects mounting structure and the construction thereof of prefabricated bench - Google Patents

A kind of pin key connects mounting structure and the construction thereof of prefabricated bench Download PDF

Info

Publication number
CN106088493A
CN106088493A CN201610633961.5A CN201610633961A CN106088493A CN 106088493 A CN106088493 A CN 106088493A CN 201610633961 A CN201610633961 A CN 201610633961A CN 106088493 A CN106088493 A CN 106088493A
Authority
CN
China
Prior art keywords
bench
pin key
ladder
prefabricated
ladder beam
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201610633961.5A
Other languages
Chinese (zh)
Inventor
方燎原
彭剑尧
张煜
王加国
徐红杰
侯振国
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Division Corp Ltd
Original Assignee
China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Division Corp Ltd filed Critical China Construction Seventh Engineering Division Corp Ltd
Priority to CN201610633961.5A priority Critical patent/CN106088493A/en
Publication of CN106088493A publication Critical patent/CN106088493A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F11/00Stairways, ramps, or like structures; Balustrades; Handrails
    • E04F11/02Stairways; Layouts thereof
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F21/00Implements for finishing work on buildings
    • E04F21/26Implements for finishing work on buildings for mounting staircases, e.g. tools for marking steps
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G13/00Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills
    • E04G13/06Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for stairs, steps, cornices, balconies, or other parts corbelled out of the wall
    • E04G13/062Falsework, forms, or shutterings for particular parts of buildings, e.g. stairs, steps, cornices, balconies foundations, sills for stairs, steps, cornices, balconies, or other parts corbelled out of the wall for stairs or steps

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Ladders (AREA)

Abstract

The present invention proposes a kind of pin key and connects mounting structure and the construction thereof of prefabricated bench, its step includes: bench keeps flat standby after hanging pedestal, set up floor occasional passage, pin key is pre-buried, the terraced beam of L-type is cast-in-place, L-type ladder back portion mortar levelling, bench lifting is held on ladder beam, and bench is finely tuned, fixed temporarily, CGM grouting material is filled, late maintaining.It provides the benefit that: node connects reasonable stress, and operation is simple, and prefabricated bench uses pin key to be connected with cast-in-place ladder beam, CGM grouting material joint filling, belongs to and flexibly connects category, connects ductility of joint high, and construction technology is simple, and quality is easily controllable.

Description

A kind of pin key connects mounting structure and the construction thereof of prefabricated bench
Technical field
The present invention relates to bench installing area, particularly relate to a kind of pin key and connect mounting structure and the construction thereof of prefabricated bench Engineering method.
Background technology
Currently, the commonly used cast-in-place mode of stair bench in architectural engineering, formwork erection is complicated, by outside environmental elements shadow Ringing big, concrete appearance Forming Quality is difficult to ensure that, needs the long period to carry out maintenance, cannot function as transport logical before form removal Road, this have impact on the duration to a certain extent.
Batch production or in-situ precast stair bench, production efficiency is high, and low cost, component quality is easily controllable, building waste Discharge is few.But prefabricated bench and cast-in-place structural connected mode and the lifting of prefabricated bench, construction technique, be that needs are urgently to be resolved hurrily Problem.
Summary of the invention
The present invention solves problems of the prior art, propose a kind of pin key connect prefabricated bench mounting structure and Its construction.
The technical scheme is that and be achieved in that:
A kind of pin key connects the mounting structure of prefabricated bench, and its composition includes: bench, pin shaft hole, suspension hook, landing slab, ladder beam, institute State bench to be arranged between upper and lower two terraced beams, the step of described bench is provided with hole for hoist, is provided with in described bench side Suspension hook described in one group, the step of described bench rear and front end respectively has pin shaft hole described in a group;Described ladder beam is L-type, in institute Stating ladder beam and be built-in with pin key, described pin shaft hole is enclosed within described pin key, and the vertical direction at described pin key passes through reinforcement by institute State ladder beam to fix with described bench, described pin shaft hole pours CGM grouting material.
The opening of described hole for hoist is positioned at the step both sides of described bench, and described suspension hook is located at the two of described bench side End.
Described pin key is L-shaped, and in described pin key lower end embedment described ladder beam, described pin key upper end is inserted into described pin shaft hole In.
Gap between described bench and ladder beam is filled with foamed glue.
A kind of pin key connects the construction of prefabricated bench, and this construction comprises the steps:
A. keep flat after bench hangs pedestal, utilize hole for hoist, bench is left under order processing pedestal, lie against by the I lumps of wood and template On the table top of composition;If there being multiple bench, stacking, using the isolation of the I lumps of wood between levels bench, stacking the number of plies and do not surpass Cross 3 layers;
B. set up floor occasional passage, immediately below bench, floor beam utilizes fastener type steel pipe scaffold set up interim logical Road, lays the II lumps of wood and template, template follows closely one tread plate every 300 above passage;
C. pin key is pre-buried, the terraced beam of L-type is cast-in-place, pre-buried pin key, casting platform plate and ladder beam, controls ladder top surface of the beam concrete flatness In the range of ± 5mm;
D. ladder top surface of the beam mortar levelling, ladder top surface of the beam uses mortar levelling, and strength classes of mortar is not lower than bench strong concrete Degree grade;
E. bench lifting being held on ladder beam, the shear wall formwork of ladder beam side and stair both sides is removed and cleans out, and makes Then the hole for hoist being connected in bench with lifting shoulder pole lifts by crane, and ensures that the vertical stress of suspension centre, bench are shelved on ladder beam as far as possible, Absolute altitude error control is within ± 5mm;
F. bench is finely tuned, is fixed temporarily, uses timber wedge to be finely adjusted bench position, elevation, it is ensured that the accuracy of location, so After utilize two reinforcements by bench with ladder beam fix;
G. CGM grouting material is filled, and uses CGM grouter to pour into CGM grouting material, space between bench and ladder beam in pin shaft hole Employing foamed glue is filled, and is in the milk, filling should be closely knit;
H. CGM grouting material is carried out water seasoning at least 7 days, when water seasoning, it is ensured that CGM grouting material has enough wet Profit state.
In process step (e), must assure that chain sling with Gravity Centre of Product in vertical state during lifting, lifting speed should uniformly delay Slowly.
The invention has the beneficial effects as follows: adjacent flights of the present invention uses prefabricated or cast-in-place mode, and single flight bench can be according to need Use prefabricated or cast-in-place mode, cast-in-place change prefabricated, prefabricated change cast-in-place easy and simple to handle.
Node connects reasonable stress, and operation is simple, and pin key is connected prefabricated bench, CGM grouting material is filled out with cast-in-place ladder beam employing Seam, belongs to and flexibly connects category, connects ductility of joint high, and construction technology is simple, and quality is easily controllable.
Accompanying drawing explanation
In order to be illustrated more clearly that the embodiment of the present invention or technical scheme of the prior art, below will be to embodiment or existing In having technology to describe, the required accompanying drawing used is briefly described, it should be apparent that, the accompanying drawing in describing below is only this Some embodiments of invention, for those of ordinary skill in the art, on the premise of not paying creative work, it is also possible to Other accompanying drawing is obtained according to these accompanying drawings.
Fig. 1 is the bench mounting structure schematic diagram of the present invention;
Fig. 2 is the structural representation of the bench of the present invention;
Fig. 3 is the structural representation that the bench of the present invention leaves pedestal under order;
Fig. 4 is the structural representation that the bench level of the present invention stacks;
Fig. 5 is the structural representation of the floor occasional passage of the present invention;
Fig. 6 is the structural representation that the pin key of the present invention is pre-buried;
Fig. 7 is the structural representation of the terraced top surface of the beam mortar levelling of the present invention;
Fig. 8 is the structural representation of the bench lifting of the present invention;
Fig. 9 is that the bench of the present invention is installed and the structural representation of ladder beam;
Figure 10 is the fine setting of the bench of the present invention, interim fixing structural representation;
Figure 11 is the structural representation of the filling of the CGM grouting material of the present invention;
Figure 12 is the structural representation of the bench lifting repetitive process of the present invention;
Figure 13 is the structural representation of the lifting shoulder pole of the present invention;
Figure 14 is the partial enlarged drawing of label 17 of the present invention;
Figure 15 is the partial enlarged drawing of label 18 of the present invention.
Detailed description of the invention
Below in conjunction with the accompanying drawing in the embodiment of the present invention, the technical scheme in the embodiment of the present invention is carried out clear, complete Describe, it is clear that described embodiment is only a part of embodiment of the present invention rather than whole embodiments wholely.Based on Embodiment in the present invention, it is every other that those of ordinary skill in the art are obtained under not paying creative work premise Embodiment, broadly falls into the scope of protection of the invention.
A kind of pin key connects the mounting structure of prefabricated bench, and its composition includes: bench 5, pin shaft hole 1, suspension hook 4, landing slab 9, ladder beam 3, described bench 5 is arranged between upper and lower two terraced beams 3, is provided with hole for hoist 2, in institute on the step of described bench 5 State bench 5 side and be provided with suspension hook 4 described in a group, the step of described bench 5 rear and front end respectively has pin shaft hole 1 described in a group; Described ladder beam 3 is L-type, is built-in with pin key 16 at described ladder beam 3, and described pin shaft hole 1 is enclosed within described pin key 16, at described pin key Described ladder beam 3 is fixed with described bench 5 by the vertical direction of 16 by reinforcement 23, pours CGM grouting in described pin shaft hole 1 Material 21.
The opening of described hole for hoist 2 is positioned at the step both sides of described bench 5, and described suspension hook 4 is located at described bench 5 side Two ends.
Described pin key 16 is L-shaped, and in described pin key 16 lower end embedment described ladder beam 3, described pin key 16 upper end is inserted into institute State in pin shaft hole 1.
Gap between described bench 5 and ladder beam 3 is filled with foamed glue 20.
A kind of pin key connects mounting structure and the construction thereof of prefabricated bench, and this construction comprises the steps:
A. bench 5 keeps flat after hanging pedestal, utilizes hole for hoist 2, leaves bench 5 under order processing pedestal, lies against the I lumps of wood 7 and mould On the table top of plate 8 composition;If there being multiple bench 5, stacking, using the I lumps of wood 7 to isolate between levels bench 5, stacking layer Number is less than 3 layers;
B. set up floor occasional passage, immediately below bench 5, floor beam 12 utilizes fastener type steel pipe scaffold to set up and faces Shi Tongdao, lays the II lumps of wood 10 and template 8, template 8 follows closely one tread plate 11 every 300 above passage;
C. pin key beam pre-buried, terraced is cast-in-place, pre-buried pin key 16, casting platform plate 9 and ladder beam concrete, controls ladder top surface of the beam 13 coagulation Soil flatness is in the range of ± 5mm;
D. ladder top surface of the beam 13 mortar levelling, ladder top surface of the beam 13 uses mortar levelling, strength classes of mortar to be not lower than bench coagulation Soil strength grade;
E. bench 5 lifting being held on ladder beam 3, the shear wall formwork of ladder beam 3 side form and stair both sides is removed and cleaning is dry Only, then the hole for hoist 2 using lifting shoulder pole 22 to be connected in bench lifts by crane, and ensures the vertical stress of suspension centre as far as possible, and bench 5 is shelved On ladder beam, absolute altitude error control is within ± 5mm;
F. bench is finely tuned, is fixed temporarily, uses timber wedge 19 to be finely adjusted bench 5 position, elevation, it is ensured that the accuracy of location, Then two reinforcements 23 are utilized bench to be fixed with ladder beam 3;
G. CGM grouting material is filled, and uses CGM grouter to pour into CGM grouting material 21 in pin shaft hole 1, between bench 5 and ladder beam 3 Space uses foamed glue 20 to fill, and is in the milk, filling should be closely knit;
H. CGM grouting material is carried out water seasoning at least 7 days, when water seasoning, it is ensured that CGM grouting material has enough wet Profit state.
In process step (e), must assure that chain sling with Gravity Centre of Product in vertical state during lifting, lifting speed should uniformly delay Slowly, during lifting bench, use steel wire to be connected on tower crane by lifting shoulder pole.
In process step (e), lifting shoulder pole 22 uses 6,25 meters of 14,2 3.8 meters long steel wire ropes of 14 meters long 16# channel-section steel Long steel wire rope, 8 shackles, 4 set lifting bolts 15 are made.
The foregoing is only presently preferred embodiments of the present invention, not in order to limit the present invention, all essences in the present invention Within god and principle, any modification, equivalent substitution and improvement etc. made, should be included within the scope of the present invention.

Claims (6)

1. pin key connects a mounting structure for prefabricated bench, and its composition includes: bench, pin shaft hole, suspension hook, landing slab, ladder beam, Described bench is arranged between upper and lower two terraced beams, it is characterised in that: on the step of described bench, it is provided with hole for hoist, described Bench side is provided with suspension hook described in a group, and the step of described bench rear and front end respectively has pin shaft hole described in a group;Described ladder Beam is L-type, is built-in with pin key at described ladder beam, and described pin shaft hole is enclosed within described pin key, and the vertical direction at described pin key is led to Cross reinforcement to be fixed with described bench by described ladder beam, described pin shaft hole pours CGM grouting material.
Pin key the most according to claim 1 connects the mounting structure of prefabricated bench, it is characterised in that: opening of described hole for hoist Mouth is positioned at the step both sides of described bench, and described suspension hook is located at the two ends of described bench side.
Pin key the most according to claim 1 connects the mounting structure of prefabricated bench, it is characterised in that: described pin key is L-shaped, In described pin key lower end embedment described ladder beam, described pin key upper end is inserted in described pin shaft hole.
Pin key the most according to claim 1 connects the mounting structure of prefabricated bench, it is characterised in that: at described bench and ladder Gap between beam is filled with foamed glue.
5. the construction of the pin key prefabricated bench of connection, it is characterised in that: this construction comprises the steps:
A. keep flat after bench hangs pedestal, utilize hole for hoist, bench is left under order processing pedestal, lie against by the I lumps of wood and template On the table top of composition;If there being multiple bench, stacking, using the isolation of the I lumps of wood between levels bench, stacking the number of plies and do not surpass Cross 3 layers;
B. set up floor occasional passage, immediately below bench, floor beam utilizes fastener type steel pipe scaffold set up interim logical Road, lays the II lumps of wood and template, template follows closely one tread plate every 300 above passage;
C. pin key is pre-buried, the terraced beam of L-type is cast-in-place, pre-buried pin key, casting platform plate and ladder beam, controls ladder top surface of the beam concrete flatness In the range of ± 5mm;
D. ladder top surface of the beam mortar levelling, ladder top surface of the beam uses mortar levelling, and strength classes of mortar is not lower than bench strong concrete Degree grade;
E. bench lifting being held on ladder beam, the shear wall formwork of ladder beam side and stair both sides is removed and cleans out, and makes Then the hole for hoist being connected in bench with lifting shoulder pole lifts by crane, and ensures that the vertical stress of suspension centre, bench are shelved on ladder beam as far as possible, Absolute altitude error control is within ± 5mm;
F. bench is finely tuned, is fixed temporarily, uses timber wedge to be finely adjusted bench position, elevation, it is ensured that the accuracy of location, so After utilize two reinforcements by bench with ladder beam fix;
G. CGM grouting material is filled, and uses CGM grouter to pour into CGM grouting material, space between bench and ladder beam in pin shaft hole Employing foamed glue is filled, and is in the milk, filling should be closely knit;
H. CGM grouting material is carried out water seasoning at least 7 days, when water seasoning, it is ensured that CGM grouting material has enough wet Profit state.
Pin key the most according to claim 5 connects the construction that prefabricated bench is installed, it is characterised in that: in step (e) In, must assure that chain sling during lifting with Gravity Centre of Product in vertical state, lifting speed should be the slowest.
CN201610633961.5A 2016-08-05 2016-08-05 A kind of pin key connects mounting structure and the construction thereof of prefabricated bench Pending CN106088493A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201610633961.5A CN106088493A (en) 2016-08-05 2016-08-05 A kind of pin key connects mounting structure and the construction thereof of prefabricated bench

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201610633961.5A CN106088493A (en) 2016-08-05 2016-08-05 A kind of pin key connects mounting structure and the construction thereof of prefabricated bench

Publications (1)

Publication Number Publication Date
CN106088493A true CN106088493A (en) 2016-11-09

Family

ID=57453767

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201610633961.5A Pending CN106088493A (en) 2016-08-05 2016-08-05 A kind of pin key connects mounting structure and the construction thereof of prefabricated bench

Country Status (1)

Country Link
CN (1) CN106088493A (en)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108385908A (en) * 2018-03-12 2018-08-10 中国建筑设计院有限公司 A kind of attachment device of assembled stair, assembled stair and its installation method
CN108560842A (en) * 2018-06-01 2018-09-21 孟凡林 With the precast concrete stair section of multipurpose hole and its preparation and application
CN109457881A (en) * 2018-12-14 2019-03-12 成都建工工业化建筑有限公司 A kind of stair and its manufacture craft of fabricated structure
CN111335561A (en) * 2020-03-06 2020-06-26 吴传江 Stair installation construction method for fabricated building
CN111535530A (en) * 2020-05-22 2020-08-14 浙江鼎兴建设有限公司 Assembled stair
CN113404235A (en) * 2021-06-17 2021-09-17 广东翔顺建筑工程有限公司 Simply-supported two-span continuous prefabricated assembled scissors stair of segmentation earlier

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07119213A (en) * 1993-10-20 1995-05-09 Tokyu Koken Kk Joint structure of precast reinforced concrete member
CN201217898Y (en) * 2008-06-19 2009-04-08 黑龙江宇辉新型建筑材料有限公司 Concrete prefabricated stairs
CN202450720U (en) * 2012-01-17 2012-09-26 深圳海龙建筑制品有限公司 Concrete prefabricated stair component
CN102767288A (en) * 2012-01-17 2012-11-07 中国建筑第四工程局有限公司 Method and structure for mounting precast reinforced concrete stairs
CN103132660A (en) * 2013-03-11 2013-06-05 新疆七星建设科技股份有限公司 Concrete precast stairway fixed end support
CN205840190U (en) * 2016-08-05 2016-12-28 中国建筑第七工程局有限公司 A kind of pin key connects the mounting structure of prefabricated bench

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH07119213A (en) * 1993-10-20 1995-05-09 Tokyu Koken Kk Joint structure of precast reinforced concrete member
CN201217898Y (en) * 2008-06-19 2009-04-08 黑龙江宇辉新型建筑材料有限公司 Concrete prefabricated stairs
CN202450720U (en) * 2012-01-17 2012-09-26 深圳海龙建筑制品有限公司 Concrete prefabricated stair component
CN102767288A (en) * 2012-01-17 2012-11-07 中国建筑第四工程局有限公司 Method and structure for mounting precast reinforced concrete stairs
CN103132660A (en) * 2013-03-11 2013-06-05 新疆七星建设科技股份有限公司 Concrete precast stairway fixed end support
CN205840190U (en) * 2016-08-05 2016-12-28 中国建筑第七工程局有限公司 A kind of pin key connects the mounting structure of prefabricated bench

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108385908A (en) * 2018-03-12 2018-08-10 中国建筑设计院有限公司 A kind of attachment device of assembled stair, assembled stair and its installation method
CN108385908B (en) * 2018-03-12 2020-03-17 中国建筑设计研究院有限公司 Connecting device of assembled stair, assembled stair and installation method of assembled stair
CN108560842A (en) * 2018-06-01 2018-09-21 孟凡林 With the precast concrete stair section of multipurpose hole and its preparation and application
CN109457881A (en) * 2018-12-14 2019-03-12 成都建工工业化建筑有限公司 A kind of stair and its manufacture craft of fabricated structure
CN111335561A (en) * 2020-03-06 2020-06-26 吴传江 Stair installation construction method for fabricated building
CN111535530A (en) * 2020-05-22 2020-08-14 浙江鼎兴建设有限公司 Assembled stair
CN111535530B (en) * 2020-05-22 2021-06-01 浙江鼎兴建设有限公司 Assembled stair
CN113404235A (en) * 2021-06-17 2021-09-17 广东翔顺建筑工程有限公司 Simply-supported two-span continuous prefabricated assembled scissors stair of segmentation earlier

Similar Documents

Publication Publication Date Title
CN106088493A (en) A kind of pin key connects mounting structure and the construction thereof of prefabricated bench
CN108005387B (en) Synchronous construction method for cast-in-place main body of assembled wallboard and short-limb shear wall
CN112854745A (en) Construction process of assembled building aluminum alloy template
CN104790675B (en) Reinforced concrete block masonry structure assemblage construction method
CN107605177A (en) The construction method of efficient precast floor slab and its independent support frame
CN108104284B (en) Wallboard connecting structure of shear wall steel arm embedded floor slab and assembly method
CN108130837A (en) A kind of prefabricated road plate and its construction method
CN105507470B (en) A kind of periphery overlapping overall assembled floor and its construction method
CN109025291A (en) A kind of construction method of separate type precast stair
CN108582466A (en) A kind of steel reinforcement cage of prefabricated box girder mould
CN104947846B (en) A kind of prefabricated integral frame light filling lining and preparation method thereof
CN110145124A (en) A kind of control shear wall level connects the reinforcement tools and its construction method of batch quality
CN112627387A (en) Rib-free type side connection method for prefabricated external wall panel
CN106906841A (en) One kind is used for lateral wall form bracing system construction
CN207003723U (en) High-rise assembled single row of holes precast shear wall and its assembling structure
CN104675112A (en) Steel stair formwork and constructing method for once pouring forming of building staircase
CN109895239B (en) Fabricated concrete stair slow platform beam slab and construction method thereof
CN105201107A (en) Construction method for stacked plate type shear wall of underground garage
CN205840190U (en) A kind of pin key connects the mounting structure of prefabricated bench
CN205224332U (en) Prefabricated wall body and prefabricated wallboard
CN110644667A (en) Assembly type bin top structure of round storage bin and assembly method thereof
CN106801384A (en) Assembled steel reinforced concrete aliform type culvert opening and construction method
CN206902913U (en) A kind of high-altitude long-span overhung structure
CN207194333U (en) A kind of hollow stair of marking time of precast concrete
CN107152112A (en) A kind of modularization Prefabricated stacking floor and its construction method for being used to drop plate region

Legal Events

Date Code Title Description
C06 Publication
PB01 Publication
C10 Entry into substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20161109

RJ01 Rejection of invention patent application after publication