CN110984359A - Low-rise assembled building structure - Google Patents
Low-rise assembled building structure Download PDFInfo
- Publication number
- CN110984359A CN110984359A CN201910675515.4A CN201910675515A CN110984359A CN 110984359 A CN110984359 A CN 110984359A CN 201910675515 A CN201910675515 A CN 201910675515A CN 110984359 A CN110984359 A CN 110984359A
- Authority
- CN
- China
- Prior art keywords
- cast
- prefabricated
- layer
- steel bars
- floor
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
- 229910000831 Steel Inorganic materials 0.000 claims abstract description 38
- 239000010959 steel Substances 0.000 claims abstract description 38
- 229910001294 Reinforcing steel Inorganic materials 0.000 claims abstract description 16
- 239000004570 mortar (masonry) Substances 0.000 claims description 14
- 230000002787 reinforcement Effects 0.000 claims description 8
- 210000002435 tendon Anatomy 0.000 claims 1
- 238000010276 construction Methods 0.000 abstract description 15
- 238000013461 design Methods 0.000 abstract description 5
- 230000000694 effects Effects 0.000 abstract description 2
- 230000002457 bidirectional effect Effects 0.000 abstract 1
- 230000003014 reinforcing effect Effects 0.000 description 12
- 238000000034 method Methods 0.000 description 6
- 238000003466 welding Methods 0.000 description 4
- 239000000919 ceramic Substances 0.000 description 3
- 238000003780 insertion Methods 0.000 description 3
- 230000037431 insertion Effects 0.000 description 3
- 230000009286 beneficial effect Effects 0.000 description 2
- 238000009435 building construction Methods 0.000 description 2
- 238000005516 engineering process Methods 0.000 description 2
- 238000009415 formwork Methods 0.000 description 2
- 239000011440 grout Substances 0.000 description 2
- 238000002360 preparation method Methods 0.000 description 2
- 238000009825 accumulation Methods 0.000 description 1
- 238000005452 bending Methods 0.000 description 1
- 239000004568 cement Substances 0.000 description 1
- 230000007547 defect Effects 0.000 description 1
- 238000009826 distribution Methods 0.000 description 1
- 238000009434 installation Methods 0.000 description 1
- 238000012423 maintenance Methods 0.000 description 1
- 238000004519 manufacturing process Methods 0.000 description 1
- 238000012986 modification Methods 0.000 description 1
- 230000004048 modification Effects 0.000 description 1
- 239000003973 paint Substances 0.000 description 1
- 230000002265 prevention Effects 0.000 description 1
- 238000010008 shearing Methods 0.000 description 1
- XLYOFNOQVPJJNP-UHFFFAOYSA-N water Substances O XLYOFNOQVPJJNP-UHFFFAOYSA-N 0.000 description 1
- 238000005303 weighing Methods 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B1/00—Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
- E04B1/16—Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material
- E04B1/164—Structures made from masses, e.g. of concrete, cast or similarly formed in situ with or without making use of additional elements, such as permanent forms, substructures to be coated with load-bearing material with vertical and horizontal slabs, only the horizontal slabs being partially cast in situ
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B2/00—Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
- E04B2/56—Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
- E04B2/64—Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members with elongated members of concrete
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04C—STRUCTURAL ELEMENTS; BUILDING MATERIALS
- E04C5/00—Reinforcing elements, e.g. for concrete; Auxiliary elements therefor
- E04C5/16—Auxiliary parts for reinforcements, e.g. connectors, spacers, stirrups
- E04C5/162—Connectors or means for connecting parts for reinforcements
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Joining Of Building Structures In Genera (AREA)
Abstract
The utility model provides a low-rise fabricated building structure, includes the foundation beam, sets up in the prefabricated wallboard of foundation beam top, sets up in the edge member at both ends about the prefabricated wallboard, sets up in the cast-in-place crossbeam in wall body top, sets up in the prefabricated floor layer of cast-in-place crossbeam top, sets up in the cast-in-place floor layer of prefabricated floor layer top, two layers are repeated construction in proper order. Wherein, double layers of bidirectional distributed steel bars are arranged in the prefabricated wall board, and a single-row corrugated pipe is embedded in the design position of the bottom of the wall board in advance; the crossbeam is embedded with a single row of vertical dowel shear keys; the wall plate reinforcing steel bars and the cross beam reinforcing steel bars positioned below the wall plate are overlapped to form a reliable whole through edge member reinforcing steel bars; the wall plate reinforcing steel bars and the cast-in-place floor plate reinforcing steel bars above the wall plate are overlapped into a whole through the cast-in-place cross beam reinforcing steel bars. The connection form of the wall plate and the beam and the connection form of the wall plate and the floor slab avoid the damage phenomenon that the upper wall body integrally slides when the wall body is sheared. The first floor prefabricated wall plate reinforcing steel bars are welded with the cast-in-place floor plate reinforcing steel bars, and the effect close to the stress performance of a cast-in-place wall body is achieved.
Description
Technical Field
The invention particularly relates to a low-rise assembled building structure, belongs to the technical field of assembled buildings, and particularly relates to the low-rise assembled building structure which is high in positioning accuracy, high in construction speed, time-saving, labor-saving and strong in stress performance.
Background
Wall body horizontal joint often has steel bar muffjoint among the low-rise assembled building structure, often has bolted connection between wallboard and the floor, but these connection methods have following problem: 1. in the construction process, grouting is not easy to occur due to the narrow and narrow grouting hole, a worker can paint cement paste on the upper grout outlet of the sleeve to make the false appearance of the flow at the upper grout outlet; 2. When the bolt connecting wall and the plate are aligned to the bolt holes, the control is difficult, the construction difficulty is relatively high, and the weighing performance is difficult to control; the invention discloses a novel assembly type building construction process based on a novel wall horizontal joint connecting technology and a floor and wallboard connecting technology, so that the construction speed, the construction cost and the stress performance are optimized.
Aiming at the problems of the assembly type building structure, the invention provides a novel low-rise assembly type building structure and a construction process thereof, aiming at overcoming the defects and shortcomings in the prior art, and the reliability of the stress performance of the whole structure is ensured on the premise of convenient construction, low construction cost and mass production.
Disclosure of Invention
In order to solve the problems, the invention provides the low-rise fabricated building structure which is high in positioning accuracy, high in construction speed, time-saving, labor-saving and strong in stress performance.
The wall structure comprises an edge member connected with a bottom beam steel bar, a prefabricated wall plate connected with the edge member steel bar, and a mortar layer connecting the prefabricated wall plate and the bottom beam, wherein the floor structure is divided into a prefabricated floor layer and a cast-in-place floor layer double-layer structure, the edge member steel bar is built after the wall plate is assembled to a specified position, an inserted bar shear key is added between the prefabricated wall plate and the beam, the bottom beam is pre-embedded with a vertical inserted bar to avoid insufficient shear strength caused by lack of shear reinforcement due to pure mortar connection between the middle prefabricated wall plate and the bottom beam, the inserted bar shear key is also pre-embedded between the two layers and the upper beam and penetrates through the cast-in-place floor layer to be inserted into the two layers of wall plates, and when the two layers of beams are poured, the reserved lap joint of the first layer of wall plate and the internal steel bar thereof are bound and the lap joint steel bar of the cast-in-place floor plate is reserved, when two layers and above crossbeams are poured, vertical joint bars are embedded in the designed positions, and the first layer structure is assembled on two layers and above wallboards.
Furthermore, the embedded dowel bars of the foundation beam are bound with the beam steel bars when the foundation beam is manufactured, and the dowel bars of two or more layers are bound with the beam steel bars before the beam is poured, and the diameter is not easy to be too small, so that the sufficient shear strength is ensured.
Furthermore, the bottom end of the prefabricated wallboard is provided with a corrugated pipe with the size matched with the joint bars, a cavity with enough thickness is reserved between the corrugated pipe and the joint bars, and the filled mortar can reach enough strength.
Further, a 20mm mortar layer is arranged between the prefabricated wall board and the bottom cross beam.
The invention has the following beneficial effects:
the prefabricated wall plate reinforcing steel bars and the bottom cross beam reinforcing steel bars are indirectly lapped together by using edge member reinforcing steel bars to form an integral reinforcing steel bar framework, so that the integral reinforcing steel bar framework is stressed cooperatively, the inserted steel bars are arranged between the prefabricated wall plate and the bottom cross beam, and the inserted steel bars are arranged between the two layers of cross beams and the two layers of prefabricated wall plates. The dowel bars are poured into the cross beam, so that the adjustment of the dowel bars is facilitated, the phenomenon that the horizontal joint loses shear resistance too early due to insufficient shear strength is avoided, and the stress performance is more excellent and is closer to that of a cast-in-place member.
In addition, the assembly type building structure can effectively simplify construction steps, is convenient to operate, has small workload, reduces construction cost and can be produced in batch.
Drawings
FIG. 1 is a detailed schematic view of a fabricated building structure of the present invention;
FIG. 2 is a detailed schematic view of the horizontal joint connection structure of the fabricated shear wall according to the present invention;
FIG. 3 is a cross-sectional view of the shear wall of the present invention shown in FIG. 1;
FIG. 4 is a detailed cross-sectional view of the shear wall of the present invention shown in FIG. 1 with horizontal joints connected;
fig. 5 is a schematic view of the internal structure of the prefabricated wall panel of the present invention: the corrugated pipe is pre-embedded in the concrete slab and is not directly connected with the vertical steel bar of the wallboard;
FIG. 6 is a schematic view of the internal structure of a shear wall foundation beam according to the present invention;
FIG. 7 is a detailed view of the assembled structural wall panel and floor slab connection of the present invention;
wherein, 1-foundation beam, 2-edge member, 3-prefabricated wall panel, 4-two layers of cast-in-place beam, 5-ceramic tile roof supported by truss structure, 6-mortar layer, 7-embedded corrugated pipe, 8-steel-inserted shear key, 9-prefabricated wall panel reserved transverse lapping steel bar, 10-prefabricated wall panel reserved longitudinal lapping steel bar, 11-foundation beam internal reinforcement, 12-foundation beam reserved lapping steel bar, 13-first layer of prefabricated wall panel, 14-second layer of prefabricated wall panel, 15-cast-in-place floor layer, 16-prefabricated floor layer, 17-prefabricated floor distribution steel bar, 18-two layers of cast-in-place beam reserved lapping steel bar
Detailed Description
As shown in fig. 1 to 7, a low-rise fabricated building structure, a wall body is connected with a horizontal joint connection structure of an upper prefabricated wall plate and a foundation beam by mortar, a floor plate is provided with a two-layer structure of a prefabricated floor layer and a cast-in-place floor layer, and the low-rise fabricated building structure generally comprises a foundation beam 1, two layers of cast-in-place beams 4, edge members 2, prefabricated wall plates 3 and a ceramic tile roof 5 supported by a truss structure.
Wherein to first floor structure, it is pre-buried at the wallboard bottom with diameter 30mm ~ 40 mm's single-row bellows 7 during the prefabricated wallboard preparation, pour diameter 20 mm's single-row joint bar 8 at the design position during the base beam preparation, build 10mm ~ 20 mm's mortar 6 on the crossbeam during assembly first, fill the concrete with bellows cavity in, then assemble the wallboard and make bellows 7 aim at with joint bar 8 and take one's place, later lap joint base beam reserves overlap joint reinforcing bar 12 and edge member reinforcing bar, edge member reinforcing bar and prefabricated wallboard transverse reinforcement 9, the edge member of pouring again, when first floor capping: the beam 4 is poured on the first layer wall body, the prefabricated floor 16 is built after the cast-in-place beam reaches a certain strength, then the cast-in-place floor layer steel bars and the reserved longitudinal lap joint steel bars 10 of the first layer wall body are bound, the dowel bars 8 are bound at set positions, and finally the floor layer is poured, wherein the construction process of the two-layer structure is the same as that of the first layer.
Wherein, overlap joint reinforcing bar 12 welding is reserved with the foundation beam to the vertical reinforcing bar of edge member, and edge member horizontal reinforcing bar and the horizontal reinforcing bar 9 welding of prefabricated wallboard, prefabricated wallboard vertical reinforcing bar do not pass the mortar layer, and pre-buried dowel bar passes the mortar layer during the assembly and gets into in the bellows of filling up the concrete in the bottom crossbeam.
Preferably, a cavity with enough thickness is reserved between the embedded corrugated pipe 7 at the bottom of the prefabricated wall board and the joint bars 8, so that the sleeve joint bars and grouting are more convenient and easier, and the concrete has enough strength.
Preferably, the diameter of the embedded dowel of the bottom cross beam is not smaller than 15mm, and is beneficial to about 20mm, so that the shear-resistant requirement is met. The design quantity of the single-row inserted bars 8 is determined according to the horizontal section height of the wallboard, and the applicable quantity of the commonly used 1800mm wall body width in the engineering is as follows: about 6; suitable number of 3600mm wall width: about 12; 5400mm wall width applicable quantity: about 18.
Preferably, the diameter of the vertical steel bar of the edge member is not less than 10mm, so that the edge member has certain bending and shearing resistance.
Preferably, the inserted bars 8 pre-embedded in the cast-in-place cross beams 4 on two or more layers finally penetrate through the cast-in-place floor layer and are inserted into the corrugated pipes in the prefabricated wall boards on the two layers; the prefabricated wallboard of first floor reserves vertical overlap joint reinforcing bar 10 and the ligature of two layers of cast-in-place crossbeam 4, and the overlap joint reinforcing bar 18 that the cast-in-place crossbeam of two layers reserved and the ligature of cast-in-place floor layer reinforcing bar.
The whole installation sequence of the building structure is as follows:
1) the method comprises the steps of ①, in the first floor, binding insertion bars 8 and reserved overlap steel bars 12 of a foundation beam with bottom beam reinforcing bars 11 according to the design positions, wherein the insertion bars 8 are arranged in a single row, maintaining until the beams meet the strength requirement as shown in figure 5, in the ② prefabricated wallboard, fixedly pouring corrugated pipes 7 into concrete according to the design positions as shown in figure 4, in the ③ assembling, filling the corrugated pipes with concrete, smearing mortar with the thickness of 20mm on the foundation beam 1, assembling the prefabricated wallboard 3 on the beam 1 according to the set positions, enabling the insertion bars 8 to be inserted into the corrugated pipes 7, in the ④, welding the bound vertical steel bars of edge members with the reserved overlap steel bars 12 of the foundation beam, welding the horizontal steel bars of the edge members with the horizontal steel bars 9 of the prefabricated wallboard (the longitudinal steel bars of the edge members need to reserve two layers of overlap steel bars), pouring the edge members 2 with concrete, maintaining until the specified strength is met, removing a formwork, in the ⑤, when the reserved first floor beam 4 is sealed, overlapping the steel bars of the first floor with the reserved slab 10, overlapping the slab 8 with the slab and the slab layer of the prefabricated wallboard, maintaining the slab, and finishing the building construction.
2) And a second floor, wherein ① is assembled, a mortar layer with the thickness of 20mm is coated at a set position above a cast-in-place floor layer 15, a second floor of prefabricated wall plate 14 is arranged at the set position, so that the dowel bars 8 correspond to the corrugated pipes 7 in the second floor of prefabricated wall plate 14, ② is used for binding the longitudinal steel bars in the second floor of edge member 2 with the reserved lap steel bars of the first floor of edge member, the transverse steel bars in the second floor of edge member 2 are bound with the transverse steel bars 9 of the prefabricated wall plate, ③ is used for pouring the concrete of the edge member 2, the formwork is removed after maintenance to a specified strength, the construction is the same as the construction of the floor when the structure ④ is closed, the ceramic tile roof supported by a truss structure additionally arranged at the top is constructed according to a conventional truss roof, the effects of water accumulation prevention and attractiveness are mainly achieved.
The above-described embodiments are merely illustrative of the preferred embodiments of the present invention, and do not limit the scope of the present invention, and various modifications and improvements made to the technical solutions of the present invention by those skilled in the art without departing from the spirit of the present invention are intended to fall within the scope of the present invention defined by the claims.
Claims (5)
1. A low-rise assembled building structure is characterized in that a wall structure comprises an edge member connected with a bottom cross beam steel bar, a prefabricated wallboard connected with the edge member steel bar and a mortar layer connecting the prefabricated wallboard and the bottom cross beam, the floor structure is divided into a prefabricated floor layer and a cast-in-place floor layer double-layer structure, wherein the edge member steel bar is built after the wallboard is assembled to a specified position, an inserted bar shear key is added between the prefabricated wallboard and the cross beam, the bottom cross beam pre-embedded vertical inserted bar is used for avoiding the insufficient shear strength caused by the lack of shear reinforcement due to the pure mortar connection between the middle prefabricated wallboard and the bottom cross beam, the inserted bar shear key is also pre-embedded when two or more cross beams are poured and penetrates through the cast-in-place floor layer to be inserted into the two layers of wallboards, the lap joint steel bar reserved on the first layer of wallboard is bound with the internal steel bar thereof and the lap joint steel bar bound with the cast-in-, when two layers and above crossbeams are poured, vertical joint bars are embedded in the designed positions, and the first layer structure is assembled on two layers and above wallboards.
2. The lap joint of cast-in-place floor slab reinforcing steel bars as claimed in claim 1, wherein the distributed reinforcing steel bars are bound with the reserved lap joint reinforcing steel bars of the two layers of cross beams, so that the prefabricated wall panel, the floor slab and the edge member form a reliable whole and are stressed together.
3. An edge member reinforcement according to claim 1, wherein the first layer of edge member reinforcement is provided with overlapping reinforcement welded to the second layer of edge member reinforcement.
4. A floor slab structure as claimed in claim 1, which is divided into a prefabricated floor slab and a cast-in-place floor slab, and the dowel bars embedded in the two or more layers of beams penetrate through the cast-in-place floor slab and are inserted into the corrugated pipes embedded in the two layers of prefabricated wall slabs.
5. The two-layer prefabricated wall panel of claim 1, wherein the assembly conditions are substantially the same as those of the first layer, the mortar layer, the edge members, the embedded shear keys for the tendons are arranged, and the assembly sequence is also the same.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910675515.4A CN110984359A (en) | 2019-07-25 | 2019-07-25 | Low-rise assembled building structure |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910675515.4A CN110984359A (en) | 2019-07-25 | 2019-07-25 | Low-rise assembled building structure |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110984359A true CN110984359A (en) | 2020-04-10 |
Family
ID=70081792
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910675515.4A Pending CN110984359A (en) | 2019-07-25 | 2019-07-25 | Low-rise assembled building structure |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110984359A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111519757A (en) * | 2020-04-16 | 2020-08-11 | 闫旺升 | Assembled concrete building connection structure |
CN113293856A (en) * | 2021-06-07 | 2021-08-24 | 上海恪耐新材料科技有限公司 | Construction method of fabricated building |
CN115234069A (en) * | 2022-07-06 | 2022-10-25 | 河南工业大学 | Assembled grain horizontal warehouse |
CN117449532A (en) * | 2023-11-01 | 2024-01-26 | 山东联强建筑工业科技有限公司 | Novel prefabricated hollow post connection structure of assembled |
Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20100218446A1 (en) * | 2006-05-18 | 2010-09-02 | Ping Qu | Structure system of concrete building for self-heat insulation |
CN203097016U (en) * | 2013-03-08 | 2013-07-31 | 沈阳建筑大学建筑设计研究院 | Assembled-type concrete frame shear wall structure |
CN204571002U (en) * | 2014-12-29 | 2015-08-19 | 华北水利水电大学 | A kind of formula that is vertically linked and packed concrete shear force wall of pre-buried bellows pore-forming |
CN107574934A (en) * | 2017-09-26 | 2018-01-12 | 中国二十二冶集团有限公司 | Fabricated shear wall embedded sleeve barrel joint bar construction method |
CN108035433A (en) * | 2018-01-14 | 2018-05-15 | 万华集成房屋(烟台)有限公司 | Prefabricated house is built and its method of construction |
CN211447322U (en) * | 2019-06-18 | 2020-09-08 | 河北工程大学 | Novel horizontal seam connection structure of assembled shear force wall |
-
2019
- 2019-07-25 CN CN201910675515.4A patent/CN110984359A/en active Pending
Patent Citations (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US20100218446A1 (en) * | 2006-05-18 | 2010-09-02 | Ping Qu | Structure system of concrete building for self-heat insulation |
CN203097016U (en) * | 2013-03-08 | 2013-07-31 | 沈阳建筑大学建筑设计研究院 | Assembled-type concrete frame shear wall structure |
CN204571002U (en) * | 2014-12-29 | 2015-08-19 | 华北水利水电大学 | A kind of formula that is vertically linked and packed concrete shear force wall of pre-buried bellows pore-forming |
CN107574934A (en) * | 2017-09-26 | 2018-01-12 | 中国二十二冶集团有限公司 | Fabricated shear wall embedded sleeve barrel joint bar construction method |
CN108035433A (en) * | 2018-01-14 | 2018-05-15 | 万华集成房屋(烟台)有限公司 | Prefabricated house is built and its method of construction |
CN211447322U (en) * | 2019-06-18 | 2020-09-08 | 河北工程大学 | Novel horizontal seam connection structure of assembled shear force wall |
Non-Patent Citations (1)
Title |
---|
张军;侯海泉;董年才;龚俊杰;郭正兴;: "全预制装配整体式剪力墙住宅结构设计及应用" * |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111519757A (en) * | 2020-04-16 | 2020-08-11 | 闫旺升 | Assembled concrete building connection structure |
CN113293856A (en) * | 2021-06-07 | 2021-08-24 | 上海恪耐新材料科技有限公司 | Construction method of fabricated building |
CN115234069A (en) * | 2022-07-06 | 2022-10-25 | 河南工业大学 | Assembled grain horizontal warehouse |
CN117449532A (en) * | 2023-11-01 | 2024-01-26 | 山东联强建筑工业科技有限公司 | Novel prefabricated hollow post connection structure of assembled |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110984359A (en) | Low-rise assembled building structure | |
CN106836479B (en) | Assembled prestressed concrete frame structure | |
CN102561553B (en) | Prefabricated concrete-filled steel tube frame-shear wall and construction method thereof | |
CN106968381B (en) | Assembled prefabricated shear wall and superimposed sheet node connected by combined grouting sleeve | |
CN109339229B (en) | Prefabricated assembled concrete-filled steel tube frame structure of perforation thick liquid anchor | |
CN105696817A (en) | Multilayer cold-formed steel integrally prefabricated house and splicing method thereof | |
CN110670770A (en) | Solid shear wall and laminated plate type edge member combined structure and construction method | |
CN204645253U (en) | A kind of prefabricated house | |
CN113833162B (en) | Shear wall structure system with high prefabrication rate and low cost and construction method | |
CN114319977B (en) | Steel pipe concrete row column type connection precast shear wall structure and construction method | |
CN109555240B (en) | Partially prestressed assembled shear wall structure | |
CN110700873A (en) | Prefabricated rail top air duct for subway station and construction method thereof | |
CN211447322U (en) | Novel horizontal seam connection structure of assembled shear force wall | |
CN212271326U (en) | Cast-in-place concrete wall body of combined truss reinforcing steel bars and steel plates | |
CN204781443U (en) | Device for connecting precast shear wall concatenation about being used for | |
CN111441513A (en) | Cast-in-place concrete wall body combining truss reinforcing steel bars and steel plates and construction method | |
CN218205681U (en) | Board strip of assembled building superimposed sheet leaks thick liquid controlling means | |
CN216892975U (en) | Prefabricated assembled coincide steel pipe concrete shear force wall | |
CN108755938B (en) | Steel core area node of assembled concrete frame | |
CN114658141B (en) | T-shaped constructional column and independent foundation connection structure of assembled composite wallboard and manufacturing method | |
CN114263275B (en) | Construction method for same-layer construction of high-rise assembled steel structure-core tube | |
CN105040855A (en) | Assembled prefabricated shear wall welding end plate and horizontal steel combination connecting device | |
CN214364434U (en) | Assembled constructional column suitable for prefabricated wallboard of frame construction | |
CN213927078U (en) | Prefabricated assembly type steel concrete mixed beam with angle steel connecting piece prefabricated plate part | |
CN110439267A (en) | A kind of aluminum alloy mould plate applied to laminated floor slab construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200410 |