CN109778864A - A kind of cubic metre of earth of stage excavation construction method - Google Patents

A kind of cubic metre of earth of stage excavation construction method Download PDF

Info

Publication number
CN109778864A
CN109778864A CN201910221060.9A CN201910221060A CN109778864A CN 109778864 A CN109778864 A CN 109778864A CN 201910221060 A CN201910221060 A CN 201910221060A CN 109778864 A CN109778864 A CN 109778864A
Authority
CN
China
Prior art keywords
excavation
earth
construction
stake
cubic metre
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910221060.9A
Other languages
Chinese (zh)
Inventor
彭涛
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
CREEC Chengdu Survey Design and Research Co Ltd
Original Assignee
CREEC Chengdu Survey Design and Research Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by CREEC Chengdu Survey Design and Research Co Ltd filed Critical CREEC Chengdu Survey Design and Research Co Ltd
Priority to CN201910221060.9A priority Critical patent/CN109778864A/en
Publication of CN109778864A publication Critical patent/CN109778864A/en
Pending legal-status Critical Current

Links

Abstract

The invention discloses a kind of cubic metre of earth of stage excavation construction methods, it is related to earth excavation technical field of construction, the present invention is the following steps are included: (1) surveying setting-out: according to established plane and elevation control system, boundary stake is released, and controls stake in each boundary setting transverse direction and longitudinal direction, every 100m is arranged one, control stake concreting, for buried depth in below ground 20cm, survey sets grid to implement construction lofting, and measures the ground elevation and design altitude of grid stake point;(2) bursting work: one layer of every explosion measures this layer of elevation in time;(3) it removes surface vegetation: clearing up, excavates excavation section earth's surface organoclay, turf and tree root, and transported to specified spoil ground;(4) excavation construction: excavating intercepting ditch in advance, and excavation takes stage excavation from top to bottom, and excavation usage mining machine when construction cubic metre of earth is cut the earth and entrucking, the present invention have the advantages that working procedure normal science, difficulty of construction are low, guarantee that the duration goes on smoothly.

Description

A kind of cubic metre of earth of stage excavation construction method
Technical field
The present invention relates to earth excavation technical field of construction, more particularly to a kind of cubic metre of earth of stage excavation construction party Method.
Background technique
Earth excavation is engineering initial stage down to the critical process in work progress, and soil and rock are loosened, be crushed, dug The engineering dug and transported, by rock and soil properties, earthwork evacuation divides earth excavation and rock excavation.Earth excavation is by construction environment Outdoor, underground is underwater, is divided into open cut, hole is dug and underwater excavation classification.In hydraulic engineering, earth excavation is widely used in field Ground is smooth and cuts slope, and hydraulic structure (sluice, dam, spillway, powerhouse of hydropower station, pumping plant building etc.) ground excavates, underground Cavern's (hydraulic tunnel, underground power house, all kinds of adits, vertical shaft and inclined shaft) is excavated, and river, channel, harbour is excavated and dredging, is filled Material, building stone and aggregate exploitation, the temporay buildings such as cofferdam or stone-laying, the dismounting of concrete structure etc..Soil Square excavation construction, including loosen, be crushed, digging dress, transport such as is slagged tap at the processes.Rock excavation, except crumbly rock can with ridge buster with Chisel is split outside method excavation, need to generally be loosened, is crushed in the method for explosion.Artificial and semi-mechanization is excavated, and spade pick, wind are used The simple tools such as pick, air drill, lift is chosen in cooperation or the means of transport of Simple compact carries out operation, is suitable for small hydraulic project. The construction of some irrigation and drainage irrigation canals and ditches directly uses ditching machine, can be once-forming, the earthwork evacuation of large and medium-sized hydraulic engineering, Multi-purpose mechanical construction.
Earth excavation construction work is larger, and the duration is tighter, needs rationally to control every one of working procedure, and existing soil Square excavation construction method is lack of standardization, not scientific and reasonable enough, and difficulty of construction is big, and construction period is caused to extend.
Therefore above-mentioned technical problem how is solved, there is very much realistic meaning to those skilled in the art.
Summary of the invention
It is an object of the invention to:, not scientific and reasonable enough, construction lack of standardization in order to solve existing earth excavation construction method The technical issues of difficulty is big, and construction period is caused to extend, the present invention provide a kind of cubic metre of earth of stage excavation construction method.
The present invention specifically uses following technical scheme to achieve the goals above:
A kind of cubic metre of earth of stage excavation construction method, comprising the following steps:
(1) surveying setting-out: according to established plane and elevation control system, boundary stake is released, and is arranged on each boundary Transverse direction and longitudinal direction controls stake, and every 100m is arranged one, controls stake concreting, and buried depth surveys the side of setting in below ground 20cm Grid implements construction lofting, and measures the ground elevation and design altitude of grid stake point, if ground elevation is greater than the point Design altitude be then excavation, be embankment if the design altitude that ground elevation is less than the point, the excavation and filling of each point is high Degree carries out mark in corresponding control stake with marking pen;
(2) bursting work: one layer of every explosion measures this layer of elevation in time;
(3) it removes surface vegetation: clearing up, excavates excavation section earth's surface organoclay, turf and tree root, and transported to specified abandoning Tu Chang;
(4) excavation construction: excavating intercepting ditch in advance, and excavation takes stage excavation from top to bottom, excavation when construction cubic metre of earth Usage mining machine is cut the earth and entrucking, when the gradient is lower than 15 °, bulldozes and incites somebody to action from up to down in certain height using bull-dozer Soil layer is pushed into low flat region.
Further, in step (1), with marking pen when marking in corresponding control stake, it is if embankment mark "+" is "-" if excavation mark.
Further, in step (1), in step (1), grid is divided into the lattice of 10m × 10m.
Further, in step (4), if find that soil layer property changes when excavation, arrangement and method for construction need to be modified immediately.
Further, it in step (4), when the earthwork transportation that digs out is to low flat region, when haul distance is in 100m, utilizes Bull-dozer push, when haul distance is more than 100m, is transported by dumper.
Beneficial effects of the present invention are as follows:
1, unwrapping wire first is being measured to excavation region, construction lofting is being implemented by control stake and grid, to survey The ground elevation and design altitude of grid stake point out, and embankment and excavation have been marked, it identifies convenient for subsequent construction, then carries out Each explosion layer is measured when bursting work, the surface vegetation generated in blasting process is cleared up, finally in explosion Excavation afterwards from top to bottom strictly controlled by carrying out the construction method excavated after measurement work and first explosion in advance by stage excavation Every one of working procedure is made, standard construction method greatly reduces difficulty of construction, ensure that construction period will not extend, even Fulfil the duration ahead of schedule.
Specific embodiment
In order to make the objectives, technical solutions, and advantages of the present invention clearer, with reference to embodiments, to the present invention It is further elaborated.It should be appreciated that described herein, specific examples are only used to explain the present invention, is not used to limit The fixed present invention, i.e., described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.Usually herein The component of the embodiment of the present invention shown in place can be arranged and be designed with a variety of different configurations.
Therefore, the model of claimed invention is not intended to limit to the detailed description in the embodiment of the present invention below It encloses, but is merely representative of selected embodiment of the invention.Based on the embodiment of the present invention, those skilled in the art are not making Every other embodiment obtained, shall fall within the protection scope of the present invention under the premise of creative work.
It should be noted that the relational terms of term " first " and " second " or the like be used merely to an entity or Operation is distinguished with another entity or operation, and without necessarily requiring or implying between these entities or operation, there are any This actual relationship or sequence.Moreover, the terms "include", "comprise" or its any other variant be intended to it is non-exclusive Property include so that include a series of elements process, method, article or equipment not only include those elements, but also Further include other elements that are not explicitly listed, or further include for this process, method, article or equipment it is intrinsic Element.In the absence of more restrictions, the element limited by sentence "including a ...", it is not excluded that including described There is also other identical elements in the process, method, article or equipment of element.
In order to which those skilled in the art better understand the present invention, below following embodiment to the present invention make further it is detailed Thin description.
Embodiment 1
The present embodiment provides a kind of cubic metre of earth of stage excavation construction methods, comprising the following steps:
A kind of cubic metre of earth of stage excavation construction method, comprising the following steps:
(1) surveying setting-out: according to established plane and elevation control system, boundary stake is released, and is arranged on each boundary Transverse direction and longitudinal direction controls stake, and every 100m is arranged one, controls stake concreting, and buried depth surveys the side of setting in below ground 20cm Grid implements construction lofting, and measures the ground elevation and design altitude of grid stake point, if ground elevation is greater than the point Design altitude be then excavation, be embankment if the design altitude that ground elevation is less than the point, the excavation and filling of each point is high Degree carries out mark in corresponding control stake with marking pen;
(2) bursting work: one layer of every explosion measures this layer of elevation in time;
(3) it removes surface vegetation: clearing up, excavates excavation section earth's surface organoclay, turf and tree root, and transported to specified abandoning Tu Chang;
(4) excavation construction: excavating intercepting ditch in advance, and excavation takes stage excavation from top to bottom, excavation when construction cubic metre of earth Usage mining machine is cut the earth and entrucking, when the gradient is lower than 15 °, bulldozes and incites somebody to action from up to down in certain height using bull-dozer Soil layer is pushed into low flat region.
Unwrapping wire first is being measured to excavation region, construction lofting is being implemented by control stake and grid, to measure The ground elevation and design altitude of grid stake point, and embankment and excavation have been marked, it identifies, then carries out quick-fried convenient for subsequent construction Each explosion layer is measured when broken operation, the surface vegetation generated in blasting process is cleared up, finally after explosion Excavation stage excavation from top to bottom, by carrying out the construction method excavated after measurement work and first explosion, strict control in advance Every one of working procedure, standard construction method greatly reduce difficulty of construction, ensure that construction period will not extend, or even mention The preceding completion duration.
Further, in step (1), with marking pen when marking in corresponding control stake, it is if embankment mark "+" is "-" if excavation mark, and label is simple and clear, convenient for identification.
Further, in step (1), in step (1), grid is divided into the lattice of 10m × 10m, improves measurement Precision.
Further, in step (4), if find that soil layer property changes when excavation, arrangement and method for construction need to be modified immediately.
Further, it in step (4), when the earthwork transportation that digs out is to low flat region, when haul distance is in 100m, utilizes Bull-dozer push, when haul distance is more than 100m, is transported, to accelerate construction progress by dumper.
The above, only presently preferred embodiments of the present invention, are not intended to limit the invention, patent protection model of the invention It encloses and is subject to claims, it is all with equivalent variations made by specification of the invention, it similarly should be included in the present invention Protection scope in.

Claims (5)

1. a kind of cubic metre of earth of stage excavation construction method, which comprises the following steps:
(1) surveying setting-out: according to established plane and elevation control system, boundary stake is released, and is arranged laterally on each boundary And longitudinally controlled stake, every 100m are arranged one, control stake concreting, buried depth sets grid in below ground 20cm, survey Implement construction lofting, and measure the ground elevation and design altitude of grid stake point, if ground elevation is greater than setting for the point Counting elevation is then excavation, is embankment if the design altitude that ground elevation is less than the point, the excavation and filling height of each point is used Marking pen carries out mark in corresponding control stake;
(2) bursting work: one layer of every explosion measures this layer of elevation in time;
(3) it removes surface vegetation: clearing up, excavates excavation section earth's surface organoclay, turf and tree root, and transported to specified spoir ?;
(4) excavation construction: excavating intercepting ditch in advance, and excavation takes stage excavation from top to bottom, and excavation when construction cubic metre of earth uses Excavator is cut the earth and entrucking, when the gradient is lower than 15 °, is bulldozed from up to down in certain height using bull-dozer and by soil layer It is pushed into low flat region.
2. a kind of cubic metre of earth of stage excavation construction method according to claim 1, which is characterized in that in step (1), with note Number pen is "+" if embankment mark when marking in corresponding control stake, is "-" if excavation mark.
3. a kind of cubic metre of earth of stage excavation construction method according to claim 1, which is characterized in that in step (1), in step Suddenly in (1), grid is divided into the lattice of 10m × 10m.
4. a kind of cubic metre of earth of stage excavation construction method according to claim 1, which is characterized in that in step (4), excavate If when discovery soil layer property when changing, arrangement and method for construction need to be modified immediately.
5. a kind of cubic metre of earth of stage excavation construction method according to claim 1, which is characterized in that in step (4), dig out Earthwork transportation to low flat region when, when haul distance is in 100m, pushed using bull-dozer, when haul distance is more than 100m, passed through Dumper transport.
CN201910221060.9A 2019-03-21 2019-03-21 A kind of cubic metre of earth of stage excavation construction method Pending CN109778864A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910221060.9A CN109778864A (en) 2019-03-21 2019-03-21 A kind of cubic metre of earth of stage excavation construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910221060.9A CN109778864A (en) 2019-03-21 2019-03-21 A kind of cubic metre of earth of stage excavation construction method

Publications (1)

Publication Number Publication Date
CN109778864A true CN109778864A (en) 2019-05-21

Family

ID=66491143

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910221060.9A Pending CN109778864A (en) 2019-03-21 2019-03-21 A kind of cubic metre of earth of stage excavation construction method

Country Status (1)

Country Link
CN (1) CN109778864A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110149831A (en) * 2019-06-03 2019-08-23 上海港城建筑安装工程有限公司 A kind of park prepartion of land method
CN111236239A (en) * 2020-01-10 2020-06-05 深圳市蛇口招商港湾工程有限公司 Earth and stone square migration method based on nearest distance priority
CN112212747A (en) * 2020-10-11 2021-01-12 中建五局土木工程有限公司 Non-blasting excavation construction method for mountain earth and stone in limited space
CN113235602A (en) * 2021-05-20 2021-08-10 中国水利水电第九工程局有限公司 Stone-square mountain excavation construction method for slope management

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110149831A (en) * 2019-06-03 2019-08-23 上海港城建筑安装工程有限公司 A kind of park prepartion of land method
CN111236239A (en) * 2020-01-10 2020-06-05 深圳市蛇口招商港湾工程有限公司 Earth and stone square migration method based on nearest distance priority
CN111236239B (en) * 2020-01-10 2022-01-25 深圳市蛇口招商港湾工程有限公司 Earth and stone square migration method based on nearest distance priority
CN112212747A (en) * 2020-10-11 2021-01-12 中建五局土木工程有限公司 Non-blasting excavation construction method for mountain earth and stone in limited space
CN112212747B (en) * 2020-10-11 2022-10-11 中建五局土木工程有限公司 Non-blasting excavation construction method for mountain earth and stone in limited space
CN113235602A (en) * 2021-05-20 2021-08-10 中国水利水电第九工程局有限公司 Stone-square mountain excavation construction method for slope management

Similar Documents

Publication Publication Date Title
CN109778864A (en) A kind of cubic metre of earth of stage excavation construction method
CN101422094B (en) Thick-bed mining subsidence-land dynamic pre-reclamation method at plane mining-area
WO2016045440A1 (en) Mining method
CN104846787B (en) Construction method for carrying out sand-blowing sea-filling land-making in shallow sea area by using cutter suction dredger
CN102182472B (en) Backfill repairing method for tunnel collapse cavity
CN105421286B (en) A kind of backhoe type dredger is combined with rig ship digs rock construction method
CN103235853B (en) Adopt the multiple base pool layout method based on earthwork balance in limit for coal-mining subsidence rand
CN112431594A (en) Green mine construction process
CN110259490A (en) A kind of Underground Subway Station construction method
CN114134877B (en) Treatment method for mining ground cracks of shallow coal seam in hilly and hilly areas of peaked landform
KR101609686B1 (en) Method for excavating base rock of on the sea
CN105112652B (en) A kind of rare earth ore in-situ leaching disposing mother liquor canal body structure
CN105387273A (en) Method for constructing natural gas pipelines in mountain environment
CN105155546B (en) A kind of construction method of prebored hole cubic meter of stone mechanical equivalent of light excavation
CN110924407A (en) Construction method for maintaining water and soil on lower slope without disturbance
CN103774698B (en) Soil engineering drainage-free construction method
CN109083122B (en) Construction method of construction operation platform in deep peat soil region
CN208266895U (en) Cofferdam is built in returning for seabed tunnel point storehouse construction
CN207987935U (en) A kind of highway Rock High Slope anchor pole pregroove marks safeguard structure
SU1765400A1 (en) Method at sail mass reclamation during preparation of quarry sanitary-protection zone
CN109958442A (en) A kind of tunnel shaft construction method
CN210288526U (en) Rich water building foundation slope earth excavation device
CN111022062B (en) Construction method for clay layer section of ramp
CN110761290B (en) Construction method for excavating deep foundation pit of high-rise building in soft weak soil or diving marsh soil
Clark et al. The Portavadie dry dock, west Scotland: a case history of the geotechnical aspects of its construction

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20190521