CN109778864A - A kind of cubic metre of earth of stage excavation construction method - Google Patents
A kind of cubic metre of earth of stage excavation construction method Download PDFInfo
- Publication number
- CN109778864A CN109778864A CN201910221060.9A CN201910221060A CN109778864A CN 109778864 A CN109778864 A CN 109778864A CN 201910221060 A CN201910221060 A CN 201910221060A CN 109778864 A CN109778864 A CN 109778864A
- Authority
- CN
- China
- Prior art keywords
- excavation
- earth
- construction
- stake
- cubic metre
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Abstract
The invention discloses a kind of cubic metre of earth of stage excavation construction methods, it is related to earth excavation technical field of construction, the present invention is the following steps are included: (1) surveying setting-out: according to established plane and elevation control system, boundary stake is released, and controls stake in each boundary setting transverse direction and longitudinal direction, every 100m is arranged one, control stake concreting, for buried depth in below ground 20cm, survey sets grid to implement construction lofting, and measures the ground elevation and design altitude of grid stake point;(2) bursting work: one layer of every explosion measures this layer of elevation in time;(3) it removes surface vegetation: clearing up, excavates excavation section earth's surface organoclay, turf and tree root, and transported to specified spoil ground;(4) excavation construction: excavating intercepting ditch in advance, and excavation takes stage excavation from top to bottom, and excavation usage mining machine when construction cubic metre of earth is cut the earth and entrucking, the present invention have the advantages that working procedure normal science, difficulty of construction are low, guarantee that the duration goes on smoothly.
Description
Technical field
The present invention relates to earth excavation technical field of construction, more particularly to a kind of cubic metre of earth of stage excavation construction party
Method.
Background technique
Earth excavation is engineering initial stage down to the critical process in work progress, and soil and rock are loosened, be crushed, dug
The engineering dug and transported, by rock and soil properties, earthwork evacuation divides earth excavation and rock excavation.Earth excavation is by construction environment
Outdoor, underground is underwater, is divided into open cut, hole is dug and underwater excavation classification.In hydraulic engineering, earth excavation is widely used in field
Ground is smooth and cuts slope, and hydraulic structure (sluice, dam, spillway, powerhouse of hydropower station, pumping plant building etc.) ground excavates, underground
Cavern's (hydraulic tunnel, underground power house, all kinds of adits, vertical shaft and inclined shaft) is excavated, and river, channel, harbour is excavated and dredging, is filled
Material, building stone and aggregate exploitation, the temporay buildings such as cofferdam or stone-laying, the dismounting of concrete structure etc..Soil
Square excavation construction, including loosen, be crushed, digging dress, transport such as is slagged tap at the processes.Rock excavation, except crumbly rock can with ridge buster with
Chisel is split outside method excavation, need to generally be loosened, is crushed in the method for explosion.Artificial and semi-mechanization is excavated, and spade pick, wind are used
The simple tools such as pick, air drill, lift is chosen in cooperation or the means of transport of Simple compact carries out operation, is suitable for small hydraulic project.
The construction of some irrigation and drainage irrigation canals and ditches directly uses ditching machine, can be once-forming, the earthwork evacuation of large and medium-sized hydraulic engineering,
Multi-purpose mechanical construction.
Earth excavation construction work is larger, and the duration is tighter, needs rationally to control every one of working procedure, and existing soil
Square excavation construction method is lack of standardization, not scientific and reasonable enough, and difficulty of construction is big, and construction period is caused to extend.
Therefore above-mentioned technical problem how is solved, there is very much realistic meaning to those skilled in the art.
Summary of the invention
It is an object of the invention to:, not scientific and reasonable enough, construction lack of standardization in order to solve existing earth excavation construction method
The technical issues of difficulty is big, and construction period is caused to extend, the present invention provide a kind of cubic metre of earth of stage excavation construction method.
The present invention specifically uses following technical scheme to achieve the goals above:
A kind of cubic metre of earth of stage excavation construction method, comprising the following steps:
(1) surveying setting-out: according to established plane and elevation control system, boundary stake is released, and is arranged on each boundary
Transverse direction and longitudinal direction controls stake, and every 100m is arranged one, controls stake concreting, and buried depth surveys the side of setting in below ground 20cm
Grid implements construction lofting, and measures the ground elevation and design altitude of grid stake point, if ground elevation is greater than the point
Design altitude be then excavation, be embankment if the design altitude that ground elevation is less than the point, the excavation and filling of each point is high
Degree carries out mark in corresponding control stake with marking pen;
(2) bursting work: one layer of every explosion measures this layer of elevation in time;
(3) it removes surface vegetation: clearing up, excavates excavation section earth's surface organoclay, turf and tree root, and transported to specified abandoning
Tu Chang;
(4) excavation construction: excavating intercepting ditch in advance, and excavation takes stage excavation from top to bottom, excavation when construction cubic metre of earth
Usage mining machine is cut the earth and entrucking, when the gradient is lower than 15 °, bulldozes and incites somebody to action from up to down in certain height using bull-dozer
Soil layer is pushed into low flat region.
Further, in step (1), with marking pen when marking in corresponding control stake, it is if embankment mark
"+" is "-" if excavation mark.
Further, in step (1), in step (1), grid is divided into the lattice of 10m × 10m.
Further, in step (4), if find that soil layer property changes when excavation, arrangement and method for construction need to be modified immediately.
Further, it in step (4), when the earthwork transportation that digs out is to low flat region, when haul distance is in 100m, utilizes
Bull-dozer push, when haul distance is more than 100m, is transported by dumper.
Beneficial effects of the present invention are as follows:
1, unwrapping wire first is being measured to excavation region, construction lofting is being implemented by control stake and grid, to survey
The ground elevation and design altitude of grid stake point out, and embankment and excavation have been marked, it identifies convenient for subsequent construction, then carries out
Each explosion layer is measured when bursting work, the surface vegetation generated in blasting process is cleared up, finally in explosion
Excavation afterwards from top to bottom strictly controlled by carrying out the construction method excavated after measurement work and first explosion in advance by stage excavation
Every one of working procedure is made, standard construction method greatly reduces difficulty of construction, ensure that construction period will not extend, even
Fulfil the duration ahead of schedule.
Specific embodiment
In order to make the objectives, technical solutions, and advantages of the present invention clearer, with reference to embodiments, to the present invention
It is further elaborated.It should be appreciated that described herein, specific examples are only used to explain the present invention, is not used to limit
The fixed present invention, i.e., described embodiments are only a part of the embodiments of the present invention, instead of all the embodiments.Usually herein
The component of the embodiment of the present invention shown in place can be arranged and be designed with a variety of different configurations.
Therefore, the model of claimed invention is not intended to limit to the detailed description in the embodiment of the present invention below
It encloses, but is merely representative of selected embodiment of the invention.Based on the embodiment of the present invention, those skilled in the art are not making
Every other embodiment obtained, shall fall within the protection scope of the present invention under the premise of creative work.
It should be noted that the relational terms of term " first " and " second " or the like be used merely to an entity or
Operation is distinguished with another entity or operation, and without necessarily requiring or implying between these entities or operation, there are any
This actual relationship or sequence.Moreover, the terms "include", "comprise" or its any other variant be intended to it is non-exclusive
Property include so that include a series of elements process, method, article or equipment not only include those elements, but also
Further include other elements that are not explicitly listed, or further include for this process, method, article or equipment it is intrinsic
Element.In the absence of more restrictions, the element limited by sentence "including a ...", it is not excluded that including described
There is also other identical elements in the process, method, article or equipment of element.
In order to which those skilled in the art better understand the present invention, below following embodiment to the present invention make further it is detailed
Thin description.
Embodiment 1
The present embodiment provides a kind of cubic metre of earth of stage excavation construction methods, comprising the following steps:
A kind of cubic metre of earth of stage excavation construction method, comprising the following steps:
(1) surveying setting-out: according to established plane and elevation control system, boundary stake is released, and is arranged on each boundary
Transverse direction and longitudinal direction controls stake, and every 100m is arranged one, controls stake concreting, and buried depth surveys the side of setting in below ground 20cm
Grid implements construction lofting, and measures the ground elevation and design altitude of grid stake point, if ground elevation is greater than the point
Design altitude be then excavation, be embankment if the design altitude that ground elevation is less than the point, the excavation and filling of each point is high
Degree carries out mark in corresponding control stake with marking pen;
(2) bursting work: one layer of every explosion measures this layer of elevation in time;
(3) it removes surface vegetation: clearing up, excavates excavation section earth's surface organoclay, turf and tree root, and transported to specified abandoning
Tu Chang;
(4) excavation construction: excavating intercepting ditch in advance, and excavation takes stage excavation from top to bottom, excavation when construction cubic metre of earth
Usage mining machine is cut the earth and entrucking, when the gradient is lower than 15 °, bulldozes and incites somebody to action from up to down in certain height using bull-dozer
Soil layer is pushed into low flat region.
Unwrapping wire first is being measured to excavation region, construction lofting is being implemented by control stake and grid, to measure
The ground elevation and design altitude of grid stake point, and embankment and excavation have been marked, it identifies, then carries out quick-fried convenient for subsequent construction
Each explosion layer is measured when broken operation, the surface vegetation generated in blasting process is cleared up, finally after explosion
Excavation stage excavation from top to bottom, by carrying out the construction method excavated after measurement work and first explosion, strict control in advance
Every one of working procedure, standard construction method greatly reduce difficulty of construction, ensure that construction period will not extend, or even mention
The preceding completion duration.
Further, in step (1), with marking pen when marking in corresponding control stake, it is if embankment mark
"+" is "-" if excavation mark, and label is simple and clear, convenient for identification.
Further, in step (1), in step (1), grid is divided into the lattice of 10m × 10m, improves measurement
Precision.
Further, in step (4), if find that soil layer property changes when excavation, arrangement and method for construction need to be modified immediately.
Further, it in step (4), when the earthwork transportation that digs out is to low flat region, when haul distance is in 100m, utilizes
Bull-dozer push, when haul distance is more than 100m, is transported, to accelerate construction progress by dumper.
The above, only presently preferred embodiments of the present invention, are not intended to limit the invention, patent protection model of the invention
It encloses and is subject to claims, it is all with equivalent variations made by specification of the invention, it similarly should be included in the present invention
Protection scope in.
Claims (5)
1. a kind of cubic metre of earth of stage excavation construction method, which comprises the following steps:
(1) surveying setting-out: according to established plane and elevation control system, boundary stake is released, and is arranged laterally on each boundary
And longitudinally controlled stake, every 100m are arranged one, control stake concreting, buried depth sets grid in below ground 20cm, survey
Implement construction lofting, and measure the ground elevation and design altitude of grid stake point, if ground elevation is greater than setting for the point
Counting elevation is then excavation, is embankment if the design altitude that ground elevation is less than the point, the excavation and filling height of each point is used
Marking pen carries out mark in corresponding control stake;
(2) bursting work: one layer of every explosion measures this layer of elevation in time;
(3) it removes surface vegetation: clearing up, excavates excavation section earth's surface organoclay, turf and tree root, and transported to specified spoir
?;
(4) excavation construction: excavating intercepting ditch in advance, and excavation takes stage excavation from top to bottom, and excavation when construction cubic metre of earth uses
Excavator is cut the earth and entrucking, when the gradient is lower than 15 °, is bulldozed from up to down in certain height using bull-dozer and by soil layer
It is pushed into low flat region.
2. a kind of cubic metre of earth of stage excavation construction method according to claim 1, which is characterized in that in step (1), with note
Number pen is "+" if embankment mark when marking in corresponding control stake, is "-" if excavation mark.
3. a kind of cubic metre of earth of stage excavation construction method according to claim 1, which is characterized in that in step (1), in step
Suddenly in (1), grid is divided into the lattice of 10m × 10m.
4. a kind of cubic metre of earth of stage excavation construction method according to claim 1, which is characterized in that in step (4), excavate
If when discovery soil layer property when changing, arrangement and method for construction need to be modified immediately.
5. a kind of cubic metre of earth of stage excavation construction method according to claim 1, which is characterized in that in step (4), dig out
Earthwork transportation to low flat region when, when haul distance is in 100m, pushed using bull-dozer, when haul distance is more than 100m, passed through
Dumper transport.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910221060.9A CN109778864A (en) | 2019-03-21 | 2019-03-21 | A kind of cubic metre of earth of stage excavation construction method |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910221060.9A CN109778864A (en) | 2019-03-21 | 2019-03-21 | A kind of cubic metre of earth of stage excavation construction method |
Publications (1)
Publication Number | Publication Date |
---|---|
CN109778864A true CN109778864A (en) | 2019-05-21 |
Family
ID=66491143
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910221060.9A Pending CN109778864A (en) | 2019-03-21 | 2019-03-21 | A kind of cubic metre of earth of stage excavation construction method |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN109778864A (en) |
Cited By (4)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110149831A (en) * | 2019-06-03 | 2019-08-23 | 上海港城建筑安装工程有限公司 | A kind of park prepartion of land method |
CN111236239A (en) * | 2020-01-10 | 2020-06-05 | 深圳市蛇口招商港湾工程有限公司 | Earth and stone square migration method based on nearest distance priority |
CN112212747A (en) * | 2020-10-11 | 2021-01-12 | 中建五局土木工程有限公司 | Non-blasting excavation construction method for mountain earth and stone in limited space |
CN113235602A (en) * | 2021-05-20 | 2021-08-10 | 中国水利水电第九工程局有限公司 | Stone-square mountain excavation construction method for slope management |
-
2019
- 2019-03-21 CN CN201910221060.9A patent/CN109778864A/en active Pending
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN110149831A (en) * | 2019-06-03 | 2019-08-23 | 上海港城建筑安装工程有限公司 | A kind of park prepartion of land method |
CN111236239A (en) * | 2020-01-10 | 2020-06-05 | 深圳市蛇口招商港湾工程有限公司 | Earth and stone square migration method based on nearest distance priority |
CN111236239B (en) * | 2020-01-10 | 2022-01-25 | 深圳市蛇口招商港湾工程有限公司 | Earth and stone square migration method based on nearest distance priority |
CN112212747A (en) * | 2020-10-11 | 2021-01-12 | 中建五局土木工程有限公司 | Non-blasting excavation construction method for mountain earth and stone in limited space |
CN112212747B (en) * | 2020-10-11 | 2022-10-11 | 中建五局土木工程有限公司 | Non-blasting excavation construction method for mountain earth and stone in limited space |
CN113235602A (en) * | 2021-05-20 | 2021-08-10 | 中国水利水电第九工程局有限公司 | Stone-square mountain excavation construction method for slope management |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN109778864A (en) | A kind of cubic metre of earth of stage excavation construction method | |
CN101422094B (en) | Thick-bed mining subsidence-land dynamic pre-reclamation method at plane mining-area | |
WO2016045440A1 (en) | Mining method | |
CN104846787B (en) | Construction method for carrying out sand-blowing sea-filling land-making in shallow sea area by using cutter suction dredger | |
CN102182472B (en) | Backfill repairing method for tunnel collapse cavity | |
CN105421286B (en) | A kind of backhoe type dredger is combined with rig ship digs rock construction method | |
CN103235853B (en) | Adopt the multiple base pool layout method based on earthwork balance in limit for coal-mining subsidence rand | |
CN112431594A (en) | Green mine construction process | |
CN110259490A (en) | A kind of Underground Subway Station construction method | |
CN114134877B (en) | Treatment method for mining ground cracks of shallow coal seam in hilly and hilly areas of peaked landform | |
KR101609686B1 (en) | Method for excavating base rock of on the sea | |
CN105112652B (en) | A kind of rare earth ore in-situ leaching disposing mother liquor canal body structure | |
CN105387273A (en) | Method for constructing natural gas pipelines in mountain environment | |
CN105155546B (en) | A kind of construction method of prebored hole cubic meter of stone mechanical equivalent of light excavation | |
CN110924407A (en) | Construction method for maintaining water and soil on lower slope without disturbance | |
CN103774698B (en) | Soil engineering drainage-free construction method | |
CN109083122B (en) | Construction method of construction operation platform in deep peat soil region | |
CN208266895U (en) | Cofferdam is built in returning for seabed tunnel point storehouse construction | |
CN207987935U (en) | A kind of highway Rock High Slope anchor pole pregroove marks safeguard structure | |
SU1765400A1 (en) | Method at sail mass reclamation during preparation of quarry sanitary-protection zone | |
CN109958442A (en) | A kind of tunnel shaft construction method | |
CN210288526U (en) | Rich water building foundation slope earth excavation device | |
CN111022062B (en) | Construction method for clay layer section of ramp | |
CN110761290B (en) | Construction method for excavating deep foundation pit of high-rise building in soft weak soil or diving marsh soil | |
Clark et al. | The Portavadie dry dock, west Scotland: a case history of the geotechnical aspects of its construction |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20190521 |