CN210288526U - Rich water building foundation slope earth excavation device - Google Patents
Rich water building foundation slope earth excavation device Download PDFInfo
- Publication number
- CN210288526U CN210288526U CN201921086526.0U CN201921086526U CN210288526U CN 210288526 U CN210288526 U CN 210288526U CN 201921086526 U CN201921086526 U CN 201921086526U CN 210288526 U CN210288526 U CN 210288526U
- Authority
- CN
- China
- Prior art keywords
- hole
- leaks
- slope
- scraper bowl
- building foundation
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Active
Links
Images
Abstract
The utility model discloses a rich water building foundation slope earth excavation device has solved the current technical problem that unloads inefficiency behind the bucket excavation earthwork under water. The utility model discloses a scraper bowl with hole that leaks, the scraper bowl is for having the hollow sphere of open-ended, is provided with the articulated seat of symmetry on the outer wall of open-ended both sides, and articulated the being connected with pull rod of articulated seat, the articulated shovel mud board that is connected with the slope to the place ahead below of open-ended side, the open-ended both sides are provided with the stopper that prevents the shovel mud board upset of the place ahead that makes progress. The utility model discloses not only small, light in weight, operation demand space are little, the removal is convenient, unload soil efficiently, can control side slope excavation slope and roughness moreover.
Description
Technical Field
The utility model relates to a rich water earthwork excavation technical field especially indicates a rich water building foundation slope earth excavation device.
Background
The earth excavation is a key process from the initial stage of the engineering to the construction process, and is an engineering for loosening, crushing, excavating and transporting out soil and rocks. According to the properties of rock and soil, the earth and stone excavation is divided into earth excavation and stone excavation.
Earth excavation is classified into open excavation, tunnel excavation and underwater excavation according to the construction environment, i.e., open excavation, underground excavation or underwater excavation. In water conservancy projects, earth excavation is widely applied to site leveling and slope cutting, foundation excavation of hydraulic buildings (floodgates, dams, spillways, hydropower station plants, pump station buildings and the like), excavation of underground caverns (hydraulic tunnels, underground plants, various flat holes, vertical shafts and inclined shafts), excavation and dredging of river channels, channels and ports, exploitation of filling materials, building stones and concrete aggregates, removal of temporary buildings such as cofferdams or the like or masonry, concrete structures and the like.
When a hydraulic building is excavated, the excavation is mostly carried out in water, generally, an excavating bucket with water leakage holes is used for excavating, but the existing excavating bucket is difficult to unload sludge after water is discharged, the sludge unloading time is usually longer than the excavating time, and the construction efficiency is slow.
SUMMERY OF THE UTILITY MODEL
To not enough among the above-mentioned background art, the utility model provides a rich water building foundation slope earth excavation device has solved the current technical problem that unloads inefficiency behind the bucket excavation earthwork under water.
The technical scheme of the utility model is realized like this: the utility model provides a rich water building foundation slope earth excavation device, is including having the scraper bowl that leaks the hole, the scraper bowl is for having the hollow sphere of open-ended, is provided with the articulated seat of symmetry on the outer wall of open-ended both sides, and articulated the being connected with pull rod of articulated seat, the articulated shovel mud board that is connected with the slope to the place ahead in the below of open-ended side, the open-ended both sides are provided with the stopper that prevents the shovel mud board upset of the place ahead that makes progress.
The hole that leaks includes first hole and the second hole that leaks, and the aperture in first hole that leaks is greater than the aperture in second hole that leaks, and first hole that leaks is located the top of scraper bowl, and the second hole that leaks is located the bottom of scraper bowl.
The limiting block is adjustably connected to the opening, a row of mounting holes are formed in different height positions of the opening, and the limiting block is in adjustable inserting fit with the different mounting holes.
The front end of the shovel plate is provided with a row of excavation teeth.
The utility model discloses not only small, light in weight, operation demand space are little, the removal is convenient, unload soil efficiently, can control side slope excavation slope and roughness moreover. The underwater shoveling and transporting bucket of the utility model embeds the digging teeth into the soil body by the dead weight, and can start the operation along the slope surface by the traction pull rod of the winch; after the soil body is pulled out of the water surface by the traction equipment, the soil body can be unloaded by manually pushing the bucket. In addition, because the shovel plate inclines towards the lower front, soil body omission can be avoided in the process of pulling the bucket, and the soil body can be gradually deeply dug and gathered. The stopper of shovel mud board top can effectively guarantee the reliability of shovel mud board process of cutting earth, through the mounted position who adjusts the stopper, can adjust the angle of shovel mud board slope, can adjust spacing angle according to the excavation demand of difference.
Drawings
In order to illustrate the embodiments of the present invention more clearly, the drawings that are needed in the description of the embodiments will be briefly described below, and it is obvious that the drawings in the description below are only some embodiments of the present invention, and that other drawings can be obtained by those skilled in the art without inventive work.
FIG. 1 is a schematic sectional view of the present invention;
fig. 2 is a left side view of fig. 1.
Detailed Description
The technical solutions in the embodiments of the present invention will be described clearly and completely with reference to the accompanying drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only some embodiments of the present invention, not all embodiments. Based on the embodiments in the present invention, all other embodiments obtained by a person skilled in the art without any creative effort belong to the protection scope of the present invention.
The outer walls of the two sides of the opening 2 are provided with symmetrical hinged seats 3, the hinged seats 3 are hinged with pull rods 4, and the pull rods 4 can be pulled manually or by using a winch. The side of opening 2 is articulated to be connected with slope lower place ahead shovel mud board 5, and the both sides of opening 2 are provided with the stopper 6 that prevents the upset of the place ahead of shovel mud board 5. Stopper 6 adjustable connection is on opening 2, and the not co-altitude position of opening 2 is provided with a row of mounting hole, stopper 6 and the adjustable grafting cooperation of mounting hole of difference.
Because the shoveling plate 5 inclines downwards and forwards, soil body omission can be avoided in the process of pulling the bucket 1, and soil body can be gradually deeply dug and gathered. The limiting block 6 above the shovel plate 5 can effectively ensure the reliability of the digging process of the shovel plate 5. In addition, through adjusting the mounted position of stopper, can adjust the angle of shovel mud board 5 slope, can adjust spacing angle according to the excavation demand of difference. When the soil in the bucket 1 is pulled to the shore by the winch, the spherical bucket 1 is rotated through the pull rod 4, and the soil in the bucket 1 can be automatically discharged through the opening 2 along with the rotation.
The other structure of this embodiment is the same as embodiment 1.
The present invention is not exhaustive and is well known to those skilled in the art.
The above description is only a preferred embodiment of the present invention, and should not be taken as limiting the invention, and any modifications, equivalent replacements, improvements, etc. made within the spirit and principle of the present invention should be included in the protection scope of the present invention.
Claims (4)
1. The utility model provides a rich water building foundation slope earth excavation device, includes scraper bowl (1) that have the hole that leaks, its characterized in that: the scraper bowl (1) is for having the hollow sphere of opening (2), is provided with articulated seat (3) of symmetry on the outer wall of the both sides of opening (2), and articulated seat (3) are articulated to be connected with pull rod (4), the articulated shovel mud board (5) that are connected with the slope to the place ahead in the lower place, the both sides of opening (2) are provided with stopper (6) that prevent the upset of the place ahead that makes progress of shovel mud board (5).
2. The device for excavating soil on the inclined side slope of the water-rich building foundation according to claim 1, which is characterized in that: the hole that leaks includes first hole (7) and second hole (8) that leaks, and the aperture that first hole (7) that leaks is greater than the aperture that second hole (8) that leaks, first hole that leaks is located the top of scraper bowl (1), and second hole (8) that leaks is located the bottom of scraper bowl (1).
3. The device for excavating soil on the inclined side slope of the water-rich building foundation according to claim 2, characterized in that: the limiting block (6) is adjustably connected to the opening (2), a row of mounting holes are formed in different height positions of the opening (2), and the limiting block (6) is in adjustable inserting fit with the different mounting holes.
4. The device for excavating the soil on the inclined side slope of the water-rich building foundation according to any one of claims 1 to 3, wherein: the front end part of the shovel plate (5) is provided with a row of excavating teeth (9).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921086526.0U CN210288526U (en) | 2019-07-12 | 2019-07-12 | Rich water building foundation slope earth excavation device |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201921086526.0U CN210288526U (en) | 2019-07-12 | 2019-07-12 | Rich water building foundation slope earth excavation device |
Publications (1)
Publication Number | Publication Date |
---|---|
CN210288526U true CN210288526U (en) | 2020-04-10 |
Family
ID=70101966
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201921086526.0U Active CN210288526U (en) | 2019-07-12 | 2019-07-12 | Rich water building foundation slope earth excavation device |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN210288526U (en) |
-
2019
- 2019-07-12 CN CN201921086526.0U patent/CN210288526U/en active Active
Similar Documents
Publication | Publication Date | Title |
---|---|---|
US6139225A (en) | Method for building an underground continuous wall | |
CN103882881B (en) | Go deep into rock construction method under water | |
CN111691425B (en) | Water conservancy project foundation pit and pipe well combined light well point dewatering and drainage method | |
CN109778864A (en) | A kind of cubic metre of earth of stage excavation construction method | |
CN112663558B (en) | Construction process for excavating weathered rock in inland river harbor pool | |
CN210288526U (en) | Rich water building foundation slope earth excavation device | |
CN202626934U (en) | Gravity wharf built on silty foundation | |
CN201778330U (en) | Clay water-stop curtain wall | |
CN111851543A (en) | Long and narrow deep foundation pit construction cofferdam structure and use method thereof | |
CN108411934B (en) | Floating tubular pile, dam retaining structure and construction method thereof | |
CN111549807B (en) | Water lowering and draining method combining water conservancy project foundation pit and pipe well with light well point | |
CN101532586A (en) | Underground pipeline installation construction device and method thereof | |
CN204435321U (en) | A kind of steam power station water intaking open channel | |
CN104846837B (en) | The construction method of ultra-deep well in a kind of bright draining foundation ditch | |
CN208815550U (en) | A kind of rich water powder land floor precipitation and recharge construction system | |
CN202577341U (en) | Pipe section foundation of large-scale immersed pipe tunnel | |
CN112962641A (en) | Construction method for dismantling riverbank cofferdam structure | |
CN113026848A (en) | Construction method of continuous high-spraying impervious wall by planing and milling method | |
CN1208523C (en) | Gravity lattice embankment wall-retaining structure construction method | |
CN112962525A (en) | Dredged soil filling and diking structure and filling bag diking method thereof | |
CN111455976A (en) | Construction method of self-setting mortar impervious wall by grooving method | |
CN204530740U (en) | A kind of large-scale immersed tube tunnel pipeline section shock insulating foundation with elastic deformation | |
CN110359513A (en) | A kind of scraper bowl and method having the trapezoidal gutter channel excavation of shoulder | |
CN212271040U (en) | Civil engineering foundation pit excavating device | |
CN211849240U (en) | Overflow structure with combined water retaining wall and drainage ditch |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
GR01 | Patent grant | ||
GR01 | Patent grant |